CSWIP 34U FEB 25 Part 2
CSWIP 34U FEB 25 Part 2
13.3.1 Polarity
When the material is magnetised it has a north and a south pole. These poles are located
at opposite ends of the material and magnetism seems to be concentrated at these
points. The north or north seeking pole of a magnet is said to be the pole pointing
towards the Earth’s North Pole; the south seeking pole pointing towards the Earth’s
South Pole.
13.4 Electromagnetism
The type of magnetism produced in a bar magnet is known as
longitudinal magnetism. In electromagnetism, when an electric
current flows through a conductor (copper wire or rod), a magnetic
field is set up around the conductor in a direction at 90 o to the electric
current. This is explained by the Right Hand Rule.
If the thumb of the right hand is extended in the direction in which the current is flowing,
then the direction of the magnetic field is represented by the fingers.
When a conductor carries an electrical current, strong magnetic flux lines are created (in
the direction of the fingers as with the Right Hand Rule see Figure 13.7), this is called
circular magnetism.
Flux density
The number of magnetic flux lines per unit area.
Symbol = B
SI unit = Tesla = T
Magnetising force
The total force tending to set up a magnetic flux in a magnetic circuit.
Symbol = H
SI unit = Ampere-turns per metre = Amps per metre.
Permeability
The ease with which a material can be magnetised.
Saturation
The stage, at which any increase in the magnetising force H applied to a
specimen, produces no significant gain in flux density B.
Effectively this is at point (a) on diagram of the Hysteresis loop.
Coercive force
The reverse magnetising force required to remove residual magnetism from a
material. On the diagram of the Hysteresis loop it is represented by (o-c).
Remanence
The magnetic flux density remaining in a material after the magnetising force has
been removed. On the Hysteresis diagram it can be any value of B, between (b)
and (e), when, H = zero.
Residual magnetic field
The magnetic field remaining in a material after the magnetising force has been
reduced to zero.
Reluctance
A measure of the degree of difficulty with which a component can be magnetised
that is analogous to resistance in an electrical circuit. It is the opposite of
permeability.
Retentivity
The magnetic flux density remaining in a material after the magnetising force has
been removed, synonymous to Remanence.
13.7 Flux leakage
A flux leakage is a break or a discontinuity in a magnetic circuit. Any abrupt change of
permeability within a magnetic specimen will change the number of flux lines that can
flow and thus, there will be a diversion of the field.
Magnetic particle inspection relies on flux leakage fields being seen on the surface of a
ferromagnetic specimen under test. All defects produce flux leakage but not all flux
leakage fields are created by defects.
Magnetic particle inspection relies on:
Magnetising the specimen to an adequate flux density.
Applying fine ferromagnetic particles over the surface of the specimen.
Being able to see the magnetic particles that gather at flux leakage fields.
The magnetic field must run in a direction so that it can be interrupted by the defect,
thus producing a flux leakage field. Also the degree of distortion at the leakage must
allow the magnetic particles to provide an adequate degree of contrast between the
leakage and the adjacent material surface, so that it is readily visible.
Flux lines will take the path of least resistance, hence the highest permeability.
The figure below shows flux lines flowing in a ferromagnetic bar, but having to divert
around an air gap, creating a flux leakage.
However, if ferromagnetic particles are
sprinkled on the bar they will start to
form a magnetic bridge across the flux
leakage and a highly preferred path.
If the flux leakage is strong, such as a
surface-breaking crack in the optimum
direction, then the visual indication will
be clear.
13.7.1 Indications
Indications are any particle indications that are seen on the specimen under test. Just as
not all flux leakage fields are defects, not all indications are due to flux leakage.
Indications can be further subdivided into:
Relevant. - Non-relevant - Spurious )زائف (كاذب
13.8.2 Electromagnets
Electromagnets are made from soft iron
laminates to reduce eddy current
losses, if powered by alternating current
(AC). The yoke laminates are encased in
a multi-turn coil usually powered by
mains electricity, which has been
stepped down to 6 or 12V. The legs of
modern equipment are normally
articulated to allow area contact on
uneven surfaces.
Electromagnets produce a longitudinal field with the test area being a circle inscribed by
the poles. Defect orientation is the same as when using a permanent magnet. BS EN ISO
9934-1 states that a lift test should be carried out prior to using for MPI. The lift test
should confirm that the electromagnet can lift 4.5kg with a pole spacing of up to
300mm.
Table 13.4 Advantages and disadvantages of electromagnets.
13.8.3 Prods
Prods induce a circular magnetic field by sending a high amperage current (typically
1000A) through the test piece. The high amperage can cause arcing between the
electrodes and test surface. Contact points must be carefully cleaned, and electrode
materials chosen to prevent contamination of the test piece.
Prods produce a distorted circular magnetic field
with defects showing at a maximum when
orientated along a line between the prod tips.
Particular care has to be taken to avoid surface
damage of the component under test due to arcing
or contamination.
OIS of Great Yarmouth manufacture and supply a
composite MPI unit that is purpose designed and
built for underwater use, see Figure 13.19.
A ferromagnetic material placed in the coil, or outside parallel to and touching the coil,
will experience longitudinal magnetism.
This method is widely used offshore and two practical applications will serve to show how
the technique may be applied.
Evenly Spaced Coil
A flexible cable is wound around the test piece so
that the area under inspection is contained within the
encircling coil with individual wraps of the coil being
spaced equidistant to each other, The area to be
tested is considered to lie between the turns of the
coil. See Figure 13.21.
As AC produces magnetic flux only on the skin of the work piece, the thickness of the
material is of no consequence, so another constant, 10 replaces T.
Close Wrapped Coil
In this technique the inspection area does not have to lie inside the encircling coils.
However, the test zone must still lie close enough to the ends of the coil to ensure an
adequate flux density in this are.
The current requirement for this technique is
determined by the formula:
Where:
Where:
d = Width of the inspection area (where field strength = 1.0T).
N = Number of turns in the coil.
I = Peak current (Amps).
30 = Constant.
Furthermore, the return cables not forming the parallel loops must be a minimum of 10d
away from the inspection area. The
direction of the field may be ascertained
by applying the Right Hand Rule. The
required current may be found by
applying the formula:
Ipeak (ac) = 30 x d
13.11 Demagnetisation
Looking at a typical Hysteresis loop for a ferromagnetic material, after the initial
magnetising force is applied and then removed, it is virtually impossible to end the test
with a zero flux density.
Even if a negative coercive force is applied it will only keep the flux density at zero, as
long as it continues to be applied.
Figure 13.29 shows that the key to
demagnetisation is that a reversing and
reducing magnetising force must be
applied, so that the Hysteresis loop
reduces until all the parameters achieve
zero. There are a number of ways to
achieve this.
13.15.3 Video
Some video cameras will capture the visible light of the fluorescent particles when the
ultraviolet light is directed on them. This signal can be recorded on disc.
13.15.4 Rubberised Tape Transfer
An adhesive rubberised tape can be applied to a dry indication. The magnetic particles
adhere to the tape, which can then be peeled off. This cannot be applied underwater.
It may have a possible use in a welding habitat.
Rubberised Tape Transfer:
Rubberised tape can be applied to a dry
indication.
This cannot be applied underwater.
