Sir,
This has reference to RO E office file no 256539 and 255968 where in
communicated the approval for “Construction of 6 Lane LVUP at Km 26+775
(Ankushapur X Road) and 6 lane VUP at Km 31+255 (Kondamadugu Junction)
on Hyderabad - Yadgiri Section of NH-163 in the State of Telangana on EPC
Mode” and requested to furnish the bid documents along with Technical
Schedules as per Policy Circular no. 11.54/2023 dated 30.10.2023 at the
earliest to invite tenders.
1
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
e. Therefore, the revised cost abstract of the estimate is as under and requested the
Competent Authority to communicate the approval for revised estimate:
2
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
Electrical, MB Grid & Municipal Water pipelines) and the summary is as
under:
d. Therefore, the revised cost abstract of the estimate is as under and requested the
Competent Authority to communicate the approval for revised estimate:
3. This office has requested the DPR consultant M/s Spera Infra
Consultants Pvt Ltd to submit the combined RFP for the both the structures
proposed I,e., 6 lane LVUP at Km 26+775 (Ankushapur Cross road) and 6 lane
VUP at Km 31+255 (Kondamadugu Junction) fir an amount of Rs,
44,97,77,972 (Excl GST) so as to invite the bid combinedly.
4. In view of the above, it is requested the Competent Authority
3
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
a. To accord the approval for revised cost to an amount of Rs.
20,81,77,291/- towards construction of 6 Lane LVUP at Km
26+775 (Ankushapur X Road) a n d an amount of Rs.
37,63,09,182/- towards construction of 6 lane VUP at Km
31+255 (Kondamadugu Junction) modified based on the utility
estimates obtained from the concerned departments.
https://drive.google.com/file/d/1IkMLd5iBKSub5CmExb60k_EoqC8q_bGU/v
usp=sharing
Note # 2
Please examine and put up.
Note # 3
Note # 4
PD is requested to resubmit the Tender Documents duly modifying the Schedule B
& C as per NHAI Policy Circular No. 11.54/2023 dated 30.10.2023 and Schdules H
as per Ministry's circular dated:11.10.2024.
4
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
MANAGER(TECHNICAL)
Note # 5
In compliance to above note, the t ender Documents duly modifying the Schedule
B & C as per NHAI Policy Circular No. 11.54/2023 dated 30.10.2023 and Schdules
H as per Ministry's circular dated:11.10.2024 are enclosed herewith for taking
further necessary action, please.
Note # 6
Note # 7
Note # 8
This has reference to the bid documents furnished by the PIU for Anksapur
and Kondamadugu locations.
5
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
and TCS-2B-1 (Km.31+600 to 31+790). In approved TCS-2B, lined drain is
proposed at edge of Service Road. However, in submitted TCS-2B-1 the lined
drain is shifted from Service Road edge to RE Wall side. Reason for the
same and connectivity of drain at Km.31+600 may be furnished.
2.3 TCS-1B & TCS-1C lengths shown as 55m. The same is 75 m as per
plan & profile. Please verify.
Note # 9
Note # 10
National Highways Authority of India,
PIU Warangal
Sub: PIU Warangal - Construction of 6 Lane LVUP at Km 26+775
(Ankushapur X Road) and 6 lane VUP at Km 31+255 (Kondamadugu Junction) on
Hyderabad - Yadgiri Section of NH-163 in the State of Telangana on EPC Mode –
Submission of Draft RFP reg.
6
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
4. DPR consultant mail dated 04.11.2024
Sir,
This has reference to RO Hyderabad mail dated 30.10.2024 wherein
communicated certain observations on the submitted bid documents for
Ankushapur and Kondamadugu locations of Hyderabad Yadgiri section of NH
163.
7
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
be furnished and cost TCS- 3083 TCS-
implication if any. 30730 30830 100 3B 30730 0 100 3B
TCS- 3160 TCS-
30830 31600 770 2B 30830 0 770 2B
TCS- 3179 TCS-
31600 31790 190 2B 31600 0 190 2B-3
TCS- 3190 TCS-
31790 31900 110 3B 31790 0 110 3B-2
b. RO Hyderabad vide E office file no 256539 and 255968 communicated the approval for
“Construction of 6 Lane LVUP at Km 26+775 (Ankushapur X Road) and 6 lane VUP at
Km 31+255 (Kondamadugu Junction) on Hyderabad - Yadgiri Section of NH-163 in the
State of Telangana on EPC Mode” for an amount of Rs. 43,69,43,783/- (Civil cost).
HYD-YGT_ANKUSHAPUR_BOD (6-LANES)_2024-11-04.pdf
HYD-YGT_KONDAMADUGU_BOD (6-LANES)_2024-11-04.pdf
8
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
RFP-BSHYD-YAD BS Final 22.10.2024.docx
Schedule-A.docx
Schedule-B.docx
Schedule-C.doc
Schedule-D.docx
Note # 11
Note # 12
Note # 13
Sir,
3 . PD, PIU, Warangal in the above Note#1 submitted the Bid proposal
along with all relevant documents for approval. As per NHAI policy circular
12.31/2023 dated 23.02.2023 the ROs can take a judicious decision to
combine bids for rectification of black spots located in nearby vicinity in
to a single bid if feasible instead of inviting separate bids for each black
spot.
9
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
4. Accordingly, PD has submitted the combine Tender documents, Drawings
and Technical schedules for the following 2 locations.
Cost put Remarks
S.
BS ID Location Proposal to Tender
No
in Cr.
