OT MCQs
OT MCQs
OPTIMIZATION TECHNIQUES
BCA IV SEM
UNIT-1
LINEAR PROGRAMMING PROBLEM
4. Which technique is used in finding a solution for optimizing a given objective, such as profit
maximization or cost minimization under certain constraints?
a) Quauing Theory
b) Waiting Line
c) Both A and B
d) Linear Programming
Answer : d)
6. What can be defined as a useful idle resource which has economic value eg; raw materials, spare
parts, finished items, etc?
a) Inventory Control
b) Inventory
c) Inventory Planning
d) None of the above
Answer : b)
8. Operations Research techniques helps the directing authority in optimum allocation of various
limited resources, such as ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Men and Machine
b) Money
c) Material and Time
d) All of the above
Answer : d)
10. ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ models involves the allocation of resources to activities in such a manner that some
measure of effectiveness is optimized.
a) Sequencing
b) Allocation Models
c) Queuing Theory
d) Decision Theory
Answer :b )
12. In ‐‐‐‐‐‐‐‐‐‐‐ models, everything is defined and the results are certain,
a) Deterministic Models
b) Probabilistic Models
c) Both A and B
d) None of the above
Answer :a )
15. The objective functions and constraints are linear relationship between ‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Variables
b) Constraints
c) Functions
d) All of the above
Answer : a)
16. Assignment problem helps to find a maximum weight identical in nature in a weighted ‐‐‐‐‐‐‐‐‐‐‐‐
a) Tripartite graph
b) Bipartite graph
c) Partite graph
d) None of the above
Answer : b)
17. All the parameters in the linear programming model are assumed to be ‐‐‐‐‐‐‐‐‐‐‐‐
a) Variables
b) Constraints
c) Functions
d) None of the above
Answer : b)
18. Graphic method can be applied to solve a LPP when there are only ‐‐‐‐‐‐‐‐‐‐‐‐‐ variable
a) One
b) More than One
c) Two
d) Three
Answer :c )
20. The variables whose coefficient vectors are unit vectors are called ‐‐‐‐‐‐‐‐‐‐‐‐
a) Unit Variables
b) Basic Variables
c) Non basic Variables
d) None of the above
Answer : b)
22. A minimization problem can be converted into a maximization problem by changing the sign of
coefficients in the ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Constraints
b) Objective Functions
c) Both A and B
d) None of the above
Answer : b)
23. If in a LPP , the solution of a variable can be made infinity large without violating the constrai the
solution is ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ nts,
a) Infeasible
b) Unbounded
c) Alternative
d) None of the above
Answer : b)
24. In maximization cases , ‐‐‐‐‐‐‐‐‐‐‐‐‐ are assigned to the artificial variables as their coefficients in the
objective function
a) +m
b) –m
c) 0
d) None of the above
Answer :a )
27. A BFS of a LPP is said to be ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ if at least one of the basic variable is zero
a) Degenerate
b) Non‐degenerate
c) Infeasible
d) Unbounded
Answer :a )
30. As for maximization in assignment problem, the objective is to maximize the ‐‐‐‐‐‐‐‐‐‐‐
a) Profit
b) optimization
c) cost
d) None of the above
Answer : a)
31. If there are more than one optimum solution for the decision variable the solution is ‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Infeasible
b) Unbounded
c) Alternative
d) None of the above
Answer : c)
32. Which LP method involves solving a series of linear equation to reach the optimal solution?
a) Graphical solution method
b) Simplex algorithm
c) Big- M method
d) Dual simplex method
Answer : b)
34. For analyzing the problem , decision – makers should normally study
a) Its qualitative aspects
b) Its quantitative aspects
c) Both A and B
d) Neither A and B
Answer :a )
40. In a manufacturing process, who takes the decisions as to what quantities and which process or
processes are to be used so that the cost is minimum and profit is maximum?
a) Supervisor
b) Manufacturer
c) Producer
d) Production manager
Answer :d )
43. Any feasible solution which optimizes (minimizes or maximizes) the objective function of the LPP is
called its ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Optimal solution
b) Non‐basic variables
c) Solution
d) Basic feasible solution
Answer :a )
44. A non – degenerate basic feasible solution is the basic feasible solution which has exactly m positive
Xi (i=1,2,…,m), i.e., none of the basic variable is ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Infinity
b) One
c) Zero
d) X
Answer : c)
45. What is also defined as the non‐negative variables which are added in the LHS of the constraint to
convert the inequality ‘< ‘ into an equation?