It may have a possible use in a welding habitat.
Figure 13.40 shows some of the factors that will affect the performance.
An explanation that affect the sensitivity of a Magnetic Particle Inspection follows.
13.16.1 Surface condition (1)
The effectiveness of the cleaning processes to produce a bright finish is an important
factor. A paint background would help if coloured magnetic particles were being used.
13.16.2 Lighting (2)
If the ambient lighting is too high, the tests must be done at night when fluorescent inks
are used. The diver inspector should monitor regularly the intensity of the ultraviolet
lamp to detect any deterioration in brightness.
13.16.3 Ink condition (3)
Important factors here include the best colour to attract the attention of the inspector
and the right size of particle. This is tightly controlled by the appropriate standard, there
could be some consideration given to larger size particles that may give better contrast.
The physical condition of the ink is also important. It should be a finely divided
suspension of particles that is delivered to the work piece and so the diver inspector
should check to see that the agitator is working continuously. This should be a regular
part of the routine.
13.16.4 Field strength (4)
This must be high enough to hold the ink to the surface of the defect.
13.16.5 Factors affecting definition
The following factors are important when considering definition.
13.16.6 Ink condition (5)
As can be seen from the chart the ink condition has an effect on both contrast and
definition. The definition can be improved if the defect outline is picked out by fine
magnetic particles.
13.16.7 Geometry of the work piece (6)
In the main, MPI has to be carried out by diver inspectors on welds that are parts of
complicated nodes in very difficult position in a hostile environment.
This might be the most significant weakness in the system and methods of improving
the procedures.
13.16.8 Efficiency of the magnetic field conditions (7)
The effectiveness with which the inspector can set up the magnetic field condition is
the heart of the magnetic particle inspection. Factors like current flow, field direction,
electrical contact of the prods, coil fill factor, need to be considered carefully.
Section 15
The Use of Video in Offshore Inspection
15 The Use of Video in Offshore Inspection
15.1 Introduction
Video is used almost universally in diving for monitoring the diver and the task.
All video should be recorded as a matter of procedure.
15.2 Advantages of video
The advantages of using video include the following:
Real-time transmission of images from the diver to the surface.
Useful for monitoring diver safety and wellbeing.
If the ship has sufficient bandwidth available then it is possible to stream the video
signal using an internet connection to a remote location, eg to the client’s headquarters.
Instant playback is possible.
Video generates a permanent record of the inspection.
The video stream may be overlaid with telemetry data from sensors relating to the
inspection.
Effectiveness and efficiency may be improved by topside specialists assisting the diver-
inspector with site identification, expert opinion and comments.
Often the video is accompanied by an audio commentary given by either the diver-
inspector or the inspection controller.
Remotely controlled cameras may be deployed in hazardous areas where it may be
imprudent to send a diver.
High definition video is available which records excellent quality images.
15.12.2 Introduction
There are four elements to a video introduction:
1 Who? Who am I? Who is the contractor? Who is the client?
For example ‘This is diver-inspector Jon Smith. The contractor is JS Diving.
The client is TWI Oil...’.
2 What? What am I doing?
For example ‘Performing a general visual inspection...’.
3 Where? Where am I?
For example ‘On the Charlie-1 leg of North Cormorant platform between zero and minus
20m elevation…’.
4 When? Time and date.
For example ‘The date is the 1st of January, 2013. The time is 16:30 hours’.
15.12.3 Termination
Do not forget to let the viewer know when the inspection has terminated.
For example ‘This concludes my inspection. The time is 17:30 hours’.
15.13 Video pointer
The diver-inspector uses a video pointer during inspections in order to provide a scale
and a colour reference for the viewer. It is also more precise دقيقwhen pointing at
features than using a finger.
An adequate video pointer may
be fabricated from a rod wrapped
with tape.
The pointer should have a series
of gradations on it – typically
every 10mm. It should also have
the primary colours near the tip.
The tip should not be sharpened.
15.14 Post-inspection
Post inspection actions should include the following:
Gently rinse the camera in fresh water. Be careful not to force water past any seals.
Clean the camera lens with lens tissue and fit the lens cap.
Inspect the equipment for damage.
Store the equipment in a dry, well ventilated place.
Complete the video log.
Finalise the DVD and label the disc.
Back up data on hard drive.
Fluency
The ability to give a fluent commentary requires practice, & there are 4 basic points to keep in mind:
Rhythm.
Speed.
Volume.
Pitch.
There are 4 elements to a video introduction:
Who?
Where?
What?
When?
Remember:
Let the viewer know the inspection has Ended
Post Inspection Actions:
Rinse the camera in fresh water.
Clean the lens & fit the lens cap.
Inspect for damage.
Store in a dry, well ventilated place.
Complete the video log.
Finalise the DVD & label the disc.
Back up data on hard drive.
Divers use a video pointer during inspections in order to provide a scale & a colour reference for the viewer:
More precise when pointing than a finger.
Should have a series of graduations – typ. 10mm.
Should have the primary colours near the tip.
The tip should not be sharpened.
Section 16
Inspection Methods Available to Inspect
Underwater Structures
16 Inspection Methods Available to Inspect Underwater Structures
16.1 Visual inspection
Visual inspection is the most commonly used method of inspection. This is because:
It is cheap and readily available.
Many features of engineering importance can be seen on the surface of the material or
structure.
It generally precedes any non-destructive testing (NDT) that is to be carried out on the
component.
However, visual inspection cannot detect sub-surface features such as lack of sidewall
fusion within a weld – hence, often the requirement for NDT.
We have two approaches to conducting underwater visual inspections:
General visual inspection (GVI)
The aim of the GVI is to provide the client with a general impression of the underwater
state of the structure. The area inspected is often not cleaned as an assessment of
marine growth is commonly conducted as part of the GVI.
The datum for the GVI is given to the diver-inspector by the inspection controller (by
reference to the client’s procedure) and will comprise of ) تتكون من(تشملa 12 o’clock
datum for clock positioning and a reference datum for distance positioning. The diver-
inspector may then report the location of features according to their clock position and
an estimation of the distance from a datum.
For example: ‘At the 6 o’clock position, 3m from leg Charlie, there is an area of impact
damage. It is approximately 1m long by ½m wide and is 20mm deep’.
Features that are likely to be reported during a GVI include:
Structural features, eg welds, pad eyes, intersecting members, etc.
Imperfections, eg impact damage, debris, tool marks, etc.
Marine growth – type, thickness and extent.
Paint coatings – type, condition and cover.
Corrosion damage, etc.
16.5 Radiography
Although X-ray radiation is used for topside inspections, the equipment is too complex
to use underwater - gamma radiation is employed instead. Gamma radiation is
produced by the radioactive decay of radioisotopes such as Iridium-192.
Gamma radiography may detect planar defects within the material if the radiation
pathway is carefully aligned to the same expected orientation as the defect.
Volumetric defects are more easily detected by radiography as the user does not
need to align the radiation pathway.
Radiography also produces a permanent recording – the radiograph. Measurements
of the sizes of features and defects within the material may be made from the
radiograph, as can the thickness of the material itself.
The main drawback in using radiographic inspection is that it is a potentially
hazardous technique. The costs of the equipment and safe management make it
relatively expensive.
