Critical Path Analysis Exam Practice Activities
Critical Path Analysis Exam Practice Activities
Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.
A – 6
B – 2
C A 2
D B 3
E C, D 4
F E 2
Exam Practice Question 1 – Network diagram
2 C
A
6 2
E F
1 4 5 6
4 2
B D
2 3 3
Exam Practice Question 2
Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.
B E
2 3
A D F H
1 2 3 4 5 6
4 4 2 5
C G
3 5
Exam Practice Question 3
Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.
3
B D
4 2
A F G
1 2 5 6 7
4 3 2
C E
2 6
4
Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.
C
A 2 4
3 E
6 2
G
1 6 7
3
B F
6 D 5
3 5
4
Exam Practice Question 5
Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.
Activity Order Duration (Days)
A - 8
B - 5
C - 3
D A 2
E B, D 6
F D 9
G E 3
H C, F, G 3
Exam Practice Question 5 – Network diagram (answers)
A D F
2 4
8 2 9
B E G H
1 3 5 6 7
5 6 3 3
C
3