0% found this document useful (0 votes)
103 views

CH 03 PP

This document contains 5 practice problems related to project management. Problem 1 involves drawing a network diagram for a construction project with 8 activities. Problem 2 involves finding the critical path for a network diagram with 5 activities. Problem 3 asks for the variance in completion time for the critical path found in Problem 2. Problem 4 involves calculating probabilities related to the expected completion time and standard deviation for a project. Problem 5 involves calculating the expected completion date, total normal cost, and cost to crash an activity to reduce the project time by 1 week, for a software development project with 7 activities.

Uploaded by

Sagar Pandey
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
103 views

CH 03 PP

This document contains 5 practice problems related to project management. Problem 1 involves drawing a network diagram for a construction project with 8 activities. Problem 2 involves finding the critical path for a network diagram with 5 activities. Problem 3 asks for the variance in completion time for the critical path found in Problem 2. Problem 4 involves calculating probabilities related to the expected completion time and standard deviation for a project. Problem 5 involves calculating the expected completion date, total normal cost, and cost to crash an activity to reduce the project time by 1 week, for a software development project with 7 activities.

Uploaded by

Sagar Pandey
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

1

Practice Problem: Chapter 3, Project Management



Problem 1:
The following represent activities in a major construction project. Draw the network to
represent this project.

Activity Immediate Predecessor
A -
B -
C A
D B
E B
F C, E
G D
H F, G


2
Problem 2:
Given the following Time Chart and Network Diagram, find the Critical Path.

Activity a m b t Variance
A 2 3 4 3 1/9
B 1 2 3 2 1/9
C 4 5 12 6 16/9
D 1 3 5 3 4/9
E 1 2 3 2 1/9




Problem 3:
What is the variance in completion time for the critical path found in Problem 2?

Problem 4:
A project has an expected completion time of 40 weeks and a standard deviation of 5
weeks. It is assumed that the project completion time is normally distributed.
(a) What is the probability of finishing the project in 50 weeks or less?
(b) What is the probability of finishing the project in 38 weeks or less?
(c) The due date for the project is set so that there is a 90% chance that the project will
be finished by this date. What is the date?



Problem 5:
3
Development of a new deluxe version of a particular software product is being
considered. The activities necessary for the completion of this project are listed in the
table below along with their costs and completion times in weeks.

Activity Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
Immediate
Predecessor
A 4 3 2,000 2,600 -
B 2 1 2,200 2,800 A
C 3 3 500 500 A
D 8 4 2,300 2,600 A
E 6 3 900 1,200 B, D
F 3 2 3,000 4,200 C, E
G 4 2 1,400 2,000 F

(a) What is the project expected completion date?
(b) What is the total cost required for completing this project on normal time?
(c) If you wish to reduce the time required to complete this project by 1 week, which
activity should be crashed, and how much will this increase the total cost?
4
ANSWERS:

Problem 1:



Problem 2:


Problem 3:

Total
variance =
variances of activities on critical path
Total
variance1/916/94/91/923/92.56 =+++==

23234.796 And1.6and2.561.6 933 o=====


5
Problem 4:

(a)
5040 Z2 5Xo ===

Therefore:
(X50)(Z2)0.97725 PP s=s=

(b)
X2 Z0.4 5o ===

Therefore:
(X38)P(Z0.4)0.34458 Ps=s=

(c) 90% Z 1.28 ( - ) / 40/ 5 _ o _ > = = =
Therefore:
1.28*54046.4weeks _=+=


Problem 5:

(a)


Project completion time is therefore t t t t t
A D E F G
+ + + + = + + + + = 4 8 6 3 4 25
(b) Total
cost$2,000$2,300$900$3,000$1,400$9,600 =++++=

(c) Crash D 1 week at an additional cost of
$2,600$2,300$300 $75 844 ==

You might also like