a) Slack variables
b) Simplex algorithm
c) Key element
d) None of the above
Answer : a)
46. Which method is an iterative procedure for solving LPP in a finite number of steps ?
a) Simplex algorithm
b) Slack variable
c) M method
d) Simplex method
Answer : d)
47. In simplex algorithm , which method is used to deal with the situation where an infeasible starting
basic solution is given?
a) Slack variable
b) Simplex method
c) M‐ method
d) None of the above
Answer : c)
49. ‐‐‐‐‐‐‐‐‐‐‐‐ is another method to solve a given LPP involving some artificial variable ?
a) Big M method
b) Method of penalties
c) Two‐phase simplex method
d) None of the above
Answer : c)
50. An objective function which states the determinants of the quantity to be either maximized or
minimized is called ‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Feasible function
b) Optimal function
c) Criterion function
d) None of the above
Answer :c )
51. A set of values X1, X2,…Xn which satisfies the constraints of the LPP is called ‐‐‐‐‐‐‐‐‐‐‐‐
a) Solution
b) Variable
c) Linearity
d) None of the above
Answer :a )
52. A basic solution which also satisfies the condition in which all basic variables are non ‐negative is
called ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Basic feasible solution
b) Feasible solution
c) Optimal solution
d) None of the above
Answer : a)
53. All the constraints are expressed as equations and the right hand side of each constraint and all
variables are non‐negative is called ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Canonical variable
b) Canonical form
c) Canonical solution
d) Both A and B
Answer : b)
55. LPP is exactly used in solving what kind of resource allocation problems?
a) Production planning and scheduling
b) Transportation
c) Sales and advertising
d) All of the above
Answer : d)
57. ‐‐‐‐‐‐‐‐‐‐‐‐‐‐ refers to the combination of one or more inputs to produce a particular output.
a) Solution
b) variable
c) Process
d) None of the above
Answer : c)
60. The solution of any transportation problem is obtained in how many stages?
a) Five
b) Four
c) Three
d) Two
Answer :d )
61. An optimal solution is the ‐‐‐‐‐‐‐‐‐‐‐ stage of a solution obtained by improving the initial solution
a) Third
b) First
c) Second
d) Final
Answer : c)
64. To make an unbalanced assignment problem balanced, what are added with all entries as zeroes?
a) Dummy rows
b) Dummy columns
c) Both A and B
d) Dummy entries
Answer : c)
65. Any set of non‐negative allocations (Xij>0) which satisfies the raw and column sum (rim requirement
)is called a ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Linear programming
b) Basic feasible solution
c) Feasible solution
d) None of the above
Answer :c )
66. A feasible solution is called a basic feasible solution if the number of non‐negative allocations is
equal to ‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) m‐n+1
b) m‐n‐1
c) m+n‐1
d) None of the above
Answer : c)
67. Any feasible solution to a transportation problem containing m origins and n destinations is said to
be ‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Independent
b) Degenerate
c) Non‐degenerate
d) Both A and B
Answer : c)
68. A path formed by allowing horizontal and vertical lines and the entire corner cells of which are
occupied is called a ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Occupied path
b) Open path
c) Closed path
d) None of the above
Answer : c)
69. Transportation algorithm can be used for minimizing the transportation cost of ‐‐‐‐‐‐‐‐‐‐‐‐ from O
origins and D destinations
a) Goods
b) Products
c) Items
d) None of the above
Answer :a )
70. If demand is lesser than supply then dummy demand node is added to make it a ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Simple problem
b) Balanced problem
c) Transportation problem
d) None of the above
Answer :b )
71. Basic cells indicate positive values and non‐ basic cells have ‐‐‐‐‐‐‐‐‐‐‐ value for flow .
a) Negative
b) Positive
c) One
d) zero
Answer : d)
72. According to transportation problem number of basic cells will be exactly ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) m+n‐0
b) n+m‐1
c) m+n‐1
d) None of the above
Answer :c )
73. Which method is suitable for solving the Transportation Problem when the number of sources is not
equal to the number of destination
a) Big-M method
b) Hungarian method
c) Modified distribution method
d) Simplex algorithm
Answer: c)
