PDF For Draft
PDF For Draft
Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress
Page 1
Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)
ID Task Task Name Duration Start Finish 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
62 MS Bar Fabrication & Shuttering Work 7 days Fri 27-09-24 Thu
for Column, Lift Wall ,Shear Wall , 03-10-24
Stair, Ramp etc.
63 Concreting Works for Column, Lift Wall 3 days Fri 04-10-24 Sun
,Shear Wall , Stair, Ramp etc. 06-10-24
64 MS Bar Fabrication For Beam & Slab 17 days Mon 07-10-24Wed 23-10-24
65 Electrical Conduit Laying Work 3 days Thu 24-10-24 Sat 26-10-24
66 Concreting Works For Beam & Slab 1 day Sun Sun
(Level: 1st Floor ) 27-10-24 27-10-24
67 1st Floor - 2nd Floor 31 days Mon 28-10-24Wed 27-11-24
68 MS Bar Fabrication & Shuttering Work 7 days Mon Sun
for Column, Lift Wall ,Shear Wall , 28-10-24 03-11-24
Stair, Ramp etc.
69 Concreting Works for Column, Lift Wall 3 days Mon Wed
,Shear Wall , Stair, Ramp etc. 04-11-24 06-11-24
70 MS Bar Fabrication For Beam & Slab 17 days Thu 07-11-24 Sat 23-11-24
71 Electrical Conduit Laying Work 3 days Sun 24-11-24 Tue 26-11-24
72 Concreting Works For Beam & Slab 1 day Wed Wed
(Level:2nd Floor ) 27-11-24 27-11-24
73 2nd Floor - 3rd Floor 31 days Thu 28-11-24Sat 28-12-24
74 MS Bar Fabrication & Shuttering Work 7 days Thu Wed
for Column, Lift Wall ,Shear Wall , 28-11-24 04-12-24
Stair, Ramp etc.
75 Concreting Works for Column, Lift Wall 3 days Thu Sat 07-12-24
,Shear Wall , Stair, Ramp etc. 05-12-24
76 MS Bar Fabrication For Beam & Slab 17 days Sun 08-12-24 Tue 24-12-24
77 Electrical Conduit Laying Work 3 days Wed 25-12-24Fri 27-12-24
78 Concreting Works For Beam & Slab 1 day Sat 28-12-24 Sat 28-12-24
(Level: 3rd Floor )
79 3rd Floor - 4th Floor 31 days Sun 29-12-24Tue 28-01-25
80 MS Bar Fabrication & Shuttering Work 7 days Sun Sat 04-01-25
for Column, Lift Wall ,Shear Wall , 29-12-24
Stair, Ramp etc.
81 Concreting Works for Column, Lift Wall 3 days Sun Tue
,Shear Wall , Stair, Ramp etc. 05-01-25 07-01-25
82 MS Bar Fabrication For Beam & Slab 17 days Wed 08-01-25Fri 24-01-25
83 Electrical Conduit Laying Work 3 days Sat 25-01-25 Mon 27-01-25
84 Concreting Works For Beam & Slab 1 day Tue Tue
(Level: 4th Floor ) 28-01-25 28-01-25
85 4th Floor - 5th Floor 31 days Wed 29-01-25Fri 28-02-25
86 MS Bar Fabrication & Shuttering Work 7 days Wed Tue
for Column, Lift Wall ,Shear Wall , 29-01-25 04-02-25
Stair, Ramp etc.
87 Concreting Works for Column, Lift Wall 3 days Wed Fri 07-02-25
,Shear Wall , Stair, Ramp etc. 05-02-25
88 MS Bar Fabrication For Beam & Slab 17 days Sat 08-02-25 Mon 24-02-25
89 Electrical Conduit Laying Work 3 days Tue 25-02-25 Thu 27-02-25
90 Concreting Works For Beam & Slab 1 day Fri 28-02-25 Fri 28-02-25
(Level: 5th Floor )
91 5th Floor - 6th Floor 29 days Sat 01-03-25 Sat 29-03-25
92 MS Bar Fabrication & Shuttering Work 7 days Sat 01-03-25 Fri 07-03-25
for Column, Lift Wall ,Shear Wall ,
Stair, Ramp etc.
