0% found this document useful (0 votes)
9 views2 pages

Case Study 8

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views2 pages

Case Study 8

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Russell McGee

Daniel Torres AGSM 301


C:\Users\danie\Documents\AGSM 301\Case Study 8.pro
Module/submodel: Project Management (PERT/CPM)
Problem title: (untitled)
Method: Three Time Estimate
Network type: Immediate predecessor list

Project Management (PERT/CPM)/Three Time Estimate Results


Activity Early Late Standard
Activity Early Start Late Start Slack Variance
time Finish Finish Deviation
Project 46 2.01 4.06

H 10 36 46 36 46 0 0 0

I 9.33 26.67 36 26.67 36 0 1.33 1.78

J 5.17 30 35.17 30.83 36 .83 .83 .69

K 4 0 4 26.83 30.83 26.83 0 0

L 2 14 16 28.83 30.83 14.83 0 0

M 3.83 26.17 30 27 30.83 .83 .5 .25

N 5 21.67 26.67 21.67 26.67 0 1 1

O 5 18.17 23.17 21.67 26.67 3.5 0 0

P 5 14 19 21.67 26.67 7.67 0 0

Q 5 9 14 23.83 28.83 14.83 0 0

R 4.5 21.67 26.17 22.5 27 .83 .5 .25

S 3.5 18.17 21.67 18.17 21.67 0 .5 .25

T 3 6 9 20.83 23.83 14.83 0 0

U 1.17 17 18.17 17 18.17 0 .17 .03

V 4.67 17 21.67 17.83 22.5 .83 .33 .11

W 3 14 17 14 17 0 1 1

X 3 14 17 14.83 17.83 .83 0 0

Y 8 6 14 6 14 0 0 0

Z 6 0 6 0 6 0 0 0

Activity time computations


Most Likely Pessimistic Standard
Optimistic time Activity time Variance
time time Deviation
H 10 10 10 10 0 0

I 8 8 16 9.33 1.33 1.78

J 1 6 6 5.17 .83 .69

K 4 4 4 4 0 0

L 2 2 2 2 0 0

M 2 4 5 3.83 .5 .25

N 4 4 10 5 1 1

O 5 5 5 5 0 0

Tuesday, November 5, 2024 3:45 PM 1 of 1


Russell McGee
Daniel Torres AGSM 301
C:\Users\danie\Documents\AGSM 301\Case Study 8.pro
Activity time computations
Most Likely Pessimistic Standard
Optimistic time Activity time Variance
time time Deviation
P 5 5 5 5 0 0

Q 5 5 5 5 0 0

R 2 5 5 4.5 .5 .25

S 3 3 6 3.5 .5 .25

T 3 3 3 3 0 0

U 1 1 2 1.17 .17 .03

V 3 5 5 4.67 .33 .11

W 2 2 8 3 1 1

X 3 3 3 3 0 0

Y 8 8 8 8 0 0

Z 6 6 6 6 0 0

Project results
Sum of crit act
4.06
var
Square root of
2.01
total

Tuesday, November 5, 2024 3:45 PM 2 of 1