Minutes of Meeting: S. NO. Job No Discussion / Decision

The meeting discussed the status of various jobs, with most jobs having 99% completion and only minor tasks pending. Specific jobs were highlighted for their remaining work, including scheduling issues and manpower requirements. Participants are asked to respond within 24 hours if there are any disagreements regarding the minutes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views2 pages

Minutes of Meeting: S. NO. Job No Discussion / Decision

The meeting discussed the status of various jobs, with most jobs having 99% completion and only minor tasks pending. Specific jobs were highlighted for their remaining work, including scheduling issues and manpower requirements. Participants are asked to respond within 24 hours if there are any disagreements regarding the minutes.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Minutes of Meeting

S.
Job no DISCUSSION / DECISION
NO.
9295 In job 9295, 99% of the work is complete; only the final 1%
1 remains, pending the completion schedule, the job is in
closure stage
9308 In job 9308 is closed, with 99% of the work completed. The
2 final 1% remains pending scheduling; therefore, the job is in
the closure stage
SONALIKA In this job, 99% of the work is completed, but the remaining
1% includes the MRS and additional ridge flashing, scheduled
3
for completion this month. Additionally, the louver issue
related to job 9277 needs to be resolved.
9277 In job 9277, 1% of the work remains for completion. The
4
team is to be deployed for MRS – rake angle
9278 In job 9278, only 1% of the work remains. Manpower has
5
been called for completion and handover
9261 In job 9261, 1% of the work is pending, including additional
6 tasks for Rashid, painting, and balance work

9359 In job 9359, only 1% of the work is pending, awaiting the


7
day-wise schedule.
9380 In job 9380, 1% of the work is pending, with the completion
8 scheduled within 10 days at a rate of 2 bays per day
.
9361 In job 9361, the final 1% of work is pending and on hold until
9
15/04/25, after which it will be handed over to the Jali
9135 In job 9135, the final work is pending due to manpower
10 requirements for account reconciliation and re-mobilization

9347 In job 9347, the final 1% of work is pending and assigned to


11 Nafiz's team

9284 In job 9284, the remaining work is pending due to balance


12
payment. (CHECK MAIL)
Page 1 of 2
Minutes of Meeting
S.
Job no DISCUSSION / DECISION
NO.
9288 In job 9288, the remaining 1% of work is pending due to
13 team mobilization.

9282 In job 9282, the remaining 1% of work is pending due to


14 louver dispatch.

9241 In job 9241, only 1% of the work is pending, which requires a


15 site visit.

16
ITD In ITD, both the material dispatch and site visit are still
pending for completion
9324 In job 9324, the final phase of additional work remains
17
pending and is yet to be completed

rticipants are requested to revert within 24 hours in case of any disagreement or discrepancy
in the above MOM. In case no such communication is received, it would be deemed that the all
the points are accepted by the participants concerned.