Progress Claim No.8 (18122020)
Progress Claim No.8 (18122020)
CONTRACT NO : PWD/HO/B009/2019
CONTRACT NO : PWD/HO/B009/2019
CHECK BOX :
EOT3
9 Liquidated & Ascertained Damaged (LAD) 0.0219% of Original Contract Sum Per Day
12 Insurance
a. Contractor All Risk Insurance Policy No.
i. Policy No. 2019-BU-E0000859
ii. Amount RM25,347.32
iii. Expiry date 27/02/2019 to 26/02/2021
13 Contractor Account
a. Bank Detail CIMB BANK
b. Account No. 8009994700
c. Bank Address -
(Resident Engineer)
JKR 143 (Rev 11/08)
CONTRACT TITLE : MEMBINA JALAN BARU TATAU KE KUALA TATAU, BINTULU DIVISION
1. Contractor Address : KEMENA HOLDING SDN BHD (115564-D) Bank CIMB BANK
Lot 3053, Block 32, Kemena Industrial Estate, A/C No. 8009994700
Jalan Bintulu - Tatau, P.O. Box 1055, Assignee Nil
Particle Date
Completion 26th February 2021
97008 Bintulu, Sarawak, Malaysia
Date
GST Registration
Tel: 086-334091/336091 Fax: 086-317493 No.
3. Value of Workdone and Materials on Site as at 15th December 2020 (Details Attached)
a) Work Done b) Materials on Site c) 6% GST up to May 2018 d) Total to Date e) i. L&AD allowed f) Previous Payment g) Amount for this Certificate
ii. Nominated
Sub Contractor
iii. Nominated
Supplier
vii. Amount for which payment voucher will be made out. 223,594.99
I Certified that under the terms of Contract No. PWD/HO/B009/2019 the sum of RM 223,594.99
Ringgit Malaysia : Two Hundred Twenty Three Thousand Five Hundred Ninety Four and Cents Ninety Nine Only.
Superintending Officer
…………………………………………………………………………………………
(Singnature)
Date :
PROJECT TITLE: MEMBINA JALAN BARU TATAU KE KUALA TATAU,
BINTULU DIVISION
PAYMENT VERIFICATION
Confirm of Contractor's Work Progress Claim No. 8 in Complience with the Contract, Drawings & Specification.
We hereby certify, confirm and verify that the quality and standard of the works and workmanship carried out on site
and materials and goods which are delivered to site as per this Interim Payment ( For the workdone and materials on
site for period ending of 15th DECEMBER 2020) are all in accordance with Contract, Drawings and Specification requirements.
Endorsement of Approval :-
(Resident Engineer)
Date: :
LAMPIRAN B1
I/We Certify that the value of work done and material on site are correct and in strict accordance with
the drawings and specification.
_______________________ ___________________________
Managing Director Resident Engineer
LAMPIRAN B1
Amount (RM)
Ringgit Malaysia : Two Hundred Twenty Three Thousand Five Hundred Ninety Four and Cents Ninety Nine
Only.
SUMMARY OF ASSESSMENT EVALUATION CLAIM NO. 8 AS AT 15th DECEMBER 2020
Item Description Contract Sum (RM) Previous Workdone Current Workdone Final Workdone Workdone (%)
INITIAL ALLOCATION (A) RECURRING ALLOCATION (B) PROGRESSIVE ALLOCATION (C) COMPLETION ALLOCATION (D) WORKDONE (A+B+C+D)
Allocation Workdone Allocation Workdone Allocation Workdone Allocation Workdone Previous Certified Current This Month Total To Date
Item No. Code No. Description Unit Qty. Rate Amount (RM) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (RM) (RM) (%)
1.1.1 A131 CIDB Levy sum - 35,000.00 35,000.00 100% 35,000.00 100% 35,000.00 35,000.00 100.00
1.2 Insurance
1.1.2.1 A121 Insurance of the Works sum - 22,400.00 22,400.00 100% 22,400.00 100% 22,400.00 22,400.00 100.00
1.1.2.2 A123 SOSCO/ Workmen Compensation Insurance sum - 2,250.00 2,250.00 100% 2,250.00 100% 2,250.00 2,250.00 100.00
1.3.3 A212 Maintenance of office mth 24 1,000.00 24,000.00 24,000.00 100% 18,000.00 75.00% 16,999.20 1,000.80 18,000.00 75.00
1.3.5 A214 Maintenance of laboratories mth 24 500.00 12,000.00 12,000.00 100% 9,999.60 83.33% 9,500.40 499.20 9,999.60 83.33
sum -
1.4.1.4 A221.6 d) 1 no. Scanner, according to specified specification 600.00 600.00 100% 600.00 100% 600.00 600.00 100.00
sum -
1.4.1.6 f) 1 no. projector, according to specified specification 1,000.00 1,000.00 100% 1,000.00 100% 1,000.00 1,000.00 100.00
sum -
1.4.1.7 g) 1 no. fax machine, according to specified specification 1,200.00 1,200.00 100% 1,200.00 100% 1,200.00 1,200.00 100.00
1.4.1.8 h) 1 no. SiDRA Software sum - 70,000.00 70,000.00 100% 70,000.00 100% 70,000.00 - 70,000.00 100.00
a) Two (2) brand new air conditioned 4 doors twin cab sum -
1.5.2 100,000.00 50,000.00 50% 50,000.00 100% 50,000.00 50% 41,665.00 83.33% 89,585.00 2,080.00 91,665.00 91.66
vehicle with minimum 2500c.c
1.5.3 b) Three (3) Motorbikes 150c.c sum - 30,000.00 15,000.00 50% 15,000.00 100% 15,000.00 50% 11,250.00 75.00% 25,624.50 625.50 26,250.00 87.50
BILL NO. 1: PRELIMINARY AND GENERAL
INITIAL ALLOCATION (A) RECURRING ALLOCATION (B) PROGRESSIVE ALLOCATION (C) COMPLETION ALLOCATION (D) WORKDONE (A+B+C+D)
Allocation Workdone Allocation Workdone Allocation Workdone Allocation Workdone Previous Certified Current This Month Total To Date
Item No. Code No. Description Unit Qty. Rate Amount (RM) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (%) (RM) (RM) (RM) (%)
1.6 Attendance for the SO/PD's Staff
1.6.1 A241 Drivers (21 x 2 = 42 man month) sum - 100,000.00 100,000.00 100% 83,330.00 83.33% 25,500.00 3,415.00 28,915.00 28.92
1.6.2 A243 Laboratory assistants (24 man month) sum - 100,000.00 100,000.00 100% 83,330.00 83.33% 79,170.00 4,160.00 83,330.00 83.33
