Sample Test Script

The document outlines the dynamic performance test procedures for Air Handler 20 (AHU-20) at Biotech, Inc., focusing on the Supply Fan's HOA switch functionality and failure alarm tests. It includes specific actions, expected results, and observed results for various tests related to the supply and return fans. The document is structured with lines for recording observations and approvals, emphasizing the importance of safety and operational integrity during testing.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views2 pages

Sample Test Script

The document outlines the dynamic performance test procedures for Air Handler 20 (AHU-20) at Biotech, Inc., focusing on the Supply Fan's HOA switch functionality and failure alarm tests. It includes specific actions, expected results, and observed results for various tests related to the supply and return fans. The document is structured with lines for recording observations and approvals, emphasizing the importance of safety and operational integrity during testing.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

AHU-20

Dynamic Performance Test – Air Handler 20

Biotech, Inc.
URS 6.1.1 The Supply fan shall be equipped with a HOA switch to enable manual operation

Accepted
Line Action Expected Result Observed Result (Y or N) Initial,
Date
1. Supply Fan (SF) HOA switch test
Reference AHU 20, Manufacturing Building West Corridors and Support
Spaces SDD
1.1 Ensure AH-20 control program is not Control program is not executing Control program is _______________
executing, is OFF, and building utility <V01AH20VWP> = ‘ON’ <V01AH20VWP> = __________
power is ‘ON’. Use ‘‘Point
Commander’’ to determine status of
<V01AH20VWP>
1.2 Set Supply Fan (SF) HOA switch to SF HOA switch is in ‘OFF’ HOA switch is in ________________
‘OFF’ position. Via ‘‘Point <V01AH20SFSS> = ‘OFF’ <V01AH20SFSS> = ___________
Commander’’ set SF Start/Stop
<V01AH20SFSS> to ‘OFF’
1.3 Via ‘Point Commander’ observe <V01AH20SDSP> = 0.0 IN WC <V01AH20SDSP> = _______ IN WC
supply duct pressure transmitter Graphic indicates fan is ‘OFF’ Graphic indicates fan is _________
<V01AH20SDSP> and use graphics
to observe SF status
1.4 Set SF HOA switch to ‘HAND’ and SF HOA switch is in ‘HAND’ SF HOA switch is in _____________
use graphics to observe SF status Graphic indicates SF is ‘OFF’ Graphic indicates SF is ___________
and use ‘Point Commander’ to <V01AH20SDSP> = 0.0 IN WC <V01AH20SDSP> = _______ IN WC
observe supply duct pressure
transmitter <V01AH20SDSP>

COMMENTS: ________________________________________________________________________________________________

________________________________________________________________________________________________

________________________________________________________________________________________________

Reviewed by: ____________________________________________ Approved by: ______________________________________

05/03/25 AHU 20 Page 1 of 8


AHU-20
Dynamic Performance Test – Air Handler 20

Biotech, Inc.
URS 8.2.1 The Supply fan failure during start or during operation when HOA switch is in AUTO shall be alarmed

Accepted
Line Action Expected Result Observed Result (Y or N) Initial,
Date
2. Equipment Failure and Alarm test
Reference AH-20, Manufacturing Building West Corridors and Support
Spaces SDD sections D & E
2.1 Ensure the HOA switch is in AUTO HOA is in AUTO and the fan is HOA is in ________
and the fan is commanded to RUN running Fan is _________________
from the HMI and is running
2.2 Fail Supply Fan by opening breaker Breaker SF-1121 is ‘OPEN’ Breaker SF-1121 is ______________
SF-1121 at MCC-M1A SF fail alarm message at Bldg 2 &4
OCS and Bldg 4 Alarm printer.
Unit shutdown procedure initiated
2.3 Wait at least 5 minutes then “Close” Wait time  5 minutes Wait time = ______________minutes
breaker SF-1121 at MCC-M1A Breaker SF-1121 is ‘Closed’ Breaker SF-1121 is ______________
2.4 From graphic, command System ‘ON’ AH-20 is starting up AH-20 is starting up ____________
and physically verify startup of AH-20 (Expected = yes)
2.5 Wait at least 5 minutes for AH-20 to Wait time  5 minutes Wait time = ______________minutes
start up and stabilize
2.6 Fail Return Fan by opening breaker Breaker RF-1122 is ‘OPEN’ Breaker RF-1122 is ______________
RF-1122 at MCC-M1A RF fail alarm message at Bldg 2 &4
OCS and Bldg 4 Alarm printer.
Unit shutdown procedure initiated
2.7 Wait at least 5 minutes then “Close” Wait time  5 minutes Wait time = ______________minutes
breaker RF-1122 at MCC-M1A Breaker RF-1122 is ‘Closed’ Breaker RF-1122 is ______________

COMMENTS: ________________________________________________________________________________________________

________________________________________________________________________________________________

Reviewed by: ____________________________________________ Approved by: ______________________________________

05/03/25 AHU 20 Page 2 of 8