1 Stability
1 Stability
Lectures prepared by
•Frequency stability
•Voltage stability
For subsequent materials assistance taken mainly from :
[2] LEONARD L. GRIGSBY, editor: POWER SYSTEM STABILITY AND CONTROL, CRC
Press, 3rd Edition, 2012
[3] Jan Machowski, Zbigniew Lubosny, Janusz W. Bialek and James R. Bumby:
Power System Dynamics Stability and Control, John Wiley & Sons, Ltd, UK, 2020.
Stability: This is the ability of a power system (having
multiple synchronous machines i.e. generators and
motors interconnected through a transmission
network) to attain the original or a new steady state
after it experiences respectively a small disturbance or
a large disturbance.
-Pmax sinδ
During fault
•During a three phase fault at point P (at t=0) on the short line
no power is transferred to the infinite bus and hence
electrical power output from the generator is zero. (Pe=0 so that Pa ≠0 i.e. the rotor
will oscillate)
•After the fault is cleared (t = tc), power same as before fault is transferred (and the
already developed acceleration becomes negative) .
Pre fault;
The rotor stays at equilibrium or steady state angleδ0
This is more precisely stated as “the kinetic energy (KE) added to the rotor during a fault
must be removed after the fault is cleared in order to restore the rotor speed to sync.
speed”.
In fact the criterion for stability is A1 ≤A2 or A4 ≤A3.
The areas below Pm line represent addition of KE while those above Pm represent removal
of KE.
However, A1 =A2 or A3= A4 criterion covers up to a critically stable condition in which the
rotor relative angle can swing up to a maximum value δmax and still regain the synchronous
speed. The corresponding clearing angle and time are termed critical clearing angle and
critical clearing time.
Critical clearing angle: δcr
This is such an angle that when the rotor position is at or before this angle, the
fault must be cleared else the rotor will swing beyond a point δmax where Pm will
permanently be more than Pe and hence the machine will loose stability.
infinite bus is
Now δ at t=tc
.
P
Note: If r1=0 i.e. a fault at the sending end bus and r2=1 i.e. after the fault is cleared the original power
curve is followed then eqn 16.73 reduces to 16.67.
Classical model
2. Then the during fault condition is reflected appropriately in this augmented Ybus
and it is reduced to nxn matrix eliminating non generator buses when n is the number
of generators.
3. Similarly the after fault condition is reflected appropriately in this augmented Ybus
and it is reduced to nxn matrix eliminating non generator buses when n is the number
of generators.
4. The Pei in the swing equation of a generator ‘i’ is evaluated using an equation where
the admittances between generator buses i and j are taken from the reduced matrix
corresponding to during or after fault condition whichever is needed. e.g., in a 3 generator
system this eqn. is
Note: Conductance G has not been
neglected in the line admittances
Discontinuity in Pa at the
Solution of swing equation using an algorithm suitable for “hand calculation”. If the step size Δt is middle of an interval
small then its accuracy increases. However, Δt =0.05 sec is often used for hand calculation purpose.
Δ
By an analysis of the load flow results:
Pm2 Pm1
δ10
δ20
For the system and given fault condition the power transferred and swing equations
during and after fault are as follows. (Y values are taken from corresponding reduced matrix
whose formation shown in latter slides)
During fault After fault
Pe1 Pe1 =0
Pe2
(increase or decrease)
Δδn /Δt =ωr, n-1/2
δn = δn -1+ Δδn (in any step δn is updated
first )
Δδn = Δδn -1+ kPa,n-1 (in any step Δδn is
updated last for use in the next step)
≈0.5 sec =T
Average frequency of
oscillation of δ2 is fr=
I/T ≈ 1/0.5 = 2 Hz
Unstable Stable
b) Operational strategies:
An analysis of the above set of equations shows that i) Increase machine excitation so that E and hence Pe
•A) acceleration (due to a fault) or deceleration (due to increases during a fault; this is performed by what is
known as PSS (Power System Stabilizer)
increase in electrical load) of a synchronous machine is ii) Fast valve control of turbines i.e. during a fault the
less and hence stability is more if turbine valve will close faster while during a sudden
1.H is higher i.e. machine rotor size is higher. increase in electrical load demand the valve will open
faster so that the difference between Pm and Pe and
2. The difference between mechanical input power (Pm) hence acceleration or deceleration reduces.
and electrical power transfer (Pe) is less. Pe can be iii) Faster fault clearing (much less than critical clearing
increased by increasing E i.e. excitation and decreasing time) using high speed relays and CBs.
iv) Selective pole operation of CBs to clear a fault i.e.
reactance X. healthy phases remain intact so that Pe after fault
increases and hence rotor acceleration becomes less.
