Lecture II 1
Lecture II 1
• PERT and CPM are the scheduling techniques which are used to plan, schedule and control a project consisting of
no. of inter-related activities. These techniques provide a frame which defines the job to be done, integrates them
in a logical sequence and provides a system of control over the progress of plan.
Objectives of CPM and PERT:
To plan, schedule and control the project consisting of a no. of inter related activities.
To define and integrate the tasks in a logical sequence.
These techniques show the precedence relationship.
Sequence of operation can be known.
To focus management attention on the most critical activities.
To know the progress of the work as related to the scheduling timing.
To plan the best possible use of resources to achieve a given goal within overall time and cost limitations.
It provides the basis for determining manpower, material and capital requirement.
Network analysis helps in designing, planning, co-ordinating, controlling and decision making in order to accomplish
the project economically in the minimum available time with the limited resources.
4 The use of dummy activity is required for representing the No dummy activity
proper sequencing
5 PERT basically does not demarcate between critical and CPM marks the critical activity
noncritical activity
6 PERT is applied in projects where resources are always CPM in applied to projects where minimum overall cost
available is the prime importance.
7 PERT is suitable in defense project & R &D, where activity Suitable for plant maintenance, civil construction projects
time can't be readily predicted etc. where activity duration is known.
Rules for Network Construction
The network should have a unique starting node (tail event) and unique completion node (head event).
No activity should be represented by more than one arrow (→) in the network.
No two activities should have the same starting node and same ending node.
Dummy activity is an imaginary activity indicating precedent relationship only. Duration of dummy activity is zero.
The length of arrow bear no relationship to activity time.
The arrow in a network identifies the logical condition of dependence.
The direction of arrow indicates the direction of work flow.
All networks are constructed logically or based on the principal of dependency.
No event can be reached in a project before the completion of precedence activity.
Every activity in the network should be completed to reach the objective.
No set of activities should form a circular loop.
• Example
A project consists of the following activities and time estimates.
Construct the network. Determine the expected task time. Show the critical path. What is the project duration.
• Assignment
A project schedule has the following characteristics:
Activity 1-2 1-4 1-7 2-3 3-6 4-5 4-8 5-6 6-9 7-8 8-9
Duration (days) 2 2 1 4 1 5 8 4 3 5 5
Construct the network and locate the critical path. Calculate the various time estimates and floats.