Cost Estimate
Cost Estimate
where
C = capital cost in pounds sterling;
N = No of functional units;
Q = plant capacity in tpy
THE FACTORIAL METHOD OF COST
ESTIMATION
1. Lang factors
The fixed capital cost of the project is given as a
function of the total purchase equipment cost by
the equation:
Ce = CSn
where
Ce = purchased equipment cost, £;
S = characteristic size parameter, in the units given
in the Table ;
C = cost constant from the Table;
n = index for that type of equipment.
SUMMARY OF THE FACTORIAL
METHOD
1. Prepare material and energy balances, draw up
preliminary flow-sheets, size major equipment
items and select materials of construction;
2. Estimate the purchase cost of the major
equipment items. Use figures and tables given in
these notes or the general literature;
3. Calculate the total physical plant cost (PPC), using
the factors given in the table above
PPC = PCE (1+ f1 +...+f9)
4. Calculate the indirect costs from the direct costs
using the appropriate factors given in the notes;
5. The direct plus indirect costs give the total fixed
capital;
6. Estimate the working capital as a percentage of
the fixed capital; 10 to 20 %;
7. Add the fixed and working capital to get the total
investment required.
OPERATING COSTS
The cost of producing a chemical product will
include the items listed below. They are divided
into two groups:
- Fixed operating costs: costs that do not vary with
production rate. These are the bills that have to
be paid whatever the quantity produced;
- Variable operating costs: costs that are
dependent on the amount of product produced.
Fixed costs
1. Raw materials;
2. Miscellaneous operating materials;
3. Utilities (Services);
4. Shipping and packaging.
The costs listed above are the direct costs of
producing the product at the plant site.
In addition to these costs the site will have to carry
its share of the Company’s general operating
expenses. These will include:
1. General overheads;
2. Research and development costs;
3. Sales expense;
4. Reserves.
These costs would add about 20 to 30 % to direct
production costs at the site.
1. Estimation of operating costs
• Raw materials
These are the major (essential) materials required
to manufacture the product. The quantities can
be obtained from the flow-sheet and multiplied
by the operating hours per year to get the annual
requirements.
The price of each material is best obtained by
getting quotations from potential suppliers, but
in the preliminary stages of a project prices can
be taken from the literature.
An indication of the prices of a selected range of
chemicals is given in the table below
• Miscellaneous materials (plant supplies)
Miscellaneous materials will include:
1. Safety clothing: hard hats, safety glasses etc;
2. Instrument charts and accessories;
3. Pipe gaskets;
4. Cleaning materials.
• Insurance
The cost of the site and plant insurance: the annual
insurance premium paid to the insurers; usually
about 1 to 2 % of the fixed capital.
• Royalties and licence fees
If the process used has not been developed
exclusively by the operating company, royalties
and licence fees may be payable. These may be
paid as a lump sum, included in the fixed capital,
or as an annual fee; or payments based on the
amount of product sold.
The cost would add about 1 to 5 % to the sales
price.
Summary of production costs
The typical values given in this table can be used to
make an approximate estimate of production
costs.
ECONOMIC EVALUATION OF PROJECTS
1. Cash flow diagrams
A - B: The investment required to design the plant.
B – C: The heavy flow of capital to build the plant,
and provide funds for start-up.
C - D: The cash-flow curve turns up at C, as the
process comes on stream and income is
generated from sales. The net cash flow is now
positive but the cumulative amount remains
negative until the investment is paid off, at point
D.
Point D is known as the break-even point and the
time to reach the break-even point is called the
pay-back time.
D – E: In this region the cumulative cash flow is
positive. The project is earning a return on the
investment;
E – F: Toward the end of project life the rate of cash
flow may tend to fall off, due to increased
operating costs and falling sale volume and price,
and the slope of the curve changes;
The point F gives the final cumulative net cash flow
at the end of the project life.
2. Tax and depreciation
Tax rates are not constant and depend on
government policy. In recent years, corporation
(profits) tax has been running at around 30 %
and this figure can be used to make an estimate
of the cash flow after tax. Depreciation rates
depend on government policy, and on the
accounting practices of the particular company.
3. Discounted cash flow (time value of money)
Interest Rate Criterion. The criterion used here is called the rate of return on investment
(ROROI) and represents the nondiscounted rate at which money is made from a fixed capital
investment. The definition is given as
Many alternative definitions for these terms can be found, and sometimes the total capital
investment (FCIL + WC + Land) is used instead of fixed capital investment. When the plant
has a salvage value (S), the fixed capital investment minus the salvage value (FCIL – S) could
be used instead of FCIL. However, because the salvage value is usually very small, it is
preferable to use FCIL alone.