1.6.3 A310 Setting out, levelling and checking of all Works sum - 50,000.00 35,000.00 70% 35,000.00 100% 15,000.00 30% 35,000.00 35,000.00 70.00
1.7 Miscellaneous
1.7.1 A262 Project sign boards (6 no.) sum - 18,000.00 18,000.00 100% 5,400.00 30% 5,400.00 5,400.00 30.00
1.7.2 A261 Progress photograph (24 months) sum - 9,600.00 9,600.00 100% 6,048.00 63.00% 6,048.00 6,048.00 63.00
sum -
Provide and update the Works Programme using Master
Programme to produce the Critical Path Method (CPM)
1.7.4 A254 15,000.00 4,500.00 30% 4,500.00 100% 10,500.00 70% 5,250.00 50.00% 9,750.00 9,750.00 65.00
and Works Breakdown Structure (WBS) etc. including
supply of software as specified in Appendix '1G'
1.9 Quality Assurance Plans sum - 5,000.00 2,500.00 50% 2,500.00 100% 2,500.00 50% 2,500.00 2,500.00 50.00
1.10.1.1 A511.1 a) Office sum - 20,000.00 4,000.00 20% 4,000.00 100% 12,000.00 60% 4,000.00 20.00% 4,000.00 4,000.00 20.00
1.10.1.2 A515.1 b) Stores and workshops sum - 20,000.00 4,000.00 20% 4,000.00 100% 12,000.00 60% 4,000.00 20.00% 4,000.00 4,000.00 20.00
1.10.1.3 A517.2 c) Workmen accommodations sum - 20,000.00 4,000.00 20% 4,000.00 100% 12,000.00 60% 4,000.00 20.00% 4,000.00 4,000.00 20.00
1.10.2.1 A521.1 a) access and haul roads sum - 50,000.00 50,000.00 100% 27,500.00 55.00% 25,000.00 2,500.00 27,500.00 55.00
1.10.2.2 Supervision (21 man-months) sum - 52,500.00 52,500.00 100% 39,375.00 75.00% 37,185.75 2,189.25 39,375.00 75.00
sum -
Mobilisation and demobilisation of construction plants
1.10.2.3 and equipments excluding piling and specialise plants 50,000.00 50,000.00 100% 15,000.00 30% 12,500.00 2,500.00 15,000.00 30.00
1.11.1 A411 Compliance to the Occupational and Health sum - 5,000.00 2,500.00 50% 2,500.00 100% 2,500.00 50% 2,500.00 2,500.00 50.00
TOTAL 1,013,550.00 359,950.00 347,350.00 221,500.00 74,625.00 375,100.00 276,182.60 57,000.00 - 624,772.85 18,969.75 643,742.60 63.51
BILL NO. 2: PILING FOR CIVIL WORKS
H251.13 a) Supply, deliver, handle and pitch initial piles with shoes
m 19,128.00 39.00 745,992.00 6,684.00 6,684.00 260,676.00
of 6m length
H254.2 d) Jointing with butt weld all round No 3,188.00 81.60 260,140.80 1,855.00 1,855.00 151,368.00
H251.13 a) Supply, deliver, handle and pitch initial piles with shoes
m 1,434.00 72.30 103,678.20
of 6m length
H254.2 d) Jointing with butt weld all round No 239.00 109.70 26,218.30
H251.13 a) Supply, deliver, handle and pitch initial piles with shoes
m 1,440.00 96.00 138,240.00
of 12m length
H254.2 d) Jointing with butt weld all round No 120.00 164.00 19,680.00
3.3.1.1 H261.1 Supply and deliver initial pile with rock shoes of 12m length No 32.00 302.60 9,683.20
3.3.1.4 H262.2 Depth driven raked at inclination ratio of 1:6 m 551.50 79.00 43,568.50
3.3.1.7 H265 Cut-off piles. Rate to include preparing heads no 32.00 90.90 2,908.80
Total 364,857.70 -
BILL NO. 4: CIVIL WORKS
4.2.2 2) Cut
4.2.2.1 F120.1 a) Cut and dispose m3 21,250.00 8.20 174,250.00 7,757.44 1,695.73 9,453.17 77,515.99
4.2.3 3) Fill
a) Excavate in earth material from original ground level (to
4.2.3.1 F311 m3 73,179.00 4.00 292,716.00 36,993.44 - 36,993.44 147,973.76
form embankment)
4.2.3.2 F311.1 b) Using excavated material to road shoulders m3 11,822.00 4.00 47,288.00 -
4.2.3.3 F311.2 c) Using excavated rock material (Provisional) m3 5,000.00 4.00 20,000.00 -
4.2.3.4 F312.1 d) Using imported earth m3 213,266.00 16.50 3,518,889.00 11,334.56 - 11,334.56 187,020.24
4.2.4 4) Replacement
4.2.4.1 a) Replacement using suitable imported earth material m3 105,048.15 16.50 1,733,294.47 -
4.2.4 4) Landscaping
4.2.4.1 F510.3 a) Spot turfing at flat areas m2 6,054.00 5.60 33,902.40 -
4.2.4.2 F510.4 b) Close turfing at slope areas m2 77,393.88 6.60 510,799.61 -
SUBTOTAL 8,557,299.12 932,440.93
BILL NO. 4: CIVIL WORKS
P201
a) Embankment toe drain (Type 1); 1,500mm wide
4.4.1.1 m 10,890.00 12.90 140,481.00 -
(average) x 600mm deep trapezoidal shape (earth drain)
4.4.1.7 g) Stream diversion channel; 12m wide x 4m deep m3 5,760.00 4.60 26,496.00 -
BILL NO. 4: CIVIL WORKS
4.4.2.3 P619.12 a) 900mm diameter single precast concrete pipe culvert No 26.00 2,807.30 72,989.80 -
4.4.2.4 P619.14 b) 1,500mm diameter single precast concrete pipe culvert No. 56.00 5,053.30 282,984.80 22.00 0.00 22.00 111,172.60
4.4.2.5 P619.52 a) 900mm diameter single precast concrete pipe culvert m3 53.00 214.90 11,389.70 -
4.4.2.6 P619.54 b) 1,500mm diameter single precast concrete pipe culvert m3 243.00 214.90 52,220.70 97.24 0.00 97.24 20,896.88
4.4.2.7 P721.12 a) 900mm diameter single precast concrete pipe culvert No. 1.00 1,684.40 1,684.40 -
4.4.2.9 b) G25 Mass Concrete-Holding the Pipe Culvert m 159.00 856.60 136,199.40 -
4.4.2.11 b) G25 mass concrete-holding the pipe culvert m 766.00 887.20 679,595.20 321.00 0.00 321.00 284,791.20
4.4.2.12.1 P622.11 a) 2.10 x 2.10m high twin box culvert m 25.00 6,478.50 161,962.50 -
4.4.2.12.2 P622.44 b) 3.60 x 3.60m high twin box culvert m 37.50 13,604.80 510,180.00 -
4.4.2.12.3 P624.55 c) 3.60 x 3.60m high triple box culvert m 39.00 23,214.50 905,365.50 -
4.4.2.13.1 P619.21 d) 2.10 x 2.10m high twin box culvert No 2.00 17,815.80 35,631.60 -
4.4.2.13.2 P619.24 e) 3.60 x 3.60m high twin box culvert No 2.00 26,345.80 52,691.60 -
