Balance
Balance
13)
• Content: The Engineer's final determination of the net balance due between
parties. Issued after Final/Partially Agreed Statement and Discharge are received.
o If Contractor still fails within 28 days of request, Engineer issues FPC for
amount Engineer fairly considers due.
Slide 94: Sub-Clause 14.14 - Conditions for Liability to Cease (Claim Inclusion)
• Content: Employer not liable for any matter/thing under Contract unless Contractor
included an amount expressly for it in:
o (a) The Final Statement or Partially Agreed Final Statement [cite: 2, 310(a)].
o (b) AND (except for post-TOC matters) the Statement at Completion (14.10)
[cite: 2, 311(b)].
Slide 95: Sub-Clause 14.14 - Conditions for Liability to Cease (Post-FPC Claim)
• Content: Unless Contractor makes a Claim under 20.2 regarding FPC amounts
within 56 days of receiving FPC copy, Contractor deemed to have accepted FPC
amounts. Employer then has no further liability, other than paying FPC balance &
returning Performance Security.
o Fraud by Employer.
o Gross negligence by Employer.
• Content:
o Promotes finality.
o Contractor must dispute FPC via Claim within 56 days or accepts it.
• Content: Governs payment currencies, proportions, and exchange rates, crucial for
international projects. Ensures transparency and manages FX risk.