CPM Full Notes
CPM Full Notes
• Layout plan.
• Set of drawings, including working drawings.
• Detailed specifications or reference to
standard specifications for each item of work
• Schedule of stores to be issued by the owner
indicating the rates and their place and issue.
• Schedule of tools and plant and other facilities
to be made available by the owner, indicating
the conditions, hire changes and the place of
delivery.
Cont…
• Global tenders:
These tenders are published in internationally
circulated news papers and any firm or contractor
around the world can fill the tender.
Such tenders are invited for very large projects as
construction of airport, tunnels, express highways
etc.
TENDER NOTICE
•Points to be included while drafting Tender Notice
•Drafting of Tender Notice.
Meaning of Tender Notice
It is very important & it should stipulate:
• Reasonable time limit for completion of the work.
• It should be in standard form of department.
• It should be displayed in daily local news
papers/notice board.
• It should be in tabular form containing essential
information about name of authority inviting
tender, specification of contractors, name of work
and location, estimated cost, price of tender,
earnest money and security deposit, last date and
accepting authority.
Points to be included while drafting tender notice.
Sd/-
Date: 16-04-2013 Executive Engineer
PIU PWD Nowgong
Department Of Civil Engineering
Important Terms in
Tendering
Work Organization & Management
Ritesh Agarwal
Time Limit:
Escalation cost:
For huge work, completion period is long. So cost of materials and labour
become more and more causing uninterest of contractor to carry out the work.
To overcome this drawback, CPWD has provided the price escalation clause to
increase the cost in standard form given by formulae.
Extension of Time (EOT) is a delay which could not be reasonably foreseen at the
time of contract signing. The granting of an Extension of Time relieves the
contractor from liability of damages such as Liquidated Damages from the
original date of contract completion for the period of the claim.
Time extension requests are normally claimed due to the following
circumstances:
Client Change Order requests for New/Additional Work not included in the
original contract documentation
Latent Conditions – unknown conditions at the time of contract signing that
affect the time for delivery of the contracted works
Adverse weather conditions.
Arbitration:
Arbitration is a private process where disputing parties agree that one or several
individuals can make a decision about the dispute after receiving evidence
and hearing arguments. Arbitration is different from mediation because the
neutral arbitrator has the authority to make a decision about the dispute.
Engineering issues
Changes in scope of work
Discovery of hazardous materials
Protection from unsafe conditions
Not having worker’s compensation insurance for employees
Extra Items:
Extra item is a term that is often used when taking off for a bill of quantities
(BoQ).When taking off for a BoQ, the term 'extra over'/Extra Item can be used to
refer to items that to a certain extent have already been measured, but have
not been priced at the full value of all their labour and materials.
Earnest money ,Security Deposit &
Defect liability period
Earnest money deposit:
• Quality of Material
• Quality of Workmanship
• Mode of Payment
The specification of each item should cover:
Types of specification:
• Brief specifications
• Detailed specifications
• Manufacturers specifications
Brief specifications
• The general specification used for estimating
the project is the brief specifications.
• The specification which gives the brief
description of various items of work,
specifying the materials, quantities,
proportion of materials and gives general idea
about the whole work.
Detailed specifications
• The specification in which detailed
information of the various quantities of
materials, procedure of workmanship to be
adopted, nature and class of work is
mentioned.
• The details specification describes the item of
work in details, accurately and complete in all
respects in relation to the drawings of the
work.
Difference between Brief and Detailed specifications
There are distinct advantages of a Gantt chart, primarily from project managers’,
project stakeholders’ perspective. It is easy for stakeholder’s to understand the
timeline, it brings clarity to everyone: when a project is going to start and
expected to complete, team can manage its time accordingly, it also establishes
accountability among stakeholders, it enables team to better coordinate project
activities thereby enabling team to improving overall efficiency.
It is easy to understand
It gives clarity of dates
It enables time management
It brings efficiency
It ensures accountability in terms of timeline
It expects coordination among stakeholders in order to deliver things as per
Gantt timeline
However Gantt chart has its own limitations. Let’s look at those briefly.
CPM (Critical Path Method) is used to assist the project manager in scheduling the
activities. It assumes that activity durations are known with certainty.
PERT (Program Evaluation and Review Technique) is used to assist in project
scheduling similar to CPM. However, PERT assumes that activity durations are
random variables.
CPM/PERT Network
Activity (Task)
Event (Node)
Dummy Activity
This doesn’t consume resources like time, cost, manpower, equipment etc.
EF= ES + duration
It is the latest time the activity must be completed without delaying project
duration.