74. In which phase is optimization done and how does that phase also checks for optimality conditions?
a) Phase II
b) Phase I
c) Phase II
d) None of the above
Answer : c)
75. Optimality conditions are expressed as ‐‐‐‐‐‐‐‐‐‐‐‐‐ incase all non‐basic cells?
a) Negligent costs
b) Advanced costs
c) Reduced costs
d) None of the above
Answer :c )
78. After determining every basic cell with in this cycle, adjustment is obtained as minimum value in
basic cells . this is known as ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Adjustment amount
b) aa
c) Both A and B
d) Alternatives
Answer :c )
79. Optimal solution is a feasible solution (not necessarily basic ) which minimizes the ‐‐‐‐‐‐‐‐‐‐
a) Time taken
b) Partial cost
c) Total cost
d) None of the above
Answer :c )
80. The allocated cells in the transportation table are called ‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Occupied cells
b) Empty cells
c) Both A and B
d) Unoccupied cells
Answer : c)
82. Once the initial basic feasible solution has been computed , what is the next step in the problem
a) VAM
b) Modified distribution method
c) Optimality test
d) None of the above
Answer :c )
83. One can find the initial basic feasible solution by using ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐ ?
a) VAM
b) MODI
c) Optimality test
d) None of the above
Answer : a)
85. In the assignment problem, what does an assignment with a zero cost signify?
a) An optimal assignment
b) A degenerate solution
c) An infeasible solution
d) An unassigned source or destination
Answer : a)
86. A given TP is said to be unbalanced, if the total supply is not equal to the total ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Optimization
b) Demand
c) Cost
d) None of the above
Answer : b)
87. If the total supply is less than the total demand, a dummy source (row) is included in the cost matrix
with ‐‐‐‐‐‐‐‐‐‐‐‐‐
a) Dummy Demand
b) Dummy Supply
c) Zero Cost
d) Both A and B
Answer :c )
90. When the number of allocations in a basic feasible solution of an m×n transportation problem is less
than m+n−1, the situation is called:
a) Balanced
b) Unbalanced
c) Degeneracy
d) Optimality
Answer: c)
91. The Modified Distribution (MODI) method uses dual variables ui and vj to calculate:
a) Initial allocation
b) Transportation cost
c) Opportunity cost for empty cells
d) Total supply and demand
Answer: c)
93.The method of finding an initial solution based upon opportunity cost is called_______.
a) North-West corner rule
b)Vogel’s Approximation
c) Jhonson’s method
d) Hungarian method
Answer: b)
99.If all the replacement ratios (calculated in the Simplex method for determining the leaving variable)
are negative or undefined, it indicates:
a) An infeasible solution
b) An unbounded solution
c) An optimal solution
d) Degeneracy
Answer: b)
100. If the objective function can be increased or decreased indefinitely without violating any
constraints, the LPP has:
a) A unique optimal solution
b) Multiple optimal solutions
c) An unbounded solution
d) An infeasible solution
Answer: c)
UNIT-2
QUEUING THEORY
11. The presence of a group of customers who arrive randomly to receive some service is identified by:
a) Reneging
b) Queuing
c) Arrival
d. Service Mechanism
Answer : b)
13.The time spent in a queuing system before the service starts is known as
a. Server time
b. Arrival time
c. Service time
d. Waiting time
Answer : d)
15.If the customer enters a queue but decides to leave before being served, this behaviour is known as
a) Reneging
b. Faffing
c Jockeying
d. Balking
Answer : a)
16.If a customer decides not to enter a waiting line as it is too long and has no time to wait, this
behavior is known as
a. Reneging
b. Faffing
c. Jockeying
d. Balking
Answer : d)
17.When there are two or more parallel queues and the customer moves from one queue to another is
called as
a. Reneging
b. Faffing
c. Jockeying
d. Ballking
Answer : c)
18.The degree to which the capacity of service station is utilized is determined by the
a. Arrival pattern
b. Service mechanism
c. Traffic intensity
d. Queue discipline
Answer : c)
19.Which of the following is used to know the probability that no one is in the system?
a. 1-λ/μ
b. λ/μ
c. λ/μ-λ
d. 1/μ-λ
Answer : a)
21.Which of the following is used to know the average number of customers in the queue system when
arrival rate is denoted by λ and service rate by u?
