The lecture discusses transportation decision modeling in supply chain management, emphasizing the importance of having multiple supply routes to mitigate risks associated with relying on a single source. It introduces the min-max problem, where companies may accept a 10% increase in transportation costs to ensure a disruption-free supply chain. The new optimization model aims to minimize the quantity shipped while ensuring that the new transportation cost does not exceed the previous cost plus a 10% allowance.

Uploaded by

at.yh.ma1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views14 pages

Lecture Notes

The lecture discusses transportation decision modeling in supply chain management, emphasizing the importance of having multiple supply routes to mitigate risks associated with relying on a single source. It introduces the min-max problem, where companies may accept a 10% increase in transportation costs to ensure a disruption-free supply chain. The new optimization model aims to minimize the quantity shipped while ensuring that the new transportation cost does not exceed the previous cost plus a 10% allowance.

Uploaded by

at.yh.ma1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

Modelling and Analytics for Supply Chain Management

Professor Anupam Ghosh


Vinod Gupta School of Management
Indian Institute of Technology Kharagpur
Lecture 13
Transportation Decisions: How to Take Decisions on Different Issues with
Transportation? [Contd.]
(Refer Slide Time 0:30)

Hello! In the previous week, we had learned about how to model transportation decisions for
the purpose of supply chain and we had taken up the first model that we can use that is the
total cost model.

And we had said there were 3 Origin Points for suppliers Madhya Pradesh, Himachal Pradesh
and Uttar Pradesh and you had 4 markets Delhi, Mumbai, Kolkata and Madras or Chennai.
Okay. And given the cause, how many units should be transported from which supplier to
which factory or which warehouse to which market so that my total transportation costs
remains minimal that model we had learned Okay.
(Refer Slide Time 1:17)

Now, if you just recollect this was the metrics that had the results okay. This metrics told us
that 12 units should be transported from Madhya Pradesh to Delhi, Madhya Pradesh 8 from
Madhya Pradesh to Mumbai nothing from Madhya Pradesh to Kolkata and Chennai, for
Himachal Pradesh nothing to these cities and Himachal should send only to Madras, Uttar
Pradesh nothing only to Kolkata Okay. So, this is 1 this is the 1 with which we ended right.
But the question that as a modeller as a supply chain modelling expert you should ask is that
if you see for all the cities what is happening is Delhi is receiving supply only from Madhya
Pradesh, no other place.

So tomorrow by any chance, if the Madhya Pradesh unit is not able to supply to Delhi, maybe
there is a machine break down, maybe there is a transport strike whatever. So tomorrow if
Madhya Pradesh unit is not able to supply to Delhi. Delhi will receive no supplies from any
place because your transportation cost, total cost model says do not supply from anywhere
except Madhya Pradesh. But tomorrow if Madhya Pradesh is not able to supply, Delhi will be
starved right, Delhi will be starving, Delhi does not have any supply from any other place,
okay.

Same applies to Mumbai; Mumbai is also receiving from Madhya Pradesh. Tomorrow if
Madhya Pradesh is not able to supply what will happen; Mumbai will also starve and starving
means what? It is a lost sale; Kolkata same thing only from Uttar Pradesh; Chennai or Madras
same thing only from Himachal Pradesh. So, this though this is the total costs the lowest cost
model, what is happening is my supply chain is becoming very, very vulnerable, very, very
vulnerable. Tomorrow if 1 route closes down, my supply chain is gone. That market will not
be serviceable, and markets not serviceable means less profit, loss of reputation, goodwill,
local competitor coming in, local competitor coming in and taking your place Okay.

So, though the question is as a modeller you should ask is, though my total cost is minimum
in this model that you are seeing total cost is minimum in this model that you are seeing. But
then is it practically advisable? Should we not have other alternate routes also in place? That
is what you should ask okay right.

(Refer Slide Time 4:44)

As you were mentioning, what will happen if I need these routes? So, I need to redraw the
equation I need to redraw I need to remodel my business of transportation decisions.

(Refer Slide Time 4:55)


This is what is called as a min max problem. Okay.

(Refer Slide Time 5:00)

What is says, if you remember the earlier model, this 1, the last line the total transport costs
incurred by the company is rupees 4131, okay is rupees 4131. What it says is if we feel that
more roads should be there, to enable a disruption fee transport movement across the country,
we need to have more routes. But that means we are not at minimum cost of 4131 because
my minimum cost means only those places should be served, all the other routes are closed
because they have more cost. So, if you want more routes, that means we are not operating at
the lowest cost now, because my lowest cost model was this 1.
(Refer Slide Time 5:50)

My lowest cost model was this 1. Now, what I want, I want this route; I want this route; I
want this route. So, when I want these there is extra cost involved. Okay. These are not the
minimum costs; this is what we want to say, okay. That means we are now at… we are not at
the minimum cost of rupees 4131.

