Problem 1 - 2024
Problem 1 - 2024
Course Outcome:
● Preparation of bill of quantities
● Analysis of rate and preparation of cost estimate
● Estimation of item of works of roadway
● Computation of volume of earthwork
● Software application in estimation
Syllabus: Preparation of bill of quantities of a simple residential building including sanitary works; Analysis of rate;
Preparation of cost estimate of a simple residential building; Computation of volume of earthwork, Preparation of mass
haul diagram; Estimation of roadway; Software application in estimation
4 Estimation of roadway 6
6 Assessment 3
Total = 39
1
Problem 1:
Estimate the quantities of all major items of work of a one storied residential building with a boundary wall
as per the following details:
• The typical floor plan of the building is given in Figure 1.1.
• A sectional elevation cut through A-A′ is shown in Figure 1.2
• Assume a boundary wall with iron gate along the perimeter of the property, with a clear space of
approx. 3 m on all four sides. The plan and cross-section of the boundary wall is provided in Figure 1.3
• The structural components of the building can be designed or assumed reasonably. Typical c/s view of
foundation and superstructure are provided in Figure 1.4 and Figure 1.5 respectively.
• Items of work may include but not limited to the following:
• Earthwork in excavation of foundation trenches (Unit - m3)
• Earthwork in filling in foundation trenches and plinth with good earth (Unit - m3)
• Single brick soling (unit - m2)
• Cement concrete for foundation, tie beam, slabs, beams, columns, lintels etc, excluding shuttering and
reinforcement (unit – m3)
• Brickwork in cement sand mortar in plinth and super structure (unit– m3)
• Shuttering with centering and staging (unit – m2)
• Reinforcement for RCC work in slabs beams columns lintels etc. including distribution bars stirrups
binders etc. (unit – Quintal/kg/tonne)
• Plaster to wall and ceiling with sand and cement mortar. (Unit – m2)
• Flooring (unit- m2)
• Tiles (Unit – m2)
• Woodwork in door and window frame, (Unit – m3)
• Panel shutters of doors and window (Unit – m2)
• MS ornamental grill with welding in window railing etc. (Unit – m2)
• Colour washing with ordinary pigment or with decorative cement base paint. (Unit - m2)
• Painting to wood and steel surfaces. (Unit - m2)
• A sample measurement form is given in Table 1. All other items, if not available, can be reasonably
assumed and categorically mentioned in the remark’s column.
• Doors – D = 1200 X 2100; D1 = 1000 X 2100; D2 = 800 X 2100
• Windows – W1 = 1200 X 1200; W2 = 700 X 1200; W3 = 500 X 500
• Exterior wall: 250 mm; Interior wall: 125 mm. The foundation of the building can be assumed to
consisting of isolating RCC footing. There may be tie beams at the foundation level as well as at the ground
level.
• Assume position of beams (including lintel beam of 150 mm) and columns appropriately. All
dimensions in mm, unless specified otherwise.
2
BED ROOM
5250 x 4500
3
4500
75
150
400
A DRG/DIN
3000 x 2000
Pillar
0.2 m
0.1 m Pillar
GL
0.5 m
5
GL
[2.1+0.01*A] m Column
0.8 m
0.40 m
0.25 m RCC (1:2:4)
0.15 m PCC (1:3:6)
0.10 m BFS
[1.7+0.01*B] m
6
Table 1 Sample measurement form
Item Description of item Unit No. Length Breadth Height Quantity Total Explanation
No. (m) (m) (m)
1. Earthwork in excavation in foundation
2. Earthwork in filling All
calculations
3. 2nd class brick flat soling and small
4. Cement concrete (1:4:8) in foundation diagrams
needed for
1st class brickwork in cement mortar(1:6) in calculations
5.
foundation and plinth should be
1st class brickwork (1:6) in superstructure shown here.
6. This column
pillars
should be
7. 10 cm thick 1st class brickwork for panels widest.
8. Cement pointing (1:4)
9. Painting
These descriptions you will get in "General These columns will only have values
items of work and their unit of and no calculations. All calculations
measurement" in explanation column only.
7
(ii) Woodwork to nearest 0.002m;
(iii) Steelwork to nearest 0.001m; reinforcement to nearest 0.005 m;
(iv) thickness of roadwork where the thickness is less than 20cm: the thickness shall be measured to nearest 0.005 m.
(b) Areas shall be worked out to the nearest 0.01 m2. For steelwork areas excluding cross sectional measurements shall be worked out to nearest 0.001 m2.
(c) Cubic contents shall be worked out to nearest 0.01 cu m except for woodwork shall be worked out to nearest 0.001 cu m.
(d) Weights shall be worked out to nearest 1 kg.
(2) Rates: The degree of accuracy in calculations depends upon the rate of the item of work. Thus, where the rates are per hundred (per %) or per thousand (per
%) units, greater accuracy is not required. But where the rates are per metre (per m) or per running metre (per rm), per square metre (per sq m), per cubic metre
(per cu m) calculations should be carried out up to two places of decimal for greater accuracy at higher rate. The limits of measurement as stated above in (1)
shall be followed. Any work done by the Contractor extra over the specified dimensions shall be ignored.
8
0.4 m
0.1 m PCC