9 - Work Inspection Request (WIR)

The document is a Work Inspection Request Register for the AF190 - ADNEC-Residences project, detailing a total of 925 requests with 845 in the latest status. It includes various inspection requests related to civil works, their submission and return dates, and their current action codes. The majority of requests are approved or approved as noted, with a few requiring revisions or under review.

Uploaded by

suman das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views55 pages

9 - Work Inspection Request (WIR)

The document is a Work Inspection Request Register for the AF190 - ADNEC-Residences project, detailing a total of 925 requests with 845 in the latest status. It includes various inspection requests related to civil works, their submission and return dates, and their current action codes. The majority of requests are approved or approved as noted, with a few requiring revisions or under review.

Uploaded by

suman das
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 55

AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE

1 AF190-CVL-WIR-001 00 Latest Inspection Request for Plot Limit 2m Corners offser CVL Al Firas 11-Mar-22 13-Mar-22 C C 2

2 AF190-CVL-WIR-002 00 Superseded Inspection Request for Setting Out Sign Board Foundation CVL Al Firas 27-Mar-22 29-Mar-22 C C 2

3 AF190-CVL-WIR-002 01 Latest Inspection Request for Setting Out Sign Board Foundation CVL Al Firas 30-Mar-22 1-Apr-22 B B 2

4 AF190-CVL-WIR-003 00 Latest Inspection Request for Guid Wall Steel Renforcement 1 to 70 & 452 to 492 CVL Al Firas 27-Mar-22 1-Apr-22 B B 5

5 AF190-CVL-WIR-004 00 Latest Inspection Request for Setting Out Sign Board Foundation 1 to 70 & 452 to 492 CVL Al Firas 27-Mar-22 1-Apr-22 C C 5

6 AF190-CVL-WIR-005 00 Latest Inspection Request for Setting out of Guid Wall 452to380 CVL Al Firas 3-Apr-22 4-Apr-22 B B 1

7 AF190-CVL-WIR-006 00 Latest Inspection Request for Guid Wall Steel Reinforcement Pile 452to380 CVL Al Firas 3-Apr-22 4-Apr-22 B B 1

8 AF190-CVL-WIR-007 00 Latest Inspection Request for Setting Out of Shoring H-beam CVL Al Firas 4-Apr-22 7-Apr-22 B B 3

9 AF190-CVL-WIR-008 00 Latest Inspection Request for Rebar and formwork of Signboard Foundation CVL Al Firas 4-Apr-22 7-Apr-22 B B 3

10 AF190-CVL-WIR-009 00 Latest Inspection request for installation of Anchor bolts and form work of Sign board Foundation prior to start concrete CVL Al Firas 4-Apr-22 7-Apr-22 B B 3

11 AF190-CVL-WIR-010 00 Latest Inspection request for Guide Wal Reinforcement from Pile Number 148 to 204 Prior to Start Concrete CVL Al Firas 7-Apr-22 10-Apr-22 B B 3

12 AF190-CVL-WIR-011 00 Latest Inspection request for Guide Wall Reinforcement from Pile 325 to 379 CVL Al Firas 8-Apr-22 11-Apr-22 B B 3

13 AF190-CVL-WIR-012 00 Latest Inspection request for Guide Wall Reinforcement from Pile Number 214 to 272 Prior to Start Concrete CVL Al Firas 11-Apr-22 13-Apr-22 B B 2

14 AF190-CVL-WIR-013 00 Latest Inspection request for Closing Site Observation Report( Ref. AND-PEC-SOR-CIV-001) CVL Al Firas 11-Apr-22 14-Apr-22 B B 3

15 AF190-CVL-WIR-014 00 Latest Inspection request for Completion of Steel Structure Signboard CVL Al Firas 11-Apr-22 14-Apr-22 B B 3

16 AF190-CVL-WIR-015 00 Latest Inspection request for Setting Out of Guide wall and Reinforcement from Pile 273 to 294&302 to 326 CVL Al Firas 12-Apr-22 14-Apr-22 B B 2

17 AF190-CVL-WIR-016 00 Latest Inspection request for Installation of Sleeve 4 Steel Pipe for Dewatering at Pile Number 445 CVL Al Firas 13-Apr-22 14-Apr-22 B B 1

18 AF190-CVL-WIR-017 00 Latest Inspection request for Installtion of Sleeve No. 04 4 Steel Pipe for Dewarting at Pile Number 45 CVL Al Firas 17-Apr-22 19-Apr-22 B B 2

19 AF190-CVL-WIR-018 00 Latest Inspection request for Setting Out of Guie Wall and Reinforcement from Pile No. 245-248 CVL Al Firas 18-Apr-22 20-Apr-22 B B 2

20 AF190-CVL-WIR-019 00 Latest Inspection request for Installaton of Sleeve No. 05 4 Steel Pipe for Dewatering at Pile No. 475 CVL Al Firas 18-Apr-22 20-Apr-22 B B 2

