0% found this document useful (0 votes)
13 views53 pages

Scheduling (Lecture 3)

The document outlines the processes of planning and scheduling in construction, emphasizing the use of network techniques such as PERT and CPM. It discusses the slow adoption of these techniques in the construction industry due to various reasons, including resistance to change and past negative experiences. Additionally, it details the steps involved in construction scheduling, the significance of network diagrams, and the calculations necessary for managing project timelines and activities.

Uploaded by

shahiszahoor50
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views53 pages

Scheduling (Lecture 3)

The document outlines the processes of planning and scheduling in construction, emphasizing the use of network techniques such as PERT and CPM. It discusses the slow adoption of these techniques in the construction industry due to various reasons, including resistance to change and past negative experiences. Additionally, it details the steps involved in construction scheduling, the significance of network diagrams, and the calculations necessary for managing project timelines and activities.

Uploaded by

shahiszahoor50
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 53

CONSTRUCTION SCHEDULING

PLANNING & SCHEDULING

Planning:
Process of choosing which method and order of work is
best among different methods available.

Scheduling:
Process of determining the interrelationship of associated
timings of operations.
NETWORK TECHNIQUES

• Planning & Scheduling with the help of network


diagrams is called Network Techniques.
• Network Techniques (Network Programming)
encompass the methods of PERT (Program
Evaluation & Review Techniques) and CPM (Critical
Path Method).
NETWORK TECHNIQUES

• Present day network techniques offer a more formal


approach to Project Management.
--- They have been adopted by some larger construction
companies and Government agencies.
---- Many packages are commercially available on a wide variety
of computer systems.
---- Many contracts include a network plan as part of their
conditions.
• However, the full utilization of techniques has yet to
be reached.
• The development of the techniques is on-going with
both user and theoretician contributing to this
development.
WHY CONSTRUCTION INDUSTRY IS
ADOPTING NETWORK TECHNIQUES TOO
SLOWLY?

• The construction Industry has generally been slow in taking up these


techniques and their universal acceptance across the industry is still
not present.
• The techniques have both advantages as well as disadvantages but
three reasons are generally advanced for reluctance to universally
acceptance of the techniques:
1- Certain sections of the construction industry refused to
acknowledge that sound analytical techniques are better
than established classical and traditional methods.
2- Some contractors have had bad first experiences with
using these techniques.
3- There was lack of suitable user-friendly computer programs
to do the tedious and elementary arithmetic involved, in the past.
STEPS IN CONSTRUCTION
SCHEDULING

• Splitting of the project into work activities


• Determining logic relationships/interrelationships
between activities.
• Construction of Network Diagrams.
• Assigning durations to work activities. (PERT and CPM
use different techniques for this)
• CPM Calculations resulting in start times, finish times
and float calculations of activities.
• Marking of Critical Path
• Construction of Bar Charts / Time phased diagrams.
ACTIVITY

 An element of work performed during the course of a project.


Or
An amount of work that can be identified so that we know what
it involves and can recognize, when it starts and finishes.
 An activity normally has an expected duration, an expected cost,
and expected resource requirements.
 Activities may be
---- On-site Activities like Excavation, Pouring, Plastering,
Brickwork etc.
---- Off-site activities like ordering materials, deliveries,
fabrication of steel, and anything which affect the
construction work.
 Activities may be Detailed or Coarse in their description.
NETWORK DIAGRAMS

• Any schematic display of the logical relationship of


project activities.
• Always drawn from left to right to reflect project
chronology.
• Usually a combination of arrows and nodes.
• A Network for a project is not unique.
• Mainly of two types:
1.Arrow Diagram
2. Node Diagram / Precedence Diagram
ARROW DIAGRAMS

• Activities shown by
Arrows. Relationship
between activities
shown by nodes / events.
• Length of arrows does
not obey any scale.
PREDECESSOR-SUCCESSOR RELATIONSHIP

• There is Start-to-finish
relationship between
activities, also called
Predecessor-Successor
Relationship.
EVENT NUMBERING

• Events are numbered in an


Arrow Diagram.
• For any given Activity, the
head event number should
be greater than the tail
event number
• Each Activity should have a
unique i & j pair.
• Situation in Figure 2.14 is
not allowed.
MILESTONES

• Events of some special


significance are called
Milestones.
CONCURRENT RELATIONSHIPS

• Works done parallel to each other constitute


Concurrent Activities. For Example, shop steel
fabrication for a building may be carried out
concurrently with site activities such as
earthmoving and foundation works.
AGGREGATED ACTIVITIES & CIRCUITS

• If a group of activities is replaced by one single activity, it is


called Aggregated Activity.
• Activities B to F in Fig 2.7 (a) are replaced by activity H in
Figure 2.7 (b).
• A Circuit or Loop of activities is given in Fig 2.8.
• Such Circuits or Loops violate the logic of precedence of
activities, thus, not allowed.
DUMMY ACTIVITIES

• An activity having zero duration and zero cost (and uses zero
resources) is called Dummy Activity.
• Dummy Activity is represented by Dashed Lined Arrow.
• A Dummy Activity may be
a---- Logic Dummy - To fulfill logic relationship
b---- Numbering Dummy – To avoid same i, j pair for
two activities’
c---- Start / Finish Dummy – To give single start or finish
activity in the network.
ARTIFICIAL ACTIVITY

• When a time delay is needed in a construction sequence, an


Artificial Activity is introduced.

