Unit 4-3
Unit 4-3
Q1) Estimate the main material requirement for a 600m, 415/240V, 3 phase line with 4
wires in vertical configuration. The line emanate from substation to feed a load of
30kW. Consider span between two poles as 60 meter.( S-22, 6M)
Ans:Data Given:
Total length of line = 600 m
Length of span between two poles = 60 m
600
No. of poles required = 60 + 1=11
Q11) State the different methods of cable termination for HT/ LT (11KV/ 415V) line.
Explain any one method in details.(W-22,S-24 4M, 6M)
OR
Explain with suitable example selection procedure of power cables in HT -distribution
including their termination of cables underground cabling.( S-23, 4M)
Factors determining selection of HT power cables
1. Current carrying capacity
2. Voltage regulation
3. Short circuit rating
4. Cable construction
5. Cable shield requiremenT
Methods of Cable Termination For HT (11KV) Line:
1. Heat Shrink
2. Lug Termination
3. Claw type termination
4. Spade termination
5. Crimping
1) Heat shrink:
Heat shrink cable terminations can be used for LV-MV-HV power cables present indoors
and outdoors. Indoors, these cable terminations connect to substation switchgear,
transformers and insulated cable boxes. Outdoors, they are used in overhead and
underground distribution lines.
Q14) State the classification of cable on voltage levels( W-23, S-24 2M)
Low tension (L.T.) Cable 0 – 1 kV
High tension (H.T.) Cable 1 – 11 kV
Super tension (S.T.) Cable 11 – 33 kV
Extra high-tension (E.H.T.) Cable 33 – 66KV
E.S.V (extra super voltage) above 132KV
Q15) How insulation resistance is tested between Conductors?( W-23, 4M)
Ans. Testing of Insulation Resistance Between Conductors.
The object of this test is to ensure that the insulation is sound between the conductors so
that there may not be an appreciable leakage between them. In this case the circuit diagram
remains the same, as shown in below Fig.3.b, except that the loop at the main switch is
removed and all the lamps and all metallic connections between the two wires of the
installation are removed from the lamp holders. Rest of all the things remaining the same
i.e, the main switch off, main fuse withdrawn, all other fuses in their positions and all
single pole switches in 'on' position, the terminals of the megger are connected to the two
poles or lines of the installation and insulation resistance is measured between two
conductors (line and neutral conductors). The insulation resistance so measured should not
50 𝑀Ω
be less than𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑢𝑡𝑙𝑒𝑡𝑠
any case the value should not be less than 0.5 M and need not ohm Number of outlets but
in to be more than one Mega ohm.
In case of PVC wires, insulation resistance must be Number of outlets
12.5 𝑀Ω
𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑜𝑢𝑡𝑙𝑒𝑡𝑠
Q16) List out the material use for H.T. 11 KV & L.T. 415 V Overhead Line( W-23, 4M
S-24,4M))
Following are the material use for H.T. 11 KV & L.T. 415 V Overhead Line
Conductors - Solid/ Stranded/Hollow/Bundled.
Material of conductor- Copper, Aluminum, all aluminum or ACSR.
Poles-Tubular steel pole, angle pole, R.C.C. poles
Insulators
Bird guards
Earth wire
Stay assembly
G.I. Clamps
Ant climbing Arrangement
Earthing set
Lightening arrestor
Cross arms
Q17) Draw the single line diagram of L.T. substation (415 V)( W-23, 4M, S-24 4M)
Q18) Explain earthing provision using suitable sketch for HT/LT distribution lines
installation. (S-23, 4M)
For distribution lines such as HT line and LT line, wire earthing is used by low
resistance wire known as the earth wire. This earth wire is connected to Earth
Electrodes, buried in the ground. For this, horizontal trenches are dug, and strip
electrodes get buried inside these trenches. The electrodes are of copper, galvanized iron or
steel.
Q19) Estimate the material required for 2 km, 11 KV overhead line to extend from
existing
line. Assume a span of 50 m.(W-24, 4M)
Considering following factors,
a) Size of Conductor: ACSR 6/1 x 2.59 mm
(b) Tabular pole or supports of 11m. Length
(c) Size of earth wire-Galvanized steel 8 SWG
(d) No. of earthing sets to be installed-3 nos.
Estimated Materials are as follows.
A) Material required for connect 2km overhead line with existing 11 KV line.
MS channel for cross arm 10 cm x 5 cm x 15 mts.- 1 No.
H.T. 11kV disc insulator with complete fitting
H.T. 11kV pin type insulator with pins and nuts to support jumper wires. -3 No.
Stay set with clamp, stay wire, rod bow, nuts, stay plate -2 set
Concreting for stay rod- 2bags
Concreting for existing pole -2bags
Earth wire damp of mild steel- 1No.
Aluminum binding wire for jumpers 1kg.
B) Fittings for H.T. straight line support
Tubular line support pole 11m long- 40 No.s
Foundation with cement concentrating for poles-40 No.
Cross arms for support to main cross arms- 80 No.s
11 kV pin insulator with pin and nuts-120 No.s
Danger board -40 No.s
Earthing wire clamps - 40 No.s
Barbed wire for anti climbing -40kg
Aluminum binding wire- 18 kg.
C) ACSR conductor 6/1 x 2.59 mm length-780 kg.
2000×3=6000 mts.
Sag 1%60 mts.
Total length = 6060 mts.
D) 8 SWG GI earth wire- 60kg.
Length 2000 m.
Sag 2% = 40 m
Total length = 2040 m
E) Material for 3 nos, earthing sets.
Earth plate Gl of 60 cm x 60 cm x 3.8 m thick -3 No.s
Gl earth wire 8 SWG, 10 mts for each set wt. 1 kg each -3 kg.
Gl pipe for earth wire 15 mm diameter (for 3 set)-30m
20 mm Gl pipe-30m
MS nut bolts, salt, charcoal, thimbles, wire mesh, funnel etc. as per earthing estimates.- as
per required
F) Painting for Poles-20 ltr.
G) Transportation charges, loading and unloading the material etc.
H) Labor Charges
11% overhead and supervision charges.