PROGRESS REPORT
NO. 14
PERIOD ENDING : 27 DISEMBER 2024
_____________________________________ _____________________________________
_____________________________________
BANDAR NUSAJAYA DEVELOPMENT SDN BHD
Senior Executive/Site Inspector
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425
(CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL
TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
TABLE OF CONTENT
2
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL
PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR
BANDAR NUSAJAYA DEVELOPMENT SDN BHD
CONTRACT NO : UEMS/BNDSB/001(24)
DEFECT LIABILITY PERIOD (D.L.P) : TWELVE (12) MONTHS + THREE (3) MONTHS + FORTEEN (14) DAYS FROM CPC.
3
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL
PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR
BANDAR NUSAJAYA DEVELOPMENT SDN BHD
4
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
(CONTRACT NO: UEMS/BNDSB/001(24))
EXECUTIVE DIRECTOR
Nasrullah Bin Muda
[email protected]
HP: 019-2280403
HEAD OF OPERATION
Ho Kah Heng
[email protected]
012-6162055
CONTRACT MANAGER
Khairul Fauzi bin Zulkafli
[email protected]
HP: 019-2347595
CONTRACT EXECUTIVE
Norliyana Syahirah
[email protected]
HP: 016-4858997
Head Quarters
Site
[email protected]
HP: 019-7226662
………………………………………………………………. ……………………………………………………………….
Abdul Rahman bin Kasim EKSB/BNDSB/EPH En Muhammad Azizan bin Jafar
Senior Project Manager rev 01 Superintanding Officer
EFFECTIVE DATE : 27 DISEMBER 2024
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD
200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU,
JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
6
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
7
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK),
ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA
DEVELOPMENT SDN BHD
Report No. : 14
Period Ending : 27/12/2024
Overall Days Ahead / Delay -55 Overall Days Ahead / Delay -65
SECTION 1 SECTION 2
Date 27/12/2024 Date 27/12/2024
Overall Schedule Progress 100% Overall Schedule Progress 78.51%
Overall Actual Progress 100% Overall Actual Progress 44.42%
Overall % Ahead / Delay 0% Overall % Ahead / Delay -34.09%
Overall Days Ahead / Delay 0 Overall Days Ahead / Delay -93
8
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK),
ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA
DEVELOPMENT SDN BHD
Overall Days Ahead / Delay -78 Overall Days Ahead / Delay -93
8
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425
(CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL
TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
9
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
10
ID Task Task Name Duration Start Finish Scheduled Actual
Mode Percentage Percentage Half 2, 2024 Half 1, 2025
27122024 27122024 M J J A S O N D J F M A
1 SITE CLEARANCE, EARTHWORKS, DETENTION POND AND 273 days Mon 10/6/24 Sun 9/3/25 84.88 60.91
OTHER INFRA WORKS ESTUARI GREENS
2 PRELIMINARIES 66 days Mon 10/6/24 Wed 14/8/24 100 100
3 SITE SURVEY AND PEGGING WORKS 22 days Mon 10/6/24 Mon 1/7/24 100 100
4 PREPARATION OF DOCUMENTATION AND MACHINES 19 days Mon 10/6/24 Fri 28/6/24 100 100
MOBILIZATION
5 INSTALLATION OF SITE HOARDING (1300m) 45 days Mon 1/7/24 Wed 14/8/24 100 100
6 INSTALLATION OF PROJECT SIGNBOARD 15 days Mon 1/7/24 Mon 15/7/24 100 100
7 MAINTENANCE OF WASH THROUGH 7 days Sat 29/6/24 Fri 5/7/24 100 100
8 SECTION 1 (1B1) 102 days Sat 29/6/24 Tue 8/10/24 100 100
9 SITE CLEARANCE AND EARTHWORK 96 days Sat 29/6/24 Wed 2/10/24 100 100
10 CLEARING WORKS 31 days Sat 29/6/24 Mon 29/7/24 100 100
11 EARTHWORKS 63 days Tue 30/7/24 Mon 30/9/24 100 100
12 INSTALLATION OF SEDIMENT FENCING 56 days Tue 23/7/24 Mon 16/9/24 100 100
13 TEMPORARY EARTHDRAIN (22Om) 58 days Tue 6/8/24 Wed 2/10/24 100 100
14 ASBUILT PREPARATION AND SUBMISSION 6 days Thu 3/10/24 Tue 8/10/24 100 100
