CMS Revision Final Edited

The document outlines various work items and production rates for the Shire Airfield upgrading project by the Ethiopian Construction Works Corporation. It details activities such as clearing, grubbing, excavation of soft and hard materials, backfilling, and installation of drainage systems, including the required labor and equipment for each task. Each work item includes production rates per day and per hour, along with utilization factors for labor and equipment.

Uploaded by

zeyineredwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views188 pages

CMS Revision Final Edited

The document outlines various work items and production rates for the Shire Airfield upgrading project by the Ethiopian Construction Works Corporation. It details activities such as clearing, grubbing, excavation of soft and hard materials, backfilling, and installation of drainage systems, including the required labor and equipment for each task. Each work item includes production rates per day and per hour, along with utilization factors for labor and equipment.

Uploaded by

zeyineredwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 188

ETHIOPIAN CONSTRUCTION WORKS CORPORATION

PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 21.01 Clearing and Grubbing Production rate (per SPD) : 1 - 1.2 Ha/day
Production rate (per Hour) : 0.125 - 0.15 Ha/hr

* 411 Activity No. in old CMS replaced by 21.01 Clearing & Grubbing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Operator 1 1.00 Dozer D8R 315 Hp 1 1.00
Helper 1 1.00
Construction Forman 1 0.2
Labor 1.00 1.00

*labor as time keeper


UF : Utilization Factor

1
1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 31.01.a Excavating Soft Material to any depth Production rate (per SPD) : 280- 320 m3/day

Production rate (per Hour) : 35 - 40 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 31.01.a Excavating Soft Material to any depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Helper 1 1.00 Roller 8 - 10 ton 1 0.15
Roller Opp. 1 0.15 Hand tools 2.00 1.00
Labourer 2 1.00
Structure Forman 1 0.2
laborer Forman 1.00 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 31.01.b. Excavating Hard Material to any depth Production rate (per SPD) : 120 - 150 m3/day

Production rate (per Hour) : 15 - 18.75 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 31.01.b. Excavating Hard Material to any depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box 0.02 Excavater Opp. 1 1.00 Excavater with Breaker 1.5 m3/330HP 1 1.00
Blasting Caps Ea 0.13 Wagondrill Opp. 1 1.00 Wagondrill with compressor 4500 kg 1 1.00
Wast Desposal m3 structure Forman 1 0.20
Helper 2 1.00
Labourer Forman 1 1.00
Labourer 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 32.02..a Back filling using the excavated Material Production rate (per SPD) : 150 - 180 M3/day

Production rate (per Hour) : 18.75 - 22.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Roller Opp. 1 1.00 Roller 8 - 10 Ton 1 1.00
Back hoe Loader 1 1.00 Water Truck 14,000 lit 1 0.25
Water T/Opp. 1 0.25 Back hoe Loader 1 1.00
Helper 2 0.38 Hand tools 5.00 1.00
Labourer 10 1.00
Laborer Forman 1.00 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 32.02.b. Back filling using imported selected material Production rate (per SPD) : 150 - 180 M3/day

Production rate (per Hour) : 18.75 - 22.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Select Material prod m3 1.25 Roller Opp. 1 1.00 Roller 8 - 10 Ton 1 1.00

Select Material Hauling m3 1.10 1.00 0.25


Back hoe Loader 1 Water Truck 14,000 lit 1

Dump Truck Opp. 1 0.20 Dump Truck 9 m3 1 0.20


Water T/Opp. 1 0.25 Back hoe Loader 1 1.00
Helper 2 0.38 Hand tools 5.00 1.00
Labourer 10 1.00
Labore Forman 1.00 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

31.03.a.i. Excavation for subsoil drainage


Work Item : systems, Excavation in soft material, om up to Production rate (per SPD) : 200 - 250 m3/day
1.5m
Production rate (per Hour) : 25 - 31.25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Helper 2 1.00 Roller 8 - 10 Ton 1 0.15
Labourer 2 1.00 Water pump ** 1 1.00
Roller Opp. 1 0.15 Hand Tools 2.00 1.00
Labrer Forman

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.03.a.ii. Excavation for subsoil drainage systems,
Work Item : Excavation in soft material, Exceeding 1.5m and up Production rate (per SPD) : 180 - 200 m3/day
3m
Production rate (per Hour) : 22.5 - 25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Helper 2 1.00 Roller 8 - 10 Ton 1 0.15
Labourer 2 1.00 Water pump ** 1 1.00
Roller Opp. 1 0.15 Hand Tools 2.00 1.00
Laborer Forman 1.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

31.03.b. EO item 31.03.a for excavation in hard


Work Item : Production rate (per SPD) : 80 - 100 M3/day
material irrespective of depth
Production rate (per Hour) : 10 - 12.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box 0.02 Excavater Opp. 1 1.00 Excavater with Breaker 1.5 m3/330HP 1 1.00
Blasting Caps Ea 0.13 Wagondrill Opp. 1 1.00 Wagondrill with Compressor 4500kg 1 1.00
Wast Desposal m3 1.25 Helper 6 1.00
Labourer Forman 1 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.04 Impermiable back filling to subsoil drainage
Work Item : Production rate (per SPD) : 150 - 180 M3/day
system
Production rate (per Hour) : 18.75 - 22.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Sect Material Prod. m3 1.25 Roller Opp. 1 1.00 Roller 8 - 10 Ton 1 1.00
Select Material Hauling m3 1.100 Excavater Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Water T/Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Helper 2 1.00 D/Truck 9 m3 1 0.20
Labourer 10 1.00
D/Truck Opp 1 0.20
Laborer Forman

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.08.b.i. 100mm dia. PVC pipes in subsoil drainage
Work Item : Production rate (per SPD) : 110 - 125 m/day
systems, Unsloted
Production rate (per Hour) : 13.75 - 15.63 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
100mm dia PVC Pipe m 1.02 Dump Truck Opp. 1 0.20 Dump Truck 9 m3 1 0.20
Laboure Forman 1 1.00 Hand Tools **
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.08.b.ii. 100mm dia. PVC pipes in subsoil drainage
Work Item : Production rate (per SPD) : 110 - 125 m/day
systems, Sloted
Production rate (per Hour) : 13.75 - 15.63 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
100mm dia PVC Pipe m 1.02 Dump Truck Opp. 1 0.20 Dump Truck 9 m3 1 0.20
Laboure Forman 1 1.00 Hand Tools **
Labourers 10 1.00
Helper(machinist) 1.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 32.01.a.i Excavation in soft material, 0m up to 1.5m Production rate (per SPD) : 300 - 350 m3/day

Production rate (per Hour) : 37.5 - 43.75 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.a.i Excavation in soft material, 0m up to 1.5m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Roller opp. 1 0.15 Roller 8 - 10 Ton 1 0.15
Structure Forman 1 0.20
Helper 1 1.00
Labourer 4 1.00
Laborer Forman 1 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.01.a.ii Excavation in soft material, Exceeding 1.5m
Work Item : Production rate (per SPD) : 200 - 250 m3/day
and up to 3m
Production rate (per Hour) : 25 - 31.25 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.a.ii Excavation in soft material, Exceeding 1.5m and up to 3m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Roller opp. 1 0.15 Roller 8 - 10 Ton 1 0.15
Structure Forman 1 0.20
Helper 2 1.00 Hand Tools 4 1.00
Labourer 4 1.00
Laborer Forman 1

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.01.a.iii Excavation in soft material, Extra in
Work Item : Production rate (per SPD) : 150 - 180 m3/day
increament of 1.5m
Production rate (per Hour) : 18.75 - 22.5 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.a.iii Excavation in soft material, Extra in increament of 1.5m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Roller opp. 1 0.15 Roller 8 - 10 Ton 1 0.15
Construction Forman 1 0.20 Water Pump 230 lit/min 1 1.00
Helper 2 1 Hand Tools 4 1.00
Water pump opp. 1 1
Labourer 4 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.01.b EO item 32.01 (a) for excavation in hard
Work Item : Production rate (per SPD) : 80 - 100 M3/day
material irrespective of depth
Production rate (per Hour) : 10 - 12.5 M3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.b EO item 32.01 (a) for excavation in hard material irrespective of depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box 0.02 Excavater Opp. 1 1.00 Excavater with Breaker 1.5 m3/33HP 1 1.00
Blasting Caps Ea 0.13 Wagon drill wtth compressor 4500kg 1 1.00
Wast Desposal m3 1.25 Wagon drill Opp. 1 1.00
Helper 3 1.00
Labourer 6 1.00
Labourer Forman 1 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Quary Rock Production for base, Surface, and
Work Item : Production rate (per SPD) : 360 - 550 M3/day
Concrete Aggregate
Production rate (per Hour) : 45 - 68.75 M3/hr

* 422 Activity No. Quarry rock Production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box 0.02 Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Blasting Caps Ea 0.13 W/drill Opp. 1 1.00 wagon Drill( Hydraulic) 10900kg 1 1.00
Excav opp 1 0.20 Excavator with Breaker 1.5m3/330HP 1 0.20
Quary Forman 1 1.00
Powder man 1 0.20
Helper 2 1.00
Labourer Forman 1 1.00
Labourer 10 0.50

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Quary Rock Hauling Production rate (per SPD) : 720 - 816 m3/day
Production rate (per Hour) : 90 - 102 m3/hr

* 423 Activity No. Quarry rock Hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Chain Loader Opp. 1 1.00 Chain Loader 2.5 - 3 m3 1 1.00
Quarry Truck Opp. 4 1.00 Quarry Truck 14 m3 4 1.00
Helper 1 1.00
Labourer 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Rock Crushing for Concrete Aggregate Production rate (per SPD) : 200 - 250 M3/day
Production rate (per Hour) : 25 - 31.5 M3/hr

* 424 Activity No. Concrete Aggregate Crushing in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Construction Forman 1.00 1.00 Crusher Plant 75 TPH 1 1.00
Crusher Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Generater Opp. 1 1.00 Welder 1 0.50
Loader Opp. 1 1.00
Labourer Forman 1 1.00
Mechanic II 1 1.00
Electrician II 1 1.00
Welder 1 0.50
Helper 2 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Class A Bedding Production rate (per SPD) : 14 - 16 m3/day
Production rate (per Hour) : 1.75 - 2 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type

Cement Qtl 3.80 1.00


Carpenter 2 1.00 Concrete Mixer 0.5 m3 1
Sand m3 0.40 1.00
Masson 4 1.00 Concrete Vib. 4 HP 1
Concrete Agg. m3 0.60 W/Truck Opp. 1 0.20 Water Truck 14,000 lit 1 0.20
Water lit 190.000 Con. Mixer Opp. 1 1.00 Dump Truck 9 m3 1 0.40
Dump Truck Opp. 1 0.40
Helper 2 1.00
Labourer 16 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Class B and C Bedding Production rate (per SPD) : 40 - 50 m3/day
Production rate (per Hour) : 5 - 6.25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Select Material m3 1.25 W/Truck Opp. 1 1.00 Water Truck 14,000 lit 1 1.00
Roller opp. 1 1.00 Roller 8 - 10 Ton 1 1.00
Helper 1 1.00
Labourer 8 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Pipe Production 900mm Production rate (per SPD) : 15.00 m/day
Production rate (per Hour) : 1.88 m/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 3 1.00 Water Truck 14,000 lit 1 0.50
Cement m3 Barsetter 4 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp 1 1.00 Concrete Vib. 4 HP 1 1.00
Concrete Agg. m3 Labourer Forman 1 0.50 Hand Tools ** 1.00
Water lit Helper 3 1.00
Labourer 15 1.00
1.00

UF : Utilization Factor 0.19


** As required 0.05
0.149

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Pipe Production Dia 1060 Production rate (per SPD) : 15.00 m/day
Production rate (per Hour) : 1.88 m/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 3 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Sand m3 Barsetter 4 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.50 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Pipe Production Dia 1220 Production rate (per SPD) : 15.00 m/day
Production rate (per Hour) : 1.88 m/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 3 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Sand m3 Barsetter 4 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.50 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.i.a. Concrete Pipe Culverts, on class A Bedding,
Work Item : Production rate (per SPD) : 25 - 30 m/day
900mm diam
Production rate (per Hour) : 3.12 - 3.75 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.i.a. Concrete Pipe Culverts, on class A Bedding, 900mm diam

Material Cost Labor cost Equipment


Material Unit Qty Title Qty UF
Equipment Type Capacity No UF
Type
Pipe Production No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class A Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.i.b. Concrete Pipe Culverts, on class A Bedding,
Work Item : Production rate (per SPD) : 25 - 30 m/day
1060mm diam
Production rate (per Hour) : 3.12 - 3.75 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.i.b. Concrete Pipe Culverts, on class A Bedding, 1060mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class A Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.i.c. Concrete Pipe Culverts, on class A Bedding,
Work Item : Production rate (per SPD) : 25 - 30 m/day
1220mm diam
Production rate (per Hour) : 3.12 - 3.75 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.i.c. Concrete Pipe Culverts, on class A Bedding, 1220mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class A Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.ii.a. Concrete Pipe Culverts, on class B Bedding,
Work Item : Production rate (per SPD) : 15.00 m/day
900mm diam
Production rate (per Hour) : 1.88 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.ii.a. Concrete Pipe Culverts, on class B Bedding, 900mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe Prod. No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class B Bedding m3 Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Production rate (per SPD) : 15.00 m/day
32.03.ii.b. Concrete Pipe Culverts, on class B Bedding,
Work Item : Production rate (per Hour) : 1.88 m/hr
1060mm diam

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.ii.b. Concrete Pipe Culverts, on class B Bedding, 1060mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe Prod. No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class B Bedding m3 Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.ii.c. Concrete Pipe Culverts, on class B Bedding,
Work Item : Production rate (per SPD) : 15.00 m/day
1220mm diam
Production rate (per Hour) : 1.88 m/day

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.ii.c. Concrete Pipe Culverts, on class B Bedding, 1220mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe Prod. No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class B Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Production rate (per SPD) : 15 - 20 M2/day
Work Item : Form Work for minor Structure Production rate (per Hour) : 1.87 - 2.5 M2/hr

* 457 Activity No.Form work minor in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Lumber m3 Carpenter II 3 1.00 Dump Truck 9 m3 1 0.20
Eucaliptuse pole Ea Labourer 10 1.00 Hand Tools ** 1.00
Nails Assorted Kg Dump Truck opp. 1 0.20

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.07.a.i. Cast insitu concrete and form work, Concrete
Work Item : including form work, Class 25/20 Concrete in class A Production rate (per SPD) : 18- 20 M3/day
Bedding
Production rate (per Hour) : 2.25 - 2.5 m3/hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 32.07.a.i. Cast insitu concrete and form work, Concrete including form work, Class 25/20 Concrete in class A Bedding

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement kg Structure Forman 1 0.20 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Labourer Forman 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 Carpenter 1 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 Masson 4 1.00 Dump Truck 9 m3 1 0.40
Class A Bedding m3 Water Truck opp. 1 0.50 Hand Tools ** 1.00
Water lit Concrete Mixer Opp. 1 1.00
Helper 4 1.00
Labourer 20 1.00
Dump Truck Opp. 1 0.40

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

32.07.a.ii. Cast insitu concrete and form work,


Work Item : Concrete including form work, Class 15/20 Concrete Production rate (per SPD) : 18 - 20 M3/day
in Blinding, Screeds and encasing of pipes

Production rate (per Hour) : 2.25 - 2.5 m3/hr

* 458 Activity No. class C concrete Minor in old CMS replaced by 32.07.a.i. Cast insitu concrete and form work, Concrete including form work, Class 25/20 Concrete in class A Bedding

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement kg Construction Forman 1 0.20 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Labourer Forman 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 Carpenter 1 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 Masson 4 1.00 Dump Truck 9 m3 1 0.40
Water lit Water Truck opp. 1 0.50 Loader 2.5 - 3 m3 1 0.20
Concrete Mixer Opp. 2 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 20 1.00
Dump Truck Opp. 1 0.40
Loader Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 300mm Pipe Production Production rate (per SPD) : 25.00 pipe/day
Production rate (per Hour) : 3.13 pipe/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 2 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.20
Sand m3 Barsetter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.20 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

32.20.a Survice Ducts, Service Duct 300mm dia.


