Assignment (Line of Balance)
Assignment (Line of Balance)
QUESTION (2)
You are given the unit network of a 61- unit project and its required to deliver the project after 28
days
a) calculate the number of crews that need to be involved in each activity
b) when will the crew no.2 in activity C enters the project and when will they leave
QUESTION (4):
The construction plan for a house is in Table, with activities' durations in days:
a) calculate the number of crews that need to be involved in each activity for scheduling a project
of 30 repetitive houses and the project has to be delivered in 85 days.
b) Given a desired target rate of four units per week, what is the number of crews to be employed
in activity B
Activity Depends on Duration (days)
A - 5
B A 5
C B 7
D C 2
E C 3
F D,E 5
QUESTION (5):
The logic network for one unit of a 15-unit project is shown below. The first unit is to be finished after
15 weeks, and a hand over rate of one unit per two weeks is to be maintained afterward. Construct
the progress chart at the end of week 25.
QUESTION (7):
The following table shows the activities included in one unit of a 40 unit housing project. The work
has progressed as planned for 25 weeks. Then, it is required to :inish the project after 10 weeks. What
is the minimum production rate for each activity to meet that target?