21 AF190-CVL-WIR-020 00 Latest Inspection request for Setting Out of Guide Wall and Reinforcement from Pile 295 to 301 CVL Al Firas 22-Apr-22 22-Apr-22 B B 0

22 AF190-CVL-WIR-021 00 Latest Inspection request for Installation of SW 200mm Steel Casing SW-01 for Dewatering at Pile 101 CVL Al Firas 22-Apr-22 25-Apr-22 B B 3

23 AF190-CVL-WIR-022 00 Latest Inspection request for Installation of IP Camera CVL Al Firas 26-Apr-22 6-May-22 B B 10

24 AF190-CVL-WIR-023 00 Latest Inspection request for Installation of Sleeve 4 Steel Pipe Dewatering at Pile Number 61 CVL Al Firas 26-Apr-22 28-Apr-22 B B 2

25 AF190-CVL-WIR-024 00 Latest Inspection request for Sleeve no. 01 (4 Steel Pipe) for Dewatering at Pile Number - 137 CVL Al Firas 27-Apr-22 6-May-22 B B 9

26 AF190-CVL-WIR-025 00 Latest Inspection request for Sleeve no. 02 (4" Steel Pipe) & SW-02, 200mm Steel Casting for Dewatering at Pile Number - 115 & 347 CVL Al Firas 4-May-22 9-May-22 B B 5

27 AF190-CVL-WIR-026 00 Latest Inspection request for Sleeve no. 07 (4" Steel Pipe) for Dewatering at Pile Number - 315 CVL Al Firas 8-May-22 9-May-22 B B 1

28 ADN-AFC-WIR-CIV-027 00 Latest Inspection of Closing Site Observation Report (Ref. No.: AND-PEC-SOR-CIV-003) CVL Al Firas 10-May-22 12-May-22 B B 2

29 ADN-AFC-WIR-CIV-028 00 Latest Inspection of Closing Site Observation Report (Ref. No.: AND-PEC-SOR-CIV-002) CVL Al Firas 10-May-22 17-May-22 B B 7
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
30 ADN-AFC-WIR-CIV-029 00 Latest Inspection for Installation of Sleeve for Dewaterign at Pile 291 CVL Al Firas 11-May-22 17-May-22 B B 6

31 ADN-AFC-WIR-CIV-030 00 Latest Inspection for Setting out of guide wall & reinformcent from Pile 205 to 213 prior to start concrete CVL Al Firas 18-May-22 22-May-22 B B 4

32 ADN-AFC-WIR-CIV-031 00 Latest Inspection for Installation of Sleeve-09 (4" Steel Pipe) for dewatering at pile 223 CVL Al Firas 19-May-22 22-May-22 B B 3

33 ADN-AFC-WIR-CIV-032 00 Superseded Inspection for Site Office layout CVL Al Firas 19-May-22 30-May-22 C C 11

34 ADN-AFC-WIR-CIV-032 01 Latest Inspection for Site Office layout CVL Al Firas 1-Jun-22 2-Jun-22 B B 1

35 ADN-AFC-WIR-CIV-033 00 Latest Inspection for Furniture Layout CVL Al Firas 19-May-22 2-Jun-22 B B 14

Submitted via ADN-AFC-SOC-


36 ADN-AFC-WIR-CIV-034 00 Latest Inspection for Closing Site Observation Report (ref. No. AND-PEC-SOR-CIV-004) CVL Al Firas 25-May-22 31-May-22 C C
0004
6

37 ADN-AFC-WIR-CIV-035 00 Latest Inspection for Setting out and Drilling Depth prior to start installation of dewatering pipes (DW-09, 10 & 11) CVL Al Firas 29-May-22 1-Jun-22 B B 3

38 ADN-AFC-WIR-CIV-036 00 Superseded Inspection for Installation of dewatering pipes (DW-09, 10 & 11) CVL Al Firas 29-May-22 1-Jun-22 C C 3

39 ADN-AFC-WIR-CIV-036 01 Latest Inspection for Installation of dewatering pipes (DW-09, 10 & 11) CVL Al Firas 2-Jun-22 5-Jun-22 B B 3

40 ADN-AFC-WIR-CIV-037 00 Superseded Inspection for Installation of Project Signboard CVL Al Firas 31-May-22 2-Jun-22 C C 2

41 ADN-AFC-WIR-CIV-037 01 Superseded Inspection for Installation of Project Signboard CVL Al Firas 5-Jun-22 12-Jun-22 C C 7

42 ADN-AFC-WIR-CIV-037 02 Latest Inspection for Installation of Project Signboard CVL Al Firas 12-Jun-22 17-Jun-22 B B 5

43 ADN-AFC-WIR-CIV-038 00 Latest Inspection for Setting out and Drilling depth prior to start installation of dewatering pipes (DW-09 & 10) CVL Al Firas 2-Jun-22 5-Jun-22 B B 3