93 Concreting Works for Column, Lift Wall 3 days Sat 08-03-25 Mon
,Shear Wall , Stair, Ramp etc. 10-03-25
94 MS Bar Fabrication For Beam & Slab 15 days Tue 11-03-25 Tue 25-03-25
95 Electrical Conduit Laying Work 3 days Wed 26-03-25Fri 28-03-25
96 Concreting Works For Beam & Slab 1 day Sat 29-03-25 Sat 29-03-25
(Level: 6th Floor )
97 6th Floor -7th Floor 41 days Sun 30-03-25Fri 09-05-25
98 EID-UL-FITR 2025 10 days Sun 30-03-25Tue 08-04-25
99 MS Bar Fabrication & Shuttering Work 7 days Wed Tue
for Column, Lift Wall ,Shear Wall , 09-04-25 15-04-25
Stair, Ramp etc.
100 Concreting Works for Column, Lift Wall 3 days Wed Fri 18-04-25
,Shear Wall , Stair, Ramp etc. 16-04-25
101 MS Bar Fabrication For Beam & Slab 17 days Sat 19-04-25 Mon 05-05-25
102 MAY DAY - 2024 0 days Thu 01-05-25Thu 01-05-25 01-05
103 Electrical Conduit Laying Work 3 days Tue 06-05-25 Thu 08-05-25
104 Concreting Works For Beam & Slab 1 day Fri 09-05-25 Fri 09-05-25
(Level: 7th Floor )
105 7th Floor - 8th Floor 35 days Sat 10-05-25 Fri 13-06-25
106 MS Bar Fabrication Column, Lift Wall, 7 days Sat 10-05-25 Fri 16-05-25
Shear Wall,Stair,Ramp etc.
107 Concreting Works for Column, Lift Wall 3 days Sat 17-05-25 Mon
,Shear Wall , Stair, Ramp etc. 19-05-25
108 MS Bar Fabrication For Beam & Slab 15 days Tue 20-05-25 Tue 03-06-25
109 EID-UL-ADHA 2025 10 days Wed 04-06-25Fri 13-06-25
110 Electrical Conduit Laying Work 3 days Fri 06-06-25 Sun 08-06-25
111 Concreting Works For Beam & Slab 1 day Mon Mon
(Level: 8th Floor ) 09-06-25 09-06-25
Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress
Page 2
Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)
ID Task Task Name Duration Start Finish 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
112 8th Floor - 9th Floor 31 days Tue 10-06-25Thu 10-07-25
113 MS Bar Fabrication & Shuttering Work 7 days Tue Mon
for Column, Lift Wall ,Shear Wall , 10-06-25 16-06-25
Stair, Ramp etc.
114 Concreting Works for Column, Lift Wall 3 days Tue Thu
,Shear Wall , Stair, Ramp etc. 17-06-25 19-06-25
115 MS Bar Fabrication For Beam & Slab 17 days Fri 20-06-25 Sun 06-07-25
116 Electrical Conduit Laying Work 3 days Mon 07-07-25Wed 09-07-25
117 Concreting Works For Beam & Slab 1 day Thu Thu
(Level: 9th Floor ) 10-07-25 10-07-25
118 9th Floor - Roof Slab 31 days Fri 11-07-25 Sun 10-08-25
119 MS Bar Fabrication & Shuttering Work 7 days Fri 11-07-25 Thu
for Column, Lift Wall ,Shear Wall , 17-07-25
Stair, Ramp etc.