Work Item : Production rate (per SPD) : 10.00 m/day
Reinforced concrete pipe, (Utility duct)

Production rate (per Hour) : 1.25 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
300mm Pipe No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Masson 2 1.00 Carier Truck 14,700 kg 1 0.30
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.30

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project 0.0765


33.01.a. Kerbing, class 25/20 concrete curbing
Work Item : Production rate (per SPD) : 150 - 180 M/day
(0.17m*0.45m)
Production rate (per Hour) : 18.75 - 22.5 M/hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 33.01.a. Kerbing, class 25/20 concrete curbing (0.17m*0.45m)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 0.306 Masson 6 1.00 Water Truck 14,000 lit 1 0.20
Sand m3 0.031 Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Lumber m2 0.450 Water Truck Opp. 1 0.20 Concrete Vib. 4 HP 2 1.00
Nails Assorted kg Con. Mixer Opp. 1 1.00 Hand Tools ** 1.00
Eucal. Pol Ea 1.00 Helper 4 1.00
Concrete Agg. M3 0.05 Labourer 20 1.00
Water lit

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Form Work for major structures' slab Production rate (per SPD) : 25.00 M2/day
Production rate (per Hour) : 3.13 M2/hr
Assume typical dimension = 14 m * 7m * 0.35m height =5m

* 465 Activity No. Form work major in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Lumber m2 1.000 Carpenter 20.00 1.00 Dump Truck 9 m3 1 1.00
Eucal.Pole Ea 1.00 D/Truck Operator 1.00 1.00 Hand tools ** 1.00
Nails Assorted Kg Labourer 60.00 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Formwork removal Production rate (per SPD) : 25 - 30 M2/day
Production rate (per Hour) : 3.12 - 3.75 M2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Carpenter 5.00 1.00 Handtools ** 1.00
Labourer 20.00 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Reinforcement Steel (Minor) Production rate (per SPD) : 275 - 300 Kg/day
Production rate (per Hour) : 34.375- 37.5 Kg/hr
1
* 455 A & B Activity No. Reinforcement steel minor in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcing Kg 1.10 Barestter 3.00 1.00 Hand tools ** 1.00
Binding Wire Kg 1.00 Helper 1.00 1.00
Labourer 10.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


33.08a. Concrete lining for open drains, Class 25/20
Work Item : Production rate (per SPD) : 140 - 160 m/day
concrete as per detail )
Production rate (per Hour) : 17.5 - 20 m/hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 33.08a. Concrete lining for open drains, Class 25/20 concrete as per detail

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.20
Cement m3 Masson 6 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Carpenter 1 1.00 Concrete Vibrater 4 HP 1 1.00
Concrete Agg. m3 Water Truck Opp. 1 0.20 Hand Tools ** 1.00
Water lit Con. Mixer Opp. 1 1.00
Helper 3 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

33.16.a. Paved drains in towns, U or Trapizoidal


Work Item : Production rate (per SPD) : 13.50 M3/day
shaped massonery drains in towns as per the drawing

Production rate (per Hour) : 1.69 M3/hr

* 456 Activity No. class B massonary Minor in old CMS replaced by 33.16.a. Paved drains in towns, U or Trapizoidal shaped massonery drains in towns as per the drawing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 1.25 Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 0.25 Masson 10 1.00 Quarry Truck 14 m3 1 0.50
Massonery Stone Prod. m3 1.25 Carpenter 1 1.00 Hand Tools ** 1.00
Water Truck Opp. 1 0.15
Quarry Truck Opp. 1 0.50
Helper 1 1.00
Labourer 22 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

33.16.b.i. Paved drains in towns, Class 25/20


reinforced concrete drains cover units including
Work Item : reinforcement and formwork as per detail, Pedesterian Production rate (per SPD) : 80-100 no/day
crossing cover as shown on the drawing (Ass.
1m*1.35m*.10m dimension)

Production rate (per Hour) : 8- 12.5 no/day

* 454 Activity No. class A concrete Minor in old CMS replaced by 33.16.b.i. Paved drains in towns, Class 25/20 reinforced concrete drains cover units including reinforcement and formwork as per detail,
Pedesterian crossing cover as shown on the drawing (Ass. 1m*1.35m*.10m dimension)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 4 1.00 Water Truck 14,000 lit 1 0.20
Cement Qtl Carpenter 1 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.20 Concrete Vibrater 4 HP 1 1.00
Concrete Agg. m3 Con. Mixer Opp. 1 1.00 Hand Tools ** 1.00
Water lit Helper 3 1.00 Loader 2.5m3 1.00 1.00
Formwork m2 Labourer 20 1.00
Loader Opp. 1 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

33.16.b.ii. Paved drains in towns, Class 25/20


reinforced concrete drains cover units including
Work Item : Production rate (per SPD) : 40- 50 no/day
reinforcement and formwork as per detail, Vehicle
crossing cover as shown on the drawing

Production rate (per Hour) : 5 - 6.25 no./hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 333.16.b.ii. Paved drains in towns, Class 25/20 reinforced concrete drains cover units including reinforcement and formwork as per detail,
Vehicle crossing cover as shown on the drawing(1*1.35*0.2)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 4 1.00 Water Truck 14,000 lit 1 0.20
Cement Qtl Carpenter 1 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.20 Concrete Vibrater 4 HP 1 1.00
Concrete Agg. m3 Con. Mixer Opp. 1 1.00 Hand Tools ** 1.00
Formwork Helper 3 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.01.b.i Grouted stone pitching, Grouted stone
Work Item : Production rate (per SPD) : 40- 45 M2/day
pitching at culverts
Production rate (per Hour) : 5- 5.625 M2/hr

* 471 Activity No. Paved waterway Grouted in old CMS replaced by 34.01.b.i Grouted stone pitching, Grouted stone pitching at culverts

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 10 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Water Truck Opp. 1 0.15 Quarry Truck 14 m3 1 0.30
Massonery Stone m3 Quarry Truck Opp. 1 0.30 Hand Tools ** 1.00
Helper 1 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.01.b.ii Grouted stone pitching, Grouted stone
Work Item : Production rate (per SPD) : 45 - 50 m2/day
pitching rural ditch
Production rate (per Hour) : 5.625 - 6.25 m2/hr

* 471 Activity No. Paved waterway Grouted in old CMS replaced by 34.01.b.ii Grouted stone pitching, Grouted stone pitching rural ditch

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 10 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Water Truck Opp. 1 0.15 Hand Tools ** 1.00
Massonery Stone prod m3 Helper 1 1.00
Massonery Stone Hauling m3 Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.01.b.iv Grouted stone pitching, Grouted stone
Work Item : Production rate (per SPD) : 40 - 45 M2/day
pitching at bridges
Production rate (per Hour) : 5 - 5.625 M2/hr

* 471 Activity No. Paved waterway Grouted in old CMS replaced by 34.01.b.iv Grouted stone pitching, Grouted stone pitching at bridges

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 10 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Water Truck Opp. 1 0.15 Hand Tools ** 1.00
Massonery Stone pro m3 Helper 1 1.00
Massonery Stone Hauling m3 Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.03.b. Stone masonery walls, Cement mortared stone
Work Item : Production rate (per SPD) : 15 - 18 m3/day
walls (1:3 mortar ratio)
Production rate (per Hour) : 1.87 - 2.25 m3/hr

* 456 Activity No. Class B Massonary in old CMS replaced by 34.03.b. Stone masonery walls, Cement mortared stone walls (1:3 mortar ratio)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Masson 10 1.00 Hand Tools ** 1.00
Massonery Stone Prod. m3 Carpenter 1 1.00
Massonery Stone Hauling. m3 Water Truck Opp. 1 0.15
Helper 1 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 41.01. Removal of Unsuitable Material Production rate (per SPD) : 1200 - 1500 m3/day
Production rate (per Hour) : 150 - 187.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Fesposal m3 1.25 Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Helper 1 1.00
Construction Forman 1.00 0.50

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


41.03.b. Road bed Preparation and the compaction of
Work Item : material, Compaction to 93% of modified AASHTO Production rate (per SPD) : 1000- 1200 m3/day
density
Production rate (per Hour) : 125 - 150 m3/hr

* 418, 419A & 419B Activity No. Road Bed Preparation in old CMS replaced by 41.03.b. Road bed Preparation and the compaction of material, Compaction to 93% of modified AASHTO density depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
m3 Construction Forman 1 0.50 Grader Komatsu 197 HP 1 1.00
Roller Opp. 1 1.00 Roller 14- 16ton 1 1.00
W/Truck Opp. 1 1.00 Dozer D8R 315 HP 1 0.20
Grader Opp. 1 1.00 W/Truck 14,000 lit 1 1.00
Dozer Opp. 1 0.20
Helper 3 1.00
Labourer 5 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


41.04.a. In situ treatment of road bed, in situ treatment
Work Item : Production rate (per SPD) : 700 - 800 m3/day
by ripping
Production rate (per Hour) : 87.5 - 100 m3/hr

* 418, 419A & 419B Activity No. Road Bed Preparation in old CMS replaced by 41.04.a. In situ treatment of road bed, in situ treatment by ripping

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Construction Forman 1 0.50 Grader Komatsu 197 HP 1 1.00
Roller Opp. 1 1.00 Roller 10 - 12 ton 1 1.00
W/Truck Opp. 1 1.00 Dozer D8R 315 HP 1 0.50
Grader Opp. 1 1.00 W/Truck 14,000 lit 1 1.00
Dozer Opp. 1 0.50
Helper 3 1.00
Labourer 5 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Borrow Material Production Production rate (per SPD) : 700 - 800 m3/day
Production rate (per Hour) : 87.5 - 100 m3/hr

* 421 B Activity No. Borrow material Production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Helper 1 1.00
Construction Forman 1 0.20

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Cap. 9m3

Work Item : Borrow Material Hauling Av.Dis 2 km Production rate (per SPD) : 2000 - 2400 m3/day
Av.Sp. 35 km/hr Production rate (per Hour) : 250 - 300 m3/hr
t for L/Unl 5m

* 413 B Activity No. Borrow material hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 7 1.00 Dump Truck 9 m3 7 1.00
Helper 1 1.00
Labourer 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

42.01.a. Cut and Borrow to fill, Material in layer


Work Item : thickness of 200mm and less compacted to 93% Production rate (per SPD) : 1300 - 1500 m3/day
modified AASHTO density

Production rate (per Hour) : 162.5 - 187.5 m3/hr

*412 A & 412 B Activity No. Common Excavation & Embankment in old CMS replaced by 42.01.a. Cut and Borrow to fill, Material in layer thickness of 200mm and less compacted to 93% modified
AASHTO density

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Grader Opp. 2 1.00 Dozer D8R 315 HP 1 1.00
Roller Opp. 2 0.80 Grader Komatsu 197 HP 2 1.00
Water Truck Opp. 2 1.00 Roller 14- 16 ton 2 0.80
Construction Forman 1 1.00 Water Truck 14,000 lit 2 1.00
Labourer Forman 1 1.00
Dozer Opp. 1 1.00
Labourer 15 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

42.01.b.ii. Improved subgrade or Capping layer,


Work Item : Improved subgrade layer compacted to 95% of Production rate (per SPD) : 1000 - 1200 m3/day
modified AASHTO density
Production rate (per Hour) : 125 - 150 m3/hr

*413 A & 417 Activity No. Borrow Excavation & Embankment & Borrow Placing in old CMS replaced by 42.01.b.ii. Improved subgrade or Capping layer, Improved subgrade layer compacted to 95% of
modified AASHTO density

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Borrow Mat prodn m3 1.25 Grader Opp. 2 1.00 Grader Komatsu 197 HP 2 1.00
Borrow Mat hauling m3 1.100 Roller Opp. 2 1.00 Roller 14 - 16ton 2 1.00
Water Truck Opp. 3 1.00 Water Truck 14,000 lit 3 1.00
Construction Forman 1 1.00
Labourer Forman 1 1.00
Labourer 20 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Cap. 9 m3

Work Item : Waste Desposal Av.Dis 3 km Production rate (per SPD) : 1400 - 1600 m3/day
Av.Sp. 25 Km/hr Production rate (per Hour) : 175 - 200 m3/hr
t for L/Unl 5m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 6 1.00 Dump Truck 9 m3 6 1.00
Helper 1 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


42.03.a. Cut to spoil material obtained from, Soft
Work Item : Production rate (per SPD) : 2000 - 2400 m3/day
excavation
Production rate (per Hour) : 250 - 300 m3/hr

*415 A & 415 B Activity No. Unclassified Excavation & Embankment in old CMS replaced by 42.03.a. Cut to spoil material obtained from, Soft excavation

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Dozer Opp. 2 1.00 Dozer D8R 315 HP 2 1.00
Construction Forman 1 0.50
Helpers 3 1.00
Labourer Forman 1 1.00
Labourers 2 1.00

UF : Utilization Factor remarks.The above condition works for only sideway spoiling. In other cases we have to consider efficiency

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


42.03.b. Cut to spoil material obtained from, Hard
Work Item : Production rate (per SPD) : 450 - 600 m3/day
excavation
Production rate (per Hour) : 56.25-75 m3/hr