44 ADN-AFC-WIR-CIV-039 00 Latest Inspection for marking of Cut-Off Levels for Secant Piles CVL Al Firas 12-Jun-22 14-Jun-22 B B 2

45 ADN-AFC-WIR-CIV-040 00 Latest Inspection for Complete Installation of Project Sign Board CVL Al Firas 14-Jun-22 17-Jun-22 B B 3

46 ADN-AFC-WIR-CIV-041 00 Latest Inspection for Marking of Cut-Off Levels for Secant Piles CVL Al Firas 17-Jun-22 20-Jun-22 B B 3

47 ADN-AFC-WIR-CIV-042 00 Superseded Inspection for Completed Secant Pile Head Breaking CVL Al Firas 17-Jun-22 20-Jun-22 C C 3

48 ADN-AFC-WIR-CIV-042 01 Latest Inspection for Completed Secant Pile Head Breaking CVL Al Firas 21-Jun-22 23-Jun-22 B B 2

49 ADN-AFC-WIR-CIV-043 00 Superseded Inspection for Completed Installation Temporary Deep Wells, DW-9 DW-10 DW-11 CVL Al Firas 17-Jun-22 20-Jun-22 C C 3

50 ADN-AFC-WIR-CIV-043 01 Superseded Inspection for Completed Installation Temporary Deep Wells, DW-9 DW-10 DW-11 CVL Al Firas 22-Jul-22 24-Jul-22 C C 2

51 ADN-AFC-WIR-CIV-043 02 Latest Inspection for Completed Installation Temporary Deep Wells, DW-9 DW-11 CVL Al Firas 26-Jul-22 29-Jul-22 B B 3

52 ADN-AFC-WIR-CIV-044 00 Latest Inspection for Installation of Temporary Well Points CVL Al Firas 17-Jun-22 20-Jun-22 B B 3

53 ADN-AFC-WIR-CIV-045 00 Latest Inspection for Setting out and Permanent Deep Well Drilling for DW-7 & DW-8 CVL Al Firas 19-Jun-22 22-Jun-22 B B 3

54 ADN-AFC-WIR-CIV-046 00 Latest Inspection for Removal of Rusted H-Beams at Site CVL Al Firas 19-Jun-22 20-Jun-22 B B 1

55 ADN-AFC-WIR-CIV-047 00 Superseded Inspection for Casting of PCC for Capping Beams at Shoring Piles CVL Al Firas 20-Jun-22 22-Jun-22 C C 2

56 ADN-AFC-WIR-CIV-047 01 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (from 1 to 23, & From 492 to 463) CVL Al Firas 24-Jun-22 28-Jun-22 B B 4

57 ADN-AFC-WIR-CIV-048 00 Latest Inspection for Completed Installation of Temporary Pipe at Deep Wells, DW-7 & DW-8 CVL Al Firas 21-Jun-22 23-Jun-22 B B 2

58 ADN-AFC-WIR-CIV-049 00 Latest Inspection for Casting of PCC Capping Beams at Shoring Piles (from 463 to 454) CVL Al Firas 22-Jun-22 23-Jun-22 B B 1

59 ADN-AFC-WIR-CIV-050 00 Latest Inspection for Marking of Cut-off Levels for Secant Piles CVL Al Firas 22-Jun-22 23-Jun-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
60 ADN-AFC-WIR-CIV-051 00 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (from 452 to 442) CVL Al Firas 24-Jun-22 28-Jun-22 B B 4

61 ADN-AFC-WIR-CIV-052 00 Latest Inspection for Setting out and Permanent Deep Well Drilling for DW-7 CVL Al Firas 26-Jun-22 28-Jun-22 B B 2

62 ADN-AFC-WIR-CIV-053 00 Latest Inspection for Marking of Cut-off Levels for Secant Piles (44 to 54) CVL Al Firas 26-Jun-22 28-Jun-22 B B 2

63 ADN-AFC-WIR-CIV-054 00 Superseded Inspection for Casting of PCC for Capping Beams at Shoring Piles (453 & 443 to 416) CVL Al Firas 27-Jun-22 28-Jun-22 C C 1

64 ADN-AFC-WIR-CIV-054 01 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (453 & 443 to 416) CVL Al Firas 12-Jul-22 13-Jul-22 A A 1

65 ADN-AFC-WIR-CIV-055 00 Latest Inspection for Marking of Cut-off Levels for Secant Piles (380 to 360) CVL Al Firas 28-Jun-22 28-Jun-22 B B 0

66 ADN-AFC-WIR-CIV-056 00 Latest Inspection for Completed Secant Pile Head breaking (24 to 43) CVL Al Firas 26-Jun-22 28-Jun-22 B B 2

67 ADN-AFC-WIR-CIV-057 00 Latest Inspection for Completed Secant Pile Head Breaking (464 to 439) CVL Al Firas 26-Jun-22 28-Jun-22 B B 2

