G7 - Construction Reports
G7 - Construction Reports
R E P O R T S
CONTENTS
PROJECT MONITORING
PROJECT CONTROL
CRASH SCHEDULING
Project Monitoring
Project monitoring is the process of
tracking, evaluating, and controlling a
project's progress to ensure it stays on
track and meets its objectives within the
defined scope, budget, and timeline. It
involves regularly assessing various aspects
of the project, such as tasks, timelines,
budget, and quality, to identify any
deviations from the plan and take
corrective actions
Project Monitoring
hjbv
Updating using PERT / CPM
EXAMPLE:
A network for a certain project, which consists of a total of seven activities, and
the durations taken to complete each of them are shown.
Assume that monitoring is being done after 10 days and the following observations
are made on the progress of the activities:
1. A new activity with duration equal to the time interval between the start of
the programme and the date of updating is introduced.
2. Next, the activities that are completed as on the date of updating are
identified.
3. Duration of completed activities is changed to zero.
4. Next, the revised durations of ‘in progress’ activities and ‘not yet started’
activities are changed depending on any new constraint and change in the
requirement.
5. Forward pass and backward pass as explained earlier are performed, and
the duration of the project along with critical activities are identified in a
similar manner.
Example: Updating precedence network
There are a total of eight activities and the durations taken to complete each of them are
shown in the network. The type of relationship along with the leads and lags are shown on the
arrows connecting two activities. The project duration is 22 days and incidentally all activities
are critical.
Monitoring is being done at the end of 14 days and the following observations are made:
1. Activity A is complete.
2. Activity B is complete.
3. Activity C is complete.
4. Activity D will take another five days to complete.
5. Activity E is 50 per cent complete and will take another six days to complete.
6. Activity G’s duration has been revised to five days.
7. Activity H’s precedence relation has been updated to FS = 2 from activity D.
8. Activity I will start three days after activity G.
ii. Updated network at the end of 14 days from the project start
In order to calculate the estimated project duration after 14 days, the early start time of
activity A is made equal to 14, and forward pass and backward pass are carried out.
The critical path of the revised network consists of activities E-G-I. The revised
project duration is 32 days, which means that there is a delay of 10 days from the
original programme.
Project Control
Effective project control ensures
cost efficiency, timely
completion, and adherence to
quality standards. Since
deviations from plans are
common in construction
projects, continuous monitoring
is essential.
Key Steps in Project Control
Gather Facts & Data
Collect real- time project
information
2 COST CONTROL
3 QUALITY CONTROL
01 SCHEDULE/ TIME/ PROGRESS
CONTROL
Bar Chart Critical Path Network
Visual Tools
Use bar charts for cumulative
progress
May lack detailed activity- level
insights
Measuring Progress at Site
Methods of Progress Measurement
Quantities Installed
This method involves counting the number of items installed and comparing it
to the planned total, providing a straightforward measure of progress.
Percent Complete
Project personnel estimate the percentage of completion for activities,
offering a subjective but practical measure of progress.
By milestones
In this method, the percentage completion value is assigned based on pre
defined estimated work for a predefined milestone.
S-Curve
Can be used to monitor the cost of a construction
project. It depicts the progress profile of a
construction project.
S-Curve Sample
Budgeted Cost for Work Scheduled (BCWS) - the budget or plan for all work
packages planned to be completed. This curve is derived from the work breakdown
structure (WBS), the project budget and the project master schedule.
Budgeted Cost of Work Performed (BCWP) - The planned costs of the work allocated
to the completed activities are the earned value. The BCWP is calculated from the
measured work complete and the budgeted costs for that work.
Actual Cost of Work Performed (ACWP) - This is the real cost of the work charged
against the completed activities. The ACWP curve is found by actual measurement of
the work completed.
EARNED VALUE METHOD
TERMINOLOGIES
Variances - Schedule and cost variances can both be calculated in monetary terms (or
in man-hour terms) from the data needed to produce the S-curves.
Schedule variance (SV) - the difference between the earned value and
the planned budget.
Cost variance (CV) - the difference between the earned value and the
actual cost of the works.
EARNED VALUE METHOD
TERMINOLOGIES
Cost Performance Index (CPI) - indicates whether the project is spending as per the
budget.
Estimate at Completion (EAC) - used to forecast the likely course a project will take
based on the current status. Can be calculated in various ways.
EARNED VALUE METHOD
TERMINOLOGIES
FOUNDATION - 1 MONTH
FRAMING - 1 MONTH
ROOFING - 1 MONTH
ELECTRICAL & PLUMBING - 1 MONTH
INTERIOR FINISHING - 1.5 MONTHS
PAINTING & CLEANUP - 0.5 MONTH
CRASH SCHEDULING: BUILDING A HOUSE FASTER
BUT SUDDENLY, THE HOMEOWNER SAYS, "WE NEED TO MOVE IN 2MONTHS EARLIER."
A PROJECT HAS
ACTIVITIES WITH THE
FOLLOWING NORMAL
AND CRASH TIMES
AND COST.
PATH #1 PATH #2
THEREFORE PATH II IS THE CRITICAL PATH AND THE CRITICAL ACTIVITIES ARE A, C, E, G AND H. THE NON-CRITICAL ACTIVITIES
ARE B, D AND F.
Step 2: Analyze the Crash Table & Calculate Cost Slopes
Formulas:
TTHE RESULT TELLS YOU HOW MUCH EXTRA YOU’LL SPEND FOR EACH WEEK YOU REDUCE THAT ACTIVITY’S DURATION.
Step 3: Crash the critical path.
RESULT:
Crashing Plan: Reduce the duration of Activities A, C, and E by 1 week
each.
New Project Duration: 22 weeks (down from 25 weeks).
Total Additional Cost: ₱3,000 (₱1,000 per activity)
Key Takeaway: Cost vs. Time Trade-Off
Ask yourself:
Is the time saved worth the extra cost?
PROBLEM 2
B 6 D
6
START 4 A F
5 5
C 3 E
1 2 2 1
5
START 4 A F
5 5
C 3 E
PATH 1= 4 + 6 + 6 + 4 = 20 WEEKS
B 6 D PATH 2= 4 + 5 + 3 + 5 = 17 WEEKS
4
6
START 4 A F
5 5
C 3 E
ADDITIONAL SCENARIO: BUDGET CONSTRAINTS
SUPPOSE THE CLIENT HAS AN EXTRA PHP 6000 TO SPEND IN RETURN FOR A
SHORTER DURATION, HOW SHORT CAN WE DECREASE THE PROJECT DURATION?
1 2 2 1
References &
Acknowledgments
LOREM IPSUM DOLOR SIT AMET, CONSECTETUR ADIPISCING ELIT.
VESTIBULUM A ULLAMCORPER MAURIS.