4.4.2.13.3 P619.27 f) 3.60 x 3.60m high triple box culvert No. 2.00 56,689.00 113,378.00 -
4.4.2.14.1 P619.62 g) 2.10 x 2.10m high twin box culvert m3 5.00 215.00 1,075.00 -
4.4.2.14.2 P619.65 h) 3.60 x 3.60m high twin box culvert m3 8.00 215.00 1,720.00 -
4.4.2.14.3 P619.68 i) 3.60 x 3.60m high triple box culvert m3 10.00 215.00 2,150.00 -
4.4.2.15.1 P721.22 a) In-situ concrete grade 25; 1,800 x 1,800 x 1,200mm deep No 8.00 1,372.80 10,982.40 -
Catchpit
4.4.2.15.2 P721.25 a) In-situ concrete grade 25; 1,500 x 1,500 x 800mm deep No 6.00 1,173.80 7,042.80 2.00 0.00 2.00 2,347.60
4.5.2 2) Sub-base
4.5.3 3) Roadbase
4.5.7.2 Q211 b) Crushed aggregate sub-base 250mm thick m2 1,298.00 25.00 32,450.00 -
c) Type 5 - Centre Line/ Lane Line (Rural Area) m 30.00 1.00 30.00 -
5.1 SUBSTRUCTURE
SG. ANNAU BRIDGE
5.1.1 ABUTMENTS
5.1.1.1 Earthwork
5.1.1.1.1 Cut to Fill
Excavation in cut shall be deemed to include trimming and
preparation of excavated surface and transportation from
source to place of fill or disposal
Excavate in earth material from original ground level to
F121.1 m3 100.00 10.00 1,000.00 -
form embankment
5.1.1.2.1 Gabion
G100 Plant and equipment
SUBTOTAL 13,011.00 -
BILL NO. 5: BRIDGE
B/F: 13,011.00 -
5.1.1.4.1 Sides
Joints
Rate for joints shall be deemed to include formwork
Dowels - sealed and capped, 32mm diameter x 1000mm
steel bars at fixed joint complete with 60mm OD rubber
I617 No 4.00 44.20 176.80 - -
dowel cap, concrete infill/ grout, compressible material and
mortar as per Drawings
BILL NO. 5: BRIDGE
B/F: 482,083.80 -
5.2 SUPERSTRUCTURE
SG ANNAU BRIDGE
5.2.1.1 H100 Plant and Equipment
Inclined internalPrestressing
Post-Tensioned tendons in precast concrete, 19 wire
standard strand to BS 5896, Class 1: nominal diameter
I624.2 No 12.00 9,690.00 116,280.00 - -
15.2mm; concrete cone anchors to BS 1477, 25m length for
I-beam as shown in Drawing
5.2.1.4 T400 Bridge Bearings
B/F: 1,049,815.80 -
Cast In-situ Concrete Deck Slab (Including Lamp Post
5.2.1.6
Plinths and Kerbs)
SUBTOTAL 1,228,592.30 -
BILL NO. 5: BRIDGE
B/F: 1,228,592.30 -
5.2.1.7 L200 Miscellaneous Metalwork
Item for miscellaneous metalwork shall be deemed to
include fixing to other work, supply of fixing components
and drilling or cutting of other work
L250.2 100mm OD x 5.4mm thick x 11.93kg/m circular m 40.00 336.50 13,460.00 - -
P410.1 100mm diameter uPVC Class "C" rain water down pipes m 18.00 28.00 504.00 - -
100mm diameter uPVC Class "C" angle elbow for rain water
P420.1 No 8.00 45.90 367.20 - -
down pipes
5.3 DIAPHRAGMS
Cast In-Situ Diaphragms
SUBTOTAL 1,313,858.75 -
BILL NO. 5: BRIDGE
B/F: 1,313,858.75 -
5.3 DIAPHRAGMS
Joints
TOTAL 1,352,618.75 -
BILL NO. 6: BRIDGE EMBANKMENT WALL
6.1.1.2.1 I111 Mass concrete blinding 50mm thick [to footing] m2 304.00 20.40 6,201.60 - -
6.1.1.3 Formwork
6.1.1.3.1 Sides
6.1.1.3.1.1 I411 F1: rough finish for buried bases m2 268.50 70.50 18,929.25 - -
SUBTOTAL 190,439.80 -
B/F: 190,439.80 -
6.1.1.4 Drainage
Item for drains shall be deemed to include geotextiles
fabric, lining and filter material
TOTAL 312,945.40 -
BILL NO. 7: ENVIRONMENTAL
7.4.5 B450 5) Quarterly air quality sampling (3 sampling locations) Lot 8.00 100.00 800.00 1.00 0.00 1.00 100.00
7.8.4 B810.4 4) Environmental monitoring report for ambient air No 8.00 500.00 4,000.00 1.00 0.00 1.00 500.00
7.8.5 B810.5 5) Environmental monitoring report for noise measurement No 8.00 500.00 4,000.00 1.00 0.00 1.00 500.00
7.9 MISCELLANEOUS
8.1.1 C120 1) Preparation of traffic management plan LS 5,000.00 90.00% 0.00% 90.00% 4,500.00
Man-
8.1.2 C130.1 a) Traffic Management Officer (1 person) 20.00 5,000.00 100,000.00 -
Mth
Man-
8.1.3 C130.2 b) Traffic Supervisor (4 persons) 24.00 3,000.00 72,000.00 62.50% 4.17% 66.67% 48,002.40
Mth
Man-
8.1.4 C130.3 c) Driver (4 persons) 24.00 2,000.00 48,000.00 62.50% 4.17% 66.67% 32,001.60
Mth
Man-
8.1.5 C130.4 d) Traffic Controller (10 persons) 24.00 1,500.00 36,000.00 62.50% 4.17% 66.67% 24,001.20
Mth
Man-
8.1.6 C130.5 e) Flagman (8 persons) 16.00 1,200.00 19,200.00 62.50% 4.17% 66.67% 12,800.64
Mth
8.1.7 C130.6 f) Provision for personal protective equipment LS 5,000.00 100.00% 0.00% 100.00% 5,000.00
g) Two (2) unit lorry (1 ton) for traffic management usage Veh-
8.1.8 C130.7 24.00 500.00 12,000.00 58.33% 4.17% 62.50% 7,500.00
including fuel and maintenance Mth
h) One (1) unit of vehicle for Traffic Officer including fuel Veh-
8.1.9 C130.8 24.00 500.00 12,000.00 0.00% 0.00% 0.00% -
and maintenance Mth
8.1.10 C130.9 i) Accommodation for traffic management team Mth 24.00 1,000.00 24,000.00 50.00% 4.17% 54.17% 13,000.80
BILL NO. 8: TRAFFIC
8.2.1 C210.2 1) Light weight movable plastic barriers LS 500.00 75.00% 5.00% 80.00% 400.00
8.2.3 C210.4 3) Light weight traffic guidance cones LS 500.00 75.00% 5.00% 80.00% 400.00
8.2.7 C210.8 7) Boneka orang bergerak (robotic flagman) LS 500.00 75.00% 5.00% 80.00% 400.00
8.3.1 C211.1 1) Not exceeding 1m2 LS 500.00 75.00% 5.00% 80.00% 400.00
moving and handling of all plant and equipment LS 50,000.00 75.00% 75.00% 37,500.00
8.6.3 3) Sub-base
C500 crushed aggregates LS 10,000.00 75.00% 75.00% 7,500.00
8.6.5 5) Surfacing
C700 i) Prime coat LS 10,000.00 -
Qty.
