Program Os Works - Libertina Amathila

The document outlines a project schedule for the upgrading of Libertina, detailing various tasks, their completion percentages, durations, and timelines from February to August 2025. Key tasks include site establishment, civil works, and water connections, with some tasks already completed while others are in progress or not started. The project is organized with milestones and critical paths to track progress effectively.

Uploaded by

Jonas Mwatange
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views1 page

Program Os Works - Libertina Amathila

The document outlines a project schedule for the upgrading of Libertina, detailing various tasks, their completion percentages, durations, and timelines from February to August 2025. Key tasks include site establishment, civil works, and water connections, with some tasks already completed while others are in progress or not started. The project is organized with milestones and critical paths to track progress effectively.

Uploaded by

Jonas Mwatange
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name % Duration Start Finish February 2025 March 2025 April 2025 May 2025 June 2025

February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025
Complete 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18
1 UPGRADING OF LIBERTINA 38% 124 days Wed 2/12/25 Mon 8/4/25 38%
AMATHILA AVENUE
2 P & G'S 100% 1 day Wed 2/12/25 Wed 2/12/25 100%
3 Project Commencement 100% 1 day Wed 2/12/25 Wed 2/12/25 100%
4 Site Establishment 95% 22 days Wed 2/12/25 Thu 3/13/25 95%
5 Establish Site 100% 21 days Thu 2/13/25 Thu 3/13/25 100%
6 Stakeholder Engagement 90% 21 days Wed 2/12/25 Wed 3/12/25 90%
7 Preparation of Traffic 100% 2 days Wed 3/12/25 Thu 3/13/25 100%
Accomodation Plan
8 Approval of Water 100% 1 day Mon 3/10/25 Mon 3/10/25 100%
Reticulation VO No.4
9 Civil Works 28% 104 days Wed 3/12/25 Mon 8/4/25 28%
10 LHS- Water Connection 77% 33 days Wed 3/12/25 Fri 4/25/25 77%
11 Installation of Slevees 35% 10 days Mon 3/31/25 Fri 4/11/25 35%
12 Procurement and 100% 14 days Wed 3/12/25 Mon 3/31/25 100%
Delivery of Water
Reticulation Material
13 Remove Existing 100% 5 days Tue 3/18/25 Mon 3/24/25 100%
Paving Works & kerbs
14 Locate of existing 100% 5 days Wed 3/19/25 Tue 3/25/25 100%
sewer and water house
connections And
Protection
15 Setting out Waterline 100% 2 days Tue 3/25/25 Wed 3/26/25 100%
16 Excavation & Trimming 95% 7 days Tue 3/25/25 Wed 4/2/25 95%
works
17 Preperation of Bedding 95% 7 days Tue 3/25/25 Wed 4/2/25 95%
And Testing
18 Pipe laying,Blanket 95% 7 days Tue 3/25/25 Wed 4/2/25 95%
Works And Testing
19 Valve And Hydrants 0% 3 days Mon 3/31/25 Wed 4/2/25 0%
20 Thrust blocks and 0% 2 days Tue 4/1/25 Wed 4/2/25 0%
Anchor Connection
21 Water Pressure Testing 0% 1 day Wed 4/16/25 Wed 4/16/25 0%
22 Backfilling & Compaction85% 5 days Thu 4/17/25 Wed 4/23/25 85%