*414 Activity No. Rock Excavation in old CMS replaced by 42.03.b. Cut to spoil material obtained from, Hard excavation

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box 0.0160 Construction Forman 1 0.50 Dozer D8R 315 HP 1 1.00
Blasting Caps Ea 0.083 Dozer Opp. 1 1.00 Wagon drill(Hydraulic) 10900kg 1 1.00
Excavater Opp. 1 1.00 Excavater with Breaker 1.5 m3/330HP 1 1.00
W/dill Opp. 1 1.00
Powder man 1 1.00
Helpers 3 1.00
Labourers 6 1.00

UF : Utilization Factor
remarks.The above condition works for only sideway spoiling. In other cases we have to consider efficiency

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Gravel Sub base Material Production Production rate (per SPD) : 600- 640 m3/day
Production rate (per Hour) : 75 - 80 m3/hr

*421 A Activity No. Select Material Production (Subbase) in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Helper 1 1.00
Labourer 2 1.00
Construction Forman 1.00 0.20

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : Gravel Sub base Material Hauling Cap. 14m3 Production rate (per SPD) : 1800 - 2000 m3/day
Av.Dis 10km Production rate (per Hour) : 225 - 250 m3/hr
Av.Sp. 40 km/hr
tfor L/Unl 5m

*431 Activity No. Select Material Hauling (Subbase) in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 11 1.00 Dump Truck 14 m3 11 1.00
Construction Forman 1 0.25
Labourers 3 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

51.01.a.ii. Unstablised gravel subbase compacted to 97


Work Item : % of modified AASHTO density layer thickness, Production rate (per SPD) : 700- 900 m3/day
150mm maximum layer thickness

Production rate (per Hour) : 87.5- 112.5 m3/hr

*432 Activity No. Select Material Placing (Subbase) in old CMS replaced by 51.01.a.ii. Unstablised gravel subbase compacted to 97 % of modified AASHTO density layer thickness, 150mm layer thickness

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Subbase Material produ. m3 1.25 Construction Forman 1 1.00 Grader Komatsu 197 HP 2 1.00
Subbase Material Hauling m3 1.10 Grader Opp. 2 1.00 Roller 14- 16 ton 2 1.00
Roller Opp. 2 1.00 W/Truck 14,000 lit 3 1.00
Water Truck Opp. 3 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 20 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Crushing of Base Course Material Production rate (per SPD) : 288 - 320 m3/day
Production rate (per Hour) : 36 - 40 m3/hr

*425 Activity No. Rock crushing for Base Course in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Quarry Material Production m3 1.25 Crusher Opp 1 1.00 Crusher Plant 75 TPH 1 1.00
Quarry Material Hauling m3 1.10 Generator Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Loader Opp. 1 1.00
Helper 1 2.00
Labourer 10 1.00
elec
mec

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Cap. 14m3
Project : Shire Airfield upgrading project Av.Dis 20 km

Work Item : Crushed Base Course Material Hauling Av.Sp. 60 km/hr Production rate (per SPD) : 1600 - 1800 m3/day

t for L/Unl 5m Production rate (per Hour) : 200 - 225 m3/hr

*433 Activity No. Base Course hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 12 1.00 Dump Truck 14 m3 12 1.00
Helper 1 1.00
Labourer 2 1.00
Labourer Forman 1 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Crushed Aggregate Base Course Mixing Production rate (per SPD) : 1000 - 1200 m3/day
Production rate (per Hour) : 125 - 150 m3/hr

*429 Activity No. Base Course material mixing in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
W/Truck Opp 1 1.00 W/Truck 14,000 m3 1 1.00
Helpers 2 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

52.01.b.ii. Crushed stone base compacted to 100% of


Work Item : modified AASHTO density, layer thickness 175mm or Production rate (per SPD) : 1200- 1400 m3/day
as shown on the drawing

Production rate (per Hour) : 150- 175 m3/hr

*434 A & 434 B Activity No. Select Material Placing in old CMS replaced by 52.01.b.ii. Crushed stone base compacted to 100% of modified AASHTO density, layer thickness 175mm or as shown on the
drawing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Base Course mixing m3 1.00 Grader Opp. 2 1.00 Grader Komatsu 197 HP 2 1.00
Base Course Hauling m3 1.100 Roller Opp. 2 1.00 Roller 14- 16ton 2 1.00
Base Course Crushing m3 1.00 W/Truck Opp 2 1.00 W/Truck 14,000 lit 2 1.00
Construction Foreman 1 1.00
Helper 4 1.00
Labourer 20 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

54.01.a. Gravel Shoulders Type 1 wearing course


Work Item : Production rate (per SPD) : 300 - 500 m3/day
compacted to 95% of modified AASHTO density

Production rate (per Hour) : 37.5 - 62.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Subbase Material prod. m3 1.25 Construction Forman 1 0.20 Grader Komatsu 197 HP 1 1.00
Subbase Material Hauling m3 1.100 Grader Opp. 1 1.00 Roller 10- 12ton 1 1.00
Roller Opp. 1 1.00 W/Truck 14,000 lit 1 1.00
Water Truck Opp. 1 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


61.01.a. Prime Coat, MC-30 cut back bitumen applied
Work Item : Production rate (per SPD) : 7,000.00 lit/day
at 0,8lit per sq.m
Production rate (per Hour) : 875.00 lit/hr

*437 Activity No. Prime coat application in old CMS replaced by 61.01.a. Prime Coat, MC-30 cut back bitumen applied at 0,8lit per sq.m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Asphalt MC-30 lit 7000.00 Asphalt dist. Opp 1 1.00 Asphalt Distributer 8000 lit 1.00 1.00
Power broom Opp. 1 0.50 Water Truck 14,000 lit 1.00 0.50
Water Truck Opp. 1 0.50 Power broom 1.00 0.50
Helpers 2 1.00
Labourers 6 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Rock Crushing for Surface Aggregate Production rate (per SPD) : 200 - 256 m3/day
Production rate (per Hour) : 25 - 32 m3/hr

*426 Activity No. Surface aggregate crushing in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Quarry Mat prodn m3 1.25 Construction Forman 1.00 1.00 Crusher Plant 75 TPH 1 1.00
Quarry Mat Hauling m3 1.100 Crusher Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Generater Opp. 1 1.00
Loader Opp. 1 1.00
Labourer Forman 1 1.00
Mechanic II 1 1.00
Electrician II 1 1.00
Welder 1 0.50
Helper 2 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project 116.666666666667


Work Item : Batch Plant Operation Production rate (per SPD) : 360 - 400 m3/day
Production rate (per Hour) : 45- 50 m3/hr

*442 Activity No. Batch Plant Operation in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Surface Agg Crushing m3 1.25 Batch plant opp. 1 1.00 Asphalt Plant 1200 kg/mix (100 TPH) 1 1.00
Aggregate Hauling m3 1.10 Loader opp. 1 1.00 Loader 2.5 - 3 m3 2 1.00
60/70 AC kg 75.00 Helpers 3 1.00 Welding Machine 400 A 1 1.00
Labourers 16 1.00 Generator 500 v 1 1.00
Generater opp. 1 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Cap. 9m3

Work Item : Asphalt Hot Mix Hauling Av. Dis 20 km Production rate (per SPD) : 360 - 400 m3/day
Av. Sp. 60 km/hr Production rate (per Hour) : 45- 50 m3/hr
t for L and Ul 5m

*443 Activity No. Asphalt mix hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
D/Truck Opp. 12 1.00 Dump Truck 9 m3 12 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

64.02.a.iii. Asphalt concrete surfacing course;


continuously graded course grading 50mm thick,
Work Item : Production rate (per SPD) : 257- 285 m3/day
asphalt concrete surface course with 60/70 penetration
grade bitumen
Specific Grav. Of Aspalt Mix Production rate (per Hour) : 32- 35 m3/hr
Opptimum Asphalt Content of 5.80%
Asphalt Content per M3 of the153.7Kg

*444 Activity No. Asphalt mix hauling in old CMS replaced by 64.02.a.iii. Asphalt concrete surfacing course; continuously graded course grading 50mm thick, asphalt concrete surface course with 60/70
penetration grade bitumen

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Batch plant operation m3 1.400 Paver Operater 1 1.00 Paver 120TPH (5m length) 1 1.00
Asphalt mix hauling m3 1.40 Roller Opp. 3 1.00 steel Roller 10 - 12 ton 2 0.50
Water Truck Opp. 1 1.00 Pneumatic Roller 24 ton 3 1.00
Helper 4 1.00 Water Truck 14,000 lit 1 1.00
Labourer Forman 1 1.00
Construction Forman 1 1.00
sensor man 2 1.00
Joint man 8 1.00
Labourers 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 64.07 Trial Sections Production rate (per SPD) : 1,500.00 m2/day
Production rate (per Hour) : 187.50 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Batch plant operation m3 105.000 Paver Operater 1 1.00 Paver 2000 kw/min (5m length) 1 1.00
Asphalt mix hauling m3 105.00 Roller Opp. 3 1.00 steel Roller 10 - 12 ton 1 1.00
Water Truck Opp. 1 1.00 Pneumatic Roller 24 ton 3 1.00
Helper 4 1.00 Water Truck 14,000 lit 1 1.00
Labourer Forman 1 1.00
Construction Forman 1 1.00
sensor man 2 1.00
Joint man 8 1.00
Material Inspecter 2 1.00
Labourers 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 64.08. 100mm diameter cores in asphaltic layers Production rate (per SPD) : 20.00 core/day
Production rate (per Hour) : 2.50 cor/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Material Inspecter 1 1.00 Core Cutter Machine 1 1.00
Helpers 4 1.00 hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Massonary Rock Production Production rate (per SPD) : 400 - 500 m3/day
Production rate (per Hour) : 50 - 62.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Opp 1 1.00 Dozer D8R 315 HP 1 1.00
Helpers 1 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Cap. 14 m3

Project : Shire Airfield upgrading project Av.Dis. 5 km

Work Item : Massonery Rock Hauling Av.Sp. 30 km/hr Production rate (per SPD) : 680 - 720 m3/day
t for L/Unl 5m Production rate (per Hour) : 85 - 90 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Chain Loader Opp. 1 1.00 Chain Loader 2.5 - 3 m3 1 1.00
Quarry Truck Opp 4 1.00 Quarry Truck 14 m3 4 1.00
Helpers 2 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Cap. 9m3

Project : Shire Airfield upgrading project Av.Dis 23km

Work Item : Sand Production and Hauling Av.Sp. 30 km/hr Production rate (per SPD) : 650 - 750 m3/day
t for L/Unl 5m Production rate (per Hour) : 81.25 - 93.75 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Construction Forman 1 0.25 Loader 2.5 - 3 m3 1 1.00
Loader Opp 1 1.00 Dump Truck 9 m3 12 1.00
Dump Truck Opp 12 1.00
Helper 1 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

81.02.a.i. Excavating Material with in the following


Work Item : Production rate (per SPD) : 280- 320 m3/day
succecive depth ranges, 0m up to 2m

Production rate (per Hour) : 35 - 40 m3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.a.i. Excavating Material with in the following succecive depth ranges, 0m up to 2m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Structure forman 1 0.20 Excavater 1.5 m3 1 1.00
Excavater Opp. 1 1.00 Roller 8 - 10 ton 1 0.20
Roller Opp. 1 0.20 Water Pump 230 lit/min 1 1.00
Helpers 3 1.00 Hand Tools ** 1.00
Labourers 5 1.00
Laborer forman 1 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

81.02.a.ii. Excavating Material with in the following


Work Item : Production rate (per SPD) : 280- 320 m3/day
succecive depth ranges, Exceeding 2m and up to 4m

Production rate (per Hour) : 35 - 40 m3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.a.ii. Excavating Material with in the following succecive depth ranges, Exceeding 2m and up to 4m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Structure forman 1 0.20 Excavater 1.5 m3 1 1.00
Excavater Opp. 1 1.00 Roller 8 - 10 ton 1 0.20
Roller Opp. 1 0.20 Water Pump 230 lit/min 1 1.00
Helpers 3 1.00 Hand Tools ** 1.00
Labourers 5 1.00
Laborer forman 1 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

81.02.a.iii. Excavating Material with in the following


Work Item : Production rate (per SPD) : 280- 320 m3/day
succecive depth ranges, Extra increment of 1m

Production rate (per Hour) : 35 - 40 m3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.a.iii. Excavating Material with in the following succecive depth ranges, Extra increment of 1m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 1.25 Structure forman 1 0.20 Excavater 1.5 m3 1 1.00
Excavater Opp. 1 1.00 Roller 8 - 10 ton 1 0.20
Roller Opp. 1 0.20 Water Pump 230 lit/min 1 1.00
Helpers 3 1.00 Hand Tools ** 1.00
Labourers 5 1.00
Laborer forman 1 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


81.02.b EO item 81.02. (a) for hard excavation
Work Item : Production rate (per SPD) : 120 - 150 M3/day
irrespective of depth
Production rate (per Hour) : 15 - 18.75 M3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.b EO item 81.02. (a) for hard excavation irrespective of depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box 0.02 Structure forman 1 0.50 Excavater/breaker 1.5 m3 1 0.50
Blasting Caps Ea 0.08 Excavater Opp. 1 0.50 Roller 8 - 10 m3 1 0.20
Wast Desposal m3 1.25 Roller Opp. 1 0.20 Wagon drill/compressor 4500kg 1 1.00

Wagon Drill Opp. 1 1.00 Hand Tools ** 1.00


Powder man 1 1.00
Helpers 2 1.00
Labourers 8 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 81.09.a. Foundation Fill, Rock Fill Production rate (per SPD) : 150 - 180 m3/day
Production rate (per Hour) : 18.75 - 22.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Quarry Rock prodn m3 1.25 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Quarry Rock Hauling m3 1.100 Helper 2 1.00 Hand Tools ** 1.00
Labourer 6 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Production rate (per SPD) : 15 - 18 M2/day
Work Item : 82.01.a. Form Works to Provide all class of finishes Production rate (per Hour) : 1.87 - 2.25 M2/hr
(Assuming 5cm lumber thickness)
* 465 Activity No.Form work minor in old CMS replaced by 82.01.a. Form Works to Provide all class of finishes (Assuming 5cm lumber thickness)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Lumber m3 1.000 Carpenter II 3 1.00 Dump Truck 9 m3 1 0.40
Eucaliptuse pole Ea 1.0000 Labourer 10 1.00 Hand Tools ** 1.00
Nails Assorted Kg Dump Truck opp. 1 0.40