Weld gauges may be used to measure small scale linear features such as undercut,
excess weld material and fillet leg-length. They may also be
used to measure angles of up to 90 degrees.
The Linear-Angular Measurement (LAM) gauge may be used to measure many small
scale linear and angular features as per the weld gauge. The LAM gauge is superior to
the weld gauge in that it may be used on a curved
surface and is particularly accurate when measuring the
depths of remedial grinds.
Large scale surface profiles may be recorded using a taut-wire survey. In this
technique, a wire is anchored at either end and stretched tight along eg a damaged
brace. Regular measurements are made along the wire to create a profile of the
deformation.
If performed twice along
perpendicular planes then a
three-dimensional
representation of the
deformation may be gained.
Taut-wire Survey
Large-scale surface profiles
Section 17
Inspection Maintenance and Repair,
Quality Assurance and Quality Control,
Recording and Reporting
17.1 Legislation relating to inspection of offshore structures
In 1992 the UK Government brought into force The Offshore Installations (Safety Case)
Regulations SI 2885 (1992). These regulations expand the Health and Safety at Work
Act (1974) to offshore structures in the UK sector of the North Sea.
DCR SI 913 (1996) Design and construction regulations
PSR SI 825 (1996) Pipeline safety regulations
PFEER SI 743 (1995) Prevention of fire, explosion and emergency response regulations
MAR SI 738 (1995) Management and administration regulations
PUWER SI 2932 (1998) Provision and use of work equipment regulations
The main intent for all requirement is to reduce any risk to be:
As low as reasonably practicable (ALARP).
DCR SI 913 (1996) and TOISCR SI 2885 (1992) specify and rely on verification NOT
certification. The regulations also specify that there must be an appointed Duty
Holder who has the authority to carry out a self certification scheme. The Duty Holder
will normally be the operating company and is responsible for ensuring that the
structure remains in a safe condition to carry out its design purpose.
The regulations specify that verification must be obtained from an Independent
Verifying Body (IVB).
There are four IVB’s appointed by the regulations:
1 Lloyd’s Register of Shipping.
2 DNV/GL.
3 Bureau Veritas.
4 American Bureau of Shipping.
There is no statutory requirement to inspect structures, however the Duty Holder must
satisfy the IVB that a particular structure or component does not require any
inspection to ensure safety and obtain verification of this.
The IVB does have the authority to stop all operations on any structure if it considers
that it is damaged or that major alterations or deterioration are likely to impair the
structure’s ability to perform its design task.
In practice the Duty Holder will invariably evolve a full inspection programme that will
ensure the safety of plant and personnel, which must be submitted to the IVB for
verification.
The Duty Holder must appoint the IVB at the design stage of the structure development
so that continuity of verification may be maintained.
17.2 Structural integrity management of ageing installations
This requires the submission of a Revised Safety Case to the HSE where material
changes to the previous Safety Case have occurred, including extension of use of the
installation beyond its original design life.
Within this context, the Duty Holder is expected to be able to demonstrate that major
hazards due to, or associated with, ageing have been identified, that they are
adequately controlled and that all relevant statutory provisions will be complied with.
This means that deterioration and degradation must be integrated into an Asset
Integrity Management (AIM) system and associated plan. The purpose of the AIM
plan is to provide a link between the assessment process and the inspection strategy on
an on-going basis.
17.3 The importance of QA and QC
QA and QC are two sides of the same coin. All the Offshore Operators operate Quality
Management Systems which all rely on Quality Assurance procedures to ensure that all
management functions, including but not limited to, efficient operations, safety,
conformance to legislation and protection of assets are completed effectively, without
waste or duplication up to required standards.
Furthermore, all these functions must be applied the same way every time to a
measurable standard; the entire system must also be actively managed and continuously
improved.
The Quality Control is applied to ensure that all the processes associated with the
Management System are in fact complied with and executed correctly. The QC ensures
that the processes meet the measured standard and that this fact is recorded.
The QA for offshore structures starts with the written procedures and continues with the
inspections, audits and other documentation that is certified and recorded throughout
the life of the structure.
The QC follows this same path, producing the documentation that verifies that the
various processes have all been completed.
There are a number of different methods that any company can adopt to ensure that
Total Quality Management (TQM) is achieved, but commonly BS EN ISO 9002:2008
is adopted.
The importance of QA and QC to any large organisation is that it is fundamental to the
ability of a company to function. Without procedures that demand a certain standard,
that are controlled by verification to ensure correct compliance, a large company would
descend into anarchy and bankruptcy very quickly in the modern business world.
QA and QC begin with the conception of the structure and will continue throughout all the
stages of the structure’s life right through to decommissioning.
The raw materials may contain flaws or manufacturing defects in spite of the best QA
and QC arrangements.
This has two ramifications:
1 The QA systems employed to minimise defects will be aimed at 100% effectiveness,
however 98% may be realistically achievable. This would be normally acceptable
provided that these defects were with design limits.
2 The presence of manufacturing defects in the raw material would not normally cause
in-service failures, but there is a small risk that they might.
Within the realms of good engineering practice and design tolerances this is acceptable.
17.14 Fabrication stage
The QA and QC continue throughout the fabrication stage of the structure development.
Welding procedures and parameters are all carefully applied and certified. Concrete
composition is monitored, confirmed and certified. All the inspection documentation and
certification is verified and filed with the remaining documents, continuing to build up the
QA database.
17.15 Launching and installation
The launching and installation stages in the structure life are again subjected to tight QC
and the relevant supervision, inspection, control and reporting processes continue to be
implemented and recorded.
It is at this stage that the most extensive underwater inspection will take place.
The inspection undertaken on the structure so far has been extensive and will not be so
comprehensive for the remainder of the life of the structure, although it will continue un-
interrupted.
17.15.1 Base line survey
The first Major In-Water Inspection will be totally comprehensive, including the entire
jacket and all underwater components, attachments and appurtenances including, of
course, the SCEs. The seabed surrounding the structure will be inspected up to 30-50m
from the base. A complete CP system survey will also be completed, including CP
readings and an anode count to confirm the presence and the physical integrity of each
anode. This survey is usually referred to as the Base Line Survey.
The base line survey will confirm that:
The structure is in the correct position.
Whether any significant damage has occurred during launch and installation.
That any damage that is identified is accurately reported and recorded.
That any significant defects are highlighted for immediate rectification.
The structure will only be declared fit for purpose when either there are no reported
significant defects or any reported significant defects have been rectified and re-
inspected and the results of the Base Line Survey are accepted by the Duty Holder and
verified by the appointed IVB.
The base line survey will be used to evolve or modify an on-going inspection programme
that will extend throughout the remaining life of the structure.
17.15.2 In service
The in-service IMR programme will ensure that adequate monitoring is accomplished to
satisfy the requirements of the Duty Holder, Safe Working Practices and to achieve
verification by the IVB.
The usual programme for in-service inspections is based on a five-year cycle.
Some items are inspected each year while others are inspected less frequently within the
five-year cycle. Each year 20% of all SCE are inspected as a matter of routine, so that
over the five years all will be inspected once. There is always the option to change the
schedule should the need to do this be identified.
A typical annual inspection would include:
CP survey.
Inspection of all risers, conductors and caissons.