• An Artificial Activity is associated with time duration but


has zero cost.
ACTIVITY DURATIONS

• Activity duration is forecasted by any of the several means, including:


(1) Check Past Records.
(2) Check Standards and / or cost guides, if available.
(3) Ask the workers, who will do it
(4) make an educated guess

• Any time units may be allotted to activity durations like days, hours, weeks,
months, shifts, etc.

• In CPM, a single duration is forecasted for an activity.

• In PERT (Program Evaluation & Review Techniques), 3 durations are


forecasted for an activity and mean taken by weighted average method.
Then, Project’s Duration or any Event Completion Time is calculated by
probability distribution.
CPM CALCULATIONS

 Calculates the following for each activity


EST = Earliest Starting Time
EFT = Earliest Finishing Time
LST = Latest Starting Time
LFT = Latest Finishing Time
TF = Total Float
FF = Free Float
 Total Float is Maximum time for which an activity can be
delayed without delaying the project.
 Free Float is maximum time for which an activity can be
delayed without delaying the start of proceeding activity.
 Total Float = Free Float + Interfering Float
FLOAT
FLOAT
FLOAT
FLOAT
EXAMPLE: SINGLE SPAN BRIDGE PROJECT
(ACTIVITY DESCRIPTION)

Activity Code Operation Dependence Est. Dur.


(Days)
ENA Earthworks, north abutment - 5
ESA Earthworks, south abutment ENA 4
CONN Construction, north abutment ENA 14
CONS Construction, south abutment ESA, CONN 12
COMN Compaction, north abutment CONN 2
COMS Compaction, south abutment CONS, COMN 2
RNB Road, north of bridge COMN 2
RSB Road, south of bridge RNB,COMS 2
PB Prefabricate bridge deck - 18
TD Transport deck to site PB 2
EB Erect bridge deck TD, CONN, 3
CONS,
COMN
LBS Lay bridge surface EB, RNB, RSB 2
ICB Install crash barriers etc. EB 1
L Landscape RNB, RSB 1
CPM CALCULATIONS

FORWARD PASS
• In Forward Pass through the network, the top two cells, of
the six-celled box at each activity are calculated.
• The top two cells give the values of EST & EFT.
• Forward Pass is carried out from left to right in the network
• The EST of first activity/activities is set to zero or some
other number.
• The EFT of the first activity/activities will be 0 + duration of
first activity/activities.
• The EST & EFT of subsequent activities are calculated as

EST = Maximum EFT of preceding activities.


EFT = EST + duration
CPM CALCULATIONS

BACKWARD PASS
• In Backward Pass through the network, the middle two cells, of
the six-celled box at each activity are calculated.
• The middle two cells give the values of LST & LFT.
• Backward Pass is carried out from right to left in the network
• The LFT of last activity/activities is set to maximum EFT of the
last activity/activities or some other number i.e. date of handing
over.
• The LST of the last activity/activities will be LFT - duration of
last activity/activities.
• The LST & LFT of activities progressing backwards in times are
then calculated as
LFT = Minimum LST of following activities.
LST = LFT - duration
CPM CALCULATIONS

FLOAT CALCULATION
• In FLOAT CALCULATION through the network, the bottom two
cells, of the six-celled box at each activity are calculated.

• The bottom two cells give the values of Total Float (TF) & Free
Float (FF).

• TF = LST - EST OR LFT - EFT


• FF = Minimum EST of following activities - EFT of activity in
question
CRITICAL PATH

• The path (or paths) in the network


diagram, from start to finish, on which all
the activities have zero total and free floats,
is called Critical Path.
• It is the longest path (or paths) from start
to finish in a net work diagram.
• It gives minimum normal time to complete
a project.
• It is usually marked by double lined / Thick
lined arrows in a network diagram.
EVENT TIME CALCULATIONS

• These give finish-time information about Events.


• A two-celled box is put adjacent to each event.
• Event EFT and the Event LFT are written as box entries.
• Underlined notations is used for event calculations.
• Event Float is the difference between LFT and EFT.
NODE DIAGRAMS

• Activities shown by Nodes, relationship between Activities


shown by arrows or links.
• These are easier to construct.
• Generally no need of dummies. Instead dummies used only to
give single start or finish.
• CPM Calculations are similar to Arrow diagrams.
BAR CHART

• Gives pictorial representation of Activities.


• Activities begin at EST and show their EFT, FF, TF,
Durations, etc.
• Arrows at the relative ends to show dependency.
• Status Line drawn on the Bar Chart to check status of
the project
• Unable to show complete interdependency between
Activities.
TIME-SCALED NETWORK DIAGRAMS

• Alternative way of pictorial representation of Activities.


• Show complete interdependency between Activities.
• Horizontal components of solid lines represent the durations
of the activities while horizontal components of broken lines
represent the activity Free Float.
• Vertical components of dashed/thick lines have no significance
as they use no time.

You might also like