Total Remaining To-Date
Amount
Item No. Description Unit Delivered Used Rate (RM)
(RM)
a b c=a-b
1 1500mm Diameter Class Z RC Pipe Culvert No 253.00 214.00 39.00 1,953.90 76,202.10
2 150mm x 150mm RC Square Pile as initial piles in 6m length No 1,950.00 - 1,950.00 39.00 76,050.00
TOTAL 216,975.30
75% Allow 162,731.48
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 2: PILING FOR CIVIL WORKS - 150mm square precast reinforced concrete piles
Item No. 2.1.1.1
Code H251.13 H251.23 H252.2 H254.2 H256.2
c) Driven d) Jointing e) Cut-off
a) Supply, b) Supply, depth with butt piles
deliver, deliver, weld all
handle and handle and round
Description pitch initial pitch Date
piles with extension
shoes of 6m piles of 6m
length length
Unit Length (m) Length (m) Length (m) Number (no) Number (no)
Total Qty 19,128.00 19,128.00 19,128.00 3,188.00 3,188.00
No.2 (LHS) 312.00 126.00 296.70 21.00 52.00 Until 25/08/2019
No.4 (LHS) 300.00 288.00 403.70 48.00 50.00
26/08/2019 to
No. 6 (RHS) 240.00 720.00 761.10 120.00 40.00
25/09/2019
No. 7 (RHS) 312.00 - 224.70 - 52.00
No. 3 (LHS) 222.00 444.00 555.00 74.00 37.00
No. 7 (LHS) 162.00 - 103.20 - 27.00
26/09/2019 to
No. 6 (RHS) 6.00 18.00 19.50 2.00 1.00
25/10/2019
No. 6 (LHS)
150.00 450.00 496.80 75.00 25.00
No. 6 (LHS) 108.00 324.00 358.80 54.00 18.00
Until 25/11/2019
No. 5(Both) 624.00 647.00 1,116.30 108.00 104.00
Workdone 26/11/19
No. 8(Both) 534.00 534.00 972.70 89.00 89.00
to 25/12/2019
Workdone 26 Dec to
No.2 (RHS) 312.00 312.00 580.08 52.00 52.00
25 Jan 2020
Workdone 26 Feb to
No.3 (RHS) 276.00 282.00 508.14 47.00 46.00
16 March 2020
Workdone 29 June to
No.10 (Both) 588.00 588.00 969.00 98.00 98.00
02 July 2020
Workdone 08 July
No.11 (Both) 588.00 1,176.00 1,691.10 196.00 98.00
2020 to 13 July 2020
Workdone 08 July
No.12 570.00 1,710.00 1,947.80 285.00 95.00 2020 to 22 August
2020
Workdone 17 Oct
No.13 588.00 1,764.00 1,916.10 294.00 98.00
2020 to 27 Oct 2020
Workdone 6,684.00 11,135.00 15,256.70 1,855.00 1,114.00
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.1 Stripping Over Cut Area Average Depth 150mm
CERTIFIED BY CONSULTANT
CALCULATED BASED ON DED CALCULATED BASED ON WORKDONE (M2)
STRIPPING AVE. LENGTH STRIPPING AREA AVE. LENGTH STRIPPING AREA QUANTITY
CH WORKDONE (M) WORKDONE %
LENGTH (M) (M) (M2) (M) (M2) (M2)
CH.0+000 - - - - - -
CH.0+025 - - - - - -
CH.0+050 - - - - - -
CH.0+075 - - - - - -
CH.0+100 11.18 5.59 139.75 11.18 5.59 139.75 100.00% 139.75
CH.0+125 13.57 12.38 309.38 13.57 12.38 309.38 100.00% 309.38
CH.0+150 10.57 12.07 301.75 10.57 12.07 301.75 100.00% 301.75
CH.0+175 - 5.29 132.13 - 5.29 132.13 100.00% 132.13
CH.0+200 - - - - - -
CH.0+225 - - - - - -
CH.0+250 5.36 2.68 67.04 5.36 2.68 67.04 100.00% 67.04
CH.0+275 14.92 10.14 253.54 14.92 10.14 253.54 100.00% 253.54
CH.0+300 18.64 16.78 419.50 18.64 16.78 419.50 100.00% 419.50
CH.0+325 22.00 20.32 508.00 22.00 20.32 508.00 100.00% 508.00
CH.0+350 19.67 20.84 520.90 19.67 20.84 520.90 100.00% 520.90
CH.0+375 18.92 19.30 482.41 18.92 19.30 482.41 100.00% 482.41
CH.0+400 15.43 17.17 429.33 15.43 17.17 429.33 100.00% 429.33
CH.0+425 12.66 14.04 351.04 12.66 14.04 351.04 100.00% 351.04
CH.0+450 - 6.33 158.23 - 6.33 158.23 100.00% 158.23
CH.0+475 - - - - - - -
CH.0+500 - - - - - - -
CH.0+525 - - - - - - -
CH.0+550 - - - - - - -
CH.0+575 - - - - - - -
CH.0+600 - - - - - - -
CH.0+625 - - - - - - -
CH.0+650 - - - - - - -
CH.0+675 - - - - - - -
CH.0+700 - - - - - - -
CH.0+725 - - - - - - -
CH.0+750 - - - - - - -
CH.0+775 - - - - - - -
CH.0+800 - - - - - - -
CH.0+825 - - - - - - -
CH.0+850 - - - - - - -
CH.0+875 - - - - - - -
CH.0+900 30.79 15.40 384.91 30.79 15.40 384.91 100.00% 384.91
CH.0+925 23.46 27.13 678.15 23.46 27.13 678.15 100.00% 678.15
CH.0+950 7.82 15.64 391.04 7.82 15.64 391.04 100.00% 391.04
CH.0+975 6.26 7.04 175.99 6.26 7.04 175.99 100.00% 175.99
CH.1+000 - 3.13 78.19 - 3.13 78.19 100.00% 78.19
CH.1+025 - - - - - - -
CH.1+050 - - - - - - -
CH.1+075 - - - - - - -
CH.1+100 - - - - - - -
CH.1+125 - - - - - - -
CH.1+150 - - - - - - -
CH.1+175 24.78 12.39 309.79 24.78 12.39 309.79 50.00% 154.89
CH.1+200 18.46 21.62 540.58 18.46 21.62 540.58 50.00% 270.29
CH.1+225 6.70 12.58 314.48 6.70 12.58 314.48 50.00% 157.24
CH.1+250 - 3.35 83.69 - 3.35 83.69 50.00% 41.84
CH.1+275 - - - - - - -
CH.1+300 - - - - - - -
CH.1+325 - - - - - - -
CH.1+350 - - - - - - -
CH.1+375 - - - - - - -
CH.1+400 - - - - - - -
CH.1+425 - - - - - - -
CH.1+450 4.65 2.33 58.14 4.65 2.33 58.14 100.00% 58.14
CH.1+475 - 2.33 58.14 - 2.33 58.14 100.00% 58.14
CH.1+500 5.08 2.54 63.44 5.08 2.54 63.44 100.00% 63.44
CH.1+525 - 2.54 63.44 - 2.54 63.44 100.00% 63.44
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.1 Stripping Over Cut Area Average Depth 150mm
CERTIFIED BY CONSULTANT