CVI of 20% of selected representative welds.
MPI or similar system eg ACFM of 20% of selected representative welds.
Complete GVI of the entire structure.
Debris and marine growth survey.
Scour survey.
Items on the damage register may be monitored during the annual inspection.
The annual inspection programme reports are monitored and used to update the damage
register and to modify the IMR programme as necessary.
17.16 Damage survey
During the service life of a structure, damage may occur at any time due to
environmental forces, accidents, failure etc. It is a requirement that all damage be
reported and that any incidents are also reported. Unfortunately, not all incidents are
actually reported and damage underwater cannot be seen unless there is an underwater
inspection programme.
It has been determined that approximately 70% of damage found offshore is primarily
due to: the biggest majority of this damage was discovered by routine inspections.
Collision by shipping. - Fatigue failure. - Dropped objects.
The basis of the inspection is to report anything that appears to be not in the as made
condition. Superimposed on top of this basic rule of thumb, are any specific instructions
contained in the Damage Survey Workbook.
17.17 How the Criteria of Non-Conformance System is applied
The Criteria for Non-Conformance is a set of parameters, issued by the Duty Holder’s
Engineering Department, that defines the limit of acceptance of any damage or defect
that may be identified during any inspection.
During any inspection if an item is identified as not being in the as made condition, the
CNC is referred to, to determine whether the anomaly is reportable or can be considered
as being within acceptable engineering parameters. As an illustration, an extract of a
typical CNC table is shown below.
In the event of finding an anomaly, the CNC will normally include either, a list of follow-up
actions that are authorised to be implemented without further instructions, or to have a
table of technical specifications that lays down these follow up actions.
The method for applying the CNC is straightforward. When any item is identified as being
outside the CNC, the actions dictated by the technical specification are implemented.
The item, and all the data concerning it, is recorded and submitted in the inspection
report. Any authorised immediate follow up action is implemented and the fact that this
has been done, together with the results of the actions taken, is recorded and reported
(figure 17.6).
In the flow chart, the reference to the job card applies to the actions taken by the Duty
Holder’s Engineering Department. A job card system, for initiating work actions of any
kind, is a common approach to control of resources, personnel and finances throughout
industry.
17.18 Documentation in an anomaly-based reporting system
The documentation involved with an anomaly-based system, is normally standardised
data report sheets and is commonly on a computer-based system.
With this method, the responsible engineers become familiar with one method of
presentation of information, which saves time when reviewing the inspection data.
Using standard data sheets also ensures that all the required information is included and
does not rely on memory.
The data report sheets will be reviewed and subsequently form the basis for:
Further follow-up or additional structural inspection programmes.
Maintenance or repair projects.
Any engineering analysis that is required by the Duty Holder.
Reports submitted to the IVB for verification.
On completion of any review action, the reports will be archived to become part of the
QA records for the structure.
17.18.1 Work scopes and workbooks in an anomaly-based system
A central feature of an anomaly-based system will be a defined Scope of Work for each
inspection campaign, detailing the extent of the inspection, the components or items to
be inspected and the required tasks. The Scope of Work will be contained in the
Workbook issued at the start of the campaign. The Workbook is a part of the
contractual documentation.
The workbook will contain:
Scope of work.
List of inspection tasks.
Procedures.
CNC.
All the required drawings.
Blank log sheets.
Blank data sheets.
Anomaly report forms.
Daily report forms.
An extract of the damage register applying to the items in the Scope of Work.
In some Operating Companies, the inspection tasks take the form of task code listings,
which contain three digit codes. Each code represents a group of tasks, all associated
with one activity. Then, within that group, different aspects or applications of the activity
can be specified (table 17.4).
Radiography
A radiograph is a permanent record by itself and is easily incorporated into a report.
Casts
These may be taken on occasion, but they are difficult to take and incorporate into a
report. There are other ways of recording the images set into casts and, whenever
possible, these are used in preference to taking a cast. When they are taken, care must
be exercised in storing them as they can be easily damaged.
EMD, EMT and ACFM incorporating computer recording
These methods are all available with computer recording facilities and the ability to have
the programme print out the data. This is ideal for incorporation into a formal report.
Sampling
This is normally a specialist form of recording of marine life for example. It does have
other uses, such as collecting gas escaping from the seabed for analysis.
Storage of samples is a difficulty that must be anticipated before the sampling is
undertaken.
17.23 Certification of personnel and equipment
Any Quality Management System (QMS) will include the requirement that personnel and
equipment are certified to a known standard. In the case of personnel in the UK sector of
the North Sea the Certification Scheme for Personnel (CSWIP) Scheme for underwater
inspectors has been adopted.
The scheme certifies four types of inspectors as detailed in the preface. The more
important proficiencies for 3.1U diver inspector level of certification is outlined below
17.23.1 CSWIP grade 3.1U diver inspector
This diver inspector will be proficient in:
Visual inspection.
The use of video in hat mounted or hand held deployment mode.
Taking still photographs.
Taking CP readings using contact type equipment.
Taking ultrasonic wall thickness readings using an ultrasonic digital thickness meter.
17.23.2 Equipment certification
Any equipment used during an inspection programme, must be certified so as to conform
to the QA requirements. This requirement is intended to ensure that all equipment is,
safe to operate, in good working order and is within the required calibration
specifications.
The requirements for legal compliance and the typical QA calibration requirements
are:
Electrical equipment shall be tested six monthly.
All electrical equipment must be tested for safety each time it is used; eg all residual
current devices (RCD) should be tested daily, any other type of electrical equipment
should be visually inspected and confirmed safe to use before each use.
All inspection equipment shall be calibration checked before and after each use.
A competent person shall calibrate all electrical equipment at intervals prescribed by
regulations or manufacturer’s recommendations and certify this fact. This includes
voltmeters and digital volt meters, which shall be calibrated annually and tagged to
confirm the date the next calibration is due.
17.24 Inspection activities in an anomaly based system
17.24.1 Real time data gathering
Real time data gathering means that the personnel on the job inspect and assess the
components under inspection. Any items, judged to be outside the CNC, will be flagged
up and recorded in real time, on video, by photography or by electronic means. This data
may then be re-evaluated, at a later date, for second opinions or follow up analysis. The
crucial point is that data is only submitted if it is judged to be anomalous at the time of
inspection.
As a comparison some forms of inspection lend themselves to retrospective inspection.
For example, Eddy Current inspection and ACFM inspection store real time data on
computer programmes. The original inspector will make on the spot judgements, but all
the data can subsequently be reviewed. The computer will contain all of the gathered
information, not a selection determined by the original inspector.
17.25 Decommissioning
When the fields become depleted, the various platforms and seabed completions will be
removed. The QA and QC will continue throughout this process to ensure that everything
actually is removed and to verify that the ocean floor is left clear of any debris.
Offshore Installations (Safety Case) Regulations (1992)
expand the Health & Safety at Work Act (1974) to
offshore structures in the UK sector of the North Sea.
These are further clarified by:
Amplifying Guidance Notes.
Approved Codes of Practice (ACOPS).
Statutory Instruments (SI).
The main intent for all of this is, to reduce any risk to
be:
As Low As Reasonably Practicable (ALARP).