15 SECTION 2 (1B2,1B3,CENTRAL PARK) 223 days Tue 30/7/24 Sun 9/3/25 78.51 44.42
16 SITE CLEARANCE AND EARTHWORK 215 days Tue 30/7/24 Sat 1/3/25 82.86 53.29
17 CLEARING WORKS 45 days Tue 30/7/24 Thu 12/9/24 100 100
18 EARTHWORKS 201 days Tue 13/8/24 Sat 1/3/25 68.16 43
19 INSTALLATION OF SEDIMENT FENCING (1500m) 165 days Tue 6/8/24 Fri 17/1/25 100 100
20 MAKE GOOD SEDIMENT BASIN 2 (130m x 50m) 50 days Tue 27/8/24 Tue 15/10/24 100 85
21 TEMPORARY EARTHDRAIN (930m) 161 days Tue 3/9/24 Mon 10/2/25 72.05 0
22 TURFING WORKS (2300m2) 14 days Mon 25/11/24 Sun 8/12/24 100 0
23 RETAINING WALL 105 days Fri 1/11/24 Thu 13/2/25 60 0
24 PILING WORKS (420m) (26nos) 20 days Fri 1/11/24 Wed 20/11/24 100 0
25 RETAINING WALL WORKS (420m) 100 days Wed 6/11/24 Thu 13/2/25 52 0
26 ASBUILT PREPARATION AND SUBMISSION 7 days Mon 3/3/25 Sun 9/3/25 0 0
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 1
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
11
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU,
JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
S-CURVE PHYSICAL
99.00% 100.00%
98.59%
100.00% 96.55%
92.84%
88.52%
90.00%
84.88%
80.81%
80.00% 76.31%
70.00%
65.71%
58.66% 59.31%
60.00%
53.53%
Scheduled Actual
50.00%
45.67%
40.00%
34.63%
30.00%
24.65%
20.00% 16.08%
10.69%
10.00% 7.60%
4.68%
2.12%
0.00%
0.00%
10/6/2024 21/6/2024 2/7/2024 12/7/2024 26/7/2024 9/8/2024 23/8/2024 6/9/2024 20/9/2024 4/10/2024 18/10/2024 1/11/2024 15/11/2024 29/11/2024
Scheduled 0.00% 2.12% 4.68% 7.60% 10.69% 16.08% 24.65% 34.63% 45.67% 53.53% 58.66% 59.63% 65.71% 76.31%
Actual 0.00% 2.00% 5.00% 8.00% 10.78% 16.57% 27.10% 35.69% 45.10% 54.25% 59.03% 59.72% 60.91% 60.91%
120.00%
99.00%
97.00%
95.00%
100.00%
93.00%
89.00%
84.00%
78.00%
80.00%
72.00%
66.00%
58.00%
60.00%
45.00%
Scheduled
Actual
36.00%
40.00%
28.00%
21.00%
20.00% 15.00%
11.00%
16.71% 16.71%
6.51% 6.51%
0.00%
0.00%
17/6/2024
24/6/2024
15/7/2024
22/7/2024
29/7/2024
12/8/2024
19/8/2024
26/8/2024
16/9/2024
23/9/2024
30/9/2024
7/10/2024
1/7/2024
8/7/2024
5/8/2024
2/9/2024
9/9/2024
14/10/2024
21/10/2024
28/10/2024
4/11/2024
11/11/2024
18/11/2024
25/11/2024
2/12/2024
9/12/2024
16/12/2024
23/12/2024
30/12/2024
13/1/2025
20/1/2025
27/1/2025
10/2/2025
17/2/2025
24/2/2025
10/3/2025
17/3/2025
6/1/2025
3/2/2025
3/3/2025
10/6/2024 21/6/2024 2/7/2024 12/7/2024 26/7/2024 9/8/2024 23/8/2024 6/9/2024 20/9/2024 4/10/2024 18/10/2024 1/11/2024 15/11/2024 29/11/2024
Schedule 0.00% 2.00% 4.00% 5.00% 7.00% 11.00% 15.00% 21.00% 28.00% 36.00% 45.00% 58.00% 66.00% 72.00%
Percentage 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.51% 6.51% 12.64% 12.64% 12.64% 12.64% 12.64% 12.64%
Certified
3.0 MANPOWER
PLANT & MACHINERY
WEATHER RECORD
12
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH
JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
14
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH
JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
16
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI,
MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
17
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
18
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR
PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
8 3472/PCL.1B/CN/IN/ESCP/204 4/6/2024
TYPICAL DETAILS AND SECTION OF SEDIMENT BASIN
RC RETAINING WALL PROFILE CH0.00 TO CH 433.01 AND RC
9 3472/PCL.1B/CN/IN/RT/100 4/6/2024
WALL PROFILE CH 0.00A TO CH 850.0A
19
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
20
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR
PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
Date Status
No. Item Revision 01 Revision 02 Remarks
Submitted (Approved)
1 Method Of Statement for Site Clearance 21/6/2024 Approved -
21
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
EKSB/JOH/2024/18/BNDSB
2 10/7/2024 RC Pipe (ø 1500mm) OKA Concrete Industries Approved 12/7/2024 No objection.