120 Concreting Works for Column, Lift Wall 3 days Fri 18-07-25 Sun
,Shear Wall , Stair, Ramp etc. 20-07-25
121 MS Bar Fabrication For Beam & Slab 17 days Mon 21-07-25Wed 06-08-25
122 Electrical Conduit Laying Work 3 days Thu 07-08-25 Sat 09-08-25
123 Concreting Works For Beam & Slab 1 day Sun Sun
(Level: Roof Slab) 10-08-25 10-08-25
124 125 mm & 250 mm Brick Work & AAC 270 days Thu Sun
Block Works 28-11-24 24-08-25
125 Basement 1 30 days Thu 28-11-24 Fri 27-12-24
126 Ground Floor 30 days Sat 28-12-24 Sun 26-01-25
127 1st Floor 30 days Mon 27-01-25Tue 25-02-25
128 2nd Floor 30 days Wed 26-02-25Thu 27-03-25
129 3rd Floor 30 days Fri 28-03-25 Sat 26-04-25
130 4th Floor 20 days Sun 27-04-25 Fri 16-05-25
131 5th Floor 20 days Sat 17-05-25 Thu 05-06-25
132 6th Floor 20 days Fri 06-06-25 Wed 25-06-25
133 7th Floor 20 days Thu 26-06-25 Tue 15-07-25
134 8th Floor 20 days Wed 16-07-25Mon 04-08-25
135 9th Floor 20 days Tue 05-08-25 Sun 24-08-25
136 Safety Net 30 days Wed 29-01-25Thu 27-02-25
137 Plaster Works ( Interior) 220 days Wed 26-02-25Fri 03-10-25
138 Basement 1 20 days Wed 26-02-25Mon 17-03-25
139 Ground Floor 20 days Tue 18-03-25 Sun 06-04-25
140 1st Floor 20 days Mon 07-04-25Sat 26-04-25
141 2nd Floor 20 days Sun 27-04-25 Fri 16-05-25
142 3rd Floor 20 days Sat 17-05-25 Thu 05-06-25
143 4th Floor 20 days Fri 06-06-25 Wed 25-06-25
144 5th Floor 20 days Thu 26-06-25 Tue 15-07-25
145 6th Floor 20 days Wed 16-07-25Mon 04-08-25
146 7th Floor 20 days Tue 05-08-25 Sun 24-08-25
147 8th Floor 20 days Mon 25-08-25Sat 13-09-25
148 9th Floor 20 days Sun 14-09-25 Fri 03-10-25
149 Plaster Work ( Exterior) 90 days Wed 16-07-25Mon 13-10-25
150 Paint Works (Interior + Exterior) 90 days Wed 16-07-25Mon 13-10-25
151 Tiles, Marble & Granite Work 90 days Wed 16-07-25Mon 13-10-25
152 Door Works 90 days Wed 16-07-25Mon 13-10-25
153 Grill Work 90 days Wed 16-07-25Mon 13-10-25
154 Façade Works (Curtain+ACP+GFRC) 170 days Tue 29-04-25Wed 15-10-25
155 Design & Drawing Approval 60 days Tue 29-04-25 Fri 27-06-25
156 Import of the Materials and Equipment 60 days Sat 28-06-25 Tue
from abroad 26-08-25
157 Installation of the Curtain Wall system 50 days Wed 27-08-25Wed 15-10-25
158 Plumbing, Sanitary Works 232 days Wed 26-02-25Wed 15-10-25
159 Rainwater Harvesting Works 60 days Sun 17-08-25Wed 15-10-25
160 Gas Connection work 232 days Wed 26-02-25Wed 15-10-25
161 Water Pump Installation works 60 days Sun 17-08-25Wed 15-10-25
162 Interior Works & Furniture 229 days Sat 01-03-25 Wed 15-10-25
163 Design & Drawing Approval 85 days Sat 01-03-25 Sat 24-05-25
164 Import Material, Preparation, And 60 days Sun Wed
Preinstallation 25-05-25 23-07-25
165 Installation & Setup Furniture 84 days Thu 24-07-25 Wed 15-10-25
166 Landscaping work 40 days Mon 25-08-25Fri 03-10-25
167 Earthwork 10 days Mon 25-08-25Wed 03-09-25
168 Soil Treatment 10 days Thu 04-09-25 Sat 13-09-25
169 Plantation Work 20 days Sun 14-09-25 Fri 03-10-25
170 STP (Civil + E/M) 30 days Sun 14-09-25Mon 13-10-25
171 Civil Work 15 days Sun 14-09-25 Sun 28-09-25
172 EM Work 15 days Mon 29-09-25Mon 13-10-25
173 Internal Electrical Work 140 days Sun 25-05-25 Sat 11-10-25
174 Electro-Mechanical Works 304 days Sat 01-03-25 Mon 29-12-25
175 Air Conditioning System (VRF System) 229 days Sat 01-03-25 Wed 15-10-25
176 Drawing and Design preparation and 30 days Sat 01-03-25 Sun
approval 30-03-25
Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress
Page 3
Proposed Tentative Work Program for Construction of Vision 2041 Smart Tower (Vision 2021 Tower-2, STP-2)
ID Task Task Name Duration Start Finish 2024 2025 2026
Mode Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
177 Import of the Materials and 120 days Mon Mon