Regulations
The Regulations specify & rely on
VERIFICATION not CERTIFICATION
Must be an appointed DUTY HOLDER who has
authority to carry out a self-certification scheme.
The Duty Holder will be a named individual of the
operating company.
He’s responsible for ensuring that the structure
remains in a safe operational condition.
Regulations specify that verification must be obtained from
an INDEPENDENT VERIFYING BODY (IVB)
There are four IVBs appointed by the regulations:
Lloyds Register of Shipping.
Det Norske Veritas / GL.
Bureau Veritas.
American Bureau of Shipping.
There are no statutory requirement to inspect
structures.
Duty Holder must satisfy the IVB that a
structure does not require any inspection to
ensure safety & obtain verification of this.
The IVB has the authority to stop all
operations, if it considers that damage,
alterations or deterioration may impair its
ability to perform its design task.
The Duty Holder will evolve a full inspection
programme, that will ensure safety
He must submit it to the IVB for
verification.
He must appoint the IVB at the design
stage so that continuity of verification is
maintained.
Design Stage
QA/QC is an integral part of the design stage
All the calculations & drawings have to be:
Prepared & completed to specified
procedures.
Have internal verification.
Be in compliance with the standards.
At this stage, the Duty Holder will nominate the
IVB.
Marking Systems
At the start, a marking system will be evolved
So that every component can be identified,
tracked, audited & inspected throughout its
life cycle.
With topside items, this may be a tag system,
where unique numbers are assigned to each
component.
The jacket will also have an identification
system.
Marking Systems
Copyright © TWI Ltd
Marking systems used in the North Sea.
Are all based on a grid system.
Structure in plan view has X & Y co-ordinates.
Depth levels are the Z component.
Personnel involved with inspection must
understand the actual system used on whatever
structure they inspect.
Unique Identification System:
Each platform has a unique 3-digit ID number.
Used as a prefix to a 6-digit number, made up of 3 pairs.
1st pair is a 2-digit code for the type of component.
Main Legs 11 - Horizontal Braces 12 - Nodes 13 etc.
Next 2 digits indicate the level.
Last 2 digits signify the location of that type of component.
Marking Systems
Alpha Numeric System
Copyright © TWI Ltd
Box Matrix System
Firstly a letter denotes each type of component.
Levels are denoted by letters:
Starts with A at the top of the jacket & works down
the alphabet as the levels descend.
Finally, 2 digits represent the X & Y co-ordinates.
Member M
Diagonal member F
Node N
Riser R
& so on for all the
types of
components
Marking Systems
Fabrication Stage
QA & QC continue throughout the fabrication
stage:
Welding procedures are all carefully applied &
certified.
Concrete composition is monitored, confirmed
& certified.
All inspection data is verified & filed with the
other documents, continuing the build up of
the QA database.
Installation Stage
Launching & Installation:
Subjected to tight QC, & the relevant
supervision, inspection control & reporting
continue to be implemented & recorded.
At this stage the most extensive underwater
inspection will take place.
The inspection undertaken on the structure so
far, has been extensive & will not be as
comprehensive for the remainder of its life,
but will continue un-interrupted.
Installation Stage
Copyright © TWI Ltd
The first major in-water inspection (Base Line
Survey)
Will comprise of:
The jacket & all underwater components,
including SCE.
The seabed will be inspected up to 50m from
the base.
A CP system survey will be completed,
including CP readings & an anode count to
confirm the presence & integrity of each
anode.
Installation Stage
Copyright © TWI Ltd
The Base Line Survey will confirm:
The structure is in the correct position.
Whether any significant damage has occurred
during installation.
Any damage identified, is accurately reported
& recorded.
Any significant defects are highlighted for
immediate rectification.
The structure will only be declared fit for purpose.
When there are no reported significant defects.
Any reported defects have been rectified.
Re-inspected.
Results accepted by the Duty Holder & verified
by the IVB.
The Base Line Survey will be used to evolve or
modify an ongoing inspection programme, that will
last throughout the remaining life of the structure.
In-Service Stage
The In-Service IMR Programme will ensure that
adequate monitoring is accomplished to satisfy
the requirements of:
The Duty Holder
Safe working practices
To achieve verification by the IVB
The usual programme for in-service inspections
is based on a 5-year cycle.
Some items are inspected each year while others
are inspected less frequently within the 5-year
cycle.
Each year, 20% of all SCE are inspected as a matter
of routine, so over the 5 years all will be inspected
once.
There is always the option to change the schedule,
should the need to do this be identified.
In-Service Stage
Copyright © TWI Ltd
A typical Annual Inspection will include:
CP survey.
Inspection of all Risers, Conductors & Caissons.
CVI of 20% of selected representative welds.
MPI of 20% of selected representative welds.
Complete GVI of the entire structure.
Debris & Marine Growth survey.
Scour survey.
Items on the damage register may be monitored.
Annual inspection reports are monitored & used to update
the damage register & to modify the IMR programme.
In-Service Stage
Copyright © TWI Ltd
Damage Survey
Damage may occur at any time due to
environmental forces, accidents, failure etc.
It’s required that all damage or incidents
are reported - This doesn’t happen.
Damage underwater cannot be seen unless
there is an underwater inspection
programme.
In-Service Stage
Copyright © TWI Ltd
70% of damage found offshore is primarily due to:
Collision by shipping
Fatigue failure
Dropped objects
The majority of this was discovered by routine inspections.
The basis of an inspection is to report anything that
appears not in the “as made” condition.
Specific instructions may be contained in the damage
survey workbook.
Reporting
The Criteria of Non-Conformance
Parameters issued by the Duty Holder’s eng. Dept.
Define the limit of acceptance of any damage or defect.
If an item is identified as not being in the as-built
condition, the CNC is referred to.
States whether the anomaly is reportable or considered
as being within the acceptable limits.
If an anomaly is found, the CNC includes either:
Follow-up actions that are authorised to be
implemented without further instructions.
Has a table of technical specifications that lays
down these follow up actions.
Reporting
Copyright © TWI Ltd
The method for applying CNC is straightforward:
When an item is identified as being outside the CNC, the
actions in the Technical Specification are implemented.
The item & all data concerning it, is recorded &
submitted in the inspection report.
Any authorised follow-up action is implemented & the
fact that this has been done, together with the results of
the actions taken, is recorded and reported.
Reporting
No! I said, “Send a 12 inch Clamp or a 3 inch plug!”
Copyright © TWI Ltd
CP Survey reporting requirements:
Visual assessment of anode condition.
% of anode wastage.
Sacrificial anode stub integrity.
ICCP cable-duct integrity & electrode
connection.
Marine growth build up on any anodes.
Metallic debris in contact with the structure.
CP readings at specified sites.
Photographs of representative anodes.
CP Survey Reporting
Copyright © TWI Ltd
Coating Inspections:
Note the % present of topcoat, primer & bare metal.
Note any blistering, burst them - if client permits &
try to collect a sample of any deposit.
Assess the condition of the steel under any blister.
Note the % of any paint cracking, sagging, wrinkling
or flaking - with the extent.
If inspecting Monel, look closely for any breaks
or deformation, in the Monel surface.
CVI Reporting
CVI Procedure.
GVI to assess any gross damage & MG
build-up.
Clean to SA2½ 75mm either side of the
weld.
