CFSE - Helpful Information1
CFSE - Helpful Information1
Certified Functional
Safety Expert
Examination Preparation
Useful Information
Section 1: Acronyms
Section 2: Glossary
Section 3: Equations
Section 4: Figures
CFSE Prep Course Useful Information
Emerson Process Management
Acronyms
Absorbing State In Markov modeling, a state (represented by a circle) that can only
be entered (arc toward).
As Low as Reasonably Also called Tolerable Region. That region of risk between
Practicable Intolerable and Broadly Acceptable. Established in the UK as that
level of risk between less than 10-3 fatalities per man-year worked
(or less than 10-4 fatalities per year for the public), de manifestus,
and greater than 10-5 fatalities per man-year worked (or greater
than 10-6 fatalities per year for the public), de minimus. The de
minimus level is the background level that occurs generally in all
work places, regardless of the risks of the work place.
Attenuation Diluting or otherwise reducing concentrations, or separating the
total quantity so that the maximum event will be smaller
Availability The probability at a specific moment in time that a repairable
system will be able to operate successfully when required to, that it
is not failed or being repaired..
Complementary Events When one outcome does not occur, the other will always occur,
e.g. heads and tails in a coin toss.
P(A) = 1 – P(B), [ P(heads) = 1 – P(Tails) ]
Consequence The measure of impact in terms of expected fatalities, injuries,
environmental damage, and/or property damage; determined by
estimating the number of receptors in the effected area
“A measure of the expected effects of an outcome case (e.g., an
ammonia cloud from a 10 lb/s leak under Stability Class D weather
conditions and a 1.4-mph wind traveling in a northerly direction
will cause 50 injuries).”
–CCPS, Guidelines for CPQRA
Containment Using equipment designed or built to higher codes or standards, or
secondary containment systems capable of capturing and
managing releases.
Control Using engineered solutions, procedures, training, and management
systems to reduce or limit the demands on the process
Dangerous Failure See “Failure, dangerous”
De Manifestus The high risk bound of the ALARP region. 10-3 fatalities per man-
year worked or 10-4 fatalities per year for the public.
De Minimus The low risk bound of the ALARP region. 10-5 fatalities per man-
year worked or 10-6 fatalities per year for the public. This is the
background level that occurs generally in all work places,
regardless of the risks of the work place.
Effect Zone For an incident that produces an incident outcome of toxic release,
the area over which the airborne concentration equals or exceeds
some level of concern.
For a flammable vapor release, the area over which a particular
incident outcome case produces an effect based on a specified
overpressure criterion.
For thermal radiation effects, the area over which a particular
incident outcome case produces an effect based on thermal damage
criteria.
–CCPS, Guidelines for CPQRA
Emergency Exposure Developed by the US National Research Council and based on
Guidance Level exposure of Health Military Personnel, exposure to concentrations
at the EEGL may produce transient irritation or central nervous
system effects but should not produce effects that are lasting or
would impair performance of a task for exposures in the range of 1
to 24 hours.
Equipment Under Control The equipment, machinery, apparatus, or plant used for
manufacturing, process, transport, medical, or other activities. The
EUC control system is separate and distinct from the EUC.
ERPG-1 Exposure concentration below which, based on one hour exposure
time, there are no significant health effects. Becoming an
Industry/Government Norm.
ERPG-2 Exposure concentration below which, based on one hour exposure
time, there are no irreversible health effects. Becoming an
Industry/Government Norm.
ERPG-3 Exposure concentration below which, based on one hour exposure
time, injury results, but no life-threatening effects. More
represents potential for fatalities. Becoming an
Industry/Government Norm.
Fail-safe State In FMEA, this is the state the component goes to when the outputs
are de-energized.
Failure, dangerous A failure that does not respond to demand from the process, i.e.
being unable to go to the defined fail-safe state.
Failure, “don’t care” A component failure that is part of the safety function, but has no
effect of the safety function of the module, sub-system, or system.
