Program

The document outlines the project timeline for the proposed Kokwo Island footbridge, detailing tasks, durations, start and finish dates, and dependencies. The project spans from February 2025 to February 2028, with various construction phases including site mobilization, foundation works, and superstructure construction. Key milestones include delivery of girders, deck installation, and final handover to the client.

Uploaded by

Chebii Kiptoo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views4 pages

Program

The document outlines the project timeline for the proposed Kokwo Island footbridge, detailing tasks, durations, start and finish dates, and dependencies. The project spans from February 2025 to February 2028, with various construction phases including site mobilization, foundation works, and superstructure construction. Key milestones include delivery of girders, deck installation, and final handover to the client.

Uploaded by

Chebii Kiptoo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Task Name Duration Start Finish Predecessors

Mode 1st Quarter 3rd Quarter


Nov Jan Mar May Jul
1 PROPOSED KOKWO ISLAND 780 days Fri 2/7/25 Thu 2/3/28
FOOTBRIDGE
2 Site Mobilization 28 days Fri 2/7/25 Tue 3/18/25
3 Site Office Construction 3 days Fri 2/7/25 Tue 2/11/25
4 Install Temporary Power & Water 4 days Wed 2/12/25 Mon 2/17/25 3
5 Transport Equipment to Site 6 days Tue 2/18/25 Tue 2/25/25 4
6 Setup Storage Areas 2 days Wed 2/26/25 Thu 2/27/25 5
7 Order Materials 1 day Fri 2/28/25 Fri 2/28/25 6
8 Receive & Inspect Materials 12 days Mon 3/3/25 Tue 3/18/25 7
9 Foundation Works 84 days Thu 3/20/25 Tue 7/15/25 8
10 Excavation for Pier Foundations 6 days Thu 3/20/25 Thu 3/27/25 8
11 Install Piles 12 days Wed 3/26/25 Thu 4/10/25 14
12 Pile Cap Construction 12 days Fri 4/11/25 Mon 4/28/25 11
13 Reinforcement Works 30 days Tue 4/29/25 Mon 6/9/25 12
14 Soil Compaction 4 days Thu 3/20/25 Tue 3/25/25
15 Concrete Pouring 26 days Tue 6/10/25 Tue 7/15/25 13
16 substructure Construction 112 days Wed 7/16/25 Thu 12/18/25
17 Pier Formwork 21 days Wed 7/16/25 Wed 8/13/25 15
18 pier Reinforcement 42 days Thu 8/14/25 Fri 10/10/25 17
19 pier Concrete Works 12 days Mon 10/13/25 Tue 10/28/25 18
20 Pier Cap Formwork 21 days Wed 10/29/25 Wed 11/26/25 19
21 Pier Cap Concrete Works 16 days Thu 11/27/25 Thu 12/18/25 20
22 Superstructure construction 210 days Fri 12/19/25 Thu 10/8/26 21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Kokwa_Island_work pro
Summary Manual Summary Rollup Progress
Date: Thu 3/27/25
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode 1st Quarter 3rd Quarter
Nov Jan Mar May Jul
23 Delivery of Girders 28 days Fri 12/19/25 Tue 1/27/26 21
24 Girder Placement 182 days Wed 1/28/26 Thu 10/8/26 23
25 decking & railing installation 112 days Fri 10/9/26 Mon 3/15/27 24
26 Deck Formwork 28 days Fri 10/9/26 Tue 11/17/26 24
27 Deck Concrete Pouring 28 days Wed 11/18/26 Fri 12/25/26 26
28 Install Handrails 56 days Mon 12/28/26 Mon 3/15/27 27
29 finishing works 140 days Tue 3/16/27 Mon 9/27/27 25
30 Install Walkway Surface/topping 84 days Tue 3/16/27 Fri 7/9/27 28
31 Install Expansion Joints 21 days Mon 7/12/27 Mon 8/9/27 30
32 Apply Protective Coating 35 days Tue 8/10/27 Mon 9/27/27 31
33 painting works to metal works 3 days Tue 8/10/27 Thu 8/12/27 31
34 electrical works 5 days Fri 8/13/27 Thu 8/19/27 31
35 testing and commissioning 56 days Tue 9/28/27 Tue 12/14/27 34
36 Load Testing 35 days Tue 9/28/27 Mon 11/15/27 32
37 Final Walkthrough Inspection 21 days Tue 11/16/27 Tue 12/14/27 36
38 Final Cleaning 6 days Wed 12/15/27 Wed 12/22/27 37
39 Handover to Client 31 days Thu 12/23/27 Thu 2/3/28 38

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Kokwa_Island_work pro
Summary Manual Summary Rollup Progress
Date: Thu 3/27/25
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Kokwa_Island_work pro
Summary Manual Summary Rollup Progress
Date: Thu 3/27/25
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Kokwa_Island_work pro
Summary Manual Summary Rollup Progress
Date: Thu 3/27/25
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4