68 ADN-AFC-WIR-CIV-058 00 Superseded Inspection for Completed Installation of reinforcement for Capping Beams (Pile 1 to 17 & Pile 492 to 475) CVL Al Firas 26-Jun-22 28-Jun-22 C C 2

69 ADN-AFC-WIR-CIV-058 01 Latest Inspection for Completed Installation of reinforcement for Capping Beams (Pile 1 to 22 & Pile 492 to 476) CVL Al Firas 12-Jul-22 13-Jul-22 B B 1

70 ADN-AFC-WIR-CIV-059 00 Latest Inspection for Completed Secant Pile Head Breaking (416 to 438) CVL Al Firas 28-Jun-22 30-Jun-22 B B 2

71 ADN-AFC-WIR-CIV-060 00 Superseded Inspection for Completed Secant Pile Head Breaking (415 to 372) CVL Al Firas 28-Jun-22 3-Jul-22 C C 5

72 ADN-AFC-WIR-CIV-060 01 Latest Inspection for Completed Secant Pile Head Breaking (415 to 372) CVL Al Firas 12-Jul-22 13-Jul-22 B B 1

73 ADN-AFC-WIR-CIV-061 00 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (24 to 44) CVL Al Firas 28-Jun-22 30-Jun-22 B B 2

74 ADN-AFC-WIR-CIV-062 00 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (415 to 380) CVL Al Firas 28-Jun-22 1-Jul-22 B B 3

75 ADN-AFC-WIR-CIV-063 00 Latest Inspection for Surveying Works & Setting-out of Capping Beams (Pile 1 to 17 & Pile 492 to 476) CVL Al Firas 29-Jun-22 3-Jul-22 B B 4

76 ADN-AFC-WIR-CIV-064 00 Latest Inspection for Installation and Fixation of Shuttering & Formworks for Capping Beams (Pile 1 to 17 & Pile 492 to 476) CVL Al Firas 29-Jun-22 3-Jul-22 B B 4

77 ADN-AFC-WIR-CIV-065 00 Latest Inspection for Installation and Fixation of Construction Joints for Capping Beams (Pile 17 & Pile 476) CVL Al Firas 29-Jun-22 3-Jul-22 B B 4

78 ADN-AFC-WIR-CIV-066 00 Latest Inspection for Marking of Cut-off levels for Secant Piles (55 to 59) CVL Al Firas 29-Jun-22 3-Jul-22 B B 4

79 ADN-AFC-WIR-CIV-067 00 Latest Inspection for Completed Secant Piles vertical Reinforcement Cut-off (Pile 1 to 17 & Pile 492 to 476) CVL Al Firas 29-Jun-22 1-Jul-22 B B 2

80 ADN-AFC-WIR-CIV-068 00 Latest Inspection for Completed Secant Pile head Breaking (Pile 44 to 59) CVL Al Firas 29-Jun-22 3-Jul-22 B B 4

81 ADN-AFC-WIR-CIV-069 00 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (44 to 59) CVL Al Firas 29-Jun-22 3-Jul-22 B B 4

82 ADN-AFC-WIR-CIV-070 00 Superseded Inspection for Setting out and permanent Deep Well Drilling for DW-1 & DW-2 CVL Al Firas 30-Jun-22 3-Jul-22 C C 3

83 ADN-AFC-WIR-CIV-070 01 Latest Inspection for Setting out and permanent Deep Well Drilling for DW-1 CVL Al Firas 12-Jul-22 14-Jul-22 B B 2

84 ADN-AFC-WIR-CIV-071 00 Superseded Inspection for Completed Installation of Temporary Deep Wells at Dw-2 & DW-7 CVL Al Firas 30-Jun-22 3-Jul-22 C C 3

85 ADN-AFC-WIR-CIV-071 01 Latest Inspection for Completed Installation of Temporary Deep Wells at Dw-1 & DW-7 CVL Al Firas 12-Jul-22 14-Jul-22 B B 2

86 ADN-AFC-WIR-CIV-072 00 Superseded Inspection for Completed Secant Pile Head Breaking (371 to 366) CVL Al Firas 30-Jun-22 3-Jul-22 C C 3

87 ADN-AFC-WIR-CIV-072 01 Latest Inspection for Completed Secant Pile Head Breaking (371 to 366) CVL Al Firas 12-Jul-22 13-Jul-22 B B 1

88 ADN-AFC-WIR-CIV-073 00 Latest Inspection for Marking of Cut-Off Levels for Secant Piles (Pile 361 to 341) & (Pile 60 - 93) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

89 ADN-AFC-WIR-CIV-074 00 Latest Inspection for Completed Secant Pile Head Breaking (from Pile 60 to 76) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
90 ADN-AFC-WIR-CIV-075 00 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (from Pile 60 to 76) CVL Al Firas 4-Jul-22 6-Jul-22 A A 2

91 ADN-AFC-WIR-CIV-076 00 Latest Inspection for Casting of PCC for Capping Beams at Shoring Piles (from Pile 379 to 364) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

