Predecessor - - A B C, D C, D E F
(ii) Activity A B C D E F G H I J K
Predecessor - - - A B B C D F H, I F, G
2. Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each
activity of the project given below and determine the Critical path of the project and duration to
complete the project.
Activity 1-2 1-3 1-5 2-3 2-4 3-4 3-5 3-6 4-6 5-6
Duration 8 7 12 4 10 3 5 10 7 4
(In weeks)
3. Calculate the total float, free float and independent float for the project whose activities are given
below.
Activity 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-10 9-10
Time 4 1 1 1 6 5 4 8 1 2 5 7
Activity 1-2 1-3 1-4 2-5 2-6 3-6 4-7 5-7 6-7
Least time 3 2 6 2 5 3 3 1 2
(days)
Greatest time 15 14 30 8 17 15 27 7 8
(days)
Most likely 6 5 12 5 11 6 9 4 5
(days)
Find the optimum scheduling of the project which minimises the total cost.