Ankushapur [TG-03-188]
Kondamadugu [TG-03-189]
10
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
Supervision charges @ 3% on
83,87,797/- 86,87,399/-
A
Maintenance charges @
82,48,000/- 85,42,609/-
2.5% on A+B for 5 years
Price Escalation @ 5% on A 1,39,79,661/- 1,44,78,999/-
Utility Shifting (Ls) 40,00,000/- -
Total 36,73,31,390/- 37,63,09,182/-
11
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
Head(F&A), RO-Hyderabad
Note # 14
The proposal of PD, PIU, Warangal at Note#10 is regarding approval for
revised cost and RFP of Black spot works at Ankushapur & Kondamadugu
junctions on NH-163 to invite bids. The same is discussed in detail in above
Note#13. PD has proposed the time period for completion of work as 12
months . As per discussions held in RO, the same time period is retained,
and Price Adjustment clause is deleted in BID DOCUMENT. By oversite in the
above note price adjustment amt is retained in the revised estimate also.
The same is corrected below.
In view of deletion of Price adjustment and proposing the provision of
utility shifting as per the actual estimates received from the user agency
the revised estimate is working out to as shown below:
Ankushapur [TG-03-188]
12
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
3 Contingency charges @ 1% 15,73,506/- 16,01,979/-
on A
Supervision charges @ 3% on
47,20,517/- 48,05,939/-
A
Maintenance charges @
46,41,842/- 47,25,840/-
2.5% on A+B for 5 years
Price Escalation @ 5% on A 78,67,528/- -
Utility Shifting (Ls) 30,00,000/- -
Total 20,74,77,057/- 20,01,67,392/-
Kondamadugu [TG-03-189]
13
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
A draft letter communicating the approval for revised sanction duly
superseding the earlier sanction is also put up for perusal and
approval please.
Note # 15
As proposed.
Note # 16
Note # 17
Sub: NHAI – RO Hyderabad – PIU-Warangal - Construction of 6-Lane
Underpasses (2 No’s) and allied works on Existing 4 Lane Hyderabad
to Yadgiri Section of NH-163 at Ankushapur (from Km.26+145 to
Km.27+295) & Kondamadugu Jn. (From Km.30+505 to 32+125) in the
State of Telangana on EPC Mode, as part of Long-term Rectification of
MoRTH Identified Black Spots (TG-03-188 & TG-03-189) – Release of
e-BG through NESL Portal – Reg
Sir,
This has reference to the subject cited above, wherein this office
has invited tenders for Construction of 6-Lane Underpasses (2 No’s) and
allied works on Existing 4 Lane Hyderabad to Yadgiri Section of NH-163 at
Ankushapur (from Km.26+145 to Km.27+295) & Kondamadugu Jn. (From
Km.30+505 to 32+125) in the State of Telangana on EPC Mode, as part of
Long-term Rectification of MoRTH Identified Black Spots (TG-03-188 & TG-
03-189).
14
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
2. Subsequently, bids evaluation was carried out and LOA is issued to
L1 Bidder M/s. Srinivasa Edifice Pvt. Ltd. [Financial Evaluation letter]
Note # 18
The proposal is regarding release of e-BG through NESL portal of the unsuccessful
bidder for Black spot work. The same may be forwarded to CGM(Fin) for taking
further action as proposed above.
Note # 19
Submitted for necessary action.
15
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
Note # 20
Note # 21
Release e-BG of RN Constructions as approved by competent authority .
Note # 22
Reference notes above
The proposal is received from RO-Hyderabad for release of e-BG vide note#17-18.
Competent Authority has already approved to release the e_BG vide note#19.
In view of above and if approved we may release following e-BGs on NeSL portal.
Note # 23
Note # 24
Approved for release .
16
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
II)
Note # 25
एनईएसएल पोटल के मा यम से उपरो त ई-बीजी बंद करने हे तु अनुरोध भेजा दया गया है ।
Request send for releasing /C losure the aforesaid E-B G s through N eS L portal.
Note # 26
Note # 27
Note # 28
17
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
2. It is hereby informed that the memorandum Containing an inventory
of the Site including the vacant and unencumbered land, the available
details at the site, specifying in reasonable details of those parts of the
Site to which vacant access and Right of Way has been given to the
Contractor, is signed on 15.04.2025 by the authorized representative of the
contractor & the undersigned, in provisions of cl. 8.2 of Contract
Agreement. A copy of the same is enclosed for record/reference and
further action, please.
Encl: As above
Note # 29
As proposed vide Note#28 , it is recommended that the Appointed Date for
the Project is to be declared w.e.f 09.04.2025, please.
Note # 30
Please examine and put up.
Note # 31
PD is requested to furnish the Hand Over Memorandum as per Cl 8.2 of CA signed
by the three counterparts (AE/Contractor/PD) to take further action.
18
File No. TGDIV-20011/37/2024-Piu Warangal (Computer No. 263445)
Generated from eOffice by KHANDESH SRINITHIN, ManagerRO Hyderabad) - KS, MANAGER(TECHNICAL), RO Hyderabad on 23/04/2025 01:19 PM
19/04/2025 12:00 PM जी.वी. भीमासे ना रे डी|G V BHEEMASENA REDDY
उप महापबं ध क (आरओ-है द राबाद)|DGM (RO-HYDERABAD)
Note # 32
Note # 33
This has reference to the note # 31, please find enclosed herewith the Handing
Over Memorandum as per Cl.8.2 of CA
Note # 34
Note # 35
19