The document is a Bill of Quantities (BOQ) for the construction of a rear side boundary wall, detailing various construction activities including earthwork, concrete work, brickwork, finishing, and miscellaneous tasks. It specifies the quantities and types of materials required for each item, along with their respective descriptions. The document serves as a comprehensive guide for estimating costs and managing the construction project.

Uploaded by

Ashok Dhamu
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Boq

The document is a Bill of Quantities (BOQ) for the construction of a rear side boundary wall, detailing various construction activities including earthwork, concrete work, brickwork, finishing, and miscellaneous tasks. It specifies the quantities and types of materials required for each item, along with their respective descriptions. The document serves as a comprehensive guide for estimating costs and managing the construction project.

Uploaded by

Ashok Dhamu
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

BILLS OF QUANTITIES (BOQ)

CONSTRUCTION OF REAR SIDE BOUNDARY WALL AT

DSR NO. DESCRIPTION OF ITEM/DSR SUB. NO. QTY.

EARTH WORK :
2.6 Earth work in excavation by mechanical means
(Hydraulic excavator) / manual means over areas
(exceeding 30cm in depth. 1.5m in width as well
as 10 sqm on plan) including disposal of
excavated earth, lead upto 50m and lift upto 1.5m,
disposed earth to be levelled and neatly dressed.

2.6.1 All kinds of soil 100


2.25 Filling available excavated earth (excluding rock) in
trenches, plinth, sides of foundations etc. in
layers not exceeding 20cm in depth, consolidating
each deposited layer by ramming and 80
watering, lead up to 50 m and lift upto 1.5 m.

PLAIN CEMENT CONCRETE WORK :

4.1 Providing and laying in position cement concrete of


specified grade excluding the cost of centring &
shuttering all work upto plinth lvl.
4.1.8 1:4:8 (1 cement: 4 coarse sand: 8 graded stone 17.25
aggregate 40mm nominal size).

REINFORCED CEMENT CONCRETE


WORK :
5.2 Reinforced cement concrete work in wall (any
thickness) including attached pilasters,buttresses,
plinth and string courses, fillets, columns, pillars,
piers, abutments, posts and struts etc. up to floor
fivelevel excluding cost of centering, shuttering,
finishing and reinforcement:

5.2.2 1:1.5:3 (1 cement :1.5 coarse sand : 3 graded 85


stone aggregate 20 mm. nominal size).
5.9 Centring and shuttering including strutting ,
propping etc. and removal of form work for :
5.9.1 Foundations, footings, bases of columns, etc. for 115
mass concrete
5.9.5 Lintels, beams, plinth beams, girders, bressumers 425
and cantilevers
5.9.6 Columns, Pillars, Piers, Abutments, Posts and 120
Struts
5.22 Reinforcement for R.C.C. work including
straightening, cutting, bending, placing in position
and binding all complete.
5.22.6 Thermo-Mechanically Treated bars. 9350

BRICK WORK

6.4 Brick work with common burnt clay F.P.S. (non


modular) bricks of class designation 7.5 in
superstructure above plinth level up to floor V
level in all shapes and sizes in :
6.4.1 Cement mortar 1:4 (1 cement : 4 coarse sand) 12

6.13 Half brick masonry with common burnt clay F.P.S.


(non modular) bricks of class designation 7.5
in superstructure above plinth level up to floor
V
6.13.1 level.
Cement mortar 1:3 (1 cement :3 coarse sand) 350

6.15 Extra for providing and placing in position 2 Nos.


6mm dia. M.S. bars at every third course of half 350
brick masonry.

FINISHING & CLADDING WORK :

13.1 12 mm cement plaster of mix :


13.1.2 1:6 (1 cement: 6 fine sand) 600
13.2 15 mm cement plaster on the rough side of single
or half brick wall of mix :
13.2.2 1:6 (1 cement: 6 fine sand) 600
13.44 Finishing walls with water proofing cement
paint
of required shade :
13.44.1 New work (Two or more coats applied @ 3.84 1200
kg/10 sqm).
13.65 Painting with black anti-corrosive bitumastic paint
of approved brand and manufacture to give an
even shade:
13.65.1 Two or more coats on new work. 55
ES (BOQ)
NDARY WALL AT SRCC

RATE PER AMOUNT

Cum.

Cum.

Cum.

Cum.
Sqm.

Sqm.

Sqm.

Kg.

Cum.

Sqm.

Sqm.

Sqm.

Sqm.

Cum.
Sqm.
DSR NO. DESCRIPTION OF ITEM/DSR SUB. NO. QTY.

MISCELLANEOUS WORK :
16.11 Dry stone pitching 22.5 cm thick including supply
of stones and preparing surface complete. 400

16.18 Fencing with angle iron post placed at required


distance embedded in cement concrete blocks,
every 15th post, last but one end post and corner
post shall be strutted on both sides and end post
on one side only and provided with horizontal
lines and two diagonals interwoven with horizontal
wires, of barbed wire weighing 9.38 kg per 100 m
(minimum), between the two posts fitted and fixed
with G.I. staples, turn buckles etc. complete. (Cost
of posts, struts, earth work and concrete work to
be paid for separately) :- Payment to be made per
metre cost of total length of barbed wire used.

16.18.1 With G.I. barbed wire 1020


16.19 Supplying at site Angle iron post & strut
of required size including bottom to be split and
bent at right angle in opposite direction for 10 650
cm length and drilling holes upto 10 mm dia.
etc.
complete.
TOTAL