Module 7 Program Evaluation Review Technique and Critical Path Method
Module 7 Program Evaluation Review Technique and Critical Path Method
Module :
PROGRAM EVALUATION REVIEW
TECHNIQUE (PERT) AND CRITICAL
PATH METHOD (CPM)
Overview:
These lessons will tackle the two project management tools that assist management in
scheduling projects: the Program Evaluation Review Technique (PERT) and Critical Path
method (CPM). PERT was developed in 1958 by the US Navy Special Project Office in
coordination with the consulting firm Booz, Allen and Hamilton. The time when the US Navy
faced the challenge of developing the Polaris submarine missile project, the soonest
possible time PERT was the tool used to plan and control the duration of this project. While
Du Pont under the effort of Morgan R. Walker and James E. Kelly of Reminton Rand
developed CPM in 1957. The team researcher was primarily concerned of finding was to
reduce the time required to perform the tasks.
Learning Objectives:
At the end of this module, the student should be able to:
1. Differentiate PERT and CPM;
2. Determine the critical path of a project; and
3. Perform crashing of activities.
Critical Path refers to the longest path through a network that is needed to complete a
project. A delay on the activities on this path will delay the completion of the entire project.
Slack time is equal to zero.
Slack time refers to the length of time in a particular activity that can be delayed or
postponed without delaying the completion of the entire project.
Formula:
Forward Pass
Slack time = Latest start (LS) - Earliest start (ES)
or
Backward Pass
Slack time = Latest finish (LF) - Earliest finish (EF)
Probability of Completion:
Formula
Z= x - u__
σ
Where:
Z - Z-score in the normal curve distribution table
x - required due date of the project
u - expected time of completion determined in the network
σ - standard deviation of activities on the critical path
Activities in a Network
Successor Activity is an activity that can be started only once a certain activity is
completed.
PERT Procedure
1. Create the list of activities that make up the project
2. Arranged the sequence of activities within the project. This is to identify the
immediate predecessor activity.
3. Estimate the activity time. In PERT, the optimistic, most likely, pessimistic time must
be determined
4. Draw the project network by satisfying the immediate predecessor activity.
5. Use forward pass to identify the earliest start and earliest finish time for each activity.
The earliest finish (EF) time for the last activity would be the project completion time.
6. Use backward pass to determine the latest start and latest finish time for each
activity. The project completion time will be the latest finish (LF) time for the last
activity.
7. Find the slack time for each activity using the formula, slack time = LS-ES of LF-EF.
8. Identify the critical activities, these are activities with zero slack time.
9. Summarize the activity schedule in tabular form.
Example:
Given the following network with activities and time estimated in days
Requirement:
Answer:
Activity Expected Time (to+4tm+tp) Variance (tp - to)²
6 6
A 2 + 4(5) + 6 = 28 4.67 (6 - 2)² =(4/6)² .44
6 6 6
B 1 + 4(3) + 7 = 20 3.33 (7-1)² = (6/6)² 1
6 6 6
C 6 + 4(7) + 10 = 44 7.33 (10 - 6)² = (4/6)² .44
6 6 6
D 5 + 4(12) + 14 = 67 11.17 (14 - 5)² = (9/6)² 2.25
6 6 6
E 3 + 4(4) + 5 = 24 4 (5 - 3)² = (2/6)² .11
6 6 6
F 8 + 4(9) + 12 = 56 9.33 (12 - 8)² = (4/6)² .44
6 6 6
G 4 + 4(6) + 8 = 36 6 (8 - 4)² = (4/6)² .44
6 6 6
H 3 + 4(6) + 8 = 35 5.83 (8 - 3)² = (5/6)² .69
6 6 6
I 5 + 4(7) + 12 = 45 7.5 (12 - 5)² = (7/6)² 1.36
6 6 6
J 12 + 4(13) + 14 = 78 13 (14 - 12)² =(2/6)² .11
6 6 6
K 1 + 4(3) + 4 = 17 2.83 (4 - 1)² = (3/6)² .25
6 6 6
Activity Predecessor Weeks ES LS EF LF Slack Path