Establish the datum - position a tape
measure & mark up the clock positions.
Measure & record the overall weld length.
Complete the CVI.
Recording Methods
Recording methods can be simple or complex:
Scratchboards.
Sketches.
Photography.
Video.
Radiography.
Casts.
EMD with computer recording.
Sampling.
Qualifications
CSWIP Grade 3.1U Diver Inspector.
This diver inspector will be proficient in:
Visual inspection
Use of CCTV in HMTV or hand-held mode.
Taking still photographs.
Taking CP readings.
Wall thickness readings using a DTM.
CSWIP Grade 3.2U Diver Inspector
This diver inspector will be proficient in:
All the 3.1U Diver Inspector Proficiencies.
The application & interpretation of MPI using:
Insulated closed coils.
Parallel coil loops.
Permanent magnets.
Electro-magnets.
Current flow prods.
The ability to use hand-held grinding tools to
carry out remedial grinding.
Profile welds & surface-breaking anomalies.
Qualifications
Copyright © TWI Ltd
CSWIP Grade 3.3U ROV Inspector
This ROV Pilot will be proficient in:
The use of CCTV in ROV deployed mode.
Taking CP readings.
Taking ultrasonic wall thickness readings
using the ROV probe technique.
Handling & managing data.
Knowledge of the capabilities & limitations of
underwater vehicles.
Qualifications
Copyright © TWI Ltd
CSWIP Grade 3.4U Underwater Inspection
Controller
The inspection controller will have knowledge of
all & be proficient in some of the following:
Visual Inspection.
The use of CCTV in hat-mounted, hand-held &
ROV deployment.
Taking still photographs.
Taking ultrasonic wall thickness readings
using an ultrasonic digital thickness meter.
The application & interpretation of MPI.
Qualifications
Copyright © TWI Ltd
CSWIP 3.4U Underwater Inspection
Controller
The inspection controller will have knowledge of
all & be proficient in some of the following:
Handling & managing data.
Knowledge of the capabilities & limitations of
underwater vehicles.
Knowledge of advanced methods of NDT.
Knowledge of the capabilities and limitations of
diver inspectors.
Knowledge of how to plan & schedule inspection
projects.
Knowledge of the application of QMS.
Qualifications
Copyright © TWI Ltd
The Inspection Controller
Must be capable of developing close working
relationships with all inspection staff involved
with any inspection project.
Some staff will be senior engineers with the
operator of the structure & tact & diplomacy
must be exercised on occasion.
Reporting
Equipment used during an inspection programme must be
certified to conform with legal & QA requirements.
Electric equipment should be tested 6 monthly.
Electric equipment must be tested for safety each time
it is used - RCD’s should be tested daily.
All inspection equipment should be calibrated before &
after each use.
Competent person calibrate all electric equipment at
intervals prescribed & certify this fact.
Reporting
Copyright © TWI Ltd
Good planning & briefings are the difference between
success & failure with any project.
It leads to efficient, inspection activities that are crucial,
in ensuring that the tasks are completed as quickly as
possible, without having to go back.
The correct items are inspected to the correct standard.
Personnel involved are focused, motivated & sufficiently
briefed & skilled to be able to recognise any defects & to
apply the correct actions to them.
Reporting
Copyright © TWI Ltd
Inspection Activities in an Anomaly Based
System
These activities are fundamental in any anomaly
based reporting system, as:
Any items inspected in ‘real time’ will not be
subjected to any secondary inspection.
Anything missed will remain undiscovered
until the next scheduled inspection.
Reporting
Copyright © TWI Ltd
Real time data gathering means that the
personnel on the job inspect & assess the
components under inspection.
Items judged to be outside the CNC will be
flagged up & recorded in real time by video,
photography or electronic means.
This data may then be re-evaluated later, for
second opinions or follow-up analysis.
The crucial point is that data is only submitted
if it is judged to be anomalous at the time it is
inspected.
Decommissioning
When the fields become depleted the various
platforms, pipelines & seabed completions will be
removed.
The QA & QC will continue throughout this
process, to ensure that everything is actually
removed & to verify that the ocean floor is left
clear of any debris.
IMR, QA/QC, Recording & Reporting
Planning Requirements - The overall campaign
will be planned months in advance, whereas
the daily tasks must be planned on a weekly &
daily basis.
IMR, QA/QC, Recording & Reporting
The Inspection Coordinator will need to consider at least:
The actual task requirements.
Procedural requirements regarding personnel
qualifications, specialised equipment or cleaning tasks.
Are hot work permits or restricted access permits
required.
Access restraints.
DSV operating parameter restrictions.
Vessel movements.
Any helicopter operations.
Supply boat schedules.
IMR, QA/QC, Recording & Reporting
The weather.
Any time
constraints.
Any task
priorities.
Copyright © TWI Ltd
19.7.2 SDDE
In the North Sea this method of diving can be employed to a maximum depth of 50m.
The diver is connected to the surface with an umbilical that contains his surface supplied
air, a communication wire connection, a pneumo-fathometer and hot water hose when
required. The diver still carries an air cylinder on his back but this is for emergency use
only.
This style of diving usually deploys the diver from the deck in a basket. The basket
provides safe access and egress from the water and will have an emergency reserve air
supply built in. Figure 19.5 refers.
19.7.4 Mini-bell
The mini-bell is submersible decompression chamber, the same as a saturation bell. The
difference is that the gas supply is air. The diver and the standby diver both lock in at the
surface on the DSV and are then deployed to the job site. At the job site the diver locks
out and is supplied with all services from the bell. On completion of the task the diver
returns to the bell and the chamber lock is closed. The bell is returned to the surface
where it is locked onto the deck chamber complex. The divers both transfer to the
chamber and complete their decompression. This method avoids the surface interval
normally associated with surface decompression.
19.8 Saturation diving
This form of diving relies on the fact that once the bloodstream is saturated with inert
gas the diver may remain in that state as long as required but still only has to pay the
same decompression time penalty whether the time is one day or 28 days (which is the
normal saturation time). The style of diving is called saturation as the divers are
saturated with inert gas at the elevated
pressure until they are decompressed. To
avoid problems with narcosis the inert gas
used is helium. In the North Sea this form
of diving must be employed for any depth
greater than 50m. It has become normal
practice to employ saturation diving
techniques as shallow as 30m and, at
times, up to 20m depending on the actual
task and availability of saturation divers.
The divers are locked into the saturation
chambers before the dive and the
breathing mixture is changed from air to
heliox. The divers are then deployed to and
recovered from the dive site in a
submersible chamber, the bell and remain
at elevated pressure for the entire 28-day
period.
The advantage with using this technique is
that a diver can be kept on the task for
approximately 8 hours at a time. The bell
can remain locked off the system for 8
hours which includes travelling time and
each diver in the two man bell can do up to
4 hours on the task.
Pressure Underwater
Pressure:
The increase in the pressure exerted on anything
that is submerged is increasing by 0.1b (100mb) for
every 1m descent. The SI unit of measure for
pressure is the Bar (b) (1bar = 14.7psi).
Absolute Pressure:
In physics pressure is measured in terms of Absolute
(Abs) pressure, which for the practical purposes
considered here is atmospheric pressure (1bar) plus
the relative pressure being exerted by the column of
water.
