Work Presentation
Work Presentation
n PM: HANNAN ALI MRIDHA n CM: HASANUR RAHMAN n Safety : MD. MOKLESURE RAHMAN
n Date: 17-09-2023 n Written by: NITISH KUMAR MONDAL
17-Sep-23 18-Sep-23
Content
Work Activity Area Work Activity Area
> Excavation Area 4(N) & ECT-ICT > Excavation Area 4(N) & ECT-ICT
> Backfilling work Area 4(N) & ECT-ICT > Backfilling work Area 4(N) & ECT-ICT
> STP MH work Area 3-1, 4(N) > STP MH work Area 3-1, 4(N)
> DI pipe installation for STP MH Area 4(N) > DI pipe installation for STP MH Area 4(N)
> CDB MH work Area 2, 4(N) & ECT-ICT > CDB MH work Area 2, 4(N) & ECT-ICT
> UPVC pipe installation for Conc DB N/A > UPVC pipe installation for Conc DB N/A
> Trial Trench work- Zone 7 ECT-ICT Area > Trial Trench work- Zone 7 ECT-ICT Area
> Concrete pouring work N/A > Concrete pouring work N/A
Others: Others:
1. LV MH 3-2 inside cleaning work. 1. LV MH 3-2 inside cleaning work
Area wise
activities
2. LV MH-65 step ladder installation purpose core cutting work 2. LV MH-65 step ladder installation purpose core cutting work
work
3. LPS-02 core cutting work for ladder installation purpose. 3. LPS-02 core cutting work for ladder installation purpose.
4. House keeping work. Area 2 4. STP MH 31,31A , CCL MH 74 top slab cover installation work. Area 2
5. House keeping work.
Others: Concreting:
1. FLO-26 base rebar binding and shuttering work 1. STP MH-NP -05, 1st lift wall shuttering and casting work
Area wise
activities
Excavation: Concreting:
1. STP MH- 36 to STP -35 Di pipe line excavation and Di pipe 1. STP MH-36 top slab shuttering and rebar casting work
Area wise work
installing work 2. EHP pipe line excavation and lean casting work
Backfilling: Others:
activities
1. STP MH 43 &44 STP MH 43-1&42 Di pipe line & EHP pipe line sand 1. STP MH- 13-3 manhole cover setting & PFH 12,13 top slab cover
level dressing & compaction work setting work
Others: Area 4 (North) 2. STP MH -35 & 37 inside top deshuttering and wall surface Area 4 (North)
1. STP MH-36 top slab shuttering and rebar work cleaning work
2. STP MH- 13-3 manhole cover setting & PFH 12,13 top slab cover 3. CDB MH 13-2 drilling work.
setting work 4. CDB MH 15-5 Cleaning work
3. CDB MH 13-2 drilling work. 5. CDB MH 16-1 drilling work
4. CDB MH 15-5 Cleaning work 6. Housekeeping & material shifting work.
5. CDB MH 16-1 drilling work
6. Housekeeping & material shifting work.
Page 1 of 2
Trial Trench/ Excavation work Trial Trench/ Excavation work
1. MH-05 To MH-06 Trial Trench Work 1. MH-05 To MH-06 Trial Trench Work
activities
1. MH-07 To MH-09 Sand Level Dressing & Brick Soling Work 1. MH-11 To MH-12 Sand Level Dressing & Compaction Work
Others: Others:
1. MH-12 Manhole cover shuttering Work ECT/ICT Area (Zone 7) 1. MH-12 Manhole cover shuttering Work ECT/ICT Area (Zone 7)
2. MH-31-3 Core Cutting & Step Ladder Setting Work 2. MH-31-2 Core Cutting & Step Ladder Setting Work
3. MH-21-1 Core Cutting Hole Grouting Work 3. MH-28-1 Core Cutting Hole Grouting Work
4. MH 23-1 grouting work 4. Housekeeping work
5. Housekeeping work
issue Coordin
ation
y d
s
Reques
ADC
t to
Page 2 of 2