Failure, not considered A component failure that is not considered in FMEDA. When
calculating the SFF, the failure rate of this failure mode is usually
divided into 50% safe failures and 50% dangerous, undetected
failures.
Failure, safe A component failure that causes the module, sub-system, or
system to go to the defined fail-safe state without a demand from
the process.
Fault Tolerance The ability of a functional unit to continue to perform a required
reducing risk.
Safety Instrumented A combination of sensors, logic solver, and final elements with a
Function specified safety integrity level that detects an out-of-limit
(abnormal) condition and brings the process to a functionally safe
state. “Interlock” is an older, imprecise term for SIF.
Safety Instrumented A system of Safety Instrumented Functions composed of sensors,
System logic solvers, and final elements for the purpose of taking the
process to a safe state when predetermined conditions are violated.
Safety Integrity Level One of three (or four) discrete integrity levels (SIL 1, SIL 2, SIL 3,
and with IEC 61508, SIL 4) that correspond to orders of
magnitude reductions of risk. SIL 4 has the highest safety
integrity; SIL 1 has the lowest safety integrity.
Safety Requirements Contains
Specification 1. The Safety Functions that have to be carried out by the
safety related systems, and
2. The Safety Integrity Levels for the various Safety
functions.
Short-term Public Exposure Developed by the US National Research Council and, in general,
Guidance Level 10-50% of EEGL (for sensitive populations), exposure to
concentrations at the SPEGL are acceptable concentrations for
exposures of members of the general public for exposures in the
range of 1 to 24 hours.
Simplification Removing or minimizing opportunities for error or failure.
Standards Consensus of an industry group on lowest level of engineering
acceptable.
Substitution Using different chemicals, equipment, or technology.
Survival Providing capabilities to mitigate a release, or effective emergency
response plans which provide adequate notification and include
sheltering-in-place or evacuation.
Systematic Failures A failure related in a deterministic way to a certain cause, which
can only be eliminated by a modification of the design or of the
manufacturing process, operational procedures, documentation, or
other relevant factors.
Threshold Limit Value – Developed by ACGIH, it is the maximum concentration to which
Ceiling workers should be exposed for any period of time.
Threshold Limit Value – Developed by ACGIH, it is the maximum concentration to which
Short Term Exposure workers can be exposed for a period of up to 15 minutes without
suffering
(1) intolerable irritation,
(2) chronic or irreversible tissue change, or
(3) narcosis sufficient to increase accident prone-ness, impair
self rescue.
Threshold Limit Value – Developed by ACGIH, it is the maximum average concentration to
Time Weighted Average which workers can be exposed over a period of 8 hours.
Toxicity The ability of a substance to produce an unwanted effect when the
chemical has reached a sufficient concentration at a certain site in
the body”
-NSC 1971, Fundamentals of Industrial Hygiene
Transient State In Markov modeling, a state (represented by a circle) that can be
entered (arc toward) and exited (arc away).
Trip Conditions and action taken to move the furnace to a safe state
when a hazardous condition is detected, e.g. Master Fuel Trip
Unreliability The probability that system will fail within a specified period of
time.
Validation Activity of demonstrating, by tests, that the Safety-Related
System, before or after installation, meets the Safety Requirements
Specification.
Verification Activity of demonstrating for each phase of the Safety Lifecycle,
by analysis, tests, or both, that, for the specific inputs, the
deliverables meet the objectives and requirements set for the
specific phase.
Equations
Laws > Regulations > Standards > Recommended Practice
Financial Equations
Single amounts
FV = PV x (1 + R)N
PV = FV / (1 + R)N
Where FV is the future value of a single amount
PV is the present value of a single amount
R is the interest or discount rate
N is the number of years
Annuities
FV = M x ((1 + R)N – 1) / R
PV = M x (1 - (1 + R)-N) / R
Where FV is the future value of an annuity
PV is the present value of an annuity
M is the annual amount, applied at the end of the year
R is the interest or discount rate
N is the number of years
Benefit Cost Ratio
B-Cratio=(Fnosis x EVnosis – Fsis x EVsis) / (Cost sis + Cost nt)
Where B-C Ratio is the ratio of benefits to costs.