92 ADN-AFC-WIR-CIV-077 00 Latest Inspection for Completed Secant Piles Vertical Reinforcement Cut-Off (From Pile 476 to 443) CVL Al Firas 4-Jul-22 6-Jul-22 A A 2

93 ADN-AFC-WIR-CIV-078 00 Latest Inspection for Installation of Reinforcement for Capping Beams (from Pile 476 to 443) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

94 ADN-AFC-WIR-CIV-079 00 Latest Inspection for Installation and Fixation of Construction Joints for Capping Beams (Pile 476 & Pile 443) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

95 ADN-AFC-WIR-CIV-080 00 Latest Inspection for Installation anf Fixation of Shuttering & Formworks for Capping Beams (from Pile 476 to 443) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

96 ADN-AFC-WIR-CIV-081 00 Latest Inspection for Surveying Works & Setting-out of Capping Beams prior to Casting Concrete (from Pile 476 to 443) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

97 ADN-AFC-WIR-CIV-082 00 Latest Inspection for Completed Secant Pile Head Breaking (from Pile 77 to 86) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

98 ADN-AFC-WIR-CIV-083 00 Latest Inspection for Marking of Cut-off Levels for Secant Piles (Pile 342 to 321 & Pile 184-232) CVL Al Firas 4-Jul-22 6-Jul-22 B B 2

99 ADN-AFC-WIR-CIV-084 00 Latest Inspection for Installation of Reinforcement for Capping beams (from Pile 443 to 395) CVL Al Firas 6-Jul-22 12-Jul-22 B B 6

100 ADN-AFC-WIR-CIV-085 00 Latest Inspection for Installation and Fixation of Construction Joint for Capping Beam (from Pile 443 to 395) CVL Al Firas 6-Jul-22 12-Jul-22 A A 6

101 ADN-AFC-WIR-CIV-086 00 Latest Inspection for Installation and Fixation of Shuttering & Formworks for Capping Beam (from Pile 443 to 395) CVL Al Firas 6-Jul-22 13-Jul-22 B B 7

102 ADN-AFC-WIR-CIV-087 00 Latest Inspection for Surveying Works and Setting-Out of Capping Beam prior to casting concrete (from Pile 443 to 395) CVL Al Firas 6-Jul-22 13-Jul-22 B B 7

103 ADN-AFC-WIR-CIV-088 00 Latest Inspection for Completed Secant Piles Vertical Reinforcement Cut-Off (from Pile 443 to 395) CVL Al Firas 6-Jul-22 12-Jul-22 A A 6

104 ADN-AFC-WIR-CIV-089 00 Latest Inspection for Reinforcement for Capping Beam (from Pile 22 to 68) CVL Al Firas 6-Jul-22 12-Jul-22 B B 6

105 ADN-AFC-WIR-CIV-090 00 Latest Inspection for Installation and Fixation of Construction Joint for Capping Beam (from Pile 22 to 68) CVL Al Firas 6-Jul-22 12-Jul-22 A A 6

106 ADN-AFC-WIR-CIV-091 00 Latest Inspection for Installation and Fixation of Shuttering & Formworks for Capping Beam (from Pile 22 to 68) CVL Al Firas 6-Jul-22 13-Jul-22 B B 7

107 ADN-AFC-WIR-CIV-092 00 Latest Inspection for Surveying Works & Setting-Out of Capping Beam prior to casting concrete (from Pile 22 to 68) CVL Al Firas 6-Jul-22 12-Jul-22 B B 6

108 ADN-AFC-WIR-CIV-093 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-Off (from Pile 22 to 68) CVL Al Firas 6-Jul-22 12-Jul-22 B B 6

109 ADN-AFC-WIR-CIV-094 00 Superseded Inspection for Installation of Reinforcement for Capping Beam (from Pile 395 to 360) CVL Al Firas 6-Jul-22 14-Jul-22 C C 8

110 ADN-AFC-WIR-CIV-094 01 Latest Inspection for Installation of Reinforcement for Capping Beam (from Pile 395 to 360) CVL Al Firas 15-Jul-22 18-Jul-22 B B 3

111 ADN-AFC-WIR-CIV-095 00 Superseded Inspection for Installation and Fixation of Construction Joint for Capping Beam (from Pile 395 to 360) CVL Al Firas 6-Jul-22 14-Jul-22 C C 8

112 ADN-AFC-WIR-CIV-095 01 Latest Inspection for Installation and Fixation of Construction Joint for Capping Beam (from Pile 395 to 360) CVL Al Firas 15-Jul-22 18-Jul-22 B B 3

113 ADN-AFC-WIR-CIV-096 00 Superseded Inspection for Installation and Fixation of Shuttering & Formworks for Capping Beam (from Pile 395 to 360) CVL Al Firas 6-Jul-22 14-Jul-22 C C 8