CALCULATED BASED ON DED CALCULATED BASED ON WORKDONE (M2)
STRIPPING AVE. LENGTH STRIPPING AREA AVE. LENGTH STRIPPING AREA QUANTITY
CH WORKDONE (M) WORKDONE %
LENGTH (M) (M) (M2) (M) (M2) (M2)
CH.1+550 - - - - - - -
CH.1+575 - - - - - - -
CH.1+600 - - - - - - -
CH.1+625 13.64 6.82 170.44 13.64 6.82 170.44 100.00% 170.44
CH.1+650 18.91 16.27 406.78 18.91 16.27 406.78 100.00% 406.78
CH.1+675 18.87 18.89 472.20 18.87 18.89 472.20 100.00% 472.20
CH.1+700 19.43 19.15 478.67 19.43 19.15 478.67 100.00% 478.67
CH.1+725 19.15 19.29 482.19 19.15 19.29 482.19 100.00% 482.19
CH.1+750 12.79 15.97 399.21 12.79 15.97 399.21 100.00% 399.21
CH.1+775 10.43 11.61 290.20 10.43 11.61 290.20 100.00% 290.20
CH.1+800 18.46 14.44 361.09 18.46 14.44 361.09 100.00% 361.09
CH.1+825 20.73 19.59 489.84 20.73 19.59 489.84 100.00% 489.84
CH.1+850 19.83 20.28 506.96 19.83 20.28 506.96 100.00% 506.96
CH.1+875 19.40 19.61 490.33 19.40 19.61 490.33 100.00% 490.33
CH.1+900 2.20 10.80 269.97 2.20 10.80 269.97 100.00% 269.97
CH.1+925 - - - - - - -
CH.1+950 - - - - - - -
CH.1+975 - - - - - - -
CH.2+000 10.79 5.40 134.91 10.79 5.40 134.91 100.00% 134.91
CH.2+025 46.40 28.59 714.86 46.40 28.59 714.86 100.00% 714.86
CH.2+050 61.19 53.80 1,344.88 61.19 53.80 1,344.88 100.00% 1,344.88
CH.2+075 66.88 64.04 1,600.91 66.88 64.04 1,600.91 100.00% 1,600.91
CH.2+100 30.23 48.56 1,213.91 30.23 48.56 1,213.91 100.00% 1,213.91
CH.2+125 - 15.12 377.93 - 15.12 377.93 100.00% 377.93
CH.2+150 - - - - - - -
CH.2+175 - - - - - - -
CH.2+200 - - - - - - -
CH.2+225 17.37 8.68 217.11 17.37 8.68 217.11 100.00% 217.11
CH.2+250 27.35 22.36 559.03 27.35 22.36 559.03 100.00% 559.03
CH.2+275 22.59 24.97 624.31 22.59 24.97 624.31 100.00% 624.31
CH.2+300 64.00 43.30 1,082.41 64.00 43.30 1,082.41 100.00% 1,082.41
CH.2+325 47.82 55.91 1,397.80 47.82 55.91 1,397.80 100.00% 1,397.80
CH.2+350 43.22 45.52 1,138.05 43.22 45.52 1,138.05 100.00% 1,138.05
CH.2+375 42.15 42.69 1,067.13 42.15 42.69 1,067.13 100.00% 1,067.13
CH.2+400 32.53 37.34 933.50 32.53 37.34 933.50 100.00% 933.50
CH.2+425 - 16.27 406.64 - 16.27 406.64 100.00% 406.64
CH.2+450 - - - - - - -
CH.2+475 - - - - - - -
CH.2+500 - - - - - - -
CH.2+525 - - - - - - -
CH.2+550 - - - - - - -
CH.2+575 - - - - - - -
CH.2+600 - - - - - - -
CH.2+625 - - - - - - -
CH.2+650 - - - - - - -
CH.2+675 - - - - - - -
CH.2+700 - - - - - - -
CH.2+725 - - - - - - -
CH.2+750 - - - - - - -
CH.2+775 - - - - - - -
CH.2+800 - - - - - - -
CH.2+825 - - - - - - -
CH.2+850 - - - - - - -
CH.2+875 - - - - - - -
CH.2+900 - - - - - - -
CH.2+925 - - - - - - -
CH.2+950 - - - - - - -
CH.2+975 - - - - - - -
CH.3+000 - - - - - - -
CH.3+025 - - - - - - -
CH.3+050 - - - - - - -
CH.3+075 - - - - - - -
CH.3+100 - - - - - - -
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.1 Stripping Over Cut Area Average Depth 150mm
CERTIFIED BY CONSULTANT
CALCULATED BASED ON DED CALCULATED BASED ON WORKDONE (M2)
STRIPPING AVE. LENGTH STRIPPING AREA AVE. LENGTH STRIPPING AREA QUANTITY
CH WORKDONE (M) WORKDONE %
LENGTH (M) (M) (M2) (M) (M2) (M2)
CH.3+125 - - - - - - -
CH.3+150 - - - - - - -
CH.3+175 - - - - - - -
CH.3+200 - - - - - - -
CH.3+225 - - - - - - -
CH.3+250 - - - - - - -
CH.3+275 - - - - - - -
CH.3+300 - - - - - - -
CH.3+325 - - - - - - -
CH.3+350 - - - - - - -
CH.3+375 - - - - - - -
CH.3+400 - - - - - - -
CH.3+425 24.37 12.18 304.56 24.37 12.18 304.56 100.00% 304.56
CH.3+450 34.77 29.57 739.21 34.77 29.57 739.21 100.00% 739.21
CH.3+475 31.35 33.06 826.55 31.35 33.06 826.55 75.77% 626.31
CH.3+500 22.60 26.98 674.43 22.60 26.98 674.43 0.00% -
CH.3+525 - 11.30 282.53 - 11.30 282.53 0.00% -
CH.3+550 - - - - - - -
CH.3+575 - - - - - - -
CH.3+600 - - - - - - -
CH.3+625 - - - - - - -
CH.3+650 - - - - - - -
CH.3+675 - - - - - - -
CH.3+700 - - - - - - -
CH.3+725 - - - - - - -
CH.3+750 - - - - - - -
CH.3+775 - - - - - - -
CH.3+800 - - - - - - -
CH.3+825 - - - - - - -
CH.3+850 - - - - - - -
CH.3+875 - - - - - - -
CH.3+900 - - - - - - -
CH.3+925 - - - - - - -
CH.3+950 - - - - - - -
CH.3+975 - - - - - - -
CH.4+000 - - - - - - -
CH.4+025 - - - - - - -
CH.4+050 - - - - - - -
CH.4+075 - - - - - - -
CH.4+100 - - - - - - -
CH.4+125 - - - - - - -
CH.4+150 - - - - - - -
CH.4+175 - - - - - - -
CH.4+200 - - - - - - -
CH.4+225 - - - - - - -
CH.4+250 - - - - - - -
CH.4+275 - - - - - - -
CH.4+300 - - - - - - -
CH.4+325 - - - - - - -
CH.4+350 - - - - - - -
CH.4+375 - - - - - - -
CH.4+400 - - - - - - -
CH.4+425 - - - - - - -
CH.4+450 - - - - - - -
CH.4+475 - - - - - - -
CH.4+500 - - - - - - -
CH.4+525 - - - - - - -
CH.4+550 - - - - - - -
CH.4+575 22.42 11.21 280.29 22.42 11.21 280.29 0.00% -
CH.4+600 27.60 25.01 625.26 27.60 25.01 625.26 0.00% -
CH.4+625 - 13.80 344.97 - 13.80 344.97 0.00% -
CH.4+650 - - - - - - -
CH.4+675 - - - - - - -