Fnosis is the frequency of the unwanted event without a SIS.
Fsis is the frequency of the unwanted event with a SIS
EVnosis is the total expected value of loss of the event without an
SIS.
EVsis is the total expected value of loss of the event with an SIS.
Cost sis is the total lifecycle cost of the SIS (annualized).
Cost nt is the cost incurred due to nuisance trips (annualized).
Probability
For independent events
P(A and B) = P(A)*P(B)
For mutually exclusive events
P(A or B) = P(A) + P(B)
For non-mutually exclusive events
P(a OR b OR … OR n) = 1 – (1-Pa)* (1-Pb)*…*(1-Pn)
Reliability Analysis
Reliability and Unreliability
Rt = P(T > t)
Where Rt is reliability for unrepairable systems for a given period of time,
Probit Analysis
Y = k1 + k2 lnV
Where V is the dose, expressed in a number of ways
k1 is a constant specific to the consequence
k2 is a second constant specific
Convert Probit, Y, to percentage by table.
SIL Assignment
Frequency Based Targets
PFDSIF = Ftarget / Funmitigated event
Where PFDSIF is used to assign the SIL, per the table from IEC61511
Ftarget is target frequency of an incident outcome, from table
Funmitigated event is the frequency without an SIS being installed
Individual Risk Targets
Ftarget (tolerable) = Findiviual risk / PLL
Where Ftarget (tolerable) is the tolerable frequency.
Findiviual risk is a function of the tolerable individual risk
PLL is the Probable Loss of Life
Risk
R = CF
Where R is risk
Ci is the consequence
Fi is the likelihood, expressed as a frequency
Risk Integral
IR = CiFi
Where IR is the Risk Integral, a one dimensional indication of risk
Ci is the consequence of the individual event (in terms of fatalities
for loss of life calculations)
Fi is the frequency of the individual event
Risk Reduction Factor
RRFSIF = 1 / PdFavg
RRFSIF = Runmitigated event / Rtolerable
Where RRFSIF is used to assign the SIL, per the table from IEC61511
Runmitigated event is the risk without an SIS being installed
Rtolerable is the tolerable risk
SIL Verification
Based on Calculated Probability of Failure on Demand
SIL = -log10 (PdFavg)
Where calculated value is truncated to integer value
PFD ~ 1 – e- t D
Where D is dangerous failure rate and S is safe failure rate.
Safe Failure Fraction (SFF)
SFF = (SD + SU + DD) / Total
SFF = 1 - (DU / Total)
Where XD is a detected failure rate and XU is an undetected failure rate.
Approximation Formulas
PFD ~ Dt only if PFD < 0.1
PFS ~ St
PFDavg ~ Dt/2
PFSavg ~ St/2
Probability Failure on Demand (max)
PFDmax = 1 - et
A UK study by the Health and Safety Executive (HSE) showed the following breakdown of
accident causes involving control systems:
Specification - 44%
Design and
Changes after implementation – 15%
commissioning - 21% Installation and
Operation and commissioning – 6%
maintenance - 15%
Scope definition
Hazard/risk analysis
Safety requirements
c
Fr
nf
ui
ci
M
m
D
S
F
e
n
n
a
o
c
y
t
ut
ct
nf
t
i
Operation,
Modification
maintenance, repair
and retrofit
Decommissioning
High Risk
Intolerable Region
ALARP or Tolerable
Region
10-6 / man-year
Broadly Tolerable Region
Negligible Risk
PFS
Reliability (Nuisance Trip) Reliability PFS
or SIS or (Nuisance Trip)
Availability Availability
PFD
PFD
Hazard Matrix
High
2 3 3
Likelihood
Moderate
1 2 3
Likelihood
Low
Not Rated 1 3
Likelihood
Minor Serious Extensive
Hazardous Event Severity Rating
Extensive (E) One that is five or more times worse than a SERIOUS 1.0 x 10-6
accident
Risk Graph Procedure
1. Catagorize Consequence, C, Occupancy, F, Probability of avoiding the Hazard, P, and
Demand Rate, W
2. Follow C, F, and P on Risk Graph to final level XN and find SIL under appropriate
Demand Rate column
Parameter Description
Consequence C Average number of fatalities likely to result
from the hazard. Determined by calculating
the average numbers in the exposed area when
the area is occupied, taking into account the
vulnerability to the hazardous event.