114 ADN-AFC-WIR-CIV-096 01 Latest Inspection for Installation and Fixation of Shuttering & Formworks for Capping Beam (from Pile 395 to 360) CVL Al Firas 15-Jul-22 18-Jul-22 B B 3

115 ADN-AFC-WIR-CIV-097 00 Superseded Inspection for Surveying Works & Setting-Out of Capping Beam prior to casting concrete (from Pile 395 to 360) CVL Al Firas 6-Jul-22 14-Jul-22 C C 8

116 ADN-AFC-WIR-CIV-097 01 Latest Inspection for Surveying Works & Setting-Out of Capping Beam prior to casting concrete (from Pile 395 to 360) CVL Al Firas 15-Jul-22 18-Jul-22 B B 3

117 ADN-AFC-WIR-CIV-098 00 Superseded Inspection for Completed Secant Pile Vertical Reinforcement Cut-Off (from Pile 395 to 360) CVL Al Firas 6-Jul-22 14-Jul-22 C C 8

118 ADN-AFC-WIR-CIV-098 01 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-Off (from Pile 395 to 360) CVL Al Firas 15-Jul-22 18-Jul-22 B B 3

119 ADN-AFC-WIR-CIV-099 00 Latest Inspection for Installation of Reinforcement for Capping Beam (from Pile 68 to 100) CVL Al Firas 12-Jul-22 14-Jul-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
120 ADN-AFC-WIR-CIV-100 00 Latest Inspection for Construction Joint for Capping Beam (from Pile 100) CVL Al Firas 12-Jul-22 14-Jul-22 B B 2

121 ADN-AFC-WIR-CIV-101 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (from Pile 68 to 100) CVL Al Firas 12-Jul-22 14-Jul-22 B B 2

122 ADN-AFC-WIR-CIV-102 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-Off (from Pile 68 to 100) CVL Al Firas 12-Jul-22 14-Jul-22 B B 2

123 ADN-AFC-WIR-CIV-103 00 Latest Inspection for Survey Works and Setting-out of Capping Beam prior to casting of concrete (from Pile 68 to 100) CVL Al Firas 12-Jul-22 14-Jul-22 B B 2

124 ADN-AFC-WIR-CIV-104 00 Superseded Inspection for Completed Installation and Fixation of Fire fighting Pumps and Fire Fighting System for office Area CVL Al Firas 12-Jul-22 12-Jul-22 C C 0

125 ADN-AFC-WIR-CIV-104 01 Latest Inspection for Completed Installation and Fixation of Fire fighting Pumps and Fire Fighting System for office Area CVL Al Firas 1-Aug-22 2-Aug-22 B B 1

126 ADN-AFC-WIR-CIV-105 00 Latest Inspection for Marking of Cut-off Levels for Secant Piles (Pile 233 to 320) CVL Al Firas 13-Jul-22 14-Jul-22 B B 1

127 ADN-AFC-WIR-CIV-106 00 Superseded Inspection for Marking of Cut-off Levels for Secant Piles (Pile 94 to 108) CVL Al Firas 13-Jul-22 14-Jul-22 C C 1

128 ADN-AFC-WIR-CIV-106 01 Latest Inspection for Marking of Cut-off Levels for Secant Piles (Pile 94 to 111) CVL Al Firas 22-Jul-22 24-Jul-22 B B 2

129 ADN-AFC-WIR-CIV-107 00 Latest Inspection for Completed Secant Pile Head Breaking (from Pile 334 to 365) CVL Al Firas 18-Jul-22 21-Jul-22 B B 3

130 ADN-AFC-WIR-CIV-108 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from Pile 180 to 224) CVL Al Firas 18-Jul-22 21-Jul-22 A A 3

131 ADN-AFC-WIR-CIV-109 00 Latest Inspection for Setting-out and Permanent Deep Well Drilling for DW-3 CVL Al Firas 18-Jul-22 20-Jul-22 B B 2

132 ADN-AFC-WIR-CIV-110 00 Latest Inspection for Marking of Cut-Off Levels for Secant Piles (from Pile 180 to 184) CVL Al Firas 18-Jul-22 21-Jul-22 B B 3

133 ADN-AFC-WIR-CIV-111 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from Pile 365 to 307) CVL Al Firas 18-Jul-22 21-Jul-22 A A 3

134 ADN-AFC-WIR-CIV-112 00 Latest Inspection for Completed Secant Pile Head Breaking (from Pile 333 to 307) CVL Al Firas 18-Jul-22 21-Jul-22 B B 3

135 ADN-AFC-WIR-CIV-113 00 Latest Inspection for Installation of Reinforcement for Capping Beam (from Pile 361 to 339) CVL Al Firas 18-Jul-22 21-Jul-22 B B 3

136 ADN-AFC-WIR-CIV-114 00 Latest Inspection for Installation of Construction Joint for Capping Beam (Pile 339) CVL Al Firas 18-Jul-22 21-Jul-22 A A 3