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


83.01.a. Steel reinforcement for structures, Mild steel
Work Item : Production rate (per SPD) : 300- 400 Kg/day
bars (Grade 300)
Production rate (per Hour) : 37.5 - 50 Kg/hr

*463 Activity No. Reinforcement Steel major in old CMS replaced by 83.01.a. Steel reinforcement for structures, Mild steel bars (Grade 300)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcing bars kg 1.10 Barsetter 4.00 1.00 Bar Cutting torch 2 1.00
Binding wire kg Cutting torch opp. 2.00 1.00 Hand Tools ** 1.00
Helper 1.00 1.00
Labourer 10.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


83.01.b. Steel reinforcement for structures, Mild steel
Work Item : Production rate (per SPD) : 250 - 350 Kg/day
bars (Grade 420)
Production rate (per Hour) : 31.25 - 43.75 Kg/hr

*463 Activity No. Reinforcement Steel major in old CMS replaced by 83.01.b. Steel reinforcement for structures, Mild steel bars (Grade 420)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcing bars kg 1.10 Barsetter 4.00 1.00 Bar Cutting torch 2 1.00
Binding wire kg Cutting torch opp. 2.00 1.00 Hand Tools ** 1.00
Helper 1.00 1.00
Labourer 10.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.01.a.i. Cast in situ concrete, Class C-30 in all super
Work Item : structure parts, abutment back wall and walls Production rate (per SPD) : 20- 30 m3/day
foundation
Production rate (per Hour) : 2.5- 3.75 m3/hr

*462 Activity No. Class A Concrete major in old CMS replaced by 84.01.a.i. Cast in situ concrete, Class C-30 in all super structure parts, abutment back wall and walls foundation

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 4.50 Structure Forman 1 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 0.40 Carpenter 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 0.60 Masson 10 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 1.100 W/Truck Opp. 1 0.50 Dump Truck 9 m3 1 0.50
Loader Opp. 1 0.50 Loader 2.5 - 3 m3 1 0.50
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 0.50
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 30 1.00

UF : Utilization Factor
** As required

PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.01.a.ii. Cast in situ concrete, Class C-20/25 in
Work Item : Production rate (per SPD) : 20 - 30 m3/day
abutment and walls footing pads
Production rate (per Hour) : 2.5- 3.75 m3/hr

*462 Activity No. Class A Concrete major in old CMS replaced by 84.01.a.ii. Cast in situ concrete, Class C-20/25 in abutment and walls footing pads

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 3.80 Structure Forman 1 0.50 Concrete Mixer 0.5 m3 1 1.00
Sand m3 0.40 Carpenter 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 0.60 Masson 10 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 1.100 W/Truck Opp. 1 0.50 Dump Truck 9 m3 1 0.50
Loader Opp. 1 0.50 Loader 2.5 - 3 m3 1 0.50
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 0.50
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 30 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.01.a.iii. Cast in situ concrete, Class C-15/19
Work Item : Production rate (per SPD) : 20- 30 m3/day
concrete in blinding
Production rate (per Hour) : 2.5 - 3.75 m3/hr

*466 Activity No. Class C Concrete major in old CMS replaced by 84.01.a.iii. Cast in situ concrete, Class C-15/19 concrete in blinding

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 3.52 Structure Forman 1 0.25 Concrete Mixer 0.5 m3 1 1.00
Sand m3 0.40 Carpenter 1 1.00 Concrete Vib. 4 HP 1 1.00
Concrete Agg. m3 0.60 Masson 10 1.00 Water Truck 14,000 lit 1 0.30
Form Work m3 1.100 W/Truck Opp. 1 0.30 Dump Truck 9 m3 1 0.50
Loader Opp. 1 0.30 Loader 2.5 - 3 m3 1 0.30
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 0.50
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 20 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.06 Approach slab for Bridges class C-25/29
Work Item : Concrete, Approach slabs for new bridges of class Production rate (per SPD) : 20 - 30 m3/day
C25/19Concrete
Production rate (per Hour) : 2.5- 3.75 m3/hr

*462 Activity No. Class A Concrete major in old CMS replaced by 84.06 Approach slab for Bridges class C-25/29 Concrete, Approach slabs for new bridges of class C25/19Concrete

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 4.00 Structure Forman 1 0.25 Concrete Mixer 0.5 m3 1 1.00
Sand m3 0.40 Carpenter 1 1.00 Concrete Vib. 4 HP 1 1.00

Concrete Agg. m3 0.60 1.00 0.30


Masson 10 Water Truck 14,000 lit 1
Form Work m3 1.100 W/Truck Opp. 1 0.30 Dump Truck 9 m3 1 0.50
Loader Opp. 1 0.30 Loader 2.5 - 3 m3 1 0.30
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 0.50
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 20 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 87.03.i. Bridge Bearings, Supply and installation of Production rate (per SPD) : 8.00 m/day
Elastomeric Bearings as shown on the drawing,
Elastomeric Bearing
Production rate (per Hour) : 1.00 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Elastomeric Bearing Ea Labourers 4.00 1.00 D/Truck 9 m3 1.00 0.15
Dump Truck Opp. 1.00 0.15

1
UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


87.07. Concrete Bridge Parapets/Railings, Class C-
Work Item : Production rate (per SPD) : 80 - 90 m/day
30/25 Concrete
Production rate (per Hour) : 10 - 11.25 m/hr

*478 Activity No. Bridge Railing Concrete in old CMS replaced by 87.07. Concrete Bridge Parapets/Railings, Class C-30/25 Concrete

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg 1.58 Masson 4 1.00 Water Truck 14,000 lit 1 0.50
Cement Qtl 4.50 Carpenter 2 1.00 Con. Mixer 0.5 m3 1 1.00
Sand m3 0.40 W/Truck Opp. 1 0.50 Con. Vibrater 4 HP 1 1.00
Concrete Agg. m3 0.600 Con. Mix. Opp. 1 1.00 Dump Truck 9 m3 1 0.30
Form Work m3 1.10 Bar Setter 1 1.00 Hand Tools ** 1.00
Dump Truck 1 0.30
Labourer 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

87.13.a.i Installation of Expanition Joint, including


Work Item : Production rate (per SPD) : 10.00 m/day
20mm compressible joint filler board

Production rate (per Hour) : 1.25 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Expanition Joint m Labourer 5 1.00 Dump Truck 9 m3 1 0.15
Dump Truck Opp 1 0.15 Hand Tools **

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

89.01.b.i. Stone Massonery Structures, Class B


Work Item : Cement Mortared Stone Massonery walls (1:3 Mortar Production rate (per SPD) : 17.00 m3/day
ratio) for culverts and other mislaneaous structures

Production rate (per Hour) : 2.13 m3/hr

*464 Activity No. Class B Massonary major in old CMS replaced by 89.01.b.i. Stone Massonery Structures, Class B Cement Mortared Stone Massonery walls (1:3 Mortar ratio) for culverts and other
mislaneaous structures

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 1.25 Structure forman 1 0.20 Water Truck (14000lit) 14,000 lit 1 0.15
Sand M3 0.35 Masson Forman 1 1.00 Dump Truck 9 m3 1 0.15
Massonary Rock M3 1.25 Masson 10 1.00 Hand Tools ** 1.00
Equaliptuse Ea Carpenter 1 1.00
Water Truck Opp. 1 0.15
Dump Truck Opp. 1 0.15
Helpers 2 0.15
Labourers 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

89.01.b.ii. Stone Massonery Structures, Class B


Work Item : Cement Mortared Stone Massonery walls (1:3 Mortar Production rate (per SPD) : 18 - 20 m3/day
ratio) for Construction of RW, Check dams

Production rate (per Hour) : 2.25 - 2.5 m3/hr

*464 Activity No. Class B Massonary major in old CMS replaced by 89.01.b.ii. Stone Massonery Structures, Class B Cement Mortared Stone Massonery walls (1:3 Mortar ratio) for Construction of RW,
Check dams

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl 1.25 Structure forman 1 0.20 Water Truck (14000lit) 14,000 lit 1 0.15
Sand M3 0.35 Masson Forman 1 1.00 Dump Truck 9 m3 1 0.15
Massonary Rock M3 1.25 Masson 10 1.00 Hand Tools ** 1.00
Equaliptuse Ea Carpenter 1 1.00
Water Truck Opp. 1 0.15
Dump Truck Opp. 1 0.15
Helpers 2 0.15
Labourers 20 1.00
Laborer forman

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 89.03. Repointing of existing Massonery walls Production rate (per SPD) : 20 - 25 m2/day

Production rate (per Hour) : 2.5 - 3.12 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.15
Sand M3 Masson 2 1.00 Dump Truck 9 m3 1 0.15
Water Truck Opp. 1 0.15 Hand Tools ** 1.00
Dump Truck Opp. 1 0.15
Helper 1 1.00
Labourers 6 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


91.03.a.ii. Galvanized Gabion boxes, 80*100 mesh
Work Item : Production rate (per SPD) : 10.00 m3/day
size, 1*1*1
Production rate (per Hour) : 1.25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Gabion Boxes no 1.00 Loader Opp. 1 0.40 Loader 2.5 - 3 m3 1.00 0.40
Massonery Stone Prod. m3 1.25 Dump Truck Opp 1 0.40 Dump Truck 9 m3 1.00 0.40
Massonery Stone Hauling m3 1.10 Masson 2 1.00
Helper 1 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 92.01.a. Delinaters Production rate (per SPD) : 25.00 no/day
Production rate (per Hour) : 3.13 no/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 2 1.00 Water Truck 14,000 lit 1 0.15
Cement Qtl Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.15 Concrete vib. 4 HP 1 1.00
Concrete Agg. m3 Con, Mixer Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Water lit Bar Setter 1 1.00 Hand Tools ** 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


92.01.b. Concrete Guide post (1.1m*0.24m*0.24m),
Work Item : Production rate (per SPD) : 20.00 no/day
C-25/20
Production rate (per Hour) : 2.50 no/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 2 1.00 Water Truck 14,000 lit 1 0.15
Cement Qtl 0.24 Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00

Sand m3 0.15 1.00


Water Truck Opp. 1 Concrete vib. 4 HP 1
Concrete Agg. m3 Con, Mixer Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Water lit Bar Setter 1 1.00 Hand Tools ** 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


92.01.c. Concrete Kilometer Posts
Work Item : Production rate (per SPD) : 18.00 no/day
(1.6m*0.24m*0.24m), C-25/20
Production rate (per Hour) : 2.25 no/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 2 1.00 Water Truck 14,000 lit 1 0.15
Cement Qtl Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.15 Concrete vib. 4 HP 1 1.00
Concrete Agg. m3 Con, Mixer Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Water lit Bar Setter 1 1.00 Hand Tools ** 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 93.01. Galvanized Guardrails on steel posts, complete Production rate (per SPD) : 30.00 m/day

Production rate (per Hour) : 3.75 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Galvanizes Steel posts m Dump Truck Opp 1 0.20 Dump Truck 9 m3 1 0.20
Carpenter 1 1.00 Welding Machine 800 A 1 0.50
Welder 1 0.50 Hand tools ** 1.00
Labourers 5 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 94.01.a. Road signs, Area not Exceeding 2m2 Production rate (per SPD) : 2.00 m2/day
Production rate (per Hour) : 0.25 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
2mm thick Aluminium plate m2 Skilled Person 1 1.00 Dump Truck 9 m3 1 0.50
Paint lit Labourers 5 1.00 Hand Tools ** 1.00

Reflective Road Sign Ea

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


94.01.b. Road signs, Area Exceeding 2m2 but not
Work Item : Production rate (per SPD) : 1.00 m2/day
exceeding 10m2
Production rate (per Hour) : 0.13 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
2mm thick Aluminium plate m2 Skilled Person 1 1.00 Dump Truck 9 m3 1 0.50
Paint lit Labourers 5 1.00 Hand Tools ** 1.00

Reflective Road Sign Ea

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.a.i. Road Trafic Markings and Road Stud, Center


Work Item : line marking with white thermoplastic road marking Production rate (per SPD) : 180.00 m/day
paint, 100mm wide continuous line

Production rate (per Hour) : 22.50 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint m3 Paint car opp. 1 1 Dump Truck 9 m3 1 0.20
Labourers 10 1 Painting Car 1 1.00
Helper 1 1 Hand Tools ** 1.00
Dump Truck Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.a.ii. Road Trafic Markings and Road Stud,


Work Item : Center line marking with white thermoplastic road Production rate (per SPD) : 180.00 m/day
marking paint, 100mm wide brocken line

Production rate (per Hour) : 22.50 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint m3 Paint car opp. 1 1 Dump Truck 9 m3 1 0.20
Labourers 10 1 Painting Car 1 1.00
Helper 1 1 Hand Tools ** 1.00
Dump Truck Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.ba.i. Road Trafic Markings and Road Stud,


Work Item : Eadge marking with yellow thermoplastic road Production rate (per SPD) : 180.00 m/day
marking paint, 100mm wide Continous/brocken line

Production rate (per Hour) : 22.50 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint m3 Paint car opp. 1 1 Dump Truck 9 m3 1 0.20
Labourers 10 1 Painting Car 1 1.00
Helper 1 1 Hand Tools ** 1.00
Dump Truck Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.c. Road Trafic Markings and Road


Stud,Lettering Symbols, Traverse lines, painted island,
Work Item : Production rate (per SPD) : 10.00 m/day
and arrested markings (white or yellow colour as
directed by the Engineer)

Production rate (per Hour) : 1.25 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint lit Skilled Person 2.00 1.00 Hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

96.03.a. Grassing, Grassing includes preparation of


grassing area with top soiling, stockpiling of top soil,
Work Item : Production rate (per SPD) : 1,000.00 m2/day
and providing and applying chemical fertilizers,
seeding, and planting the grass cutting, all complete

Production rate (per Hour) : 125.00 m2/day

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Top soil m3 Skilled Person 1 1.00 Dump Truck 9 m3 1 0.40
Lime ton Labourer 10 1.00 Hand Tools ** 1.00

Super Phosphate ton Dump Truck Opp. 1 0.40

Limestone Ammonium Nitrate ton

Planting og grass cuttings m2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

96.03.b. Grassing, Planting of trees (Neem tree


(Azadirachta indica) Bosilia papyyrifera, Acacia seyal
and/or other approved local trees) by the road side in .6
dia. Holes, 1m deep dug in the ground, mixing the soil
Work Item : Production rate (per SPD) : 30.00 Ea/day
with decayed farm yard/sludge manure planting the
saplings, backfilling the trench, watering, fixing the
tree guardfixing the tree guard and maitaining the plant
for one year, all complete