Occupancy F Probability that the exposed area is occupied.
Determined by calculating the fraction of time
the area is occupied.
Probability of avoiding the hazard P The probability that exposed persons are able
to avoid the hazard if the protection system
fails on demand. This depends on there being
independent methods of alerting the exposed
persons to the hazard and manual methods of
preventing the hazard or methods of escape.
Demand Rate W The number of times per year that the
hazardous event would occur if no SIS was
fitted. This can be determined by considering
all the failures which can lead to one hazard
and estimating the overall rate of occurrence.
Parameter—Consequence Classification Comments
Average number of fatalities. CA Minor Injury 1. The classification
CB Range 0.01 to 0.1 system has been
This can be calculated by determining the average
developed to deal
number of people present when the area exposed to the CC Range > 0.1 to 1
with injury and death
hazard is occupied and multiplying by the vulnerability to CD Range > 1 to people.
the identified hazard. The vulnerability is determined by
the nature of the hazard being protected against. The 2. For the interpretation
following factors can be used. of CA, CB, CC, and
CD, the consequences
V=0.01 Small release of flammable or toxic
of the accident and
V = 0.1 Large release of flammable or toxic
normal healing shall
V = 0.5 As above but highly toxic or flammable
be taken into account.
V=1 Rupture or explosion
Parameter—Occupancy Classification Comments
This is calculated by determining the length of time the FA Rare to more often 3. The classification
area exposed to the hazard is occupied during a normal exposure in the system has been
working period. hazardous zone. developed to deal
Occupancy less
NOTE – If the time in the hazardous area is different
than 0.1.
depending on the shift being operated then the maximum FB Frequency to with injury and death
should be selected. permanent to people.
exposure in the
NOTE – It is only appropriate to use FA where it can be
hazardous zone.
shown that the demand rate is random and not related to
when occupancy could be higher than normal. The latter
is usually the case with demands that occur at equipment
start-up.
Parameter—Probability of avoiding the hazard Classification Comments
If the protection system fails to operate. PA Adopted if all 4. PA should only be
conditions in selected if all the
Comment 4 are following are TRUE:
satisfied.
Facilities are provided
PB Adopted if all the to alert the operator
conditions are not that the SIS has failed
satisfied. Independent facilities
are provided to shut
down such that the
hazard can be avoided
or which enable all
persons to escape to a
safe area.
The time between the
operator being alerted
and a hazardous event
occurring exceeds one
hour.
Parameter—Demand Rate Classification Comments
Without protection system. WA Demand rate less 5. The purpose of the W
than 0.03 per year. factor is to estimate
To determine the demand rate it is necessary to consider
WB Demand rate the frequency of the
all sources of failure that can lead to one hazardous event.
between 0.3 and hazard taking place
In determining thee demand rate, limited credit can be
0.03 per year. without the addition
allowed for control system performance and intervention.
WC Demand rate of the SIS.
The performance that can be claimed if the control system
between 3 and 0.3
is not designed and maintained according to IEC61511 is 6. If the demand rate is
per year.
limited to below the performance ranges associated with very high (e.g., 10 per
SIL 1. For demand rates year) the SIL has to
higher than 3 per be determined by
year higher another method or the
integrity shall be risk graph must be
needed. recalibrated. Then
the operation mode is
high demand or
continuous (IEC,
61511-1, Clause
3.1.48.2).