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.1 Stripping Over Cut Area Average Depth 150mm
CERTIFIED BY CONSULTANT
CALCULATED BASED ON DED CALCULATED BASED ON WORKDONE (M2)
STRIPPING AVE. LENGTH STRIPPING AREA AVE. LENGTH STRIPPING AREA QUANTITY
CH WORKDONE (M) WORKDONE %
LENGTH (M) (M) (M2) (M) (M2) (M2)
CH.4+700 - - - - - - -
CH.4+725 - - - - - - -
CH.4+750 - - - - - - -
CH.4+775 - - - - - - -
CH.4+800 - - - - - - -
CH.4+825 - - - - - - -
CH.4+850 - - - - - - -
CH.4+875 - - - - - - -
CH.4+900 - - - - - - -
CH.4+925 - - - - - - -
CH.4+950 - - - - - - -
CH.4+975 - - - - - - -
CH.5+000 - - - - - - -
CH.5+025 - - - - - - -
CH.5+050 - - - - - - -
CH.5+075 - - - - - - -
CH.5+100 - - - - - - -
CH.5+125 - - - - - - -
CH.5+150 - - - - - - -
CH.5+175 - - - - - - -
CH.5+200 - - - - - - -
CH.5+225 - - - - - - -
CH.5+250 - - - - - - -
CH.5+275 - - - - - - -
CH.5+300 - - - - - - -
CH.5+325 - - - - - - -
CH.5+350 - - - - - - -
CH.5+375 - - - - - - -
CH.5+400 - - - - - - -
CH.5+425 - - - - - - -
CH.5+450 - - - - - - -
CH.5+475 - - - - - - -
CH.5+500 - - - - - - -
CH.5+525 - - - - - - -
CH.5+550 - - - - - - -
CH.5+575 - - - - - - -
CH.5+600 - - - - - - -
CH.5+625 - - - - - - -
CH.5+650 - - - - - - -
CH.5+675 - - - - - - -
CH.5+700 - - - - - - -
CH.5+725 - - - - - - -
CH.5+750 - - - - - - -
CH.5+775 - - - - - - -
CH.5+800 - - - - - - -
CH.5+825 - - - - - - -
CH.5+850 - - - - - - -
CH.5+875 - - - - - - -
CH.5+900 - - - - - - -
CH.5+925 - - - - - - -
CH.5+950 - - - - - - -
CH.5+975 - - - - - - -
CH.6+000 - - - - - - -
CH.6+025 - - - - - - -
CH.6+050 - - - - - - -
CH.6+075 - - - - - - -
CH.6+100 - - - - - - -
CH.6+125 - - - - - - -
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.1 Stripping Over Cut Area Average Depth 150mm
CERTIFIED BY CONSULTANT
CALCULATED BASED ON DED CALCULATED BASED ON WORKDONE (M2)
STRIPPING AVE. LENGTH STRIPPING AREA AVE. LENGTH STRIPPING AREA QUANTITY
CH WORKDONE (M) WORKDONE %
LENGTH (M) (M) (M2) (M) (M2) (M2)
CH.6+150 - - - - - - -
CH.6+175 - - - - - - -
CH.6+200 - - - - - - -
CH.6+225 - - - - - - -
CH.6+250 - - - - - - -
CH.6+275 - - - - - - -
CH.6+300 - - - - - - -
CH.6+325 - - - - - - -
CH.6+350 - - - - - - -
CH.6+375 - - - - - - -
CH.6+400 - - - - - - -
CH.6+425 - - - - - - -
CH.6+450 - - - - - - -
CH.6+475 - - - - - - -
CH.6+500 - - - - - - -
CH.6+525 - - - - - - -
CH.6+550 - - - - - - -
CH.6+575 - - - - - - -
CH.6+600 - - - - - - -
CH.6+625 - - - - - - -
CH.6+650 - - - - - - -
CH.6+675 - - - - - - -
CH.6+700 - - - - - - -
CH.6+725 - - - - - - -
CH.6+750 - - - - - - -
Stripping Over Cut Area m2 Workdone for Stripping Over Cut Area m2 Certified by Consultant m2
CALCULATION FOR CUT BASED ON DED CALCULATION FOR FILL WORKDONE FOR CUT WORKDONE FOR FILL
BASED ON DED
CH.0+000 0 - - - - - 22.91 - -
CH.0+025 25 - - - - - 18.09 20.50 512.44
CH.0+050 25 - - - - - 16.62 17.35 433.87
CH.0+075 25 - - - - - 7.30 11.96 298.99
CH.0+100 25 4.75 2.37 59.34 20.96 38.38 0.32 3.81 95.13
CH.0+125 25 2.77 3.76 93.90 46.41 47.49 1.04 0.68 16.97
CH.0+150 25 1.81 2.29 57.18 45.26 11.91 0.08 0.56 13.99 -
CH.0+175 25 - 0.90 22.61 19.82 2.79 99.72 49.90 1,247.43 91.34 45.67 25 1,141.75
CH.0+200 25 - - - - - 10.81 55.26 1,381.60 6.51 48.93 25 1,223.13
CH.0+225 25 - - - - - 12.24 11.52 288.09 3.26 25 81.38
CH.0+250 25 1.48 0.74 18.53 10.06 8.47 7.56 9.90 247.48
CH.0+275 25 6.50 3.99 99.71 38.03 61.68 0.01 3.79 94.68
CH.0+300 25 7.60 7.05 176.19 62.93 113.26 - 0.01 0.16
CH.0+325 25 16.66 12.13 303.25 76.20 227.05 0.12 0.06 1.47
CH.0+350 25 15.37 16.02 400.41 78.13 322.28 0.51 0.32 7.88
CH.0+375 25 13.22 14.30 357.43 72.36 285.06 0.07 0.29 7.32
CH.0+400 25 7.32 10.27 256.78 64.40 192.38 0.19 0.13 3.26
CH.0+425 25 10.42 8.87 221.79 52.66 169.13 1.01 0.60 14.92
CH.0+450 25 - 5.21 130.28 23.73 106.54 14.52 7.77 194.13
CH.0+475 25 - - - - - 21.23 17.88 446.91
CH.0+500 25 - - - - - 24.76 22.99 574.86
CH.0+525 25 - - - - - 16.52 20.64 515.98
CH.0+550 25 - - - - - 27.00 21.76 544.03
CH.0+575 25 - - - - - 33.70 30.35 758.73
CH.0+600 25 - - - - - 17.45 25.57 639.26
CH.0+625 25 - - - - - 15.98 16.71 417.80
CH.0+650 25 - - - - - 35.56 25.77 644.16
CH.0+675 25 - - - - - 41.91 38.73 968.26 -
CH.0+700 25 - - - - - 46.85 44.38 1,109.48 32.76 16.38 25 409.50
CH.0+725 25 - - - - - 58.78 52.82 1,320.42 41.79 37.28 25 931.88
CH.0+750 25 - - - - - 66.01 62.40 1,559.93 51.91 46.85 25 1,171.25
CH.0+775 25 - - - - - 56.17 61.09 1,527.31 25.96 25 648.88
CH.0+800 25 - - - - - 42.36 49.27 1,231.64
CH.0+825 25 - - - - - 40.08 41.22 1,030.53
CH.0+850 25 - - - - - 23.40 31.74 793.54
CH.0+875 25 - - - - - 18.30 20.85 521.21
CH.0+900 25 61.05 30.53 763.18 57.74 705.44 4.45 11.37 284.34
CH.0+925 25 31.39 46.22 1,155.53 101.72 1,053.80 8.49 6.47 161.71
CH.0+950 25 8.02 19.71 492.63 58.66 433.97 6.51 7.50 187.43