Production rate (per Hour) : 3.75 Ea/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Trees Ea Labourers 10 1.00 Dump Truck 9 m3 1 0.15
Dump Truck Opp. 1 0.40 Hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 21.01 Clearing and Grubbing Production rate (per SPD) : 1.3 - 1.5 Ha/day
Production rate (per Hour) : 0.16 - 0.19 Ha/hr

* 411 Activity No. in old CMS replaced by 21.01 Clearing & Grubbing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Operator 1 1.00 Dozer D8R 315 Hp 1 1.00
Helper 1 1.00

con.form

UF : Utilization Factor

1
1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 31.01.a Excavating Soft Material to any depth Production rate (per SPD) : 200 - 250 m3/day

Production rate (per Hour) : 25 - 31.25 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 31.01.a Excavating Soft Material to any depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Helper 1 1.00 Roller 8 - 10 ton 1 0.15
Roller Opp. 1 0.15
Labourer 2 1.00
conf.form

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 31.01.b. Excavating Hard Material to any depth Production rate (per SPD) : 80 - 100 m3/day

Production rate (per Hour) : 10 - 12.5 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 31.01.b. Excavating Hard Material to any depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box Excavater Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Blasting Caps Ea Wagondrill Opp. 1 1.00 Wagondrill 10,900 kg 1 1.00
Wast Desposal m3 Jack Hammer Opp. 1 0.50 Compresser 9 kg/m3 1 1.00
Helper 3 1.00 Jack Hammer 330 HP 1 0.50
Labourer Forman 1 1.00
Labourer 4 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 32.02..a Back filling using the excavated Material Production rate (per SPD) : 150 - 180 M3/day

Production rate (per Hour) : 18.75 - 22.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Roller Opp. 1 1.00 Roller 8 - 10 Ton 1 1.00
Excavater Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Dump Truck Opp. 1 0.20 Dump Truck 9 m3 1 0.20
Water T/Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Helper 3 1.00
Labourer 10 1.00
con.form

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 32.02.b. Back filling using imported selected material Production rate (per SPD) : 150 - 180 M3/day

Production rate (per Hour) : 18.75 - 22.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Select Material m3 Roller Opp. 1 1.00 Roller 8 - 10 Ton 1 1.00

Excavater Opp. 1 0.50 Water Truck 14,000 lit 1 0.15

Dump Truck Opp. 1 0.20 Dump Truck 9 m3 1 0.20


Water T/Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Helper 3 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

31.03.a.i. Excavation for subsoil drainage


Work Item : systems, Excavation in soft material, om up to Production rate (per SPD) : 200 - 250 m3/day
1.5m
Production rate (per Hour) : 25 - 31.25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Helper 1 1.00 Roller 8 - 10 Ton 1 0.15
Labourer 2 1.00 Water pump 230 lit/min 1 1.00
Roller Opp. 1 0.15 Hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.03.a.ii. Excavation for subsoil drainage systems,
Work Item : Excavation in soft material, Exceeding 1.5m and up Production rate (per SPD) : 180 - 200 m3/day
3m
Production rate (per Hour) : 22.5 - 25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Helper 1 1.00 Roller 8 - 10 Ton 1 0.15
Labourer 2 1.00 Water pump 230 lit/min 1 1.00
Roller Opp. 1 0.15 Hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

31.03.b. EO item 31.03.a for excavation in hard


Work Item : Production rate (per SPD) : 80 - 100 M3/day
material irrespective of depth
Production rate (per Hour) : 10 - 12.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box Excavater Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Blasting Caps Ea Wagondrill Opp. 1 1.00 Wagondrill 10,900 kg 1 1.00
Wast Desposal m3 Helper 6 1.00 Compresser 9 kg/m3 1 1.00
Jack Hammer Opp. 1 0.50 Jack Hammer 330 HP 1 0.50
Labourer Forman 1 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.04 Impermiable back filling to subsoil drainage
Work Item : Production rate (per SPD) : 150 - 180 M3/day
system
Production rate (per Hour) : 18.75 - 22.5 M3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Sect Material Prod. m3 Roller Opp. 1 1.00 Roller 8 - 10 Ton 1 1.00
Select Material Haulingm3 Excavater Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Water T/Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Helper 3 1.00 D/Truck 9 m3 1 0.20
Labourer 10 1.00
D/Truck Opp 1 0.20

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.08.b.i. 100mm dia. PVC pipes in subsoil drainage
Work Item : Production rate (per SPD) : 110 - 125 m/day
systems, Unsloted
Production rate (per Hour) : 13.75 - 15.63 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
100mm dia PVC Pipe m Dump Truck Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Laboure Forman 1 1.00 Hand Tools **
Labourers 10 1.00
tradesman

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


31.08.b.ii. 100mm dia. PVC pipes in subsoil drainage
Work Item : Production rate (per SPD) : 110 - 125 m/day
systems, Sloted
Production rate (per Hour) : 13.75 - 15.63 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
100mm dia PVC Pipe m Dump Truck Opp. 1 0.50 Dump Truck 9 m3 1 0.50
Laboure Forman 1 1.00 Hand Tools **
Labourers 10 1.00
tradesman

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 32.01.a.i Excavation in soft material, 0m up to 1.5m Production rate (per SPD) : 200 - 250 m3/day

Production rate (per Hour) : 25 - 31.25 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.a.i Excavation in soft material, 0m up to 1.5m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Roller opp. 1 0.02 Roller 8 - 10 Ton 1 0.15
Construction Forman 1 0.02 Water Pump 230 lit/min 3 0.50
Helper 2 1.00
Water pump opp. 3 0.30
Labourer 4 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.01.a.ii Excavation in soft material, Exceeding 1.5m
Work Item : Production rate (per SPD) : 180 - 200 m3/day
and up to 3m
Production rate (per Hour) : 22.5 - 25 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.a.ii Excavation in soft material, Exceeding 1.5m and up to 3m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Roller opp. 1 0.15 Roller 8 - 10 Ton 1 0.15
Construction Forman 1 0.20 Water Pump 230 lit/min 1 1.00
Helper 2 1.00 Hand Tools ** 1.00
Water pump opp. 1 1.00
Labourer 4 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.01.a.iii Excavation in soft material, Extra in
Work Item : Production rate (per SPD) : 150 - 180 m3/day
increament of 1.5m
Production rate (per Hour) : 18.75 - 22.5 m3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.a.iii Excavation in soft material, Extra in increament of 1.5m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Roller opp. 1 0.15 Roller 8 - 10 Ton 1 0.15
Construction Forman 1 0.20 Water Pump 230 lit/min 1 1.00
Helper 2 1 Hand Tools ** 1.00
Water pump opp. 1 1
Labourer 4 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.01.b EO item 32.01 (a) for excavation in hard
Work Item : Production rate (per SPD) : 80 - 100 M3/day
material irrespective of depth
Production rate (per Hour) : 10 - 12.5 M3/hr

* 451 Activity No. Structural Excavation minor in old CMS replaced by 32.01.b EO item 32.01 (a) for excavation in hard material irrespective of depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box Excavater Opp. 1 0.50 Excavater 1.5 m3 1 0.50
Blasting Caps Ea Jack Hammer opp. 1 0.50 Compresser 9 kg/m3 1 1.00
Wast Desposal m3 Wagon drill Opp. 1 1.00 Wagon drill 10,900kg 1 1.00
Helper 3 1.00 Jack Hammer 330 HP 1 0.50
Labourer 6 1.00
Labourer Forman 1 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Quary Rock Production for base, Surface, and
Work Item : Production rate (per SPD) : 360 - 550 M3/day
Concrete Aggregate
Production rate (per Hour) : 45 - 68.75 M3/hr

* 422 Activity No. Quarry rock Production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Blasting Caps Ea W/drill Opp. 1 1.00 Air Compresser 9 kg/m3 1 1.00
Quary Forman 1 1.00 W/drll 10,900 kg 1 1.00
Powder man 1 1.00
Helper 2 1.00
Labourer Forman 1 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Quary Rock Hauling Production rate (per SPD) : 720 - 816 m3/day
Production rate (per Hour) : 90 - 102 m3/hr

* 423 Activity No. Quarry rock Hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Chain Loader Opp. 1 1.00 Chain Loader 2.5 - 3 m3 1 1.00
Quarry Truck Opp. 4 1.00 Quarry Truck 14 m3 4 1.00
Helper 1 1.00
Labourer 2 1.00
Quary Forman 1 0.50

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Rock Crushing for Concrete Aggregate Production rate (per SPD) : 180 - 200 M3/day
Production rate (per Hour) : 22.5 - 25 M3/hr

* 424 Activity No. Concrete Aggregate Crushing in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Material Production Sup. 1.00 1.00 Crusher Plant 75 TPH 1 1.00
Crusher Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Generater Opp. 1 1.00
Loader Opp. 1 1.00
Labourer Forman 1 1.00
Mechanic II 1 1.00
Electrician II 1 1.00
Helper 2 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Class A Bedding Production rate (per SPD) : 14 - 16 m3/day
Production rate (per Hour) : 1.75 - 2 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type

Cement Qtl 1.00


Carpenter 2 1.00 Concrete Mixer 0.5 m3 1
Sand m3 1.00
Masson 4 1.00 Concrete Vib. 4 HP 1
Concrete Agg. m3 W/Truck Opp. 1 0.40 Water Truck 14,000 lit 1 0.40
Water lit Con. Mixer Opp. 1 1.00 Dump Truck 9 m3 1 0.25
Dump Truck Opp. 1 0.25
Helper 2 1.00
Labourer 20 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Class B and C Bedding Production rate (per SPD) : 40 - 50 m3/day
Production rate (per Hour) : 5 - 6.25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Select Material m3 W/Truck Opp. 1 1.00 Water Truck 14,000 lit 1 1.00
Roller opp. 1 1.00 Roller 8 - 10 Ton 1 1.00
Helper 1 1.00
Labourer 8 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Pipe Production 900mm Production rate (per SPD) : 15.00 m/day
Production rate (per Hour) : 1.88 m/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 3 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Sand m3 Barsetter 4 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.50 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Pipe Production Dia 1060 Production rate (per SPD) : 15.00 m/day
Production rate (per Hour) : 1.88 m/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 3 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Sand m3 Barsetter 4 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.50 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Pipe Production Dia 1220 Production rate (per SPD) : 15.00 m/day
Production rate (per Hour) : 1.88 m/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 3 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.50
Sand m3 Barsetter 4 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.50 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.i.a. Concrete Pipe Culverts, on class A Bedding,
Work Item : Production rate (per SPD) : 25 - 30 m/day
900mm diam
Production rate (per Hour) : 3.12 - 3.75 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.i.a. Concrete Pipe Culverts, on class A Bedding, 900mm diam

Material Cost Labor cost Equipment


Material Unit Qty Title Qty UF
Equipment Type Capacity No UF
Type
Pipe Production No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class A Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.i.b. Concrete Pipe Culverts, on class A Bedding,
Work Item : Production rate (per SPD) : 25 - 30 m/day
1060mm diam
Production rate (per Hour) : 3.12 - 3.75 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.i.b. Concrete Pipe Culverts, on class A Bedding, 1060mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class A Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.i.c. Concrete Pipe Culverts, on class A Bedding,
Work Item : Production rate (per SPD) : 25 - 30 m/day
1220mm diam
Production rate (per Hour) : 3.12 - 3.75 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.i.c. Concrete Pipe Culverts, on class A Bedding, 1220mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class A Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.ii.a. Concrete Pipe Culverts, on class B Bedding,
Work Item : Production rate (per SPD) : 15.00 m/day
900mm diam
Production rate (per Hour) : 1.88 m/hr

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.ii.a. Concrete Pipe Culverts, on class B Bedding, 900mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe Prod. No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class B Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Production rate (per SPD) : 15.00 m/day
32.03.ii.b. Concrete Pipe Culverts, on class B Bedding,
Work Item : Production rate (per Hour) : 1.88 m/hr
1060mm diam

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.ii.b. Concrete Pipe Culverts, on class B Bedding, 1060mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe Prod. No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class B Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.03.ii.c. Concrete Pipe Culverts, on class B Bedding,
Work Item : Production rate (per SPD) : 15.00 m/day
1220mm diam
Production rate (per Hour) : 1.88 m/day

* 453 Activity No. Pipe Installation in old CMS replaced by 32.03.ii.c. Concrete Pipe Culverts, on class B Bedding, 1220mm diam

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Pipe Prod. No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Class B Bedding m Masson 4 1.00 Carier Truck 14,700 kg 1 0.50
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.50

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Production rate (per SPD) : 15 - 18 M2/day
Work Item : Form Work for minor Structure Production rate (per Hour) : 1.87 - 2.25 M2/hr

* 457 Activity No.Form work minor in old CMS replaced by this activ

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Lumber m3 Carpenter II 3 1.00 Dump Truck 9 m3 1 0.40
Eucaliptuse pole Ea Labourer 10 1.00 Hand Tools ** 1.00
Nails Assorted Kg Dump Truck opp. 1 0.40

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


32.07.a.i. Cast insitu concrete and form work, Concrete
Work Item : including form work, Class 25/20 Concrete in class A Production rate (per SPD) : 15 - 18 M3/day
Bedding
Production rate (per Hour) : 1.87 - 2.25 m3/hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 32.07.a.i. Cast insitu concrete and form work, Concrete including form work, Class 25/20 Concrete in class A Bedding

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement kg Construction Forman 1 0.20 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Labourer Forman 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 Carpenter 1 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 Masson 4 1.00 Dump Truck 9 m3 1 0.40
Class A Bedding m3 Water Truck opp. 1 0.50 Loader 2.5 - 3 m3 1 0.20
Water lit Concrete Mixer Opp. 2 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 20 1.00
Dump Truck Opp. 1 0.40
Loader Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

32.07.a.ii. Cast insitu concrete and form work,


Work Item : Concrete including form work, Class 15/20 Concrete Production rate (per SPD) : 18 - 20 M3/day
in Blinding, Screeds and encasing of pipes

Production rate (per Hour) : 2.25 - 2.5 m3/hr

* 458 Activity No. class C concrete Minor in old CMS replaced by 32.07.a.i. Cast insitu concrete and form work, Concrete including form work, Class 25/20 Concrete in class A Bedding

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement kg Construction Forman 1 0.20 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Labourer Forman 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 Carpenter 1 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 Masson 4 1.00 Dump Truck 9 m3 1 0.40
Water lit Water Truck opp. 1 0.50 Loader 2.5 - 3 m3 1 0.20
Concrete Mixer Opp. 2 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 20 1.00
Dump Truck Opp. 1 0.40
Loader Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 300mm Pipe Production Production rate (per SPD) : 25.00 pipe/day
Production rate (per Hour) : 3.13 pipe/hr

* 452 Activity No. Pipe production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 2 1.00 Loader 2.5 - 3 m3 1 0.50
Cement m3 Loader Opp. 1 0.50 Water Truck 14,000 lit 1 0.20
Sand m3 Barsetter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Concrete Agg. m3 Water Truck Opp 1 0.20 Concrete Vib. 4 HP 1 1.00
Water lit Labourer Forman 1 1.00 Hand Tools ** 1.00
Helper 4 1.00
Labourer 15 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

32.20.a Survice Ducts, Service Duct 300mm dia.


