Manishji Singed

The document provides a detailed quantity and preliminary rate analysis for construction work at a specified plot in Indore, including excavation, concrete work, brickwork, flooring, finishing, and installations. It lists various construction activities along with their quantities, unit rates, and total amounts, culminating in a total estimated cost of 925,153. The analysis is signed by Chartered Engineer Sunil Modi.

Uploaded by

revaluefinance
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views2 pages

Manishji Singed

The document provides a detailed quantity and preliminary rate analysis for construction work at a specified plot in Indore, including excavation, concrete work, brickwork, flooring, finishing, and installations. It lists various construction activities along with their quantities, unit rates, and total amounts, culminating in a total estimated cost of 925,153. The analysis is signed by Chartered Engineer Sunil Modi.

Uploaded by

revaluefinance
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ER.

SUNIL MODI
CHARTERED ENGINEER
REG. NO.- AM1956224
ADDRESS: - MARUTI NAGAR, BETMA ROAD, SAGOR KUTI
MOB. NO. +917869808388
__________________________________________________________________________________________
Quantity and Preliminary Rate Analysis of Shri Manish Thakur S/o Shri Mahesh Thakur at
Plot No. 42 (West Part), Gali No. 02, Dabagar Mohalla, Ward No. 10, Zone No. 04, Indore (M.P.)

Plot Area - 13'5" X 40 = 536 Sq.Ft.


Total Ground Floor + S/C Tower Construction Area - 616.67 Sq. Ft.

S. No. DESCRIPTION QUANTITY UNIT RATE AMOUNT

1 Excavation Work
Excavation Work by mechanical
means (Hydraulic excavatior)/
manual means in foundation
Ordinary Rock 8 Cub. M. 216 1728

2 P.C.C. Work
Providing and laying position of
specified gradde excluding the cost
of centering and shuttering -
All Work up to plinth level
M-10 1.5 Cub. M. 3890 5835

3 R.C.C. Work
Providing and laying position
excluding the cost of centering,
Shuttering, finishing and
reinforcement - (Up to Plinth level)
M-20 Grade Concrete 3 Cub. M. 5091 15273
R.C.C. Work in Beam, supspended
floors, roofs, chajjas, staircases
excluding the cost of centering,
Shuttering, finishing and
reinforcement - (Above to
Plinth Level)
M-20 Grade Concrete 24.5 Cub. M. 5284 129458

Reinforcement for R.C.C. Work


TMT Bars 1850 K.G. 62.9 116365

4 Brick Work
Brick Work with well burnt chimney
bricks with cement mortar (1:4) 18 Cub. M. 5818 104724

5 Stone Work
Kitchen Stand 60 mm 6 Sq. M. 1299 7794

Digitally signed by SUNIL MODI


SUNIL MODI Date: 2025.04.22 16:57:16
+05'30'
6 Flooring Work
Providing and laying tiles 600x600mm 70 Sq. M. 1081 75670

7 Finishing Work
20 mm Cement Plaster 1:4
(1 Cement : 4 Sand) 1100 Sq. M. 175 192500

Colour Painting Work


Applying once coat of water
thinnable cement primer 1100 Sq. M. 24 26400
Wall Painging With Plastic
Emulsion paint two coat 1100 Sq. M. 64 70400

8 Doors
Wooden Frames for door and
window with sal wood 0.5 Cub. M. 71308 35654
Pre-Laminated flat pressed 3-Layer
25mm playwood 9 Sq. M. 1383 12447
Aluminium doors 5 Sq. M. 849 4245

9 Windows
Galvanised Steel window 12mm bar 38 K.G. 130 4940
Aluminium windows with 4mm glass 21 Sq. M. 849 17829

10 Sanitary Installatins
Providing and fixing water closet
squatting pan (Indian Type) 1 Nos 2995 2995
Kitchen sink with drain boar 610x510
mm bown depth 200 mm 1 Nos 2948 2948
Ovel shape wash basin 1 Nos 7948 7948

11 Water Supply
Providing and fixing drainage pipe
and other pipes and taps, shaver 45000 L.S. 1 45000

12 Electricity Work
Providing and fitting electrical
appliances including labour charges
and equipments 45000 L.S. 1 45000

Total 925153