Minutes of Meeting: S. NO. Job No Discussion / Decision
Minutes of Meeting: S. NO. Job No Discussion / Decision
S.
Job no DISCUSSION / DECISION
NO.
9295 In job 9295, 99% of the work is complete; only the final 1%
1 remains, pending the completion schedule, the job is in
closure stage
9308 In job 9308 is closed, with 99% of the work completed. The
2 final 1% remains pending scheduling; therefore, the job is in
the closure stage
SONALIKA In this job, 99% of the work is completed, but the remaining
1% includes the MRS and additional ridge flashing, scheduled
3
for completion this month. Additionally, the louver issue
related to job 9277 needs to be resolved.
9277 In job 9277, 1% of the work remains for completion. The
4
team is to be deployed for MRS – rake angle
9278 In job 9278, only 1% of the work remains. Manpower has
5
been called for completion and handover
9261 In job 9261, 1% of the work is pending, including additional
6 tasks for Rashid, painting, and balance work
16
ITD In ITD, both the material dispatch and site visit are still
pending for completion
9324 In job 9324, the final phase of additional work remains
17
pending and is yet to be completed
rticipants are requested to revert within 24 hours in case of any disagreement or discrepancy
in the above MOM. In case no such communication is received, it would be deemed that the all
the points are accepted by the participants concerned.
Page 2 of 2