Lect. 6 Planning and Scheduling Techniques
Lect. 6 Planning and Scheduling Techniques
Chapter 3
Lecture 6
In this part
• What is planning?
• Importance of planning
• Process of planning
• Methods of Planning
Terminology
• Milestone
• Deliverables
• Activities
• Scope
• WBS
Terminology…
Level 2: Subsystem
Why WBS?
Level 3: Task
WBS
Resource Planning
7
Terminology…
• WBS:
• Process of subdividing/decomposing (breaking down)
project deliverables and project work into smaller, more
manageable components
• Why?
- for accurate estimates, a performance measurement &
control
- for clear responsibility assignments
❑Benefit:
• WBS organizes & defines the total scope of the project
Create WBS
• Create WBS
• Project sub-divided into hierarchical units of tasks,
work packages, and work units.
• Each part of unit tasks, work packages and work
units is budget able, in terms of money, labor hours,
and other requisite resources.
• Project is breakdown into a group of activities.
• Each activity is breakdown into a task list.
• This task list is put into a calendar.
• Then, assign people, time, money and other
resources.
Create WBS…
• Schedule Task list into calendar.
• Assigning people, time, money to each activity.
• Make themselves competent.
• Managing “intelligent” people.
Create WBS…
• Breakdown task into activities
• Top-down refinement possible
• List activities which form a single operation or function which you know is
achievable
• Work breakdown structure
• (Product breakdown structure)
Create WBS…
Example of WBS: “Holiday”
Create WBS…
List of activities;
Booking:
• get brochures
• choose resort
• make booking
• confirm booking
Travel documents:
• check passport
• book tickets
• get insurance
• visas
• travel money
• etc.
What is Planning?
❖Group 5 students
❖Write 1 reason per student
❖Share your ideas in your home group
❖Present 2 reasons per group
Why Project Planning?
❖4 basic reasons for Project Planning (Kerzner)
1. to eliminate or reduce uncertainty
2. to improve efficiency of the operation
3. to obtain better understanding of the objectives
4. to provide a basis for monitoring & controlling the work
Project Planning
20 Processes involve: (refer Knowledge Area and Process Table)
1. Develop PM Plan }PIM
2. Collect Requirements }
3. Define Scope } PSM
4. Create WBS }
5. Define Activities }
6. Sequence Activities }
7. Estimate Activity Resources } PTM
8. Estimate Activity Duration }
9. Develop Schedule
Project Planning
10. Estimate Cost } PCM
11. Determine Budget } PCM
12. Plan Quality } PQM
13. Develop Human Resource Plan } PHRM
14. Plan Communications } PComM
15. Plan Risk Management }
16. Identify Risks }
17. Perform Qualitative Risk Analysis } PRM
18. Perform Quantitative Risk Analysis }
19. Plan Risk Responses }
20. Plan Procurement } PPM
Project Planning…
9 Major Components of the planning phase: (Kerzner)
• Objectives = a goal, target
• Program = the strategy to be followed & major actions
to be taken to achieve the objectives
• Schedule = activities to start & complete
• Budget = planned expenditure
• Forecast = a projection what will happen in certain time
• Organization = structures, duties & responsibilities
• Policy = guide for decision making
• Procedure = detailed method for carrying out a policy
• Standard = a level of individual/group performance
Strategy = plans or methods created for the purpose of a
a goal;
Thank you