It is equal to the latest occurrence time of the head event.
Latest Start time (LS)
It is the latest possible time; an activity can be started without delaying the
project.
LS= LF – duration
For any activity, the number on the Tail Event should not be greater than
that on the Head Event.
In other words, the number on Head Event must always be greater than
that on tail Event.
Department Of Civil Engineering
The main objective in the analysis through PERT is to find out the
completion for a particular event within specified date. The PERT approach takes
into account the uncertainties. The three time values are associated with each
activity.
PERT CPM
1. PERT is used for non-repetitive jobs 1. CPM is used for repetitive job like
like planning the assembly of the space. building a house
2. it is a probabilistic model. 2. It is a deterministic model.
3. It is event-oriented as the results of 3. It is activity-oriented as the result or
analysis are expressed in terms of calculations are considered in terms of
events or distinct points in time activities or operations of the project.
indicative of progress.
4. It is applied mainly for planning and 4. It is applied mainly for construction
scheduling research programmes. and business problems.
5. PERT incorporates statistical analysis 5. CPM does not incorporate statistical
and thereby determines the analysis in determining time estimates,
probabilities concerning the time by because time is precise and known.
which each activity or entire project
would be completed.
6. PERT serves as useful control device 6. It is difficult to use CPM as a control
as it assists management in controlling device for the simple reason that one
a project by calling attention to such must repeat the entire evaluation of
delays the project each time the changes are
introduced into the network.
1. Optimistic time – It is the shortest possible time in which the activity can
be finished. It assumes that everything goes very well. This is denoted by t0.
2. Most likely time – It is the estimate of the normal time the activity would
take. This assumes normal delays. If a graph is plotted in the time of completion
and the frequency of completion in that time period, then most likely time will
represent the highest frequency of occurrence. This is denoted by tm.
3. Pessimistic time – It represents the longest time the activity could take if
everything goes wrong. As in optimistic estimate, this value may be such that only
one in hundred or one in twenty will take time longer than this value. This is
denoted by tp.
In PERT calculation, all values are used to obtain the percent expected value
te = ( t0 + 4 tm + tp ) / 6
The earliest event time represents the earliest time an event can possibly
begin; conventionally, it is zero for the first event.
The Latest allowable occurrence time is the latest time by which an event
must occur to keep the project on schedule (without delaying the project).
Slack of Event
The slack for an event is the difference between its Latest Occurrence Time
and Earliest Occurrence Time. It gives the amount of time the occurrence of the
event can be delayed without delaying the project's completion time.
Critical Path
Example 1
Task: A B C D E F G H I J K
Least time: 4 5 8 2 4 6 8 5 3 5 6
Greatest time: 8 10 12 7 10 15 16 9 7 11 13
Most likely time: 5 7 11 3 7 9 12 6 5 8 9
Find the earliest and latest expected time to each event and also critical path in
the network.
Example 2
Resource Allocation
Resource Smoothing
Overall, project costs are the total funds needed to monetarily cover and
complete a business transaction or work project.
1. Direct costs – Direct costs are those directly involved with, and necessary in
order to complete said project.
2. Indirect costs – Indirect costs for a project are costs which do not directly
lead to project completion but are still vital for the company or individual
working on said project. As such, they are a part of individual project costs.
In the construction projects, time and cost have a very close relationship.
That relationship can be illustrated in a linear fashion, which means for the same
type of project, the greater the volume of work the greater the cost and time are
required in order to complete the whole project.
Project Crashing
In CPM, time is related to cost and the object is to develop an optimum time-cost
relationship.
• The overall project duration can be reduced by reducing the duration of only the
critical activities in the project network. The durations of such activities may be
reduced in two ways.
(a) By deploying more resources for the early completion of such activities.
(b) By relaxing the technical specifications for such activities.
• In CPM, there are two time and cost estimates for each activity: 'normal
estimate' and crash estimate'.In the normal estimate, the emphasis is on cost
with time being associated with minimum cost. The'crash' estimate involves the
absolute minimum time required for the job and the cost necessary to
achieve it. Here the emphasis is on 'time'.
Normal time (tn): Normal time is the standard time that an estimator
would usually allow for an activity.
Crash time (tc): Crash time is the minimum possible time in which an
activity can be completed, by employing extra resources. Crash time is that
time, beyond which the activity cannot be shortened by any amount of
increase in resources.
Normal cost (Cn): This is direct cost required to complete the activity in
normal time duration.
Crash cost (Cc): This is the direct cost corresponding to the completion of
the activity within crash time.