a. λ/μ
b. 1/(μ-λ)
c. λ/μ(μ-λ)
d. λ/(μ-λ)
Answer : d)
22.Which of the following is used to know the average time a customer spends in the queue system
when arrival rate is denoted by 2. and service rate by u?
a. λ/μ
b. 1/(μ-λ)
c. λ/μ(μ-λ)
d. λ/(μ-λ)
Answer : b)
24. Which of the following is not a key operating characteristic for a queuing system
a) Utilization factor
b) Percent idle time
c) Average time spent waiting in the system and queue
d) None
Answer : d)
28. Which of the cost estimated and performance measures are not used for economic analysis of a
queuing system
a) Cost per server per unit of time
b) Cost per unit of time for a customer waiting in the system
c) Average number of customer in the system
d) Average waiting time of customer in the system
Answer : d)
33. As per queue discipline, the following is not a negative behavior of a customer:
(a) Balking
(b) Reneging
c)Boarding
d) Collusion
Answer : c)
39. If the operating characteristics of a queue are dependent on time, then is said to be:
a) Transient state
b) Busy state
c) Steady-state
d) Explosive state
Answer : a)
12.What is the impact of a higher discount rate on the present worth of future costs?
(a) It increases the present worth.
(b) It decreases the present worth.
(c) It has no impact on the present worth.
(d) The impact depends on the lifespan of the asset.
Answer: (b)
13.Which of the following is NOT a typical assumption made in basic replacement analysis? (a) Future
costs and benefits can be reasonably estimated.
(b) The technology of the replacement asset will remain constant over its lifespan.
(c) The discount rate will remain constant over the study period.
(d) Inflation will significantly impact all cost components equally.
Answer: (d)
14. The capital recovery factor is used to:
(a) Calculate the present worth of a future sum.
(b) Calculate the future value of a present sum.
(c) Convert a present sum into a series of equal annual payments over a specified period.
(d) Calculate the interest rate.
Answer: (c)
17.In a situation where an asset fails suddenly and unexpectedly, the replacement decision is often
driven by:
(a) Economic analysis alone.
(b) The book value of the asset.
(c) The immediate need to restore operations.
(d) The availability of a technologically superior replacement.
Answer: (c)
18. Which of the following is a situation where a group replacement policy might be more economical
than individual replacement?
(a) When assets are expensive and have long individual lifespans.
(b) When assets are numerous, inexpensive, and failure of one leads to significant disruption.
(c) When maintenance costs are very high for individual assets.
(d) When the technology of the assets is rapidly changing.
Answer: (b)
20. Which of the following is a key input required for most replacement analysis techniques? (a) The
brand name of the asset.
(b) The color of the asset.
(c) The expected lifespan of the asset.
(d) The weight of the asset.
Answer: (c)
21. What is the primary focus when analyzing the replacement of an asset that fails gradually?
(a) Minimizing the initial investment cost of the new asset.
(b) Balancing the increasing operating and maintenance costs of the old asset with the cost of a new
one.
(c) Maximizing the resale value of the old asset.
(d) Ensuring uninterrupted operation at all costs.
Answer: (b)
22. In replacement analysis, what does the term "opportunity cost" refer to?
(a) The cost of missing out on a potential resale value.
(b) The cost of not replacing an asset sooner and incurring higher operating costs.
(c) The potential return that could be earned from investing the money used for a new asset elsewhere.
(d) The cost of training employees to use a new asset.
Answer: (c)
23.In the context of group replacement, what is a key factor to determine the optimal replacement
interval?
(a) The initial purchase cost of each individual item.
(b) The cost of individual replacement versus the cost of group replacement.
(c) The resale value of the items being replaced.
(d) The brand of the items being replaced.
Answer: (b)
24. In replacement analysis, a low salvage value at the end of an asset's life tends to:
(a) Make keeping the old asset more attractive.
(b) Make replacing the old asset sooner more attractive.
(c) Have no impact on the replacement decision.
(d) Increase the annual equivalent cost of the new asset.
Answer: (b)
25.When money value changes with time at 20%, the discount factor for the 2nd year is
(a) 1
(b)0.833
(c) 0
(d)0.6955
Answer: (b)
27.The type of failure that usually occurs in old age of the machine is
(a) Random failure
(b)Early failure
(c) Chance failure
(d)Wear - out failure
Answer: (d)
28.Which of the following is the correct assumption for replacement policy when money value does not
change with time?
