0% found this document useful (0 votes)
40 views4 pages

Stock Requirements List

The Stock Requirement List is a crucial SAP report that provides real-time visibility into logistics by displaying demand and supply elements affecting material stock. Demand elements, represented as negative stock, include sales orders and planned independent requirements, while supply elements, shown as positive stock, encompass purchase requisitions and planned orders. This report is essential for various business functions beyond production, including sales, materials management, and inventory management.

Uploaded by

jatin.tiwari198
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views4 pages

Stock Requirements List

The Stock Requirement List is a crucial SAP report that provides real-time visibility into logistics by displaying demand and supply elements affecting material stock. Demand elements, represented as negative stock, include sales orders and planned independent requirements, while supply elements, shown as positive stock, encompass purchase requisitions and planned orders. This report is essential for various business functions beyond production, including sales, materials management, and inventory management.

Uploaded by

jatin.tiwari198
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Stock/Requirements List

The Stock requirement list is used to display the real time stock situation and all the demand and
supply elements. This is (arguably) the most important report for the logistics function in SAP as it
displays anything and everything happening in the logistics area. This is a dynamic list which displays
real time situation every time the report is executed using the Transaction Code: MD04.

Demand Elements: MRP elements which generates the requirement for the material stock and thus
credit (or reduce) the stock in the Plant or warehouse is called as Demand elements. Demand
Elements are, thus, represented as ‘-ve’ stock in Stock Requirement list (Transaction Code: MD04).

Some of the most common Demand elements which are displayed in MD04 are as follows:

• Concrete demands for Finished Goods from customer in terms of Sales order or schedule
lines

• Planned Independent Requirements for Finished Goods coming up from S&OP - Sales
forecast.

• Material Reservations

• Dependent Requirements for a Semi finished or Raw material.

Supply elements: MRP elements which fulfills the requirements and thus debit (or add) the stock in
the Plant or warehouse is called a supply element. Supply elements are represented with ‘+ve’ stock
in Stock Requirement list (Transaction Code: MD04).

Some of the most common Supply elements which are displayed in MD04 are as follows:

• Purchase Requisition for externally procured materials which are then converted to Purchase
order

• Planned order for inhouse produced materials which are subsequently converted to
Production order.

Figure 1: Stock Requirement List


The first row always displays the ‘Stock’ which is the current stock in the plant.

The stock requirement list displays various fields like Date, MRP Element, MRP Element data,
Rescheduling date, exception message, Receipt/Requirement Quantity, Available quantity, storage
location and production version. You can also display Vendor and customer.

Date displays the of the demand/supply element.

MRP Element displays the demand/supply element like independent requirement, planned order,
sales order, delivery, production order etc.

MRP Element data displays a lot of information for the MRP element like:

• The customer order number, delivery number, planned order number, production order
number etc.

• The requirement type for the Independent requirement like VSF, LSF etc. which displays if
the requirement is for make-to order or make-to stock scenario.

• If the planned order is firmed.

• Displays the production order number and order type. It also displays if the order has been
released.

Receipt/Requirement Quantity displays the quantity of the demand/supply element. Demand


elements quantities are displayed as negative while supply element quantities are displayed as
positive.

Available Quantity displays the net stock that would be available on a date based on demand &
supply elements.

The system generates the exception messages to attract Planner’s attention. The planner can double
click on the exception message and view the details of the exception message at the bottom of the
screen. In the Figure 1, we can see the exception message ‘10’ which means ‘Reschedule In’ which is
one of the most common exception messages a planner would observe. Another common exception
message is ‘15’ which means ‘Reschedule Out’. For rescheduling exception messages, system
proposes a date in the Rescheduling Date’ column.

Table below shows a list of exception messages available in Stock Requirement list together with the
selection groups:

Table: Exception messages

Selection Group Exception No. Exception Message

69 Recursive BOM components possible

1 2 New, and opening date in the past

5 Opening date in the past


3 New, and start date in the past

2 6 Start date in the past

63 Production start before order start

4 New, and finish date in the past

3 7 Finish date in the past

64 Production finish after order finish

1 Newly created order proposal

42 Order proposal has been changed

44 Order proposal re-exploded

46 Order proposal has been manually changed


4
61 Scheduling: Customizing inconsistent

62 Scheduling: Master data inconsistent

80 Reference to retail promotion

82 Item is blocked

50 No BOM exists

52 No BOM selected
5
53 No BOM explosion due to missing config.

55 Phantom assembly not exploded

25 Excess stock

26 Excess in individual segment

27 Excess Stock Applied to Superceding Mat.

27 Underdelivery tolerance

40 Coverage not provided by master plan

6 56 Shortage in the planning time fence

57 Disc. matl partly replaced by follow-up

58 Uncovered reqmt after effective-out date

59 Receipt after effective-out date

60 Disc., Rec. Applied to Superceding Mat.

70 Max. release qty - quota exceeded


96 Stock fallen below safety stock level

10 Reschedule in

15 Reschedule out
7
20 Cancel process

30 Plan process according to schedule

8 98 Abnormal end of materials planning

Figure 2: Order Report

You can click on the button ‘Show Overview Tree’ to display ‘Order Report as shown in Figure 2. You
can display all the components which are required for the order. This is a multilevel report which
displays the components and their receipt elements. The order report can help you determine any
potential issues in production of the assemblies or procurement of the components. The order
report can also be executed using the Transaction Code: MD4C.

There is a common misconception that Stock Requirement list is relevant for production planners or
production supervisor only. However, the fact is that MD04 is the most important report as it gives a
quick snapshot of everything happing within the supply chain. It displays information not only for
production but also from other business functions like sales and distribution, materials management,
inventory management, quality management etc.