The cost slope is the slope of the direct cost curve, approximated as straight
line. It is defined as follows
The total project cost is the sum of the direct cost and the indirect costs.
We find that the minimum total cost is obtained at duration known as the
optimum duration. The corresponding cost is known as the minimum cost.
If the project duration is increased, total cost will increase, while if project
duration is decreased to the crash value, project cost will be the highest.
Crashing of non-critical activities does not serve any purpose as they do not
control the project duration and completing them earlier does no benefit
rather it increases the project cost.
Material Management
Ordering Cost- Ordering costs are the costs related to the preparation of a
supplier’s order, including the cost of placing an order, inspection costs,
documentation costs, and others.
Typically, ordering costs include expenses for a purchase order, labor
costs for the inspection of goods received, labor costs for placing the goods
received in stock, labor costs for issuing a supplier’s invoice and labor costs
for issuing a supplier payment.
Bill Voucher
• Bill is a detailed account • Voucher is legal receipt
of claim for works done for proof against
or supply made. payment made.
Daily Diary
Annual & Special Repair
Work Organization & Management
Ritesh Agarwal
Daily Diary
Following are some of the major uses and benefits of having a well-maintained
Daily Diary.
This maintenance service is carried out to maintain the aesthetics of buildings and
services as well as to preserve their life, some works like white washing,
distempering, painting, cleaning of lines; tanks etc. are carried out periodically.
These works are planned on year to year basis.
The works of periodical nature like White washing, colour washing, distempering,
painting etc. are called Annual Repair works and these are generally undertaken;
through system of contracts.
The periodicity of applying white washing and colour washing for a building has
been laid down by the Government. The periodicity is two years for white
washing and colour washing and three years for painting. In addition, works such
as patch repair to plaster, minor repairs to various items of work, replacement of
glass panes, replacement of wiring damaged due to accident, replacement of
switches, sockets tiles, Gap filling of hedges/perennial beds,
Replacement/Replanting of trees, shrubs, painting of tree guards, planting of
annual beds and trimming /pruning of plants etc., which are not emergent works
and are considered to be of routine type, can be collected and attended to for a
group of houses at a time and particular period of financial year, depending upon
the exigency. Such works can be done under day to day repair also. The yard stick
for annual repairs covers both the above facilities
Special Repairs
Special repairs of building are undertaken to replace the existing parts of buildings
and services which get deteriorated on ageing of buildings. It is necessary to
prevent the structure & services from deterioration and restore it back to its
original conditions to the extent possible.
As the building ages, there is deterioration to the various parts of the building and
services. Major repairs and replacement of elements become inevitable. It
becomes necessary to prevent the structure from deterioration and undue wear
and tear as well as to restore it back to its original conditions to the extent
possible. The following types of works in general are undertaken under special
repairs: -
Construction Management,
Organization & its
terminologies
Construction Planning & Management
Ritesh Agarwal
Construction Management
The five integral functions of management to run a highly successful enterprise are:
1. Planning
2. Organizing
3. Staffing
4. Directing
5. Controlling
1. Planning
It is the basic function of management. It deals with chalking out a future
course of action & deciding in advance the most appropriate course of actions
for achievement of pre-determined goals.
Thus planning is a systematic thinking about ways & means for
accomplishment of pre- determined goals. Planning is necessary to ensure
proper utilization of human & non-human resources.
It is an intellectual activity and it also helps in avoiding confusion,
uncertainties, risks, wastages etc.
2. Organizing
It is the process of bringing together physical, financial and human resources
and developing productive relationship amongst them for achievement of
organizational goals. To organize a business involves determining & providing
human and non-human resources to the organizational structure.
Organizing as a process involves:
Identification of activities.
Classification of grouping of activities
Assignment of duties
Delegation of authority and creation of responsibility.
3. Staffing
It is the function of manning the organization structure and keeping it
manned. Staffing has assumed greater importance in the recent years due to
advancement of technology, increase in size of business, complexity of human
behavior etc.
Staffing involves:
Manpower planning
Recruitment, selection & placement
Training & development
Remuneration
Performance appraisal
Promotions & transfer.
4. Directing
It is that part of managerial function which actuates the organizational
methods to work efficiently for achievement of organizational purposes.
Direction is that inert-personnel aspect of management which deals directly
with influencing, guiding, supervising, motivating sub-ordinate for the
achievement of organizational goals.
Direction has following elements:
Supervision
Motivation
Leadership
Communication.