/EG&CP/015
EKSB/JOH/2024/18/BNDSB
3 23/7/2024 BRC (A7 &A8) Engtex Metals Sdn Bhd Approved 26/7/2024 No objection.
/EG&CP/020
22
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425
(CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL
TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
23
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
24
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK),
ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA
DEVELOPMENT SDN BHD
25
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL
PARK), ISKANDAR PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR
BANDAR NUSAJAYA DEVELOPMENT SDN BHD
Instruction Date
No. Type Reference Description Remark
By Issued
26
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR
PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
1 ZLSB 17/10/2024 3472/INF/MEMO-01 Check and repair sediment fencing 18/10/2024 1/11/2024 3472/INF/MEMO-01 Done repair
27
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR
PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
Safety
1 1 100 0 0
Supervisor
Total 3 3 100% 0 0
No. of
No. of Skilled Nos. of
Accredited (%) of Accredited % of Remarks (Interview
Trade Workers(CIDB Submitted to
Skilled Skilled Workers Submitted by CIDB etc.)
) CIDB
Workers
Brick Layer 1 1 100% 0 0 -
Carpenter 1 1 100% 0 0 -
Machinery
2 2 100% 0 0 -
Operator
Excavator
2 2 100% 0 0% -
Operator
Compactor
1 1 100% 0 0% -
Operator
Total 7 7 100% 0 0%
PERCENTAGE PERCENTAGE
TOTAL
ACCREDITED SUBMITTED
PERCENTAGE (%)
(%) (%)
Supervisor 100% 0% 100%
Skilled
100% 0% 100%
Workers
29
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
28
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI,
DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
2 11/09/24 361,141.29 680,084.29 20/09/24 26/09/24 257,097.45 530,140.45 29/11/24 257,097.45 530,140.45
3 15/10/24 493,881.70 1,173,965.99 30/10/24 05/11/24 170,502.55 700,643.00 06/12/24 170,502.55 700,643.00
29
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI
GREEN) & PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM
PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR
NUSAJAYA DEVELOPMENT SDN BHD
30
Progress Photo ESTUARI GREEN
13/12/2024 – 27/12/2024
No activities on site
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREEN)
& PTD 200425 (CENTRAL PARK), ISKANDAR PUTERI, MUKIM PULAI,
DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA
DEVELOPMENT SDN BHD
Item Remarks
14 Workers Quarters & Site EKSB has relocated workers quarter at SILC.
Office
15 Safety, Health Environment HSE report will be email on 4/12/2024.
Report
16 IMS ISO Audit / SIRIM Audit Complied.
17 Project HSE Compliance Submission & Approved Date –
Plan (PHSECP) Pending at client side
2.2 Environmental & Sustainability Matters
Item Remarks
3
4
Average:
2.4 CIDB Green Card & Accreditation Status
Trade/Category No. Total of No. CIDB Percentage No. CIDB Percentage No of Interview
Manpower Green CIDB GC(%) Accredited CIDB Submitted Date by
Card Accredited Accreditation CIDB
(%)
Main Contractor
Project Manager 1 1 100% 0 0% 0 -
Supervisor 2 2 100% 0 0% 0 -
Safety supervisor 1 1 100% 0 0% 0
TOTAL 4 4 100% 0 0% 0 -
2.5 QUALITY
Item Remarks
Average: 67.2%
SITE MEETING MINUTES
PROPOSED RESIDENTIAL DEVELOPMENT IN PTD 222111 (ESTUARI GREENS) & PTD 200425 (CENTRAL PARK), ISKANDAR
PUTERI, MUKIM PULAI, DAERAH JOHOR BAHRU, JOHOR DARUL TA’ZIM FOR BANDAR NUSAJAYA DEVELOPMENT SDN BHD
− SITE CLEARANCE, EARTHWORKS AND OTHER INFRA WORKS
Attendance:
*(Pn. Isfalina Ismail) Bandar Nusajaya Development Sdn. Bhd. Client - Project BND-EPL