(a) No Capital cost
(b) No scrap value
(c) Constant scrap value
(d Zero maintenance cost
Answer: (c)
UNIT-4
INVENTORY THEORY
1.Which of the following is not an inventory?
a. Machines
b. Raw material
c. Finished products
d. Consumable tools
Answer:a)
2.The following classes of costs are usually involved in inventory decisions except
a.Cost of ordering
b.Carrying cost
c.Cost of shortages
d. Machining cost
Answer :d)
3.The cost of insurance and taxes are included in
a.Cost of ordering
b.Set up cost
c.Inventory carrying cost
d.Cost of shortages
Answer :c)
7.The time period between placing an order its receipt in stock is known a
a. Lead time
b. Carrying time
c. Shortage time
d. Over time
Answer: a)
Where, D-Annual demand (units), S-Cost per order, h=Annual carrying cost per unit
Answer: a)
11.The order cost per order of an inventory is Rs. 400 with an annual carrying cost of Rs. 10 per unit. The
Economic Order Quantity (EOQ) for an annual demand of 2000 units is
a. 400
b. 440
c.480
d. 500
Answer: a
14. Costs incurred each time an order is placed are known as:
a) Holding costs.
b) Shortage costs.
c) Ordering costs.
d) Unit costs.
Answer: c)
15.The cost resulting from demand exceeding the available inventory is called:
a) Holding cost.
b) Ordering cost.
c) Setup cost.
d) Shortage cost.
Answer: d)
16. In the Economic Order Quantity (EOQ) model, which of the following assumptions is typically
made?
a) Demand is variable.
b) Lead time is uncertain.
c) Orders are received instantaneously.
d) Unit cost varies with order quantity.
Answer: c)
17. The EOQ formula aims to minimize the total _________________ costs.
a) Purchasing and production.
b) Ordering and holding.
c) Holding and shortage.
d) Ordering and shortage.
Answer: b)
21.In the EPQ model, the maximum inventory level is always _________________ the EOQ.
a) Equal to.
b) Greater than.
c) Less than.
d) Unrelated to.
Answer: c)
24. The average inventory level in the basic EOQ model is:
a) The order quantity.
b) Half of the order quantity.
c) Safety stock plus order quantity.
d) Annual demand divided by 2.
Answer: b)
26.In inventory models with probabilistic demand, the reorder point is calculated by adding safety stock
to the:
a) Average demand during lead time.
b) Maximum possible demand.
c) Economic Order Quantity.
d) Minimum possible demand.
Answer: a)
33.Which of the following is a key input for calculating the Economic Production Quantity (EPQ)?
a) Setup cost per production run.
b) Ordering cost per order.
c) Shortage cost per unit.
d) Transportation cost per unit.
Answer: a)
34. If the annual demand for an item doubles, the EOQ will:
a) Remain the same.
b) Double.
c) Increase by a factor of 2.
d) Decrease by a factor of 2.
Answer: c)
35.Which of the following is a qualitative factor that might influence inventory decisions?
a) Holding costs.
b) Ordering costs.
c) Supplier reliability.
d) Demand rate.
Answer: c)
36. Economic order quantity is that quantity at which cost of holding and carrying inventory is:
a) Maximum and equal
b) Minimum and equal
c) It can be maximum or minimum depending upon case to case
d) Minimum and unequal
Answer: b)
37. Which of the following describes the behavior of total ordering costs?
a) Rise as the order quantity rises
b) Equal the number of orders placed times the cost of placing an order
c) Rise as the average stock level rises
d) Fall with the per period usage rate
Answer: b)
38. Which of the following describe the behavior of total holding costs?
a) They always exceed total ordering costs.
b) They decline as the cost of the inventory item rises
c) Rise as the order quantity rises
d) They decline with the average stock level
Answer: c)
UNIT-5
JOB SEQUENCING
3. The total time required to complete all jobs in a system is known as:
a) Flow time.
b) Lateness.
c) Makespan.
d) Tardiness.
Answer: c)
4. The time a job spends in the system from arrival to completion is called:
a) Processing time.
b) Waiting time.
c) Flow time.
d) Completion time.
Answer: c)
5. The difference between the completion time and the due date of a job is:
a) Flow time.
b) Lateness.
c) Makespan.
d) Processing time.