Equipment from abroad 31-03-25 28-07-25
178 Installation of the HVAC system 50 days Tue 29-07-25 Tue 16-09-25
179 Testing & Commissioning 29 days Wed 17-09-25Wed 15-10-25
180 Fire Protection, Fire Detection and 229 days Sat 01-03-25 Wed
Alarm System 15-10-25
181 Drawing and Design preparation and 30 days Sat 01-03-25 Sun
approval 30-03-25
182 Import of the Materials and 120 days Mon Mon
Equipment from abroad 31-03-25 28-07-25
183 Piping, cabling and installation of 50 days Tue Tue
the equipment 29-07-25 16-09-25
184 Commissioning of the FPFDA system 29 days Wed 17-09-25Wed 15-10-25
185 SUBSTATION WORK 220 days Sat 01-03-25 Mon 06-10-25
186 Drawing and Design preparation and 30 days Sat 01-03-25 Sun
approval 30-03-25
187 Import of the Materials and 120 days Mon Mon
Equipment from abroad 31-03-25 28-07-25
188 Installation of the Substation system 50 days Tue 29-07-25 Tue 16-09-25
189 Commissioning of Sub-Station 20 days Wed 17-09-25Mon 06-10-25
190 LIFT WORK 229 days Sat 01-03-25 Wed 15-10-25
191 Drawing and Design preparation and 20 days Sat 01-03-25 Thu
approval 20-03-25
192 Import of the Materials and 120 days Fri 21-03-25 Fri 18-07-25
Equipment from abroad
193 Installation of the Lift 60 days Sat 19-07-25 Tue 16-09-25
194 Commissioning of Lift 29 days Wed 17-09-25Wed 15-10-25
195 Solar System 180 days Sat 01-03-25 Wed 27-08-25
196 Drawing and Design preparation and 30 days Sat 01-03-25 Sun
approval 30-03-25
197 Import of the Materials and 90 days Mon Sat 28-06-25
Equipment from abroad 31-03-25
198 Installation of the equipment 60 days Sun 29-06-25 Wed 27-08-25
199 Installation of the Solar system 15 days Sun 13-07-25 Sun 27-07-25
200 Optical Fiber and Networking System 185 days Sat 01-03-25 Mon 01-09-25
201 Drawing and Design preparation and 20 days Sat 01-03-25 Thu
approval 20-03-25
202 Import of the Materials and 90 days Fri 21-03-25 Wed
Equipment from abroad 18-06-25
203 Piping, cabling and installation of 45 days Thu Sat 02-08-25
the equipment 19-06-25
204 Commissioning of the Networking 30 days Sun Mon
system 03-08-25 01-09-25
205 Surveillance System 220 days Sat 01-03-25 Mon 06-10-25
206 Drawing and Design preparation and 20 days Sat 01-03-25 Thu
approval 20-03-25
207 Import of the Materials and 90 days Fri 21-03-25 Wed
Equipment from abroad 18-06-25
208 Piping, cabling and installation of 60 days Thu Sun
the equipment 19-06-25 17-08-25
209 Installation of the Surveillance system50 days Mon 18-08-25Mon 06-10-25
210 Video Conferencing, Stage Lighting & 200 days Sat 01-03-25 Tue
Sound System 16-09-25
211 Drawing and Design preparation and 20 days Sat 01-03-25 Thu
approval 20-03-25
212 Import of the Materials and 90 days Fri 21-03-25 Wed
Equipment from abroad 18-06-25
213 Piping, cabling and installation of 60 days Thu Sun
the equipment 19-06-25 17-08-25
214 Commissioning of the Stage Lighting 30 days Mon Tue
& Sound system 18-08-25 16-09-25
215 Integrated Building Management 214 days Sat 01-03-25 Tue
System (IBMS) 30-09-25
216 Drawing and Design preparation and 30 days Sat 01-03-25 Sun
approval 30-03-25
217 Import of the Materials and 90 days Mon Sat 28-06-25
Equipment from abroad 31-03-25
218 Piping, cabling and installation of 60 days Sun Wed
the equipment 29-06-25 27-08-25
219 Installation of the IBMS System 20 days Thu 11-09-25 Tue 30-09-25
220 Testing and Commissioning of the 10 days Thu Sat 25-10-25
whole Building Systems 16-10-25
221 Project Cleaning and ready for handover
27 days Sun 26-10-25 Fri 21-11-25
222 Final Bill Submission, Clearance & 38 days Sat 22-11-25 Mon
Handing Taking Over 29-12-25
223 Project End 0 days Tue 30-12-25 Tue 30-12-25 30-12
Project: Construction of Vision Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress
Page 4