137 ADN-AFC-WIR-CIV-115 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (from Pile 361 to 339) CVL Al Firas 18-Jul-22 21-Jul-22 B B 3

138 ADN-AFC-WIR-CIV-116 00 Latest Inspection for Survey Works and Setting-out of Capping Beam prior to Casting of Concrete (from Pile 361 to 339) CVL Al Firas 18-Jul-22 21-Jul-22 B B 3

139 ADN-AFC-WIR-CIV-117 00 Latest Inspection for Completed Secant Pile Virtical Reinforcement Cut-Off (from Pile 361 to 339) CVL Al Firas 18-Jul-22 21-Jul-22 A A 3

140 ADN-AFC-WIR-CIV-118 00 Superseded Inspection for Installation of Reinforcement for Capping Beam (from pile 191 to 224) CVL Al Firas 19-Jul-22 24-Jul-22 C C 5

141 ADN-AFC-WIR-CIV-118 01 Latest Inspection for Installation of Reinforcement for Capping Beam (from pile 191 to 224) CVL Al Firas 26-Jul-22 29-Jul-22 B B 3

142 ADN-AFC-WIR-CIV-119 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-off (from pile 191 to 224) CVL Al Firas 19-Jul-22 21-Jul-22 A A 2

143 ADN-AFC-WIR-CIV-120 00 Latest Inspection for Installation of Reinforcement for Capping Beam (from Pile 338 to 305) CVL Al Firas 20-Jul-22 21-Jul-22 B B 1

144 ADN-AFC-WIR-CIV-121 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-Off (from Pile 338 to 305) CVL Al Firas 20-Jul-22 21-Jul-22 B B 1

145 ADN-AFC-WIR-CIV-122 00 Latest Inspection for Installation of Construction Joint for Capping Beam (from Pile 338 to 305) CVL Al Firas 20-Jul-22 21-Jul-22 B B 1

146 ADN-AFC-WIR-CIV-123 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (from Pile 338 to 305) CVL Al Firas 20-Jul-22 21-Jul-22 B B 1

147 ADN-AFC-WIR-CIV-124 00 Latest Inspection for Survey Works and Setting-out Capping Beam Prior to Casting of Concrete (from Pile 338 to 305) CVL Al Firas 20-Jul-22 21-Jul-22 B B 1

148 ADN-AFC-WIR-CIV-125 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (from Pile 191 to 224) CVL Al Firas 20-Jul-22 26-Jul-22 B B 6

149 ADN-AFC-WIR-CIV-126 00 Latest Inspection for Survey Works and Setting-out of Capping Beam Prior to Casting Concrete (from Pile 191 to 224) CVL Al Firas 20-Jul-22 26-Jul-22 B B 6
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
150 ADN-AFC-WIR-CIV-127 00 Latest Inspection for Installation of Construction Joint for Capping Beam (from Pile 191 to 224) CVL Al Firas 20-Jul-22 25-Jul-22 B B 5

151 ADN-AFC-WIR-CIV-128 00 Superseded Inspection for FDT Test at backfilled Area outside Capping Beam CVL Al Firas 22-Jul-22 24-Jul-22 C C 2

152 ADN-AFC-WIR-CIV-128 01 Latest Inspection for FDT Test at backfilled Area outside Capping Beam CVL Al Firas 25-Jul-22 27-Jul-22 B B 2

153 ADN-AFC-WIR-CIV-129 00 Latest Inspection for Completed Secant Pile Head Breaking (from Pile 264 to 306 & Pile 180 to 235) CVL Al Firas 22-Jul-22 24-Jul-22 B B 2

154 ADN-AFC-WIR-CIV-130 00 Latest Inspection for Completed Secant Pile head Breaking (from Pile 87 to 111) CVL Al Firas 22-Jul-22 24-Jul-22 B B 2

155 ADN-AFC-WIR-CIV-131 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from Pile 264 to 308) CVL Al Firas 22-Jul-22 24-Jul-22 A A 2

156 ADN-AFC-WIR-CIV-132 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from Pile 234 to 255) CVL Al Firas 22-Jul-22 24-Jul-22 A A 2

157 ADN-AFC-WIR-CIV-133 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (ffrom Pile 225 to 233) CVL Al Firas 22-Jul-22 24-Jul-22 A A 2

158 ADN-AFC-WIR-CIV-134 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from Pile 257 to 263) CVL Al Firas 22-Jul-22 25-Jul-22 A A 3

159 ADN-AFC-WIR-CIV-135 00 Latest Inspection for Setting out and permanent Deep Well Drilling for DW-6 and Dw-10 CVL Al Firas 24-Jul-22 25-Jul-22 B B 1

160 ADN-AFC-WIR-CIV-136 00 Latest Inspection for Marking of Cut-off Levels for Secant Piles (from Pile 180 to 150 & Pile 112 to 149) CVL Al Firas 24-Jul-22 25-Jul-22 B B 1