Answer: b)
7. Which rule sequences jobs based on the shortest processing time first?
a) First-Come, First-Served (FCFS)
b) Shortest Processing Time (SPT)
c) Earliest Due Date (EDD)
d) Longest Processing Time (LPT)
Answer: b)
8. Which rule prioritizes jobs with the earliest promised delivery date?
a) First-Come, First-Served (FCFS)
b) Shortest Processing Time (SPT)
c) Earliest Due Date (EDD)
d) Longest Processing Time (LPT)
Answer: c)
10. The Longest Processing Time (LPT) rule is often used to:
a) Minimize the number of tardy jobs.
b) Maximize machine utilization, especially in parallel processing.
c) Reduce the average flow time.
d) Ensure fairness among jobs.
Answer: b)
13. In Johnson's rule, the job with the smaller processing time is scheduled:
a) Earlier, regardless of the machine.
b) Earlier if it's on the first machine, later if it's on the second.
c) Later if it's on the first machine, earlier if it's on the second.
d) Later, regardless of the machine.
Answer: b)
15. Which sequencing rule is most effective in minimizing the maximum tardiness?
a) FCFS
b) SPT
c) EDD
d) LPT
Answer: c)
16. The performance of a job sequencing rule can be evaluated based on metrics like:
a) Makespan, average flow time, and total cost.
b) Number of employees, machine efficiency, and profit margin.
c) Material usage, energy consumption, and customer satisfaction.
d) Production volume, inventory levels, and marketing spend.
Answer: a)
17. In job shop scheduling, which sequence of operation typically result in optimal resource utilization
and minimization of job waiting time:
a) FCFS(First come first serve)
b) SPT(Short processing time)
c) EDD(Earliest due date)
d) LPT (Longest processing time)
Answer: b)
18. Which of the following environments involves jobs flowing through a fixed sequence of machines?
a) Job shop.
b) Flow shop.
c) Open shop.
d) Flexible manufacturing system.
Answer: b)
20. Which environment is characterized by different jobs requiring processing on different machines in
different sequences?
a) Job shop.
b) Flow shop.
c) Open shop.
d) Cellular manufacturing.
Answer: a)
21.The total time required to complete all the jobs in a job sequence problem is known as ______
a) Processing time
b) Idle time
c) Elapsed time
d) Lead time
Answer: c)
22. Which of the following is an analytical method for solving job sequencing problems?
a) Shortest Processing Time (SPT) rule.
b) Earliest Due Date (EDD) rule.
c) Johnson's rule.
d) First-Come, First-Served (FCFS) rule.
Answer: c)
24. A critical ratio less than 1 indicates that the job is:
a) Ahead of schedule.
b) On schedule.
c) Behind schedule.
d) Of low priority.
Answer: c)
25. Which of the following is NOT a common assumption made in basic job sequencing problems?
a) Machines are continuously available.
b) Setup times are negligible.
c) Preemption is allowed.
d) Jobs are independent of each other.
Answer: c)
26. The process of rearranging jobs to optimize one or more objectives is known as:
a) Production planning.
b) Capacity planning.
c) Job sequencing.
d) Inventory control.
Answer: c)
27. In a two-machine flow shop using Johnson's rule, if a job has a shorter processing time on the
second machine, it should be placed:
a) Towards the beginning of the sequence.
b) Towards the end of the sequence.
c) In the middle of the sequence.
d) Its position doesn't matter.
Answer: b)
28. Which of the following rules is dynamic, meaning the priority of jobs can change as they are
processed?
a) SPT
b) EDD
c) Critical Ratio
d) LPT
Answer: c)
29. When setup times are significant and sequence-dependent, the simple sequencing rules may:
a) Perform better than more complex algorithms.
b) Still provide optimal solutions.
c) Lead to suboptimal schedules.
d) Become easier to implement.
Answer: c)
32.In a job sequencing problem, which of the following criteria is typicallyNOT considered for minimizing
completion time?
a) Earliest due date
b) Critical ratio
c) Shortest processing time
d) Latest due date
Answer: d)
33. If there are n jobs to be performed one at a time on each of m machine the possible sequences
would be:
a) (n!)m
b) (m!)n
c) nm
d) mn
Answer:a )
34. What is the maximum total profit
a) 190
b) 210
c) 180
d) 200
Answer:a )