Appeal Vol 1 - Compressed
Appeal Vol 1 - Compressed
VERSUS
PAPER-BOOK
[FOR INDEX PLEASE SEE INSIDE]
VOLUME – I
(PAGE 1 TO 246)
VERSUS
MASTER INDEX
VOLUME - I
VOLUME - II
VOLUME - III
VOLUME - IV
VOLUME - VI
MEMO OF PARTIES
VERSUS
THROUGH
APPELLATE JURISDICTION
Insolvency and Bankruptcy Code, 2016, (the “Code”) against the order
3794/MB/C-III/2019.
allowing” prayer “c” of the I.A. No. 2694 of 2023 in C.P. No. (IB)
12, the Appellant apprehends that the newly appointed Valuer may
Memorandum.
the resolution plan was incorrectly approved by the CoC without all
and Regulations.
Valuers with regard to the Barter flats as also KDMC flats. Thus,
erroneous.
different methods and further failing to value the actual assets which
THROUGH
DATE PARTICULARS
applicants.
10
constructed thereto.
Debtor.
12 herein.
15.02.2023.
31.03.2023 Pvt. Ltd. and Naman Developers Pvt. Ltd. The said
29.04.2023 Appellant Bank filed I.A. No. 2694 of 2023 in C.P. No.
ordered thereafter.
therewith.
deferred;
valuer.
3794/MB/C-III/2019.
Impugned Order.
22.01.2025.
21.02.2025
THROUGH
submits as follows:
Appellate Tribunal may deem fit and proper in the facts and
2.2 The Appellant / Applicant states that the detailed facts leading to
the filing of the present appeal and present application has been
as part and parcel of the present application and the same are not
2.3 The Appellant / Applicant states that the impugned order was
impugned order and the date of uploading the impugned order may
3.1 The Appellant / Applicant is based out of Mumbai and after the
reviewed the impugned order and took steps to obtain legal advice
advised to file an appeal, and the necessary approval for filing the
21
3.2 That in the meanwhile the Appellant applied for the certified copy
humbly submitted that the period for obtaining the certified copy
limitation.
3.3 While so, the initial draft was received on 18.02.2025 and the same
impugned order
Total 6 days
3.5 That the Appellant / Applicant most respectfully submits that the
delay in filing of the present appeal was neither wilful, nor wanton
but only due to the bonafide reasons and sufficient cause set out
efforts been moving with due diligence and the delay was not
3.6 That the Appellant / Applicant most respectfully submits that the
justice.
4. BALANCE OF CONVENIENCE:
Appellant/Applicant.
27
that pending the hearing and disposal of the present Appeal, this
b) Direct that the hearing and approval of the Resolution Plan by the
Appellate Tribunal may deem fit and proper in the facts and
2.2 The Appellant / Applicant states that states that the detailed facts
and the same may be read as part and parcel of the present
application and the same are not repeated herein for the sake of
brevity.
29
3.1 The Appellant / Applicant states that they have a strong prima
Debtor.
be set aside.
Appellant.
justice.
4. BALANCE OF CONVENIENCE:
submits as follows:
Mumbai.
Documents.
2.2 The Appellant / Applicant state that the detailed facts leading to
the filing of the present appeal and present application has been
read as part and parcel of the present application and the same
3.1 The Appellant / Applicant submits that that due to paucity of time
and to avoid any further delay in filing the present Appeal, the
Appellate Tribunal.
justice.
4. BALANCE OF CONVENIENCE:
Applicant.