23 Compaction Testing 0% 2 days Thu 4/24/25 Fri 4/25/25 0%
24 LHS Roadworks 0% 39 days Mon 4/14/25 Thu 6/5/25 0%
25 Cut-to-Spoil 0% 10 days Mon 4/14/25 Fri 4/25/25 0%
26 Roadbed 0% 3 days Mon 4/28/25 Wed 4/30/25 0%
27 Subbase 0% 5 days Thu 5/1/25 Wed 5/7/25 0%
28 Base 0% 5 days Fri 5/16/25 Thu 5/22/25 0%
29 Surfacing 0% 4 days Fri 5/30/25 Wed 6/4/25 0%
30 Pre-road Marking And 0% 1 day Thu 6/5/25 Thu 6/5/25 0%
Road Signange
31 Kerbing and Channeling 0% 5 days Fri 5/23/25 Thu 5/29/25 0%
32 Filling of side walks 0% 3 days Fri 5/23/25 Tue 5/27/25 0%
33 Spraying of Side walks 0% 3 days Fri 5/30/25 Tue 6/3/25 0%
34 RHS - Water Connection 24% 66 days Mon 3/24/25 Mon 6/23/25 24%
35 Installation of Slevees 0% 10 days Mon 3/31/25 Fri 4/11/25 0%
36 Remove Existing 100% 10 days Mon 3/24/25 Fri 4/4/25 100%
Paving Works & kerbs
37 Locate of existing 100% 10 days Tue 3/25/25 Mon 4/7/25 100%
sewer and water house
connections And
Protection
38 Setting out Waterline 0% 10 days Mon 3/24/25 Fri 4/4/25 0%
39 Excavation & Trimming 0% 10 days Mon 3/24/25 Fri 4/4/25 0%
works
40 Preperation of Bedding 0% 10 days Mon 3/24/25 Fri 4/4/25 0%
And Testing
41 Pipe laying,Blanket 0% 10 days Tue 3/25/25 Mon 4/7/25 0%
Works And Testing
42 Valve And Hydrants 0% 3 days Thu 4/3/25 Mon 4/7/25 0%
43 Thrust blocks and 0% 3 days Thu 4/3/25 Mon 4/7/25 0%
Anchor Connection
44 Water Pressure Testing 0% 1 day Thu 6/19/25 Thu 6/19/25 0%
45 Backfilling & Compaction0% 5 days Mon 6/16/25 Fri 6/20/25 0%
46 Compaction Testing 0% 1 day Mon 6/23/25 Mon 6/23/25 0%
47 Connection On to 0% 1 day Fri 6/20/25 Fri 6/20/25 0%
Existing Water Supply
48 House Connections 0% 1 day Fri 6/20/25 Fri 6/20/25 0%
49 RHS Roadworks 0% 44 days Wed 6/4/25 Mon 8/4/25 0%
50 Cut-to-Spoil 0% 10 days Wed 6/4/25 Tue 6/17/25 0%
51 Get existing Manholes 0% 14 days Wed 6/18/25 Mon 7/7/25 0%
to Level
52 Roadbed 0% 5 days Wed 6/18/25 Tue 6/24/25 0%
53 Subbase 0% 5 days Wed 6/25/25 Tue 7/1/25 0%
54 Base 0% 5 days Thu 7/10/25 Wed 7/16/25 0%
55 Surfacing 0% 2 days Fri 7/25/25 Mon 7/28/25 0%
56 Pre-road Marking And 0% 2 days Tue 7/29/25 Wed 7/30/25 0%
Road Signange
57 Kerbing and Channeling 0% 6 days Thu 7/17/25 Thu 7/24/25 0%
58 Filling of side walks 0% 4 days Fri 7/18/25 Wed 7/23/25 0%
59 Spraying of Side walks 0% 6 days Mon 7/21/25 Mon 7/28/25 0%
60 Speedhumb 0% 4 days Tue 7/29/25 Fri 8/1/25 0%
61 Final Road Marking & 0% 3 days Wed 7/30/25 Fri 8/1/25 0%
Signange
62 Practical Handover 0% 1 day Mon 8/4/25 Mon 8/4/25 0%

Critical Task Baseline Milestone Project Summary Inactive Milestone Duration-only Start-only External Milestone
Project: Program os works- Libertina A
Date: Mon 4/7/25 Critical Split Split Baseline Split Summary Progress External Tasks Inactive Summary Manual Summary Rollup Finish-only Deadline
Critical Progress Task Progress Baseline Milestone Summary External Milestone Manual Task Manual Summary External Tasks