(Refer Slide Time 6:25)

.
Now, what the company says that no we should have more routes for that even if 10 percent
extra cost is required let us have it, but let us have let us plan or design a disruption free
supply chain. So, the company may say that they are willing to accept 10 percent increase in
cost. So, the new allowable cost becomes 4131 plus 10 percent that is rupees 4544. Okay, so,
4131 is the optimal cost that we got from yesterday, the last week. So 4131, they are willing
to accept 10 percent increase in cost. So, the new allowable cost because 4544 Okay, hope
you have understood this part.

(Refer Slide Time 7:00)

Now I am going very slowly through this model, okay, hope you remember the previous
model right hope you remember the previous model this was our previous model minimize
the total cost there is on top, minimize the total cost.

(Refer Slide Time 7:23)


Okay, subject to these were my supplies and these were my demands right? Okay. So this
was my total cost, this was the sorry this is 2016 that is it is that some type of graphic error
here so 11 I think okay, so anyway, whatever you just check up.

(Refer Slide Time 8:02)

And so, that was my cost right. Now what we want to say is look at this so that was my
original model right? And you are adding a 10 percent extra cost. I am going through this
slide very-very slowly, we introduce a variable s, we introduce a variable s, where S is the
maximum quantity possible to be shipped on any route that is Madhya Pradesh to Mumbai,
MP to Kolkata, Madhya Pradesh to Kolkata, etc. Earlier what was the variable X 1, X 2, X 3
right? This was the quantity that was getting shipped right. Now we are saying we are
introducing a variable s, where S is the maximum possible quantity that can be shipped.
Right.

What was X 1, X 2, X 3, the quantity that was getting shipped X 1 X 2 X 3 X 4 are the ideal
quantities that should be shipped to keep the total cost to a minimum, agreed? X 1, X 2, X 3,
X 4, are the ideal quantities that should be shipped to keep the total cost to the minimum that
is why in some cases X 1 and X 2 are 0 that is why in some cases X 1, X 2 are 0 so many
blank boxes in the matrix that we just now drew that means they are 0 right X 1, X 2, X 3 are
0. So, X 1, X 2, X 3, X 4 are ideal quantities that should be shipped repeating again X 1, X 2,
X 3, X 4 are the ideal quantities that should be shipped what was S we have introduced, S is
the maximum quantity that is possible to be shipped.

So, ideally S should be equal to the xs okay. S is the maximum quantity that should be
shipped, X is the ideal quantity that should be shipped. So to have a proper optimization, my
S should equal to x. Right? So S 1 is S equal to X 1, S 2 is equal to X 2, X 3 is equal to S 3.
That is ideal. Ideally, this should happen. If I am introducing a variable X, then this should…
to keep the total cost minimum, S should be equal to X. Right? I am stopping for a second,
you understand this first, understand this very carefully. I am stopping, look at the slide, read
it and you understand okay, right.

(Refer Slide Time 11:02)

But since we are not following the optimal solution for minimal cost and allowing for some
quantity of product movement along some more routes, the value of S 1 may not equal to X
1, the value of Si may not equal to Xi. For example, in the previous model if you remember,
if you remember, okay. Sorry.

(Refer Slide Time 11:38)

If you remember what was this thing? X 1 was 12, X 2 was 8, but X 3 is 0, X 4 is 0, X 5 is 0,
etc, right? X 2, to X 7 at least is 0, right? X 2 to X 7 at least is 0, right okay.

(Refer Slide Time 12:07)

So, what we are saying now is what we are saying now is that since we are not following the
optimal solution for minimal cost and allowing for some quantity of product movement along
some more routes, value of S i may not equal X i. Remember, X 3 was 0 just now we
checked up in the table. So, ideally, if it is a minimal cost model, S 3 should also equal to 0
because I am keeping the cost at the minimum, my X 4 was 0 so S 4 should also be 0. My X
5 was 0 so S 5 should also be 0, right? X 6 was 0. So X S 6 should also be 0. But now, what
we are saying is what we are saying is that let us remove some of them then you will
understand my X 3 Okay.