Work Item : Production rate (per SPD) : 10.00 m/day
Reinforced concrete pipe, (Utility duct)

Production rate (per Hour) : 1.25 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
300mm Pipe No Masson Forman 1 1.00 Loader 2.5 - 3 m3 1 0.50
Masson 2 1.00 Carier Truck 14,700 kg 1 0.30
Loader Opp. 1 0.50 Hand Tools ** 1.00
Labourer 10 1.00
Carier Truck Opp 1 0.30

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


33.01.a. Kerbing, class 25/20 concrete curbing
Work Item : Production rate (per SPD) : 150 - 180 M/day
(0.17m*0.45m)
Production rate (per Hour) : 18.75 - 22.5 M/hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 33.01.a. Kerbing, class 25/20 concrete curbing (0.17m*0.45m)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 6 1.00 Water Truck 14,000 lit 1 0.20
Sand m3 Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Lumber m3 Water Truck Opp. 1 0.20 Concrete Vib. 4 HP 2 1.00
Nails Assorted kg Con. Mixer Opp. 1 1.00 Hand Tools ** 1.00
Eucal. Pol Ea Helper 4 1.00
Concrete Agg. M3 Labourer 20 1.00
Water lit

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Form Work for major structures' slab Production rate (per SPD) : 34.30 M3/day
Production rate (per Hour) : 4.29 M2/hr
Assume typical dimension = 14 m * 7m * 0.35m height =5m

* 465 Activity No. Form work major in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Lumber M3 Carpenter 20.00 1.00 Dump Truck 9 m3 1 1.00
Eucal.Pole Ea D/Truck Operator 1.00 1.00 Hand tools ** 1.00
Nails Assorted Kg Labourer 60.00 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Formwork removal Production rate (per SPD) : 25 - 30 M2/day
Production rate (per Hour) : 3.12 - 3.75 M2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Carpenter 5.00 1.00 Handtools ** 1.00
Labourer 20.00 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Reinforcement Steel (Minor) Production rate (per SPD) : 285 - 300 Kg/day
Production rate (per Hour) : 35.6 - 37.5 Kg/hr
1
* 455 A & B Activity No. Reinforcement steel minor in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcing Kg Barestter 3.00 1.00 Hand tools ** 1.00
Binding Wire Kg Helper 1.00 1.00
Labourer 10.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


33.08a. Concrete lining for open drains, Class 25/20
Work Item : Production rate (per SPD) : 130 - 150 m/day
concrete as per detail )
Production rate (per Hour) : 16.25 - 18.75 m/hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 33.08a. Concrete lining for open drains, Class 25/20 concrete as per detail

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.20
Cement m3 Masson 6 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Carpenter 1 1.00 Concrete Vibrater 4 HP 1 1.00
Concrete Agg. m3 Water Truck Opp. 1 0.20 Hand Tools ** 1.00
Water lit Con. Mixer Opp. 1 1.00
Helper 3 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

33.16.a. Paved drains in towns, U or Trapizoidal


Work Item : Production rate (per SPD) : 15.00 M3/day
shaped massonery drains in towns as per the drawing

Production rate (per Hour) : 1.88 M3/hr

* 456 Activity No. class B massonary Minor in old CMS replaced by 33.16.a. Paved drains in towns, U or Trapizoidal shaped massonery drains in towns as per the drawing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Masson 10 1.00 Quarry Truck 14 m3 1 0.50
Massonery Stone Prod.m3 Carpenter 1 1.00 Hand Tools ** 1.00
Water lit Water Truck Opp. 1 0.15
Quarry Truck Opp. 1 0.50
Helper 4 1.00
Labourer 22 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

33.16.b.i. Paved drains in towns, Class 25/20


reinforced concrete drains cover units including
Work Item : reinforcement and formwork as per detail, Pedesterian Production rate (per SPD) : 30 - 50 no/day
crossing cover as shown on the drawing (Ass.
2m*1.32m*.15m dimension)

Production rate (per Hour) : 3.75 - 6.25 no/day

* 454 Activity No. class A concrete Minor in old CMS replaced by 33.16.b.i. Paved drains in towns, Class 25/20 reinforced concrete drains cover units including reinforcement and
formwork as per detail, Pedesterian crossing cover as shown on the drawing (Ass. 2m*1.32m*.15m dimension)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 4 1.00 Water Truck 14,000 lit 1 0.20
Cement Qtl Carpenter 1 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.20 Concrete Vibrater 4 HP 1 1.00
Concrete Agg. m3 Con. Mixer Opp. 1 1.00 Hand Tools ** 1.00
Water lit Helper 3 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

33.16.b.ii. Paved drains in towns, Class 25/20


reinforced concrete drains cover units including
Work Item : Production rate (per SPD) : 35 - 50 no/day
reinforcement and formwork as per detail, Vehicle
crossing cover as shown on the drawing

Production rate (per Hour) : 4.37 - 6.25 no./hr

* 454 Activity No. class A concrete Minor in old CMS replaced by 333.16.b.ii. Paved drains in towns, Class 25/20 reinforced concrete drains cover units including reinforcement and
formwork as per detail, Vehicle crossing cover as shown on the drawing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Bar Kg Masson 4 1.00 Water Truck 14,000 lit 1 0.20
Cement Qtl Carpenter 1 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.20 Concrete Vibrater 4 HP 1 1.00
Concrete Agg. m3 Con. Mixer Opp. 1 1.00 Hand Tools ** 1.00
Water lit Helper 3 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.01.b.i Grouted stone pitching, Grouted stone
Work Item : Production rate (per SPD) : 44 - 50 M2/day
pitching at culverts
Production rate (per Hour) : 5.5 - 6.25 M2/hr

* 471 Activity No. Paved waterway Grouted in old CMS replaced by 34.01.b.i Grouted stone pitching, Grouted stone pitching at culverts

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 10 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Water Truck Opp. 1 0.15 Quarry Truck 14 m3 1 0.30
Massonery Stone m3 Quarry Truck Opp. 1 0.30 Hand Tools ** 1.00
Water lit Helper 1 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.01.b.ii Grouted stone pitching, Grouted stone
Work Item : Production rate (per SPD) : 50 - 60 m2/day
pitching rural ditch
Production rate (per Hour) : 6.25 - 7.5 m2/hr

* 471 Activity No. Paved waterway Grouted in old CMS replaced by 34.01.b.ii Grouted stone pitching, Grouted stone pitching rural ditch

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 10 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Water Truck Opp. 1 0.15 Quarry Truck 14 m3 1 0.30
Massonery Stone m3 Quarry Truck Opp. 1 0.30 Hand Tools ** 1.00
Water lit Helper 1 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.01.b.iv Grouted stone pitching, Grouted stone
Work Item : Production rate (per SPD) : 44 - 50 M2/day
pitching at bridges
Production rate (per Hour) : 5.5 - 6.25 M2/hr

* 471 Activity No. Paved waterway Grouted in old CMS replaced by 34.01.b.iv Grouted stone pitching, Grouted stone pitching at bridges

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson 10 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Water Truck Opp. 1 0.15 Quarry Truck 14 m3 1 0.30
Massonery Stone m3 Quarry Truck Opp. 1 0.30 Hand Tools ** 1.00
Water lit Helper 1 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


34.03.b. Stone masonery walls, Cement mortared stone
Work Item : Production rate (per SPD) : 15 - 18 m3/day
walls (1:3 mortar ratio)
Production rate (per Hour) : 1.87 - 2.25 m3/hr

* 456 Activity No. Class B Massonary in old CMS replaced by 34.03.b. Stone masonery walls, Cement mortared stone walls (1:3 mortar ratio)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.15
Sand m3 Masson 10 1.00 Quarry Truck 14 m3 1 0.30
Massonery Stone Prod.m3 Carpenter 1 1.00 Hand Tools ** 1.00
Water lit Water Truck Opp. 1 0.15
Quarry Truck Opp. 1 0.30
Helper 1 1.00
Labourer 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 41.01. Removal of Unsuitable Material Production rate (per SPD) : 1200 - 1500 m3/day
Production rate (per Hour) : 150 - 187.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Fesposal m3 Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Helper 1 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


41.03.b. Road bed Preparation and the compaction of
Work Item : material, Compaction to 93% of modified AASHTO Production rate (per SPD) : 900 - 960 m3/day
density
Production rate (per Hour) : 112.5 - 120 m3/hr

* 418, 419A & 419B Activity No. Road Bed Preparation in old CMS replaced by 41.03.b. Road bed Preparation and the compaction of material, Compaction to 93% of modified
AASHTO density depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
m3 Construction Forman 0.5 0.50 Grader Komatsu 197 HP 1 1.00
Roller Opp. 1 1.00 Roller 10 - 12 ton 1 1.00
W/Truck Opp. 1 1.00 Dozer D8R 315 HP 1 0.50
Grader Opp. 1 1.00 W/Truck 14,000 lit 1 1.00
Dozer Opp. 1 0.50
Helper 3 1.00
Labourer 15 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


41.04.a. In situ treatment of road bed, in situ treatment
Work Item : Production rate (per SPD) : 500 - 700 m3/day
by ripping
Production rate (per Hour) : 62.5 - 87.5 m3/hr

* 418, 419A & 419B Activity No. Road Bed Preparation in old CMS replaced by 41.04.a. In situ treatment of road bed, in situ treatment by ripping

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Construction Forman 1 0.50 Grader Komatsu 197 HP 1 1.00
Roller Opp. 1 1.00 Roller 10 - 12 ton 1 1.00
W/Truck Opp. 1 1.00 Dozer D8R 315 HP 1 0.50
Grader Opp. 1 1.00 W/Truck 14,000 lit 1 1.00
Dozer Opp. 1 0.50
Helper 3 1.00
Labourer 15 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Borrow Material Production Production rate (per SPD) : 700 - 800 m3/day
Production rate (per Hour) : 87.5 - 100 m3/hr

* 421 B Activity No. Borrow material Production in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Helper 1 1.00
Construction Forman 1 0.50
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Cap. 9m3

Work Item : Borrow Material Hauling Av.Dis 2 km Production rate (per SPD) : 2000 - 2400 m3/day
Av.Sp. 35 km/hr Production rate (per Hour) : 250 - 300 m3/hr
t for L/Unl 5m

* 413 B Activity No. Borrow material hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 7 1.00 Dump Truck 9 m3 7 1.00
Helper 1 1.00
Labourer 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

42.01.a. Cut and Borrow to fill, Material in layer


Work Item : thickness of 200mm and less compacted to 93% Production rate (per SPD) : 1300 - 1500 m3/day
modified AASHTO density

Production rate (per Hour) : 162.5 - 187.5 m3/hr

*412 A & 412 B Activity No. Common Excavation & Embankment in old CMS replaced by 42.01.a. Cut and Borrow to fill, Material in layer thickness of 200mm and less compacted to
93% modified AASHTO density

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Grader Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Roller Opp. 2 0.80 Grader Komatsu 197 HP 1 1.00
Water Truck Opp. 2 1.00 Roller 10 - 12 ton 2 0.80
Construction Forman 1 1.00 Water Truck 14,000 lit 2 1.00
Labourer Forman 1 1.00 d.t
Dozer Opp. 1 1.00
Labourer 20 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

42.01.b.ii. Improved subgrade or Capping layer,


Work Item : Improved subgrade layer compacted to 95% of Production rate (per SPD) : 1000 - 1200 m3/day
modified AASHTO density
Production rate (per Hour) : 125 - 150 m3/hr

*413 A & 417 Activity No. Borrow Excavation & Embankment & Borrow Placing in old CMS replaced by 42.01.b.ii. Improved subgrade or Capping layer, Improved subgrade layer
compacted to 95% of modified AASHTO density

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Grader Opp. 1 1.00 Grader Komatsu 197 HP 1 1.00
Roller Opp. 2 1.00 Roller 10 - 12 ton 2 1.00
Water Truck Opp. 2 1.00 Water Truck 14,000 lit 2 1.00
Construction Forman 1 1.00 d/t
Labourer Forman 1 1.00
Labourer 20 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Cap. 9 m3

Work Item : Waste Desposal Av.Dis 3 km Production rate (per SPD) : 1400 - 1600 m3/day
Av.Sp. 25 Km/hr Production rate (per Hour) : 175 - 200 m3/hr
t for L/Unl 5m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 6 1.00 Dump Truck 9 m3 6 1.00
Helper 1 1.00
Labourer 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


42.03.a. Cut to spoil material obtained from, Soft
Work Item : Production rate (per SPD) : 960 - 1200 m3/day
excavation
Production rate (per Hour) : 120 - 150 m3/hr

*415 A & 415 B Activity No. Unclassified Excavation & Embankment in old CMS replaced by 42.03.a. Cut to spoil material obtained from, Soft excavation

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Construction Forman 1 0.50
Helpers 2 1.00
Labourer Forman 1 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


42.03.b. Cut to spoil material obtained from, Hard
Work Item : Production rate (per SPD) : 340 - 400 m3/day
excavation
Production rate (per Hour) : 42.5 - 50 m3/hr

*414 Activity No. Rock Excavation in old CMS replaced by 42.03.b. Cut to spoil material obtained from, Hard excavation

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box Construction Forman 1 0.50 Dozer D8R 315 HP 1 1.00
Blasting Caps Ea Quary Forman 1 1.00 Air Compresser 9 kg/m3 1 1.00
Waste Desposal m3 Dozer Opp. 1 1.00 Wagon drill 10,900 kg 1 1.00
Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
W/dill Opp. 1 1.00
Powder man 1 1.00
Helpers 3 1.00
Labourers 6 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Gravel Sub base Material Production Production rate (per SPD) : 800 - 880 m3/day
Production rate (per Hour) : 100 - 110 m3/hr

*421 A Activity No. Select Material Production (Subbase) in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dozer Opp. 1 1.00 Dozer D8R 315 HP 1 1.00
Helper 1 1.00
Labourer 2 1.00
c.forman

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : Gravel Sub base Material Hauling Cap. 14m3 Production rate (per SPD) : 1800 - 2000 m3/day
Av.Dis 10km Production rate (per Hour) : 225 - 250 m3/hr
Av.Sp. 40 km/hr
tfor L/Unl 5m