Copyright © TWI Ltd
Gauge or Relative Pressure
In practical everyday measurements of pressure, Gauge
pressure is normally considered. This is a direct reading of
the pressure being exerted on the measuring pressure
gauge without taking into account the atmospheric
pressure.
Some chamber gauges can be adjusted manually to take
changing air pressure into account.
Pressure Increase With Water Depth
For every 10m descent into the ocean the pressure
increase is 1 bar.
Pressure Underwater
The Gas Laws
All gasses react physically in the same
manner and there is a set of Gas Laws that
state these reactions.
There are two major factors that affect gases:
Pressure
Temperature
The volume of any gas will be affected by
changes to either of these factors.
Boyle’s LawCopyright © TWI Ltd
Boyle’s Law is the basic Gas Law and states:
‘Provided the temperature remains constant, as the
pressure acting on a gas increases, the volume of the
gas will vary inversely and proportionally’
This Law is very important when considering any
gas filled item that is going to be immersed. It is
especially important for divers as their diving
suits, lungs and ears are gas filled spaces that
react to this Law.
harles’ Law states that:
’Either the pressure or the volume of a gas is directly
proportional to the change in absolute temperature’.
Charles’ Law - Dalton’s Law
Copyright © TWI Ltd
Dalton’s Law states that:
‘The total pressure of a mixture of gases is the sum of
the partial pressures of each constituent gas in the mix’.
This Law is very important to divers as the partial pressure
of a gas determines its toxicity to the body. Even oxygen
becomes toxic at elevated partial pressures. Because of
this, IMCA sets a limit for the PPO2 in a breathing mixture
to 1.5ba while the diver is in the wate
Henry’s Law
Henry’s Gas Law states that:
’The amount of gas that will dissolve in a
liquid is directly proportional to the
partial pressure of that gas’.
Important Gases
Oxygen (O2) is an odourless, tasteless, gas
that is necessary to support life. It is not
combustible but it supports combustion. If
the partial pressure of O2 in a breathing
mixture of gases rises above 1.8 ba it
becomes toxic.
Carbon Dioxide (CO2) is a waste product of
metabolism and combustion. A maximum of
20millibar (0.02 ba) partial pressure of CO2
may be tolerated in a breathing mix.
Important Gases
Copyright © TWI Ltd
Carbon Monoxide (CO) is an extremely toxic
by-product of combustion. If it is breathed in,
haemoglobin has approximately 200 times
greater affinity for it than oxygen.
As haemoglobin cells in the blood transport
oxygen round the body, this is a serious
possible toxic affect.
The concentration of CO in a breathing gas
can be no more than 1 ppm (0.000001 ba)
and preferably should be zero.
Important Gases
Copyright © TWI Ltd
Nitrogen (N2) is an inert, colourless,
odourless, tasteless gas that makes up
approximately 79% of the atmosphere.
At an elevated partial pressure of
approximately 3.16b (which is reached at a
water depth of 30m) N2 becomes narcotic.
The narcotic effects of the gas then get
progressively worse as the pp increases. This
is one reason for replacing N2 with Helium in
breathing gases used below a depth of 50m.
Buoyancy
Archimedes Principle:
Any body wholly or partially submerged in a liquid will
experience an up-thrust equal to the volume of liquid
displaced.
This is critical to a diver as he must achieve
neutral buoyancy so that he is not struggling to
stay down or to ascend.
This is achieved by using lead weights and
buoyancy aids in his suit.
ROV’s have similar buoyancy chambers built in.
Approved Codes of Practice (ACoP
In the UK there are 6 (ACoP) that lay down specific
requirements for different styles of diving.
These arise out of the UK Legislation embodied in the Health
and Safety at Work Act as stated in the SI 2776, The Diving
at Work Regulations 1997.
The 6 ACoP are:-
Commercial diving projects offshore.
Commercial diving projects inshore.
Media diving projects.
Recreational diving projects.
Scientific and archaeological diving projects.
Police diving.
Air Diving
Air Diving is limited to a depth of 50m for two reasons:
Firstly, because of the effects of Nitrogen Narcosis,
which manifests itself on divers going deeper than
30m.
The effect is very similar to drunkenness, loss of
cognitive sense and a general feeling of euphoria.
This is a dangerous state for any diver to be in as it
interferes with the ability to make rational decisions
that may affect the diver’s wellbeing or even life.
The second reason is decompression, because the
deeper a diver goes the greater the time penalty that
has to be paid for safe decompression.
Deployment Methods
Air divers may be deployed using different
methods.
Self-contained Underwater Breathing
Apparatus (SCUBA).
Surface Demand Diving Equipment (SDDE).
Wet Bell.
Mini-bell.
Deployment Methods
Copyright © TWI Ltd
SDDE (Surface Demand Diving Equipment)
In the North Sea this method is employed to a
max. depth of 50m.
The diver is connected to the surface by an
‘umbilical’ that contains his surface supplied
air, a communication wire, a pneumofathometer,
a hot water hose when required,
plus electrical cables for the TV camera and
light.
SDDE (Surface Demand Diving Equipment).
Modern umbilicals have an inherent load-bearing
capability; also the diver still carries an air
cylinder (bailout bottle) on his back but this is
for emergency use only.
This style of diving usually deploys the diver
from the deck in a basket. The basket provides
safe access and egress from the water and will
have an emergency reserve air supply built in.
Wet Bell Deployment
An alternative method for the deployment of an SDDE
diver is a wet bell.
This is an adaptation to a basket that further improves
safety by adding an air bubble in the top of the bell and
more ‘on board’ gas.
This provides a safe haven in the water as well as safe
access and egress.
The stand-by diver is deployed in the wet bell with the
diver, which also enhances safety.
Mini-bel
A mini-bell is a submersible decompression chamber the
same as a saturation bell. The difference is that the gas
supply is air.
The diver and the standby diver both lock in at the surface
on the DSV and are then deployed to the job site.
At the job site the diver locks out and is supplied with all
services from the bell.
On completion of the task the diver returns to the bell and
the chamber lock is closed.
Deployment Methods
Copyright © TWI Ltd
The bell is returned to the surface where it is
locked onto the deck chamber complex.
The divers both transfer to the chamber and
complete their decompression.
This method avoids the surface interval
normally associated with surface
decompression.
Deployment Methods
Copyright © TWI Ltd
Saturation Diving
This form of diving relies on the fact that once the
bloodstream is saturated with inert gas, the diver may
remain in that state as long as required but still only has
to pay the same decompression time penalty whether the
time is one day or 28 days (which is the normal saturation
time).
It’s called saturation as the divers are saturated with inert
gas at the elevated pressure until they are decompressed.
To avoid problems with narcosis the inert gas used is
Helium.
Deployment Methods
Copyright © TWI Ltd
In the North Sea this form of diving must be employed
for any depth greater than 50m.
It has become normal practice to employ saturation
diving techniques as shallow as 30m and at times up to
20m depending on the actual task and availability of
saturation divers.
The divers are locked into the saturation chambers
before the dive and the breathing mixture is changed
from air to Heliox.
Deployment Methods
Copyright © TWI Ltd
The divers are then deployed to and recovered from the
dive site in a submersible chamber, the ‘bell’ and remain
at elevated pressure for the entire 28-day period.