(Refer Slide Time 13:30)

Now what X 3 was 0, now what we are saying is that no X 3 route that is Madhya Pradesh to
Kolkata, MP to Kolkata X 3 route should not be 0 we should use that route. So and we are
saying so my S 3 will now not be 0. S 3 will be what, S 3 will be S 3 will be greater than 0
right, so what we are saying is there will be situations when S 3 is not equal to X 3. Since we
are not following the minimal cost model X where X 3 is 0, S 3 should also be 0 ideally if X
is 0, S is also 0. If X is 0 S is also 0 because S is the quantity ship but now you are saying that
no, we should ship some quantity. So there will be situations when X 3 that is the ideal
quantity to be shipped is not equal to S 3 ideal quantity to be shipped was 0. And now we are
saying that okay, no, you send at least 2 units, so definitely X 3 is 0 and 2 units is not equal
to 0. So there will be situations when s3 will not be equal to X 3 right? Okay, have you
understood right okay.
(Refer Slide Time 15:20)

So, the values of S i may not equal to X i okay right. As we mentioned, so, S 3 is not equal to
X 3 rather S 3 is greater than equal to X 3 because X 3 is 0 so we are sending some units right
so S 3 will be greater than equal to X 3, right, this applies for other routes also. So, S3 is not
equal to X 3, rather S 3 is greater than equal to X 3, but more than quantity sent on a high
cost route. So, you were sending more quantities on a route that should have 0. So, you are
sending it in a high cost route. So, more the quantity sent on a high cost route more will be
my total cost. More will be my total cost. So, my objective function is to minimize this S.
What is S? The quantity that has being sent on all the routes right okay.

So, again My S 3 is not equal to X 3 ideally they should be equal if it is an ideal value point
ideal method, but we are saying that some quantity has to be sent by that route to enable that
market to be serviced during times of emergency okay because if you are depending only on
1 source then it will then that that source may stop producing, stop delivering. So, so you
have to have an alternate source ready, alternate source for supplier selection also you may
say this is the model for supplier selection also that we learned in the previous model okay.
So, some quantity has to be sent so S 3 is greater than equal to X 3. This applies for other
routes also, more the quantity sent on the high cost route more will be my total cost. So, my
objective is to minimize the value of S okay right that is my objective.
(Refer Slide Time 17:13)

So, my new optimization model becomes minimize S, my new optimization model becomes
minimise S, subject to demand constraints remain the same, supply constraints remain the
same, new total cost of transportation, it will increase right. New total cost of transportation is
what? We had said that we will have the earlier cost of rupees 4131 plus 10 percent that was
what the company allowed me for enabling this multiple routes movement right. So, my new
total transportation cost should be less than equal to cost under pure optimization model plus
10 percent addition. This is the maximum right, this is the maximum allowable limit given by
the supply chain planners of the organization that look you have multiple routes, but my total
cost should not be more than 10 percent of the previous model. So, my previous model was
cost, cost under the pure optimization model and 10 percent addition. So, my new
transportation cost should be less than equal to this earlier cost model, right, my new
transportation cost should be less than equal to my earlier cost plus 10 percent.

And definitely this last one, the amount the new quantity to be sent on every route is either
greater than or equal to the ideal quantity, okay. The new quantity sent on a route is either
greater than or equal to the ideal quantity okay the new quantity sent on a route is greater than
or equal to the ideal quantity, this is my constraints right.
(Refer Slide Time 19:32)

So, when we model it again let us see what equations we have got, minimize s subject to
there was a typographic error here So, 20, 16, 11 supply constraint, demand constraint, this is
my cost constraint and this will be 4131 plus 10 percent of 4131 right this is my total cost
should be less than the earlier cost plus 10 percent escalation okay, total costs should be less
than the earlier cost plus 10 percent escalation and the Ss should be greater than equal to the
Xs or S n greater than equal to X n or Si greater than equal to Xi. So, basically quantities sent
should be greater than equal to the optimal quantity, okay right. So, this is the new model that
comes up. And again when you solve this model using LiPS 1.11.1 or any Excel Based linear
programming, you will get the changed direction.

(Refer Slide Time 21:24)


Now, the question that comes in is, in this new model this was my earlier model right. Some
cases are all blanks maybe 7, maybe 9 ok this was earlier model, and the new model we are
saying these are my Ss right these are my S. New model will all the cells be full with some
quantity means will all the Si be greater than Xi that is the question, will all the cells be filled
with some quantity, because we are saying that there should be alternate additional routes
available question is. Answer is no, all the cells will not be filled up with more quantity at
least some cells will be filled up.

So, all Ss will not be greater than equal to Xs in some case, in some cases S will be equal to
X ok, for some routes the Ss will be greater than Xs okay. So, this is so, this is the model
okay this is called as a min-max or max-min model.

(Refer Slide Time 22:38)

Now, okay if the object is this was minimization of the maximum because we are sending the
maximum quantity in any route and we are minimizing this quantity. So, this was a min-max
problem. Next is max-min, if the objective is to maximize the minimum value, change the
objective from min to max and change the sign of the constraints linking the variables S from
greater than equal to less than equal sign okay, that will solve your problem right. Now, we
will end this section here. In the next section, we will deal with the maximum flow, the
minimal and the minimal spanning tree problem. Okay. Thank You!