Critical Path Analysis Exam Practice Activities

The document contains a series of exam practice questions focused on completing critical path diagrams for various project activities. Each question provides a list of activities, their order, and durations, requiring the identification of the critical path and the calculation of early start times (EST) and late finish times (LFT). The questions progressively increase in complexity, challenging the reader to apply project management concepts effectively.

Uploaded by

kk.jadamspam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views10 pages

Critical Path Analysis Exam Practice Activities

The document contains a series of exam practice questions focused on completing critical path diagrams for various project activities. Each question provides a list of activities, their order, and durations, requiring the identification of the critical path and the calculation of early start times (EST) and late finish times (LFT). The questions progressively increase in complexity, challenging the reader to apply project management concepts effectively.

Uploaded by

kk.jadamspam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Exam Practice Question 1

Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.

Activity Order Duration ( Days)

A – 6

B – 2

C A 2

D B 3

E C, D 4

F E 2
Exam Practice Question 1 – Network diagram

2 C
A
6 2

E F
1 4 5 6
4 2

B D
2 3 3
Exam Practice Question 2

Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.

Activity Order Duration ( Days)


A – 4
B A 2
C A 3
D B, C 4
E D 3
F D 2
G D 5
H E, F, G 5
Exam Practice Question 2 – Network diagram

B E
2 3

A D F H
1 2 3 4 5 6
4 4 2 5

C G
3 5
Exam Practice Question 3

Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.

Activity Order Duration ( Days)


A __ 4
B A 4
C A 2
D B 2
E C 6
F D&E 3
G F 2
Exam Practice Question 3 – Network diagram

3
B D
4 2

A F G
1 2 5 6 7
4 3 2

C E
2 6
4

Project duration: 17 days; Critical path: A C E F & G


Exam Practice Question 4

Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.

Activity Order Duration (Days)


A – 6
B – 6
C A 3
D B 4
E C, B 2
F D 5
G E, F 3
Exam Practice Question 4 – Network diagram

C
A 2 4
3 E
6 2

G
1 6 7
3

B F
6 D 5
3 5
4
Exam Practice Question 5

Complete the critical path diagram using the data below, including the EST and LFT for
each activity in the project. Identify the critical path.
Activity Order Duration (Days)
A - 8
B - 5
C - 3
D A 2
E B, D 6
F D 9
G E 3
H C, F, G 3
Exam Practice Question 5 – Network diagram (answers)

A D F
2 4
8 2 9

B E G H
1 3 5 6 7
5 6 3 3

C
3