The advantage with using this technique is that a diver can
be kept on the task for approximately 8 hours at a time.
The bell can remain locked off the system for 8 hours,
which includes travelling time and each diver in the two
man bell can do up to 4 hours on the task.
Intervention Techniques Used
Underwater
The diver is still limited by decompression consideration
however, in that there is an upward excursion limit that
cannot be exceeded.
The diver will effectively be decompressing if he makes an
upward excursion to a shallower depth, which is at a lesser
pressure than his working depth.
The actual upward excursion that is permissible on any
dive is, therefore, tightly controlled.
Intervention Techniques Used
Underwater
Copyright © TWI Ltd
Also, if the diver goes deeper, there is a
decompression consideration in that the saturation
chamber on deck is held at a pressure equivalent to
what is called the ‘storage depth’.
The divers may go deeper than this but again, only
within fixed parameters, if they go deeper than
allowed, the deck chambers must be blown down to a
greater depth to accommodate the divers on their
return.
Intervention Techniques Used
Underwater
Copyright © TWI Ltd
If there is a requirement for a saturation
diver to work at different depths during his
dive, (called a ‘bell run’), the shallow upward
excursions must be completed first.
The diver is then worked down to the deeper
tasks.
Diver Heating
When Helium is used to replace N2 in the breathing mixture,
its greater thermal conductivity (approximately 7 times
greater) presents a problem.
The divers lose body heat much more quickly breathing Heliox
and therefore, much more attention has to be paid to heating.
The requirements are:
Diving depth less than 50m extra heating not required.
Diving depth 50m to 150m suit heating must be
supplied.
Diving depth >150m suit and gas heating must be
supplied.
ROV’s
IMCA Guidance Note 051 states that there are 5
classes of ROV.
(Class 1) Pure Observation
This type of vehicle is capable of video observation
only.
(Class 2) Observation with Payload Option
This type of vehicle can carry additional equipment as
well as video cameras, such as CP probes, sonar
transponders, FMD units and similar devices.
(Class 3) Work-class Vehicle
These vehicles are large with manipulators
and space for additional equipment.
They are fitted with multiplexing facilities to
allow for numerous additional instruments
and tools to be fitted.
The umbilical will also have spare conductors
for this same purpose.
ROV’s
Copyright © TWI Ltd
(Class 4) Towed or Bottom Crawling Vehicles.
The towed type has no propulsion but may be
manoeuvred by vanes. The bottom crawler
has tracks or wheels and drives along the
seabed.
(Class 5) Prototype or Development Vehicle.
These are vehicles under development or
special purpose vehicles that do not fit into
the other categories.
Copyright ©
Hydrodynamic Forces
The following will affect both the vessel and the ROV.
Wave action
Tidal effects
Currents
Wind
The vessel will have a designed thruster configuration that will
determine its actual operating parameters.
The ship’s master and watch officers will get to know their
vessel and will be able to position it to its best capabilities
within its design parameters.
Generally speaking ROV deployment is possible in slightly
more severe weather conditions than air divers.
Hydrodynamic Forces
Copyright © TWI Ltd
Effects on the ROV
The wave and wind action will initially affect the
launching and recovery of the vehicle.
The general methods for launching an ROV are:
Articulated HIAB type crane.
A-frame.
Fixed deployment cursor or guide wire system.
Crane and quick release hook.
Launching Systems
HIAB Type
This method does not require much deck space so has an
advantage on a smaller vessel.
There is easy access to the vehicle for maintenance or
repair.
A docking mechanism may be fitted which allows for a
smoother launch and recovery and the mechanism
responds quite quickly and is therefore handy in marginal
launch and recovery operations.
This system is usually limited in use to Class 2 vehicles.
Launching Systems
Copyright © TWI Ltd
A-frame Launching System
This system may be mounted on a skid,
mounted over the stern or mounted over the
side of the vessel depending on the weatherkeeping
characteristics of the support vessel.
There is easy access to the vehicle for
maintenance and repair.
A docking mechanism may be fitted.
Launching Systems
Copyright © TWI Ltd
Vehicle is suspended from the frame during
launch and recovery.
During marginal conditions the ROV may develop
a swing that risks damaging it and the A-frame,
which tends to limit the weather parameter.
This system may be used with any class of ROV.
Launching Systems
Copyright © TWI Ltd
Fixed Deployment Cursor Or Guide Wire System
This system is normally installed in a Moon Pool on a
purpose designed support vessel.
The whole system becomes dedicated to the vehicle in
use.
The launch and recovery may be possible in somewhat
more severe weather conditions than the other
systems.
Normally purpose designed facilities are
incorporated to allow easy access for
maintenance and repair.
There may be an issue in the event of the
vehicle becoming dead in the water, as it may
not be possible to recover it to the cursor.
This system is normally reserved for large
Class 3 ROV’s.
Launching Systems
Copyright © TWI Ltd
Crane and Quick Release Hook
A “go-getcha” or line release hook is attached to the ship’s
crane & the ROV is lifted over the side, once launched the
hook is released & the vehicle is free to dive.
The system does not have to be installed on the support
vessel and all that is required is a suitable crane.
There is easy access to the vehicle for maintenance and
repair and the vehicle can be placed anywhere on deck in
reach of the crane.
This system is more weather dependent than other methods.
Vehicle Affected by Hydrodynamic
Forces
The vehicle thruster configuration will determine how it
can react to the hydrodynamic forces acting on it.
There will be a maximum power output available for
thrusters and each thruster will also have a maximum
power consumption and output.
The vehicle has to maintain position in three dimensions
and try to deal with any wave surge when operating at
shallow depths. This may prove impossible at times and, in
marginal weather conditions, there is a limit to how
shallow any vehicle can operate even though it may be
safe to launch it.
Umbilical or Tether Management
System (TMS)
The greatest drag on the ROV will be due to the umbilical
or tether.
This in turn means that the greatest consideration must be
given as to how to minimise this.
Any currents at the work site will have marked affects on
the tether, to the extent that all thruster power may be
required on the fore and aft thrusters just to overcome the
drag force on the tether.
A TMS may be a ‘top hat’ or ‘garage’ system. Both have
advantages and disadvantages.
Umbilical or Tether Management
System (TMS)
Copyright © TWI Ltd
The top hat can recover a dead vehicle better
but the reeling system sometimes fouls up.
The garage gives better protection to the
vehicle but may interfere with some
maintenance tasks.
On the other hand any TMS will add
complications to the handling of the vehicle
while an umbilical only requires a winch and
keeps the system simple.
The advantages of a TMS are:
There is less drag on the tether.
The operational ‘footprint’ can be increased.
The weather window may be increased.
There is less likelihood of fouling the
umbilical in the ship’s thrusters.
The ROV will not be so subjected to heave
once released from the TMS.
Umbilical or Tether Management
System (TMS)
Copyright © TWI Ltd
When working on a pipeline the ROV gains from
using a TMS by:
Reducing umbilical drag.
Reducing heave.
Avoiding being pulled off during vessel manoeuvres.
When working on a structure the advantages
are:
Easier penetration into the structure.
Less heave at shallow depths.
Better manoeuvrability as the tether can be neutrally
buoyant causing little drag.