•B) The critical clearing time increases i.e. a machine can v) In case generation i.e. mechanical power output from
turbine cannot be increased when needed, the last resort
retain stability for a longer time if is to shed electrical demand (load) using under frequency
1. H is higher auto load shed relays installed at substations, to reduce
2. Pre-fault power (equal to Pm neglecting loss) is lower. the difference between Pm and Pe .
Rotor angle vs. frequency vs. voltgae stability:
A brief overview of rotor angle stability.
Rotor angle stability is concerned with the ability of interconnected synchronous machines of a power system
to remain in synchronism under normal operating conditions and after being subjected to a small scale or large
(i.e. transient stability) disturbance. It depends on the machines’ ability to maintain/restore equilibrium
between electromagnetic (i.e. electrical) torque and mechanical torque of each synchronous machine in the
system. A fundamental factor influencing this category of system stability is the manner in which the power
outputs of synchronous machines vary as their rotor angles change. The time frame of interest in transient
stability studies is usually limited to 3–5 s following the disturbance. It may extend to 10 s for very large systems
with many machines leading to several modes of oscillations.
Frequency stability:
A subtle difference between frequency and rotor angle stability:
Though change in rotor angle causes change in frequency, the frequency stability is concerned
with the ability of a power system to maintain steady frequency within a nominal range
following a severe system upset resulting in a significant imbalance between the overall system
generation and load. It depends on not only machines’ ability but also on the ability of the system
to restore balance between system generation and load, with minimum loss of load. Obviously a
frequency stability study needs modeling fast processes viz. primary control i.e. generators’
governor response and secondary control i.e. AGC actions, modeling voltage and frequency
sensitivity of loads, under frequency relay actions etc. and also slow processes such as boiler and
turbine dynamics. Usually the devices used for frequency control are not modeled in rotor angle
or voltage stability studies. The overall time frame of interest for frequency stability extends to
several minutes. Therefore, it is categorized as a long-term phenomenon.
Voltage stability:
Voltage stability is concerned with the ability of a power system to maintain steady voltages at all buses in the
system under normal operating conditions, and after being subjected to a small or a large disturbance. Voltage
instability may occur in both forms i.e. (i) progressive fall or rise and (ii) sustained fall at some or all the buses.
The possible outcome of voltage instability is loss of load in the area where voltages reach unacceptably low values, or
a loss of integrity of the power system.
The main factor contributing to voltage instability is usually the higher reactive power losses and the resulting voltage
drops that occur when high levels of active power and reactive power flow through inductive reactances associated
with the transmission network; this limits the capability of transmission network for power transfer. The power
transfer and voltage support are further limited when some of the generators hit their field current limits. The driving
force for voltage instability is usually the loads; in response to a disturbance resulting in network-wide voltage
reduction, power consumed by the loads tends to be restored by the actions of fast acting devices such as
electronically controlled motor loads, HVDC converters, under voltage load shed relays or slow acting devices such as
distribution voltage regulators, tap-changing transformers and thermostats . So the time frame of interest for voltage
stability problems may vary from a few seconds (short term) to tens of minutes (long term).
However, stability is usually determined by the resulting outage of equipment rather than the severity of the initial disturbance. In many
cases, static analysis techniques can be used to estimate stability margins.
A criterion for small disturbance voltage stability is that, at a given operating condition for every bus in the system, the bus voltage
magnitude increases as the reactive power injection at the same bus is increased. A system is voltage unstable if, for at least one bus in
the system, the bus voltage magnitude (V) decreases as the reactive power injection (Q) at the same bus is increased. In other words, a
system is voltage stable if V–Q sensitivity is positive for every bus and unstable if V–Q sensitivity is negative for at least one bus.
The loadability margins ( i.e. limits of increasing load until voltage collapse occurs) is one of the indices of voltage instability and this
can be computed using power flow based methods.
All solutions to these power flow
equations, as the system load level
PL is increased, can be plotted to
yield PV curves (bus voltage vs.
active power load levels) or QV
curves (bus voltage vs. reactive
power load levels) for this system.