CH.0+975 25 6.05 7.04 175.90 26.40 149.50 5.23 5.87 146.69
CH.1+000 25 - 3.03 75.63 11.73 63.90 6.27 5.75 143.71
CH.1+025 25 9.84 4.92 123.04 - 123.04 8.98 7.62 190.58
CH.1+050 25 - 4.92 123.04 - 123.04 21.06 15.02 375.46
CH.1+075 25 - - - - - 43.43 32.25 806.14
CH.1+100 25 - - - - - 55.94 49.68 1,242.10
CH.1+125 25 - - - - - 37.35 46.64 1,166.04
CH.1+150 25 - - - - - 29.70 33.52 838.08
CH.1+175 25 35.24 17.62 440.48 46.47 394.01 27.23 28.47 711.63
CH.1+200 25 28.56 31.90 797.41 81.09 716.33 19.93 23.58 589.55
CH.1+225 25 5.52 17.04 425.89 47.17 378.72 20.14 20.04 500.92
CH.1+250 25 - 2.76 68.95 12.55 56.40 34.18 27.16 678.98
CH.1+275 25 - - - - - 57.88 46.03 1,150.66
CH.1+300 25 - - - - - 91.36 74.62 1,865.41
CH.1+325 25 - - - - - 50.10 70.73 1,768.24
CH.1+350 25 - - - - - 27.92 39.01 975.25
CH.1+375 25 - - - - - 6.64 17.28 432.03
CH.1+400 25 - - - - - 3.38 5.01 125.26
CH.1+425 25 - - - - - 4.59 3.98 99.58
CH.1+450 25 2.02 1.01 25.28 8.72 16.55 0.83 2.71 67.69
CH.1+475 25 - 1.01 25.28 8.72 16.55 2.74 1.78 44.60
CH.1+500 25 0.97 0.49 12.14 9.52 2.62 2.13 2.43 60.85
CH.1+525 25 - 0.49 12.14 9.52 2.62 7.30 4.71 117.79
CH.1+550 25 - - - - - 9.41 8.35 208.80
CH.1+575 25 - - - - - 15.00 12.20 305.04
CH.1+600 25 - - - - - 13.05 14.03 350.63
CH.1+625 25 3.76 1.88 46.98 25.57 21.41 0.40 6.73 168.15
CH.1+650 25 9.98 6.87 171.78 61.02 110.76 - 0.20 4.98
CH.1+675 25 12.89 11.43 285.86 70.83 215.03 - - -
CH.1+700 25 15.07 13.98 349.49 71.80 277.69 - - -
CH.1+725 25 15.19 15.13 378.29 72.33 305.96 - - -
EARTHWORKS
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.2 & 4.2.3 Cut and Fill
CALCULATION FOR CUT BASED ON DED CALCULATION FOR FILL WORKDONE FOR CUT WORKDONE FOR FILL
BASED ON DED
CALCULATION FOR CUT BASED ON DED CALCULATION FOR FILL WORKDONE FOR CUT WORKDONE FOR FILL
BASED ON DED
CALCULATION FOR CUT BASED ON DED CALCULATION FOR FILL WORKDONE FOR CUT WORKDONE FOR FILL
BASED ON DED
3,743.68 93,591.89 4,347.30 89,244.59 11,855.24 296,212.08 1,529.99 38,249.65 1,152.44 36,993.44 1,933.12 48,328.00
EARTHWORKS
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.2 & 4.2.3 Cut and Fill
CALCULATION FOR CUT BASED ON DED CALCULATION FOR FILL WORKDONE FOR CUT WORKDONE FOR FILL
BASED ON DED
EARTHWORKS
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.4.3 - Imported Granular Material
CALCULATED BASED ON DED WORKDONE
Chainage Width Ave. Width Distance Depth Vol (m3) Width Ave. Width Distance Depth Vol (m3)
Ch2115 16.89 16.89
Ch2125 21.52 19.21 10.00 0.30 57.62 21.52 19.21 10.00 0.30 57.62
Ch2150 24.02 22.77 25.00 0.30 170.77 24.02 22.77 25.00 0.30 170.78
Ch2175 24.11 24.06 25.00 0.30 180.46 24.11 24.06 25.00 0.30 180.47
Ch2200 23.06 23.59 25.00 0.30 176.89 23.06 23.59 25.00 0.30 176.89
Ch2215 18.95 21.01 15.00 0.30 94.54 18.95 21.01 15.00 0.30 94.54
680.27
Ch4615 18.25
Ch4625 24.25 21.25 10.00 0.30 63.75
Ch4650 27.00 25.62 25.00 0.30 192.17
Ch4675 26.95 26.97 25.00 0.30 202.30
Ch4700 27.25 27.10 25.00 0.30 203.25
Ch4725 26.81 27.03 25.00 0.30 202.74
Ch4750 27.07 26.94 25.00 0.30 202.05
Ch4775 27.89 27.48 25.00 0.30 206.10
Ch4800 29.32 28.61 25.00 0.30 214.54
Ch4825 31.35 30.33 25.00 0.30 227.49
Ch4850 33.50 32.42 25.00 0.30 243.17
Ch4875 32.29 32.89 25.00 0.30 246.70
Ch4900 31.14 31.71 25.00 0.30 237.86
Ch4925 30.89 31.01 25.00 0.30 232.61
Ch4950 31.31 31.10 25.00 0.30 233.25
Ch4975 29.99 30.65 25.00 0.30 229.89
Ch5000 27.52 28.76 25.00 0.30 215.68
Ch5025 27.55 27.54 25.00 0.30 206.51
Ch5050 28.59 28.07 25.00 0.30 210.51
Ch5075 29.43 29.01 25.00 0.30 217.58
Ch5100 29.92 29.68 25.00 0.30 222.58
Ch5125 30.65 30.29 25.00 0.30 227.14
Ch5150 29.48 30.06 25.00 0.30 225.48
Ch5175 28.25 28.86 25.00 0.30 216.46
Ch5200 28.15 28.20 25.00 0.30 211.47
Ch5225 27.28 27.71 25.00 0.30 207.84
Ch5250 28.77 28.02 25.00 0.30 210.16
Ch5275 27.09 27.93 25.00 0.30 209.45
Ch5300 27.10 27.09 25.00 0.30 203.20
Ch5325 27.60 27.35 25.00 0.30 205.14
Ch5350 27.23 27.41 25.00 0.30 205.61
Ch5375 27.25 27.24 25.00 0.30 204.29
Ch5400 27.98 27.62 25.00 0.30 207.13
Ch5425 28.68 28.33 25.00 0.30 212.48
Ch5450 28.29 28.48 25.00 0.30 213.62
Ch5475 27.34 27.81 25.00 0.30 208.61
Ch5500 26.27 26.81 25.00 0.30 201.05
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.2.4.3 - Imported Granular Material
CALCULATED BASED ON DED WORKDONE
Chainage Width Ave. Width Distance Depth Vol (m3) Width Ave. Width Distance Depth Vol (m3)
Ch5525 24.51 25.39 25.00 0.30 190.44
Ch5550 23.60 24.05 25.00 0.30 180.41
Ch5575 22.82 23.21 25.00 0.30 174.07
Ch5600 23.71 23.27 25.00 0.30 174.49
Ch5625 25.06 24.38 25.00 0.30 182.88
Ch5650 23.33 24.19 25.00 0.30 181.45
Ch5675 21.93 22.63 25.00 0.30 169.71
Ch5700 21.04 21.48 25.00 0.30 161.12
Ch5725 20.47 20.75 25.00 0.30 155.65
Ch5750 18.83 19.65 25.00 0.30 147.36