*431 Activity No. Select Material Hauling (Subbase) in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 11 1.00 Dump Truck 14 m3 11 1.00
Construction Forman 1 0.25
Labourers 3 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

51.01.a.ii. Unstablised gravel subbase compacted to 97


Work Item : % of modified AASHTO density layer thickness, Production rate (per SPD) : 800 - 1000 m3/day
150mm maximum layer thickness

Production rate (per Hour) : 100 - 125 m3/hr

*432 Activity No. Select Material Placing (Subbase) in old CMS replaced by 51.01.a.ii. Unstablised gravel subbase compacted to 97 % of modified AASHTO density layer thickness,
150mm layer thickness

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Subbase Material m3 Construction Forman 1 1.00 Grader Komatsu 197 HP 1 1.00
Grader Opp. 1 1.00 Roller 12 - 14 ton 2 1.00
Roller Opp. 2 1.00 W/Truck 14,000 lit 2 1.00
Water Truck Opp. 2 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 15 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Crushing of Base Course Material Production rate (per SPD) : 240 - 256 m3/day
Production rate (per Hour) : 30 - 32 m3/hr

*425 Activity No. Rock crushing for Base Course in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Crusher Opp 1 1.00 Crusher Plant 75 TPH 1 1.00
Generator Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Loader Opp. 1 1.00 Generator 500 v 1 1.00
Helper 1 2.00
Labourer 1 10.00
elec
mec

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Cap. 14m3
Project : Shire Airfield upgrading project Av.Dis 20 km

Work Item : Crushed Base Course Material Hauling Av.Sp. 60 km/hr Production rate (per SPD) : 1600 - 1800 m3/day

t for L/Unl 5m Production rate (per Hour) : 200 - 225 m3/hr

*433 Activity No. Base Course hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Base Course m3 Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Dump Truck Opp. 12 1.00 Dump Truck 14 m3 12 1.00
Helper 1 1.00
Labourer 2 1.00
Labourer Forman 1 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Crushed Aggregate Base Course Mixing Production rate (per SPD) : 1000 - 1200 m3/day
Production rate (per Hour) : 125 - 150 m3/hr

*429 Activity No. Base Course material mixing in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Loader Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
W/Truck Opp 1 1.00 W/Truck 14,000 m3 1 1.00
Helpers 2 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

52.01.b.ii. Crushed stone base compacted to 100% of


Work Item : modified AASHTO density, layer thickness 175mm or Production rate (per SPD) : 1000 - 1200 m3/day
as shown on the drawing

Production rate (per Hour) : 125 - 150 m3/hr

*434 A & 434 B Activity No. Select Material Placing in old CMS replaced by 52.01.b.ii. Crushed stone base compacted to 100% of modified AASHTO density, layer thickness 175mm or
as shown on the drawing

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Base Course m3 Grader Opp. 1 1.00 Grader Komatsu 197 HP 1 1.00
Roller Opp. 2 1.00 Roller 12 - 14 ton 2 1.00
W/Truck Opp 2 1.00 W/Truck 14,000 lit 2 1.00
Construction Foreman 1 1.00
Helper 2 1.00
Labourer 15 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

54.01.a. Gravel Shoulders Type 1 wearing course


Work Item : Production rate (per SPD) : 800 - 1000 m3/day
compacted to 95% of modified AASHTO density

Production rate (per Hour) : 100 - 125 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Subbase Material m3 Construction Forman 1 1.00 Grader Komatsu 197 HP 1 1.00
Grader Opp. 1 1.00 Roller 12 - 14 ton 1 1.00
Roller Opp. 1 1.00 W/Truck 14,000 lit 1 1.00
Water Truck Opp. 1 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 15 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


61.01.a. Prime Coat, MC-30 cut back bitumen applied
Work Item : Production rate (per SPD) : 7,000.00 lit/day
at 0,8lit per sq.m
Production rate (per Hour) : 875.00 lit/hr

*437 Activity No. Prime coat application in old CMS replaced by 61.01.a. Prime Coat, MC-30 cut back bitumen applied at 0,8lit per sq.m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Asphalt MC-30 lit Asphalt dist. Opp 1 1.00 Asphalt Distributer 8000 lit 1.00 1.00
Power broom Opp. 1 0.50 Water Truck 14,000 lit 1.00 0.50
Water Truck Opp. 1 0.50 Power broom 1.00 0.50
Helpers 2 1.00
Labourers 6 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Rock Crushing for Surface Aggregate Production rate (per SPD) : 140 - 160 m3/day
Production rate (per Hour) : 17.5 - 20 m3/hr

*426 Activity No. Surface aggregate crushing in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Material Production Sup. 1 1.00 Crusher Plant 75 TPH 1 1.00
Crusher Opp. 1 1.00 Loader 2.5 - 3 m3 1 1.00
Generater Opp. 1 1.00 Generator 500 v 1 1.00
Loader Opp. 1 1.00
Labourer Forman 1 1.00
Mechanic II 1 1.00
Electrician II 1 1.00
Helper 2 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Batch Plant Operation Production rate (per SPD) : 375 - 400 m3/day
Production rate (per Hour) : 46.87 - 50 m3/hr

*442 Activity No. Batch Plant Operation in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Batch plant opp. 1 1.00 Asphalt Plant 1200 kg/mix (150 TPH) 1 1.00
Welder 1 1.00 Loader 2.5 - 3 m3 2 1.00
Loader opp. 1 1.00 Welding Machine 400 A 1 1.00
Helpers 3 1.00 Generator 500 v 1 1.00
Labourers 16 1.00
Generater opp. 1 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Cap. 9m3

Work Item : Asphalt Hot Mix Hauling Av. Dis 20 km Production rate (per SPD) : 375 - 400 m3/day
Av. Sp. 60 km/hr Production rate (per Hour) : 46.87 - 50 m3/hr
t for L and Ul 5m

*443 Activity No. Asphalt mix hauling in old CMS replaced by this activity

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Ac 60/70 m3 D/Truck Opp. 12 1.00 Dump Truck 9 m3 12 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

64.02.a.iii. Asphalt concrete surfacing course;


continuously graded course grading 50mm thick,
Work Item : Production rate (per SPD) : 375 - 400 m3/day
asphalt concrete surface course with 60/70 penetration
grade bitumen
Specific Grav. Of Aspalt Mix Production rate (per Hour) : 46.87 - 50 m3/hr
Opptimum Asphalt Content of 5.80%
Asphalt Content per M3 of the153.7Kg

*444 Activity No. Asphalt mix hauling in old CMS replaced by 64.02.a.iii. Asphalt concrete surfacing course; continuously graded course grading 50mm thick, asphalt concrete surface
course with 60/70 penetration grade bitumen

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Ac 60/70 m3 Paver Operater 1 1.00 Paver 2000 kw/min (5m length) 1 1.00
Roller Opp. 3 1.00 steel Roller 10 - 12 ton 1 1.00
Water Truck Opp. 1 1.00 Pneumatic Roller 24 ton 3 1.00
Helper 4 1.00 Water Truck 14,000 lit 1 1.00
Labourer Forman 1 1.00
Construction Forman 1 1.00
sensor man 2 1.00
Joint man 8 1.00
Material Inspecter 2 1.00
Labourers 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 64.07 Trial Sections Production rate (per SPD) : 1,500.00 m2/day
Production rate (per Hour) : 187.50 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Ac 60/70 m3 Paver Operater 1 1.00 Paver 2000 kw/min (5m length) 1 1.00
Roller Opp. 3 1.00 steel Roller 10 - 12 ton 1 1.00
Water Truck Opp. 1 1.00 Pneumatic Roller 24 ton 3 1.00
Helper 4 1.00 Water Truck 14,000 lit 1 1.00
Labourer Forman 1 1.00
Construction Forman 1 1.00
sensor man 2 1.00
Joint man 8 1.00
Material Inspecter 2 1.00
Labourers 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 64.08. 100mm diameter cores in asphaltic layers Production rate (per SPD) : 40.00 core/day
Production rate (per Hour) : 5.00 cor/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Material Inspecter 1 1.00 Core Cutter Machine 1 1.00
Helpers 4 1.00 hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : Massonary Rock Production Production rate (per SPD) : 400 - 500 m3/day
Production rate (per Hour) : 50 - 62.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Quarry Rock m3 Chain Loader Opp. 1 1.00 Chain Loader 2.5 - 3 m3 1 1.00
Dozer Opp 1 1.00 Dozer D8R 315 HP 1 1.00
Helpers 2 1.00
Labourers 2 1.00
q/forman

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Cap. 14 m3

Project : Shire Airfield upgrading project Av.Dis. 5 km

Work Item : Massonery Rock Hauling Av.Sp. 30 km/hr Production rate (per SPD) : 680 - 720 m3/day
t for L/Unl 5m Production rate (per Hour) : 85 - 90 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Quarry Rock m3 Chain Loader Opp. 1 1.00 Chain Loader 2.5 - 3 m3 1 1.00
Quarry Truck Opp 4 1.00 Quarry Truck 14 m3 4 1.00
Helpers 2 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Cap. 9m3

Project : Shire Airfield upgrading project Av.Dis 23km

Work Item : Sand Production and Hauling Av.Sp. 30 km/hr Production rate (per SPD) : 650 - 750 m3/day
t for L/Unl 5m Production rate (per Hour) : 81.25 - 93.75 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Sand m3 Construction Forman 1 0.25 Loader 2.5 - 3 m3 1 1.00
Loader Opp 1 1.00 Dump Truck 9 m3 12 1.00
Dump Truck Opp 12 1.00
Helper 1 1.00
Labourers 2 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

81.02.a.i. Excavating Material with in the following


Work Item : Production rate (per SPD) : 200 - 250 m3/day
succecive depth ranges, 0m up to 2m

Production rate (per Hour) : 25 - 31.25 m3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.a.i. Excavating Material with in the following succecive depth ranges, 0m up to 2m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Construction Forman 1 0.50 Excavater 1.5 m3 1 1.00
Excavater Opp. 1 1.00 Roller 8 - 10 ton 1 0.20
Roller Opp. 1 0.20 Water Pump 230 lit/min 1 1.00
Helpers 3 1.00 Hand Tools ** 1.00
Labourers 5 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

81.02.a.ii. Excavating Material with in the following


Work Item : Production rate (per SPD) : 180 - 200 m3/day
succecive depth ranges, Exceeding 2m and up to 4m

Production rate (per Hour) : 22.5 - 25 m3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.a.ii. Excavating Material with in the following succecive depth ranges, Exceeding 2m and up to 4m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Construction Forman 1 0.50 Excavater 1.5 m3 1 1.00
Excavater Opp. 1 1.00 Roller 8 - 10 ton 1 0.20
Roller Opp. 1 0.20 Water Pump 230 lit/min 1 1.00
Helpers 3 1.00 Hand Tools ** 1.00
Labourers 5 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

81.02.a.iii. Excavating Material with in the following


Work Item : Production rate (per SPD) : 120 - 150 m3/day
succecive depth ranges, Extra increment of 1m

Production rate (per Hour) : 15 - 18.75 m3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.a.iii. Excavating Material with in the following succecive depth ranges, Extra increment of 1m

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Waste Desposal m3 Construction Forman 1 0.50 Excavater 1.5 m3 1 1.00
Excavater Opp. 1 1.00 Roller 8 - 10 ton 1 0.20
Roller Opp. 1 0.20 Water Pump 230 lit/min 1 1.00
Helpers 3 1.00 Hand Tools ** 1.00
Labourers 5 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


81.02.b EO item 81.02. (a) for hard excavation
Work Item : Production rate (per SPD) : 80 - 100 M3/day
irrespective of depth
Production rate (per Hour) : 10 - 12.5 M3/hr

*461 Activity No. Structural Excavation major in old CMS replaced by 81.02.b EO item 81.02. (a) for hard excavation irrespective of depth

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Dynamite Box Construction Forman 1 0.50 Excavater 1.5 m3 1 0.50
Blasting Caps Ea Excavater Opp. 1 0.50 Roller 8 - 10 m3 1 0.20
Wast Desposal m3 Roller Opp. 1 0.20 Wagon drill 10,900 kg 1 1.00

Jack hammer Opp. 1 0.50 Jack hammer 330 Hp 1 0.50


Wagon Drill Opp. 1 1.00 Compressor 9 kg/m3 1 1.00
Powder man 1 1.00 Hand Tools ** 1.00
Helpers 2 1.00
Labourers 8 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 81.09.a. Foundation Fill, Rock Fill Production rate (per SPD) : 150 - 180 m3/day
Production rate (per Hour) : 18.75 - 22.5 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Quarry Rock m3 Roller Opp. 1 1.00 Roller 10 - 12 ton 1 1.00
Excavater Opp. 1 1.00 Excavater 1.5 m3 1 1.00
Quarry Truck Opp. 1 1.00 Quarry Truck 14 m3 1 1.00
Helper 2 1.00 Hand Tools ** 1.00
Labourer 6 1.00

UF : Utilization Factor

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project Production rate (per SPD) : 15 - 18 M2/day
Work Item : 82.01.a. Form Works to Provide all class of finishes Production rate (per Hour) : 1.87 - 2.25 M2/hr
(Assuming 5cm lumber thickness)
* 465 Activity No.Form work minor in old CMS replaced by 82.01.a. Form Works to Provide all class of finishes (Assuming 5cm lumber thickness)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Lumber m3 Carpenter II 3 1.00 Dump Truck 9 m3 1 0.40
Eucaliptuse pole Ea Labourer 10 1.00 Hand Tools ** 1.00
Nails Assorted Kg Dump Truck opp. 1 0.40

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


83.01.a. Steel reinforcement for structures, Mild steel
Work Item : Production rate (per SPD) : 500 - 571 Kg/day
bars (Grade 300)
Production rate (per Hour) : 62.5 - 71.37 Kg/hr

*463 Activity No. Reinforcement Steel major in old CMS replaced by 83.01.a. Steel reinforcement for structures, Mild steel bars (Grade 300)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcing bars kg Barsetter 4.00 1.00 Bar Cutting torch 2 1.00
Binding wire kg Cutting torch opp. 2.00 1.00 Hand Tools ** 1.00
Helper 1.00 1.00
Labourer 10.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


83.01.b. Steel reinforcement for structures, Mild steel
Work Item : Production rate (per SPD) : 500 - 571 Kg/day
bars (Grade 420)
Production rate (per Hour) : 62.5 - 71.37 Kg/hr

*463 Activity No. Reinforcement Steel major in old CMS replaced by 83.01.b. Steel reinforcement for structures, Mild steel bars (Grade 420)

