Program
Program
Page 1
ID Task Task Name Duration Start Finish Predecessors
Mode 1st Quarter 3rd Quarter
Nov Jan Mar May Jul
23 Delivery of Girders 28 days Fri 12/19/25 Tue 1/27/26 21
24 Girder Placement 182 days Wed 1/28/26 Thu 10/8/26 23
25 decking & railing installation 112 days Fri 10/9/26 Mon 3/15/27 24
26 Deck Formwork 28 days Fri 10/9/26 Tue 11/17/26 24
27 Deck Concrete Pouring 28 days Wed 11/18/26 Fri 12/25/26 26
28 Install Handrails 56 days Mon 12/28/26 Mon 3/15/27 27
29 finishing works 140 days Tue 3/16/27 Mon 9/27/27 25
30 Install Walkway Surface/topping 84 days Tue 3/16/27 Fri 7/9/27 28
31 Install Expansion Joints 21 days Mon 7/12/27 Mon 8/9/27 30
32 Apply Protective Coating 35 days Tue 8/10/27 Mon 9/27/27 31
33 painting works to metal works 3 days Tue 8/10/27 Thu 8/12/27 31
34 electrical works 5 days Fri 8/13/27 Thu 8/19/27 31
35 testing and commissioning 56 days Tue 9/28/27 Tue 12/14/27 34
36 Load Testing 35 days Tue 9/28/27 Mon 11/15/27 32
37 Final Walkthrough Inspection 21 days Tue 11/16/27 Tue 12/14/27 36
38 Final Cleaning 6 days Wed 12/15/27 Wed 12/22/27 37
39 Handover to Client 31 days Thu 12/23/27 Thu 2/3/28 38
Page 2
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
Page 3
3rd Quarter 1st Quarter 3rd Quarter 1st Quarter 3rd Quarter 1st Quarter
Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
Page 4