W3 W2 W1
CA X1
a --- ---
PA X2
CB
FA 1 a ---
PB X3
CC
FB
PA
2 1 a
PB X4
FA
FB PA P
3 2 1
B X5
FA
CD PA
4 3 2
X6
FB
PB b 4 3
De Morgan’s Theorem:
These Two Partial Logic Diagrams are Equivalent.
Energized = 1 Energized = 0
Logic Solver Logic Solver
1= Energized
AND OR
Energized = 1 Energized = 0
No Event
Frequency Prob(= 1) Prob(= 1) Prob(= 1) Frequency
Markov Models
OK FAIL OK FAIL
Unrepairable System
(This is an example of an absorbing model,
because there are one or more absorbing states.)
Repairable System
(This is an example of a regular model,
because there are no absorbing states.)
2
2 OK 1 OK FAIL
to State 0 to State 1
1– from State 0
P=
1– from State 1
Product User
Product
Maintenance
Field Monitoring
Maintenance D
Field Monitoring
Change Management
Requirements Change Management V&V
Requirements
User Requirement Specification Use and Mis-Use Scenarios Validation
D Requirement Specification
V&V Plan and Procedures
Validation User
V&V V&V Plan and Procedures Validation tests os) Automated Regression Tests
Functi enari Automated Regression TestsV&V
ons an re sc
d limitati
ons (Failu
Iteration a tion te
sts .
Documentation
Valid Documentation
ional
Addit
Guidelines for installation,
Architecture Additional functions and limitations Guidelinesmaintenance
for installation,
Architecture operation,
operation, maintenance
and error handling
D
instruc tions Doc
Graphical Design Spec. Operation and exception handling and error handling
Graphical
(RT-SA,Design
UML) Spec. Posit
D ive-
(RT-SA,Spec.
Interface UML) / Ne
gativ
V&V Interface Spec. e-Te
Stati sts -
c+D Erro
ynam r han
ic An dling Integration Test
alysis Integration Test
Int User
er Tests to show the correct
fac Tests to show the correct D
eS interaction of functions
pe interaction of functions V&V
c.
Safety
Requirements
Specification
Select
Technology
Select
Architecture
SIS
Conceptual Safety
Design Determine Test System
Philosophy Design
Reliability
Evaluation
Performance
Target Met?
Yes? Go on to installation.
1/PFD(t)
SIL 4
SIL 3
1/PFDAVG
SIL 2
1/PFD(t)
SIL 4
SIL 3 1/PFDAVG
SIL 2
test interval
SIL 1 period
time
Redundant Architectures
Comparitive Performance
PFDAVG low
O 1oo2 O 1oo2D
O 2oo3D
Best Performance
O 1oo1D
O 1oo1
high
O 2oo2D
O 2oo2
high Spurious Trip Rate low
MooND Architecture.
The “D” nomenclature refers to architectures that use automatic diagnostics, made effective via
microprocessor power starting in the late 1980’s, to reconfigure the system after a diagnostic has
detected a failure. Diagnostics without reconfiguration do not warrant the “D” nomenclature.
Injuries
73 - 6% Deaths
12 -1%
Accidents
1058 - 93%
Smoke Detectors
o Ionization
o Photoelectric
Heat Detectors
o Fixed Temperature
Fusible Element
Bimetallic
o Rate of Rise
o Line
Non-Integrating
Integrating
Manual Call Points
Carbon Monoxide Detectors
Flame Detectors
o Ultraviolet detectors
o Infrared detectors
o UV/IR detectors
o Dual spectrum IR detectors
o Triple spectrum IR detectors
Follow IEC Follow IEC Follow IEC Follow IEC Follow IEC Follow IEC
61508 61511 61511 61508 61508 61511