44
4. BALANCE OF CONVENIENCE:
1. DETAILS OF APPEAL:
and Bankruptcy Code, 2016, (the “Code”) against the order dated
The Appellant humbly submits that the subject matter of the present
6. LIMITATION:
The Appellant states that the impugned Order was pronounced by the
out only the brief facts giving rise to the present Appeal, and the
Appellant craves leave and liberty to refer and rely upon the detailed
facts as set out in I.A. No. 2694 of 2023 in C.P. No. (IB) 3794/MB/C-
Mumbai:
12 are the valuers appointed during the CIRP (“CIRP Valuers”). The
7.3. The Corporate Debtor had approached the Appellant Bank for
Primary Security:
valued at Rs. 360.07 Crore; however, the value of the unsold land and
Consultants Pvt. Limited dated 5th November 2012 is Rs. 262.12 Crore
described as below:
7.5. Before the disbursal of the loan amount, the Appellant Bank had
as follows:
TOTAL 186.98
Approx. 187.00
58
7.6. When the Appellant Bank had disbursed the loan, it was on the
and Appellant Bank has issued the same. A true copy of list of
59
7.7. While initially the Corporate Debtor was repaying the loan amount
however they later failed to service the loan account due to which it
Bankruptcy Act 1993 before the Ld. Debts Recovery Tribunal (O.A.
7.8. Further, the Appellant Bank also initiated action under SARFAESI
iii All Bank accounts, including without limitation, the Debt Service
Reserve Account, the Retention Account (or any account in
substitution thereof), major maintenance reserve accounts, letters
of credit, escrow account and other reserves and such other Bank
accounts that maybe opened in terms hereof and of Projects
Documents and over all funds from time to time deposited therein
and over all Authorised Investments or other securities
representing all amounts credited thereto (of CD).
v Right, title and interest, claims and demands in and to the Project
Documents, contracts as amended, varied or Supplemented from
time to time duly acknowledged and consented to by the relevant
counter-parties to such Project Documents to the extent not
expressly provided in each such Project Documents, all as
amended, varied or supplemented from time to time both present
and future (of CD).
vi Right, title and interest, claims and demands in and to and under
all the Government Approvals, Clearances, licenses of the
project, both present and future (of CD).
vii Right, title and interest, claims and demands in EPC Contracts,
all letters of credit, guarantees including contractor guarantees,
sponsors guarantees and liquidated damages and performance
bonds provided by any party to the Project documents or
contracts in favour of the Borrower both present and future (of
CD).
61
viii Right, title and interest, claims and demands in, to and under all
Insurance Contracts / Insurance Proceeds of the Project, both
present and future (of CD).
7.9. Thus it is clear from the above said that from 22.09.2017 (the date of
Agreement for Sale or to execute any Sale Deed. Further the entire
name (i) Mr. Kunal Kantilal Vikamsey (in short “Mr. Kunal”) & (ii)
M/s Adroit Appraisers and Research Private Limited (in short “M/s
below:
* Serial No. 1 is of vacant land in the Project “Swarajya” & Serial Nos.
SUMMARY
Sr. Project Sub- Status Fair Market Liquidation
No. Name Project / Value (Rs.) Value (Rs.)
Building
1 Swarajya Swarajya Completed 11,99,88,000 8,39,91,600
Project (b+c) (b+c)
70
7.14. The summary of the valuation of M/s Adroit Appraisers and Research
Sr. Built Up Sector Bldg. Flat Derived Rate Fair Market Value
No. Area No. No. Nos. Per SFT in Rs.
(SFT) (INR)
1 523 1 13 704 3,800 19,87,400
2 523 2 14 705 3,800 19,87,400
3 523 2 15 602 3,800 19,87,400
4 523 2 15 403 3,800 19,87,400
5 523 2 15 404 3,800 19,87,400
6 523 2 16/A 406 3,800 19,87,400
7 523 2 16/A 506 3,800 19,87,400
8 523 2 16/B 2 3,800 19,87,400
9 523 2 19/A 1 3,800 19,87,400
10 523 2 19/A 605 3,800 19,87,400
11 523 2 19/A 701 3,800 19,87,400
12 523 2 19/A 702 3,800 19,87,400
13 523 2 19/A 704 3,800 19,87,400
14 523 2 19/A 705 3,800 19,87,400
15 523 2 19/A 706 3,800 19,87,400
16 523 2 19/B 5 3,800 19,87,400
17 523 2 19/B 701 3,800 19,87,400
18 523 2 19/B 703 3,800 19,87,400
19 523 2 19/B 704 3,800 19,87,400
20 523 2 19/B 705 3,800 19,87,400
21 523 2 19/B 706 3,800 19,87,400
22 523 2 18 5 3,800 19,87,400
23 523 2 18 4 -- --
TOTAL 4,37,22,800
Deducting Pending Property Tax 1,21,23,796
Total Fair Value (INR) 3,15,99,004
housing development
named as “Swarajya”,
Village Ambivali, al.