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcing bars kg Barsetter 4.00 1.00 Bar Cutting torch 2 1.00
Binding wire kg Cutting torch opp. 2.00 1.00 Hand Tools ** 1.00
Helper 1.00 1.00
Labourer 10.00 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.01.a.i. Cast in situ concrete, Class C-30 in all super
Work Item : structure parts, abutment back wall and walls Production rate (per SPD) : 16 - 20 m3/day
foundation
Production rate (per Hour) : 2 - 2.5 m3/hr

*462 Activity No. Class A Concrete major in old CMS replaced by 84.01.a.i. Cast in situ concrete, Class C-30 in all super structure parts, abutment back wall and walls foundation

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Construction Forman 1 0.50 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Carpenter 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 Masson 10 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 W/Truck Opp. 1 0.50 Dump Truck 9 m3 1 1.00
Loader Opp. 1 0.50 Loader 2.5 - 3 m3 1 0.50
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 1.00
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 30 1.00

UF : Utilization Factor
** As required

PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.01.a.ii. Cast in situ concrete, Class C-20/25 in
Work Item : Production rate (per SPD) : 16 - 20 m3/day
abutment and walls footing pads
Production rate (per Hour) : 2 - 2.5 m3/hr

*462 Activity No. Class A Concrete major in old CMS replaced by 84.01.a.ii. Cast in situ concrete, Class C-20/25 in abutment and walls footing pads

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Construction Forman 1 0.50 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Carpenter 1 1.00 Concrete Vib. 4 HP 2 1.00
Concrete Agg. m3 Masson 10 1.00 Water Truck 14,000 lit 1 0.50
Form Work m3 W/Truck Opp. 1 0.50 Dump Truck 9 m3 1 1.00
Loader Opp. 1 0.50 Loader 2.5 - 3 m3 1 0.50
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 1.00
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 30 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.01.a.iii. Cast in situ concrete, Class C-15/19
Work Item : Production rate (per SPD) : 18 - 20 m3/day
concrete in blinding
Production rate (per Hour) : 2.25 - 2.5 m3/hr

*466 Activity No. Class C Concrete major in old CMS replaced by 84.01.a.iii. Cast in situ concrete, Class C-15/19 concrete in blinding

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Construction Forman 1 0.25 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Carpenter 1 1.00 Concrete Vib. 4 HP 1 1.00
Concrete Agg. m3 Masson 10 1.00 Water Truck 14,000 lit 1 0.30
Form Work m3 W/Truck Opp. 1 0.30 Dump Truck 9 m3 1 0.50
Loader Opp. 1 0.30 Loader 2.5 - 3 m3 1 0.30
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 0.50
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 20 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


84.06 Approach slab for Bridges class C-25/29
Work Item : Concrete, Approach slabs for new bridges of class Production rate (per SPD) : 14 - 16 m3/day
C25/19Concrete
Production rate (per Hour) : 1.75 - 2 m3/hr

*462 Activity No. Class A Concrete major in old CMS replaced by 84.06 Approach slab for Bridges class C-25/29 Concrete, Approach slabs for new bridges of class C25/19Concrete

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Construction Forman 1 0.25 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Carpenter 1 1.00 Concrete Vib. 4 HP 1 1.00

Concrete Agg. m3 1.00 0.30


Masson 10 Water Truck 14,000 lit 1
Form Work m3 W/Truck Opp. 1 0.30 Dump Truck 9 m3 1 0.50
Loader Opp. 1 0.30 Loader 2.5 - 3 m3 1 0.30
Con. Mix. Opp. 1 1.00 Hand Tools ** 1.00
Dump Truck Opp. 1 0.50
Labourer Forman 1 1.00
Helpers 2 1.00
Labourers 20 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 87.03.i. Bridge Bearings, Supply and installation of Production rate (per SPD) : 8.00 m/day
Elastomeric Bearings as shown on the drawing,
Elastomeric Bearing
Production rate (per Hour) : 1.00 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Elastomeric Bearing Ea Labourers 4.00 1.00 D/Truck 9 m3 1.00 0.15
Dump Truck Opp. 1.00 0.15

1
UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


87.07. Concrete Bridge Parapets/Railings, Class C-
Work Item : Production rate (per SPD) : 80 - 90 m/day
30/25 Concrete
Production rate (per Hour) : 10 - 11.25 m/hr

*478 Activity No. Bridge Railing Concrete in old CMS replaced by 87.07. Concrete Bridge Parapets/Railings, Class C-30/25 Concrete

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 4 1.00 Water Truck 14,000 lit 1 0.50
Cement Qtl Carpenter 2 1.00 Con. Mixer 0.5 m3 1 1.00
Sand m3 W/Truck Opp. 1 0.50 Con. Vibrater 4 HP 1 1.00
Concrete Agg. m3 Con. Mix. Opp. 1 1.00 Dump Truck 9 m3 1 0.30
Form Work m3 Bar Setter 1 1.00 Hand Tools ** 1.00
Dump Truck 1 0.30
Labourer 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

87.13.a.i Installation of Expanition Joint, including


Work Item : Production rate (per SPD) : 10.00 m/day
20mm compressible joint filler board

Production rate (per Hour) : 1.25 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Expanition Joint m Labourer 5 1.00 Dump Truck 9 m3 1 0.15
Dump Truck Opp 1 0.15 Hand Tools **

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

89.01.b.i. Stone Massonery Structures, Class B


Work Item : Cement Mortared Stone Massonery walls (1:3 Mortar Production rate (per SPD) : 15 - 18 m3/day
ratio) for culverts and other mislaneaous structures

Production rate (per Hour) : 1.87 - 2.25 m3/hr

*464 Activity No. Class B Massonary major in old CMS replaced by 89.01.b.i. Stone Massonery Structures, Class B Cement Mortared Stone Massonery walls (1:3 Mortar ratio) for
culverts and other mislaneaous structures

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Construction Forman 1 0.10 Water Truck (14000lit) 14,000 lit 1 0.15
Sand M3 Masson Forman 1 1.00 Dump Truck 9 m3 1 0.15
Massonary Rock M3 Masson 10 1.00 Hand Tools ** 1.00
Equaliptuse Ea Carpenter 1 1.00
Water Truck Opp. 1 0.15
Dump Truck Opp. 1 0.15
Helpers 2 0.15
Labourers 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

89.01.b.ii. Stone Massonery Structures, Class B


Work Item : Cement Mortared Stone Massonery walls (1:3 Mortar Production rate (per SPD) : 18 - 20 m3/day
ratio) for Construction of RW, Check dams

Production rate (per Hour) : 2.25 - 2.5 m3/hr

*464 Activity No. Class B Massonary major in old CMS replaced by 89.01.b.ii. Stone Massonery Structures, Class B Cement Mortared Stone Massonery walls (1:3 Mortar ratio) for
Construction of RW, Check dams

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Construction Forman 1 0.10 Water Truck (14000lit) 14,000 lit 1 0.15
Sand M3 Masson Forman 1 1.00 Dump Truck 9 m3 1 0.15
Massonary Rock M3 Masson 10 1.00 Hand Tools ** 1.00
Equaliptuse Ea Carpenter 1 1.00
Water Truck Opp. 1 0.15
Dump Truck Opp. 1 0.15
Helpers 2 0.15
Labourers 20 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 89.03. Repointing of existing Massonery walls Production rate (per SPD) : 20 - 25 m2/day

Production rate (per Hour) : 2.5 - 3.12 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Cement Qtl Masson Forman 1 1.00 Water Truck 14,000 lit 1 0.15
Sand M3 Masson 2 1.00 Dump Truck 9 m3 1 0.15
Water Truck Opp. 1 0.15 Hand Tools ** 1.00
Dump Truck Opp. 1 0.15
Helper 1 1.00
Labourers 6 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


91.03.a.ii. Galvanized Gabion boxes, 80*100 mesh
Work Item : Production rate (per SPD) : 10.00 m3/day
size, 2*1*1
Production rate (per Hour) : 1.25 m3/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Gabion Boxes no Loader Opp. 0.4 1.00 Loader 2.5 - 3 m3 1.00 0.40
Massonery Stone Prod.m3 Dump Truck Opp 0.4 1.00 Dump Truck 9 m3 1.00 0.40
Massonery Stone
m3 Masson 2 1.00
Hauling
Helper 1 1.00
Labourer 10 1.00

UF : Utilization Factor

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 92.01.a. Delinaters Production rate (per SPD) : 25.00 no/day
Production rate (per Hour) : 3.13 no/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 2 1.00 Water Truck 14,000 lit 1 0.15
Cement Qtl Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.15 Concrete vib. 4 HP 1 1.00
Concrete Agg. m3 Con, Mixer Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Water lit Bar Setter 1 1.00 Hand Tools ** 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


92.01.b. Concrete Guide post (1.1m*0.24m*0.24m),
Work Item : Production rate (per SPD) : 20.00 no/day
C-25/20
Production rate (per Hour) : 2.50 no/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 2 1.00 Water Truck 14,000 lit 1 0.15
Cement Qtl Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00

Sand m3 0.15 1.00


Water Truck Opp. 1 Concrete vib. 4 HP 1
Concrete Agg. m3 Con, Mixer Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Water lit Bar Setter 1 1.00 Hand Tools ** 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


92.01.c. Concrete Kilometer Posts
Work Item : Production rate (per SPD) : 18.00 no/day
(1.6m*0.24m*0.24m), C-25/20
Production rate (per Hour) : 2.25 no/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Reinforcement Steel Kg Masson 2 1.00 Water Truck 14,000 lit 1 0.15
Cement Qtl Carpenter 2 1.00 Concrete Mixer 0.5 m3 1 1.00
Sand m3 Water Truck Opp. 1 0.15 Concrete vib. 4 HP 1 1.00
Concrete Agg. m3 Con, Mixer Opp. 1 1.00 Dump Truck 9 m3 1 1.00
Water lit Bar Setter 1 1.00 Hand Tools ** 1.00
Labourer Forman 1 1.00
Helpers 3 1.00
Labourers 10 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

Work Item : 93.01. Galvanized Guardrails on steel posts, complete Production rate (per SPD) : 30.00 m/day

Production rate (per Hour) : 3.75 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Galvanizes Steel posts m Dump Truck Opp 1 0.20 Dump Truck 9 m3 1 0.20
Carpenter 1 1.00 Welding Machine 800 A 1 0.50
Welder 1 0.50 Hand tools ** 1.00
Labourers 5 1.00

UF : Utilization Factor
** As required

ETHIOPIAN CONSTRUCTION WORKS CORPORATION


PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


Work Item : 94.01.a. Road signs, Area not Exceeding 2m2 Production rate (per SPD) : 2.00 m2/day
Production rate (per Hour) : 0.25 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
2mm thick Aluminium m
p2 Skilled Person 1 1.00 Dump Truck 9 m3 1 0.50
Paint lit Labourers 5 1.00 Hand Tools ** 1.00

Reflective Road Sign Ea

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project


94.01.b. Road signs, Area Exceeding 2m2 but not
Work Item : Production rate (per SPD) : 1.00 m2/day
exceeding 10m2
Production rate (per Hour) : 0.13 m2/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
2mm thick Aluminium m
p2 Skilled Person 1 1.00 Dump Truck 9 m3 1 0.50
Paint lit Labourers 5 1.00 Hand Tools ** 1.00

Reflective Road Sign Ea

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.a.i. Road Trafic Markings and Road Stud, Center


Work Item : line marking with white thermoplastic road marking Production rate (per SPD) : 180.00 m/day
paint, 100mm wide continuous line

Production rate (per Hour) : 22.50 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint m3 Paint car opp. 1 1 Dump Truck 9 m3 1 0.20
Labourers 10 1 Painting Car 1 1.00
Helper 1 1 Hand Tools ** 1.00
Dump Truck Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.a.ii. Road Trafic Markings and Road Stud,


Work Item : Center line marking with white thermoplastic road Production rate (per SPD) : 180.00 m/day
marking paint, 100mm wide brocken line

Production rate (per Hour) : 22.50 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint m3 Paint car opp. 1 1 Dump Truck 9 m3 1 0.20
Labourers 10 1 Painting Car 1 1.00
Helper 1 1 Hand Tools ** 1.00
Dump Truck Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.ba.i. Road Trafic Markings and Road Stud,


Work Item : Eadge marking with yellow thermoplastic road Production rate (per SPD) : 180.00 m/day
marking paint, 100mm wide Continous/brocken line

Production rate (per Hour) : 22.50 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint m3 Paint car opp. 1 1 Dump Truck 9 m3 1 0.20
Labourers 10 1 Painting Car 1 1.00
Helper 1 1 Hand Tools ** 1.00
Dump Truck Opp. 1 0.2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

95.01.c. Road Trafic Markings and Road


Stud,Lettering Symbols, Traverse lines, painted island,
Work Item : Production rate (per SPD) : 10.00 m/day
and arrested markings (white or yellow colour as
directed by the Engineer)

Production rate (per Hour) : 1.25 m/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Paint lit Skilled Person 2.00 1.00 Hand Tools ** 1.00

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

96.03.a. Grassing, Grassing includes preparation of


grassing area with top soiling, stockpiling of top soil,
Work Item : Production rate (per SPD) : 1,000.00 m2/day
and providing and applying chemical fertilizers,
seeding, and planting the grass cutting, all complete

Production rate (per Hour) : 125.00 m2/day

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Top soil m3 Skilled Person 1 1.00 Dump Truck 9 m3 1 0.40
Lime ton Labourer 10 1.00 Hand Tools ** 1.00

Super Phosphate ton Dump Truck Opp. 1 0.40

Limestone Ammonium
ton
Nitrate
Planting og grass cuttinm2

UF : Utilization Factor
** As required

1
ETHIOPIAN CONSTRUCTION WORKS CORPORATION
PROJECT ACTIVITY PERFORMANCE

Project : Shire Airfield upgrading project

96.03.b. Grassing, Planting of trees (Neem tree


(Azadirachta indica) Bosilia papyyrifera, Acacia seyal
and/or other approved local trees) by the road side in .6
dia. Holes, 1m deep dug in the ground, mixing the soil
Work Item : Production rate (per SPD) : 30.00 Ea/day
with decayed farm yard/sludge manure planting the
saplings, backfilling the trench, watering, fixing the
tree guardfixing the tree guard and maitaining the plant
for one year, all complete

Production rate (per Hour) : 3.75 Ea/hr

Material Labor Equipment


Material Unit Qty Title No UF
Equipment Type Capacity No UF
Type
Trees Ea Labourers 10 1.00 Dump Truck 9 m3 1 0.15
Dump Truck Opp. 1 0.40 Hand Tools ** 1.00

UF : Utilization Factor
** As required