5. Controlling
The purpose of controlling is to ensure that everything occurs in conformities
with the standards. An efficient system of control helps to predict deviations
before they actually occur. Therefore controlling has following steps:
Establishment of standard performance.
Measurement of actual performance.
Comparison of actual performance with the standards and
finding out deviation if any
Corrective action.
Types of Construction
Light Construction
Heavy Construction
Industrial Construction
Light Construction
Heavy Construction
Industrial Construction
Concept
Contracts and Bid Documents
Bidding
Construction
Construction Payments
Completion
1. Concept
All construction projects begin with planning and design also referred to as
"architectural programming." Numerous overlapping steps occur during this
conceptual or design phase, prior to actual construction of the project.
3. Bidding
The fourth stage of the construction process, called fieldwork, is the actual
construction of the project. Fieldwork is broken down into building permits,
subcontractors, scheduling subcontractors, shop drawings, project submissions, and
change orders.
5. Construction Payments
6. Completion
The final phase of the construction process is known as the completion stage,
and it readies the building for occupancy.
CONSTRUCTION TEAM
Architect
The Architect develops the buildings’ design, taking the Client’s brief and
combining it with the advice of the Specialist Consultants. This then has to be
developed to meet the requirements of the Building Regulations and increasingly
sustainability. Architects have significant involvement in product selection.
Contractor
The Contractor oversees and manages the construction of the building for the
Client, following the Architect and Engineers’ designs. The work is delivered under a
contractual agreement. The Main Contractor will select Sub- contractors based on
the capability, availability and price. Sub-contractors include many specialist trades.
Engineer
Working with the architect will be a number of engineers that are responsible
for structural, mechanical and electrical design. The Structural Engineer is a key
member of the Project Team. Structural Engineers design the skeleton or structure
of the building, enabling Architects to focus their talents on creating a design that
satisfies their client’s demands.
The Role of a Construction Project Manager
Principles of Organization
1. Line Organization.
2. Line and staff Organization.
3. Functional Organization.
Line Organization
Line organization is the most oldest and simplest method of administrative
organization. According to this type of organization, the authority flows from top to
bottom in a concern. The line of command is carried out from top to bottom. This is
the reason for calling this organization as scalar organization which means scalar
chain of command is a part and parcel of this type of administrative organization. In
this type of organization, the line of command flows on an even basis without any
gaps in communication and co-ordination taking place.
Line and staff Organization
Line and staff organization is a modification of line organization and it is more
complex than line organization. According to this administrative organization,
specialized and supportive activities are attached to the line of command by
appointing staff supervisors and staff specialists who are attached to the line
authority.
Functional Organization
In this type of organization, the whole work is divided in such a way that each
person has to perform a minimum number of functions and is responsible for those
functions.
Features of Functional Organization:
1. The entire organizational activities are divided into specific functions such as
operations, finance, marketing and personal relations.
2. Complex form of administrative organization compared to the other two.
3. Three authorities exist- Line, staff and function.
4. Principle of unity of command does not apply to such organization as it is
present in line organization.
Detailed Project Report (DPR)
In a Detailed Project Report, the project plan is elaborately laid out explaining
the idea, the various functions required to be performed, estimation and allocation
of resources required supported by a Project Feasibility report. It’s ideally a final set
of documents and blueprints before project execution that also focuses on the
forecasted Return on Investment, risks and mitigation measures. A Detailed Project
Report traditionally includes the following in order:
A DPR acts as a ladder towards success to make your project reach great heights.
If the project report is prepared by putting a tremendous amount of effort into
details, you will surely get good results later.
Administrative approval-
For any work or project require by a dept. an approval of the competent
authority of the dept. w.r.t. Cost is necessary at the first instance this approval
authorizes the engg. dept. to take up the work in hand.
The administrative approval denotes the formal acceptance of the concerned
dept. for the said proposal. Engg. Dept. prepares the preliminary plans and
approximate estimate and submits to concerned dept for administrative approval.
The Engineering Dept. takes up the work and prepares plans, detail designs
and estimates and then executes the work only after administrative approval is
given by concerned dept.
Budget provision-
For any work or project it is necessary to provide finance oroginally the
estimates are prepared by PWD and sent to the secretary of the dept. and
consequently to the finance dept,.
The assurance of finance dept. for allotment of funds to the estimates, fully or
partly, submitted above in writing is known as budget provision. Engg. Dept takes up
execution
Technical Sanction:-
After obtaining the approval a detailed estimate and detailed drawings are
prepared and sanctioning of competent authority is obtained such sanctioning is
termed as technical sanctioning.
Piece (Petty) Work Method