Kalyan, Dist. Thane.
ANNEXURE – A/5.
7.16. The Appellant states that certain objections / issues were raised by
a) The Appellant Bank from the initial stage have been pressing
audit will not be served. Edelweiss have also been supporting the
Members that the Forensic Audit Report shall have to be only for
a period of 2 years.
Swarajya was also discussed along with the issue of handing over
72
the flats to the flat buyers who have made payment of full sale
Appellant Bank has stated that they have issued only 110 NOC’s.
have also been sold prior to Appellant Banks loan which cannot
the Units have been charged to them and without NOC possession
over the possession of flats since they have issued only 118 NOC’s
and the balance flats have been sold without their NOC. RP
clarified that they are getting a Legal Opinion on the said issue.
Three Resolution Plans have been received and the same was
discussed.
7.17. Incidentally in the 3rd COC meeting held during CIRP it was
below:
74
accordingly by the
Resolution Applicant in his
Resolution Plan.
In the event of Liquidation
the claims of such home
buyers as Unsecured
Financial Creditors will be
addressed as per the
waterfall mechanism under
section 53 of the IBC.
7.19. That the issue of handing over the possession was dealt with in the
7.20. The Appellant states that the Resolution Professional has taken up
a stand (as that of their Advocate) that majority of the flats have
Corporate Debtor has also sold 165 number of flats / Units after
with only 2628 Units. Thus the total Units dealt with in the
7.21. During the CIRP, the Appellant was informed by the Resolution
land have been utilized for construction and the balance of 14.60
Acres have all been consumed for other purposes such as MSEB,
property
taxes of Rs.
1,12,23,796
the final
FMV of Rs.
3,15,99,004
have been
arrived at.
4 Whether the flats RP cannot No comments of Valuer (as
of KDMC have provide they are not concerned)
been available as clarify on the
security in the same as the
event of KDMC will
liquidation contest
legally the
said issue
revealed that the Sector I & II has been developed only in a portion of
project area and a huge portion of open land is still left. However, the
IM does not disclose the said fact anywhere, whereas describing the
“Ramrajya” project it has been clearly mentioned that out of the total
under the presently developed two sectors and there is no open land
Pvt. Ltd. the final FMV of Rs. 3,15,99,004 has been arrived. Details of
already handed over to Barter has not been evaluated at all. Even out
of the total 23 KDMC flats valuation has been taken of only 22 flats.
After deduction of pending property taxes, the fair market value has
been arrived at only mere Rs. 4,37,22,800/- which is far below the real
The valuation methods of the two Valuers are not in uniformity. Two
neither of them has been able to properly explain the rationale behind
have not provided any reason for accepting the said two valuation
and Research Pvt. Ltd. did not take the said flats in consideration.
Possibly the Resolution Applicants are also not clear about the issue,
due to which the Resolution Plans which are placed for voting have not
7.23. That during the CIRP, three Resolution Plans were received from
EKA Life Limited, Esgee Real Estate Developers Pvt. Ltd. and
Naman Developers Pvt. Ltd. The said Resolution Plans have been
modified from time to time and certain clarifications have also been
Naman Developers Pvt. Ltd. was approved and the results of e-voting
is as follows:
Count 7 1 0 1
7.25. On 29.04.2023, the Appellant Bank filed I.A. No. 2694 of 2023 in
Project Swarajya.
i) Any other relief as this Hon’ble Tribunal may deem fit and
proper.
