Program Os Works - Libertina Amathila
Program Os Works - Libertina Amathila
February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025
Complete 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18
1 UPGRADING OF LIBERTINA 38% 124 days Wed 2/12/25 Mon 8/4/25 38%
AMATHILA AVENUE
2 P & G'S 100% 1 day Wed 2/12/25 Wed 2/12/25 100%
3 Project Commencement 100% 1 day Wed 2/12/25 Wed 2/12/25 100%
4 Site Establishment 95% 22 days Wed 2/12/25 Thu 3/13/25 95%
5 Establish Site 100% 21 days Thu 2/13/25 Thu 3/13/25 100%
6 Stakeholder Engagement 90% 21 days Wed 2/12/25 Wed 3/12/25 90%
7 Preparation of Traffic 100% 2 days Wed 3/12/25 Thu 3/13/25 100%
Accomodation Plan
8 Approval of Water 100% 1 day Mon 3/10/25 Mon 3/10/25 100%
Reticulation VO No.4
9 Civil Works 28% 104 days Wed 3/12/25 Mon 8/4/25 28%
10 LHS- Water Connection 77% 33 days Wed 3/12/25 Fri 4/25/25 77%
11 Installation of Slevees 35% 10 days Mon 3/31/25 Fri 4/11/25 35%
12 Procurement and 100% 14 days Wed 3/12/25 Mon 3/31/25 100%
Delivery of Water
Reticulation Material
13 Remove Existing 100% 5 days Tue 3/18/25 Mon 3/24/25 100%
Paving Works & kerbs
14 Locate of existing 100% 5 days Wed 3/19/25 Tue 3/25/25 100%
sewer and water house
connections And
Protection
15 Setting out Waterline 100% 2 days Tue 3/25/25 Wed 3/26/25 100%
16 Excavation & Trimming 95% 7 days Tue 3/25/25 Wed 4/2/25 95%
works
17 Preperation of Bedding 95% 7 days Tue 3/25/25 Wed 4/2/25 95%
And Testing
18 Pipe laying,Blanket 95% 7 days Tue 3/25/25 Wed 4/2/25 95%
Works And Testing
19 Valve And Hydrants 0% 3 days Mon 3/31/25 Wed 4/2/25 0%
20 Thrust blocks and 0% 2 days Tue 4/1/25 Wed 4/2/25 0%
Anchor Connection
21 Water Pressure Testing 0% 1 day Wed 4/16/25 Wed 4/16/25 0%
22 Backfilling & Compaction85% 5 days Thu 4/17/25 Wed 4/23/25 85%
23 Compaction Testing 0% 2 days Thu 4/24/25 Fri 4/25/25 0%
24 LHS Roadworks 0% 39 days Mon 4/14/25 Thu 6/5/25 0%
25 Cut-to-Spoil 0% 10 days Mon 4/14/25 Fri 4/25/25 0%
26 Roadbed 0% 3 days Mon 4/28/25 Wed 4/30/25 0%
27 Subbase 0% 5 days Thu 5/1/25 Wed 5/7/25 0%
28 Base 0% 5 days Fri 5/16/25 Thu 5/22/25 0%
29 Surfacing 0% 4 days Fri 5/30/25 Wed 6/4/25 0%
30 Pre-road Marking And 0% 1 day Thu 6/5/25 Thu 6/5/25 0%
Road Signange
31 Kerbing and Channeling 0% 5 days Fri 5/23/25 Thu 5/29/25 0%
32 Filling of side walks 0% 3 days Fri 5/23/25 Tue 5/27/25 0%
33 Spraying of Side walks 0% 3 days Fri 5/30/25 Tue 6/3/25 0%
34 RHS - Water Connection 24% 66 days Mon 3/24/25 Mon 6/23/25 24%
35 Installation of Slevees 0% 10 days Mon 3/31/25 Fri 4/11/25 0%
36 Remove Existing 100% 10 days Mon 3/24/25 Fri 4/4/25 100%
Paving Works & kerbs
37 Locate of existing 100% 10 days Tue 3/25/25 Mon 4/7/25 100%
sewer and water house
connections And
Protection
38 Setting out Waterline 0% 10 days Mon 3/24/25 Fri 4/4/25 0%
39 Excavation & Trimming 0% 10 days Mon 3/24/25 Fri 4/4/25 0%
works
40 Preperation of Bedding 0% 10 days Mon 3/24/25 Fri 4/4/25 0%
And Testing
41 Pipe laying,Blanket 0% 10 days Tue 3/25/25 Mon 4/7/25 0%
Works And Testing
42 Valve And Hydrants 0% 3 days Thu 4/3/25 Mon 4/7/25 0%
43 Thrust blocks and 0% 3 days Thu 4/3/25 Mon 4/7/25 0%
Anchor Connection
44 Water Pressure Testing 0% 1 day Thu 6/19/25 Thu 6/19/25 0%
45 Backfilling & Compaction0% 5 days Mon 6/16/25 Fri 6/20/25 0%
46 Compaction Testing 0% 1 day Mon 6/23/25 Mon 6/23/25 0%
47 Connection On to 0% 1 day Fri 6/20/25 Fri 6/20/25 0%
Existing Water Supply
48 House Connections 0% 1 day Fri 6/20/25 Fri 6/20/25 0%
49 RHS Roadworks 0% 44 days Wed 6/4/25 Mon 8/4/25 0%
50 Cut-to-Spoil 0% 10 days Wed 6/4/25 Tue 6/17/25 0%
51 Get existing Manholes 0% 14 days Wed 6/18/25 Mon 7/7/25 0%
to Level
52 Roadbed 0% 5 days Wed 6/18/25 Tue 6/24/25 0%
53 Subbase 0% 5 days Wed 6/25/25 Tue 7/1/25 0%
54 Base 0% 5 days Thu 7/10/25 Wed 7/16/25 0%
55 Surfacing 0% 2 days Fri 7/25/25 Mon 7/28/25 0%
56 Pre-road Marking And 0% 2 days Tue 7/29/25 Wed 7/30/25 0%
Road Signange
57 Kerbing and Channeling 0% 6 days Thu 7/17/25 Thu 7/24/25 0%
58 Filling of side walks 0% 4 days Fri 7/18/25 Wed 7/23/25 0%
59 Spraying of Side walks 0% 6 days Mon 7/21/25 Mon 7/28/25 0%
60 Speedhumb 0% 4 days Tue 7/29/25 Fri 8/1/25 0%
61 Final Road Marking & 0% 3 days Wed 7/30/25 Fri 8/1/25 0%
Signange
62 Practical Handover 0% 1 day Mon 8/4/25 Mon 8/4/25 0%
Critical Task Baseline Milestone Project Summary Inactive Milestone Duration-only Start-only External Milestone
Project: Program os works- Libertina A
Date: Mon 4/7/25 Critical Split Split Baseline Split Summary Progress External Tasks Inactive Summary Manual Summary Rollup Finish-only Deadline
Critical Progress Task Progress Baseline Milestone Summary External Milestone Manual Task Manual Summary External Tasks
Page 1