Work Presentation

The document outlines the work activities conducted by subcontractor SINAMM on September 17-18, 2023, including excavation, backfilling, and various installation works across multiple areas. It details specific tasks such as STP MH work, pipe installations, and housekeeping, along with manpower and equipment used. Additionally, it notes that no overtime work was performed during this period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views2 pages

Work Presentation

The document outlines the work activities conducted by subcontractor SINAMM on September 17-18, 2023, including excavation, backfilling, and various installation works across multiple areas. It details specific tasks such as STP MH work, pipe installations, and housekeeping, along with manpower and equipment used. Additionally, it notes that no overtime work was performed during this period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

n Subcontractor Name: : SINAMM

n PM: HANNAN ALI MRIDHA n CM: HASANUR RAHMAN n Safety : MD. MOKLESURE RAHMAN
n Date: 17-09-2023 n Written by: NITISH KUMAR MONDAL
17-Sep-23 18-Sep-23
Content
Work Activity Area Work Activity Area
> Excavation Area 4(N) & ECT-ICT > Excavation Area 4(N) & ECT-ICT
> Backfilling work Area 4(N) & ECT-ICT > Backfilling work Area 4(N) & ECT-ICT
> STP MH work Area 3-1, 4(N) > STP MH work Area 3-1, 4(N)
> DI pipe installation for STP MH Area 4(N) > DI pipe installation for STP MH Area 4(N)
> CDB MH work Area 2, 4(N) & ECT-ICT > CDB MH work Area 2, 4(N) & ECT-ICT
> UPVC pipe installation for Conc DB N/A > UPVC pipe installation for Conc DB N/A
> Trial Trench work- Zone 7 ECT-ICT Area > Trial Trench work- Zone 7 ECT-ICT Area
> Concrete pouring work N/A > Concrete pouring work N/A
Others: Others:
1. LV MH 3-2 inside cleaning work. 1. LV MH 3-2 inside cleaning work
Area wise

activities

2. LV MH-65 step ladder installation purpose core cutting work 2. LV MH-65 step ladder installation purpose core cutting work
work

3. LPS-02 core cutting work for ladder installation purpose. 3. LPS-02 core cutting work for ladder installation purpose.
4. House keeping work. Area 2 4. STP MH 31,31A , CCL MH 74 top slab cover installation work. Area 2
5. House keeping work.

Others: Concreting:
1. FLO-26 base rebar binding and shuttering work 1. STP MH-NP -05, 1st lift wall shuttering and casting work
Area wise

activities

2. STP MH-NP-03 & 04 wall de-shuttering work Others:


3. STP MH - NP -02 & 03 final lift wall shuttering work
work

1. FLO-26 base rebar binding amd shuttering work


4. Housekeeping work. 2. STP MH - NP -02 & 03 & 04 final lift wall shuttering work
Area 3-1 Area 3-1
3. Housekeeping work.

Excavation: Concreting:
1. STP MH- 36 to STP -35 Di pipe line excavation and Di pipe 1. STP MH-36 top slab shuttering and rebar casting work
Area wise work

installing work 2. EHP pipe line excavation and lean casting work
Backfilling: Others:
activities

1. STP MH 43 &44 STP MH 43-1&42 Di pipe line & EHP pipe line sand 1. STP MH- 13-3 manhole cover setting & PFH 12,13 top slab cover
level dressing & compaction work setting work
Others: Area 4 (North) 2. STP MH -35 & 37 inside top deshuttering and wall surface Area 4 (North)
1. STP MH-36 top slab shuttering and rebar work cleaning work
2. STP MH- 13-3 manhole cover setting & PFH 12,13 top slab cover 3. CDB MH 13-2 drilling work.
setting work 4. CDB MH 15-5 Cleaning work
3. CDB MH 13-2 drilling work. 5. CDB MH 16-1 drilling work
4. CDB MH 15-5 Cleaning work 6. Housekeeping & material shifting work.
5. CDB MH 16-1 drilling work
6. Housekeeping & material shifting work.

Page 1 of 2
Trial Trench/ Excavation work Trial Trench/ Excavation work
1. MH-05 To MH-06 Trial Trench Work 1. MH-05 To MH-06 Trial Trench Work

Area wise work


2. MH-14 Trial Pit Manually excavation work 2. MH-14 Trial Pit Manually excavation work
Backfilling & Compaction: Backfilling & Compaction:

activities
1. MH-07 To MH-09 Sand Level Dressing & Brick Soling Work 1. MH-11 To MH-12 Sand Level Dressing & Compaction Work
Others: Others:
1. MH-12 Manhole cover shuttering Work ECT/ICT Area (Zone 7) 1. MH-12 Manhole cover shuttering Work ECT/ICT Area (Zone 7)
2. MH-31-3 Core Cutting & Step Ladder Setting Work 2. MH-31-2 Core Cutting & Step Ladder Setting Work
3. MH-21-1 Core Cutting Hole Grouting Work 3. MH-28-1 Core Cutting Hole Grouting Work
4. MH 23-1 grouting work 4. Housekeeping work
5. Housekeeping work

B) Overtime : 6:00pm-10:00pm (No Work) B) Overtime : 6:00pm-10:00pm (No Work)


Over time work

N/A Area 3-1 N/A Area 3-1


activity

Manpower Equipments/Tools Manpower Equipments/Tools


1. Engineer- 0 1. Excavator-0 1. Engineer-0 1. Excavator-0
2. HSE personnel :0 2. Dumptruck- 0 Area 3-1 2. HSE personnel :0 2. Dumptruck- 0 Area 3-1

3. Supervisor :0 3. Roller- 0 3. Supervisor :0 3. Roller- 0


4. Electrician-0 4. Stationary Pump- 0 4. Electrician-0 4. Stationary Pump-
C) Worker : (Area2:0) + (Area 3-1:0) +(Area 4 North:0) C) Worker : (Area2:0) + (Area 3-1:0) +(Area 4 North:0)
0
+(Area4 South:5)+(Area 5:0) +(ECT, ICT Area:0)= 0 +(Area4 South:5)+(Area 5:0) +(ECT, ICT Area:0)= 0
Person Person
Safet Require

issue Coordin
ation
y d

s
Reques

ADC
t to