A true copy of the I.A. No. 2694 of 2023 in C.P. No. (IB)
the Appellant Bank alongwith the tabulated charts before the Ld.
ANNEXURE – A/13. The Appellant had filed the plan for the
Project Swarajya and the Google Earth image along with their I.A.
of the plan for Project Swarajya and the Google Earth image is
by the Bank. A true copy of the Reply dated NIL July 2023 filed by
7.27. The Respondent No. 12, the Appellant, and the Respondent No.1 also
Mumbai. The Appellant also filed a copy of the Plan approved and
3794/MB/C-III/2019.
A/22.
Creditors was held wherein the CoC inter alia resolved, by a majority
8.1 The Ld. Adjudicating Authority, Mumbai erroneously held that there
Memorandum.
8.2 The Ld. Adjudicating Authority, Mumbai erroneously held that there
8.3 The valuation exercise carried out during CIRP is erroneous and not
on proper parameters.
8.4 That if proper valuation would have been made by both the CIRP
Valuers, the correct market price fair value and liquidation value
III/2019?
8.8 Whether the Ld. Adjudicating Authority erred by failing to set aside
8.9 Whether the Ld. Adjudicating Authority by failing to set aside the
Information Memorandum?
8.13 Whether the Impugned Order deserves to be set aside for non-
documents on record?
8.14 Any other questions of law that may arise at the time of arguments,
for which the Appellant craves leave and liberty of this Hon’ble
Appellate Tribunal.
9. GROUNDS OF APPEAL:
“partly allowing” prayer “c” of the I.A. No. 2694 of 2023 in C.P.
concerned.
90
Mumbai.
“partly allowing” the I.A. No. 2694 of 2023 in C.P. No. (IB)
the CoC without all the relevant information and contrary to the
The Appellant once again out of abundant caution reiterates that the
Information Memorandum.
Memorandum.
Memorandum.
Swarajya project consists of an area of about 26 acres which in turn has been
divided into two sectors Sector 1 and Sector 2. Sector 1 consists of 18 buildings
project is situated at Village Ambivali, Taluka Kalyan, District Thane. The survey
nos. of the land are 1/3, 2/3, 5, 6, 3/1, 2, 3, 74/8 to 12, 76/3, 4, 5, 11, 14, 24, 26,
27, 28p, 74/13, 15, 4/1 to 5, 4/6/2, 7 to 10, 12, 14, 5/1, 2, 76/8, 9, 10, 12 and 75.
All the buildings under this project are of G+5 to G+7 structures and Occupation
Certificate has been received for these buildings. Sector 1 buildings have been
fully completed and a total of 1160 units have been constructed, of which 1134
units have been sold and possession of 1074 units have been handed over. The
Company has entered into barter arrangements for 26 units for which underlying
agreements have not been made available. Possession of these units have also not
been handed over to the counter party. Sector 1 also consists of 55 shops of which
Some of the buildings in Sector 2 are partially complete. A total of about 1530
units have been constructed, of which 1468 units have been sold and possession
of 590 units have been handed over. A total of 372 units are in completed stage
for which full money has been received and possession is yet to be handed over.
The Resolution Professional had approached COC for a decision to hand over
these units on “as is where is basis” and not accept claims from these unit holders.