En. Omar Jusoh Bandar Nusajaya Development Sdn. Bhd. Client - Project BND-EPL
Pn. Saloha Samat Bandar Nusajaya Development Sdn. Bhd. Client - Project BND-EPL
En. Mohd Fakhri Hafiz Bandar Nusajaya Development Sdn. Bhd. Client - Project BND-EPL
*(En. Amal Asyraf Husain) UEM Sunrise Sdn. Bhd. Client - Contract UEMS-CM
Pn. Jayyidah Muhammad UEM Sunrise Sdn. Bhd. Client - Contract UEMS-CM
*(Pn. Diyana Izzati Shamsudin) UEM Sunrise Sdn. Bhd. Client - Contract UEMS-CM
*(Pn. Reena Farina Mohd Rizal) UEM Sunrise Sdn. Bhd. Client - Contract UEMS-CM
En. Sangeleswaran a/l Sangarapandy UEM Sunrise Sdn. Bhd. Client - HSSE UEMS-HSSE
*(En. Muhd Yusri Sapieh) UEM Sunrise Sdn. Bhd. Client - HSSE UEMS-HSSE
*(En. Amir) UEM Sunrise Sdn. Bhd. Client – Site Team UEMS-SITE
*(En. Wan Hairul Azhar Wan Hussein) UEM Sunrise Sdn. Bhd. Client – Site Team UEMS-SITE
*(Mr. Peter Lim) Zaidun-Leeng Sdn. Bhd. Infra Engineer - C&S ZLSB
En. Muhammad Azizan Jaafar Zaidun-Leeng Sdn. Bhd. Infra Engineer - C&S ZLSB
En. Muhammad Redza Zaidun-Leeng Sdn. Bhd. Infra Engineer - C&S ZLSB
*(Pn. Hannah Syafiah Ridzuan) Zaidun-Leeng Sdn. Bhd. Infra Engineer - C&S ZLSB
*(En. Mohd Firdaus Ishak) Zaidun-Leeng Sdn. Bhd. C&S IOW ZLSB
Pn. Nur Amira Pakatan Ukur Bahan Sdn. Bhd. Quantity Surveyor PUBSB
*(En. Nasrullah Dato Muda) Emaskang Sdn. Bhd. Contractor EKSB
Mr. Ho Kah Heng Emaskang Sdn. Bhd. Contractor EKSB
En. Rahman Kasim Emaskang Sdn. Bhd. Contractor EKSB
Pn. Tuan Nur Syahira Emaskang Sdn. Bhd. Contractor EKSB
En. Khairul Rijal Emaskang Sdn. Bhd. Contractor EKSB
En. Khairul Hazmie Emaskang Sdn. Bhd. Contractor EKSB
En. Aidil Ramzan Emaskang Sdn. Bhd. Contractor EKSB
En. Mohamad Khairul Emaskang Sdn. Bhd. Contractor EKSB
Absent with Apologies: *( )
CONTRACT INFORMATION
10. Liquidated and Ascertained Damages (LAD) : Section 1 – RM500.00 per calendar day
: Section 2 – RM1,400.00 per calendar day
MINUTES OF MEETING (MOM) NO. 14
Action Date of
Item Description
/ Status Action
1.0 INTRODUCTION
1.1 ZLSB requested all parties to go through Minutes of Meeting No. 13. Info
1.2 ZLSB informed all parties accepted MOM No. 13. Info
2.1 ZLSB informed Contract Information has been listed at front page of MOM for reference. -
3.2 Contractor Progress Report: Progress Report No. 13 (Period ending: 13/12/2024) received Info
on 17/12/2024.
4.0 CIDB
Accredited (%)
Date by CIDB
CIDB GC(%)
Accreditation
Green Card
No. Total of
Percentage
Percentage
Accredited
Manpower
Submitted
No. CIDB
No. CIDB
Interview
No of
CIDB
Main Contractor
Project 1 1 100% 0 0% 0 -
Manager
Supervisor 1 1 100% 0 0% 0 -
Safety 1 1 100% 0 0% 0
supervisor
TOTAL 1 1 100% 0 0% 0 -
Sub Contractor (To seperate skilled & unskilled workers)
Bar bending
Bar cutting
Brick Layer 1 1 100% 0 0 0 0
Carpenter 1 1 100% 0 0 0 0
Drain Layer 1 1 100% 0 0 0 0
Machinery 2 2 100% 0 0 0 0
Operator
Drainage
Excavator 2 2 100% 0 0 0 0
Backhoe
Compactor 1 1 100% 0 0 0 0
Infra(turfing) 4 4 100% 0 0 0 0
TOTAL
Previous
TOTAL 12 12 100% 0 0 0 0
Current
5.1 Nil.
Page 2 | 4
MINUTES OF MEETING (MOM) NO. 14
6.1 Nil.
Item Remarks
1 QAQC Inspector En Muhammad Yusri Sapieh
2 OJT -
Average: 67.2%
9.1 ZLSB requested EKSB to maintain the signage throughout the construction period. Info
11.1 ZLSB informed that they will meet En. Haji Fadzly from Jab. Kejuruteraan to discuss the Info 22/12/2024
application of proposed slope and gabion wall along the sectional part of the pond.
Page 3 | 4
MINUTES OF MEETING (MOM) NO. 14
Please note the action columns and undertake to complete your respective tasks as agreed.
Page 4 | 4