Ch5765 18.48 18.65 15.00 0.30 83.93
9,381.32
Ch6040 18.41
Ch6050 18.91 18.66 10.00 0.30 55.98
Ch6075 19.36 19.14 25.00 0.30 143.53
Ch6100 19.41 19.39 25.00 0.30 145.39
Ch6125 19.89 19.65 25.00 0.30 147.35
Ch6150 20.06 19.98 25.00 0.30 149.81
Ch6175 21.12 20.59 25.00 0.30 154.44
Ch6200 21.65 21.38 25.00 0.30 160.38
Ch6225 21.06 21.35 25.00 0.30 160.13
Ch6250 25.89 23.47 25.00 0.30 176.03
Ch6275 30.20 28.04 25.00 0.30 210.31
Ch6300 30.55 30.37 25.00 0.30 227.78
Ch6325 32.14 31.34 25.00 0.30 235.06
1,966.21
Ch6380 31.85 -
Ch6400 31.14 31.49 20.00 0.30 188.96
Ch6425 31.65 31.40 25.00 0.30 235.47
Ch6450 31.99 31.82 25.00 0.30 238.65
Ch6475 31.50 31.74 25.00 0.30 238.07
Ch6500 30.42 30.96 25.00 0.30 232.17
Ch6525 25.71 28.06 25.00 0.30 210.45
Ch6550 22.04 23.87 25.00 0.30 179.05
Ch6575 20.03 21.04 25.00 0.30 157.78
Ch6600 19.65 19.84 25.00 0.30 148.79
Ch6625 19.06 19.35 25.00 0.30 145.13
Ch6650 19.00 19.03 25.00 0.30 142.71
Ch6660 19.74 19.37 10.00 0.30 58.11
2,175.32
Ch4615 18.25
Ch4625 24.25 21.25 10.00 212.51
Ch4650 27.00 25.62 25.00 640.58
Ch4675 26.95 26.97 25.00 674.32
Ch4700 27.25 27.10 25.00 677.49
Ch4725 26.81 27.03 25.00 675.79
Ch4750 27.07 26.94 25.00 673.51
Ch4775 27.89 27.48 25.00 687.01
Ch4800 29.32 28.61 25.00 715.14
Ch4825 31.35 30.33 25.00 758.31
Ch4850 33.50 32.42 25.00 810.56
Ch4875 32.29 32.89 25.00 822.35
Ch4900 31.14 31.71 25.00 792.86
Ch4925 30.89 31.01 25.00 775.36
Ch4950 31.31 31.10 25.00 777.51
Ch4975 29.99 30.65 25.00 766.29
Ch5000 27.52 28.76 25.00 718.93
Ch5025 27.55 27.54 25.00 688.38
Ch5050 28.59 28.07 25.00 701.69
Ch5075 29.43 29.01 25.00 725.26
Ch5100 29.92 29.68 25.00 741.93
Ch5125 30.65 30.29 25.00 757.14
Ch5150 29.48 30.06 25.00 751.59
Ch5175 28.25 28.86 25.00 721.54
Ch5200 28.15 28.20 25.00 704.90
Ch5225 27.28 27.71 25.00 692.79
Ch5250 28.77 28.02 25.00 700.54
Ch5275 27.09 27.93 25.00 698.15
Ch5300 27.10 27.09 25.00 677.34
Ch5325 27.60 27.35 25.00 683.79
Ch5350 27.23 27.41 25.00 685.36
Ch5375 27.25 27.24 25.00 680.98
Ch5400 27.98 27.62 25.00 690.43
Ch5425 28.68 28.33 25.00 708.26
Ch5450 28.29 28.48 25.00 712.06
Ch5475 27.34 27.81 25.00 695.36
Ch5500 26.27 26.81 25.00 670.15
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
BILL NO. 4: Item 4.3.3.1 - Bamboo Mattress and Non-woven geotextile
CALCULATED BASED ON DED CALCULATED BASED ON WORKDONE
Chainage Width Ave. Width Distance Area (m2) Width Ave. Width Distance Area (m2)
Ch5525 24.51 25.39 25.00 634.79
Ch5550 23.60 24.05 25.00 601.35
Ch5575 22.82 23.21 25.00 580.23
Ch5600 23.71 23.27 25.00 581.64
Ch5625 25.06 24.38 25.00 609.59
Ch5650 23.33 24.19 25.00 604.82
Ch5675 21.93 22.63 25.00 565.71
Ch5700 21.04 21.48 25.00 537.06
Ch5725 20.47 20.75 25.00 518.83
Ch5750 18.83 19.65 25.00 491.19
Ch5765 18.48 18.65 15.00 279.75
31,271.08
Ch6040 18.41
Ch6050 18.91 18.66 10.00 186.61
Ch6075 19.36 19.14 25.00 478.45
Ch6100 19.41 19.39 25.00 484.64
Ch6125 19.89 19.65 25.00 491.17
Ch6150 20.06 19.98 25.00 499.38
Ch6175 21.12 20.59 25.00 514.81
Ch6200 21.65 21.38 25.00 534.60
Ch6225 21.06 21.35 25.00 533.78
Ch6250 25.89 23.47 25.00 586.78
Ch6275 30.20 28.04 25.00 701.04
Ch6300 30.55 30.37 25.00 759.26
Ch6325 32.14 31.34 25.00 783.54
6,554.04
-
Ch6380 31.85 -
Ch6400 31.14 31.49 20.00 629.85
Ch6425 31.65 31.40 25.00 784.90
Ch6450 31.99 31.82 25.00 795.50
Ch6475 31.50 31.74 25.00 793.55
Ch6500 30.42 30.96 25.00 773.89
Ch6525 25.71 28.06 25.00 701.50
Ch6550 22.04 23.87 25.00 596.84
Ch6575 20.03 21.04 25.00 525.93
Ch6600 19.65 19.84 25.00 495.96
Ch6625 19.06 19.35 25.00 483.75
Ch6650 19.00 19.03 25.00 475.69
Ch6660 19.74 19.37 10.00 193.71
7,251.06
Embankment Toe
4.4.1.1 10,890.00 - -
Drain
Cascading Slope
4.4.1.4 22.00 22.00 -
Drain
Stream diversion
4.4.1.7 5,760.00 - -
Channel
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
Item: 4.4.2.2 (P604.3) - 1500mm ø single precast concrete pipe culvert
1 0+092.703 1500 ø 1 1
2 0+173.574 1500 ø 1 1 1 1
3 0+567.565 1500 ø 1 1 1
4 1+068.305 1500 ø 1 1 1 1
5 1+295.125 1500 ø 1 1 1 1
6 1+598.002 1500 ø 1 1 1 1
7 1+868.744 1500 ø 0 1 2 1 2 2+ no Sump VO
8 1+939.150 1500 ø 1 1 1 1
9 2+148.232 1500 ø 1 1 1 1
10 2+622.020 1500 ø 1 1 1 1
11 2+674.969 1500 ø 1 1 1 1
12 2+917.963 1500 ø 1 1 1 1
13 3+117.466 1500 ø 1 1 1 1
14 3+316.808 1500 ø 1 1
15 3+640.923 1500 ø 1 1
16 3+717.851 1500 ø 1 1
17 4+014.777 1500 ø 1 1
18 4+162.457 1500 ø 1 1
19 4+237.457 1500 ø 1 1
20 4+340.552 1500 ø 1 1
21 4+486.597 1500 ø 1 1
22 4+714.245 1500 ø 1 1
23 4+948.708 1500 ø 1 1
24 5+114.911 1500 ø 1 1
25 5+316.646 1500 ø 1 1
26 5+446.467 1500 ø 1 1
27 5+615.726 1500 ø 1 1
28 6+200.000 1500 ø 1 1
Total Quantity 55 2 22 2 0 0
Project Title: Membina Jalan Baru Tatau ke Kuala Tatau, Bintulu Division
Item: 4.4.2.6 (P619.54) - Grouted Stone Pitching at Inlet and Outlet