94
Since the COC did not take decision in this matter, the Resolution Professional has
filed IA with the Hon’ble NCLT, Mumbai seeking direction in this matter. The
The Company has entered barter arrangements for 40 units for which
underlying agreements have not been made available. Possession of these units
have also not been handed over to the counter party. A total 21 units have been
provided as security to KDMC as payment was due to them. Sector 2 also consists
The project has been given as a security against the loan taken from Central Bank
of India. The Resolution Professional has been advised by Central Bank of India
that they have given NOC for a total of 118 customers. The details of these NOCs
There were more than 154 bookings taken by the Company in Sector 2 (building
no. 21, 22A and 22B) and 922 bookings in building in Sector 2C and 2D. However,
the Company cancelled the construction plan, and these unit holders were
Further, the Company also received suo-moto cancellation notice from customers
for these building in the ‘Swarajya’ project, for which refund was not initiated. An
Project Swarajya:
9.14. BECAUSE it is evident from the above that the Respondent No.2
9.15. BECAUSE in the year 2013 when the loan was sanctioned by the
9.16. BECAUSE when the valuation was taken up by Appellant Bank (at
the time of sanctioning of loan) total unsold area for said project
was of 728112 Sq. ft. which was valued at Rs. 269 Crores. Thus, the
Resolution Professional’s stand that the flats have all been sold
incorrect.
Acres and the same when converted into sq. mts./ sq.ft. is as below:
105218 sq. mts. equivalent to 11,32,560 sq. ft. This means that there
are 468 plots in total with the standard size of 60 x 40 sq. ft.
in both Sectors):
(in Rupees)
9.22. BECAUSE the entire valuation exercise done on the assets of the
the root of the matter which affects the rights of all stakeholders and
forward.
9.24. BECAUSE both the Valuers failed to value the vacant land which
completed but still has substantial intrinsic value as also FSI already
approved for project which still remains exploited. All this will
surely have empirical intrinsic value to assess the project which was
also vacant land having huge value have been totally neglected by
the interest of justice the entire exercise have to be set aside. The
No.
Sr. of Outstanding
No. Details Flats Amount Received Amount Total Amount
1 Sector 1 214 16,98,91,628.85 2,11,25,191.78 19,10,16,820.63
2 Sector 2 307 24,61,20,140.93 2,66,30,261.43 27,27,50,402.36
521 41,60,11,769.78 4,77,55,453.21 46,37,67,222.99
9.29. BECAUSE the unsold flats of 356 Units (which are partially
No. 5).
Memorandum and its Annexures are not tallying with each other. In
9.31. BECAUSE though the Resolution Professional and his Counsel (in
their legal opinion) have taken up a stand that many of the flats have
and 4).
9.32. BECAUSE it is shocking to observe that 191 flats have been sold /
22.09.2017. The said sale itself is invalid for the reason that the flats
remain under attachment from the said date (Refer Table Nos. 2 and
3).
104
not done.
9.34. BECAUSE as the market value fair value and liquidation value
stakeholders.
9.35. BECAUSE if proper valuation would have been made by both the
“Swarajya” project would have been very huge to the benefit of all
Resolution Applicant.
105
errors.
No.2.
9.41. Any other ground as may be available to the Appellant for which
the Appellant crave leave to add, amend or delete the grounds at any
106
time on or before the hearing of the matter, or that may arise at the
time of arguments.
The Appellant declares that they have not previously filed any writ
issues raised in the present Appeal, before any other Court or judicial
documents;
record.
107
The Appellant has not preferred any other appeal before the Hon’ble
The Appellant has paid the Court Fees on Bharat Kosh and the receipt
Memorandum of Appeal.
mail and the proof of service is enclosed along with the present
appeal.
The Appellant has stated all the material particulars up to this stage in
present case, questions of law and grounds of appeal raises herein, the
above, the points in dispute and questions of law set out in paragraph
to:
(a) Set aside the Impugned Order dated 21.01.2025 passed by the
rejection of prayers (a), (e), (f), (g) and (h) of I.A. No. 2694 of
(b) Stay the Impugned Order dated 21.01.2025 passed by the Ld.
(c) Direct that the hearing and approval of the Resolution Plan by
(d) Alternatively, direct that all further steps taken in the CIRP of
present Appeal;
ANNEXURE - A/2
152
153
154
155
156
157
158
159
160
161
162
163
164
165
166
ANNEXURE - A/3
167
168
169
170
171
ANNEXURE - A/4
172
173
174
ANNEXURE - A/5
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
ANNEXURE - A/6
237
238
239
240
241
242
243
244
245
246