161 ADN-AFC-WIR-CIV-137 00 Latest Inspection for Completed Secant Pile head Breaking (from Pile 112 to 118) CVL Al Firas 24-Jul-22 25-Jul-22 B B 1

162 ADN-AFC-WIR-CIV-138 00 Latest Inspection for Completed Casting of PCC for Capping beams at Shoring Piles (from Pile 181 to 165) CVL Al Firas 24-Jul-22 25-Jul-22 A A 1

163 ADN-AFC-WIR-CIV-139 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from Pile 77 to 108) CVL Al Firas 24-Jul-22 25-Jul-22 A A 1

164 ADN-AFC-WIR-CIV-140 00 Latest Inspection for Installation of Reinforcement for Capping Beam Pile 305 to 253 CVL Al Firas 28-Jul-22 1-Aug-22 B B 4

165 ADN-AFC-WIR-CIV-141 00 Latest Inspection for Construction Joint for Capping Beam (Pile 305 to 253) CVL Al Firas 28-Jul-22 1-Aug-22 A A 4

166 ADN-AFC-WIR-CIV-142 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (Pile 305 to 253) CVL Al Firas 28-Jul-22 1-Aug-22 B B 4

167 ADN-AFC-WIR-CIV-143 00 Latest Inspection for Survey Works and Setting-out of Capping Beam prior to Casting of Concrete (Pile 305 to 253) CVL Al Firas 28-Jul-22 1-Aug-22 B B 4

168 ADN-AFC-WIR-CIV-144 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-off (Pile 305 to 253) CVL Al Firas 28-Jul-22 1-Aug-22 B B 4

169 ADN-AFC-WIR-CIV-145 00 Latest Inspection for Installation of Reinforcement for Capping Beam (Pile 79 to 100) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

170 ADN-AFC-WIR-CIV-146 00 Latest Inspection for Installation of Construction joint for Capping Beam (Pile 79 to 100) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

171 ADN-AFC-WIR-CIV-147 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (Pile 79 to 100) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

172 ADN-AFC-WIR-CIV-148 00 Latest Inspection for Survey Works and Setting-out of Capping Beam Prior to Casting of Concrete (Pile 79 to 100) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

173 ADN-AFC-WIR-CIV-149 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-off (Pile 79 to 100) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

174 ADN-AFC-WIR-CIV-150 00 Latest Inspection for Installation of Reinforcement for Capping Beam (Pile 253-225) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

175 ADN-AFC-WIR-CIV-151 00 Latest Inspection for Completed Secant Pile Vertical Reinforcement Cut-Off (Pile 253-225) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

176 ADN-AFC-WIR-CIV-152 00 Latest Inspection for Installation and Fixation of Shutter & Formworks for Capping Beam (Pile 253-225) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

177 ADN-AFC-WIR-CIV-153 00 Latest Inspection for Survey Works and Setting-out of Capping Beam prior to Casting of Concrete (Pile 253-225) CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

178 ADN-AFC-WIR-CIV-154 00 Latest Inspection for Completed Secant Pile Head Breaking from Pile 236 to 263 CVL Al Firas 29-Jul-22 1-Aug-22 B B 3

179 ADN-AFC-WIR-CIV-155 00 Latest Inspection for Completed Secant Pile Head Breaking from Pile 119 to 179 CVL Al Firas 29-Jul-22 1-Aug-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
180 ADN-AFC-WIR-CIV-156 00 Latest Inspection for Completed Casting of PCC for Capping Beams at Shoring Piles (from 109 to 164) CVL Al Firas 29-Jul-22 1-Aug-22 A A 3

Inspection for Installation of Reinforcement for Cappinig Beam and Completed Secant Pile Vertical Reinforcement Cut-off Pile
181 ADN-AFC-WIR-CIV-157 00 Latest
191 to 167
CVL Al Firas 31-Jul-22 3-Aug-22 B B 3

Inspection for Installation of Reinforcement for Capping Beam and Completed Secant Pile Vertical Reinforcement Cut-off Pile
182 ADN-AFC-WIR-CIV-158 00 Latest
100 to 135
CVL Al Firas 31-Jul-22 3-Aug-22 B B 3

Inspection for Installation of Reinforcement for Capping Beam and Completed Secant Pile Vertical Reinforcement Cut-off Pile
183 ADN-AFC-WIR-CIV-159 00 Latest
135 to 167
CVL Al Firas 31-Jul-22 3-Aug-22 B B 3

Inspection for Installation and Fixation of Shutter & Formworks and Surveying Works and Setting-out of Capping Beam Pile 191
184 ADN-AFC-WIR-CIV-160 00 Latest
to 167
CVL Al Firas 1-Aug-22 3-Aug-22 B B 2

Inspection for Installation and Fixation of Shutter & Formworks and Surveying Works and Setting-out of Capping Beam Pile 100
185 ADN-AFC-WIR-CIV-161 00 Latest
to 135
CVL Al Firas 1-Aug-22 3-Aug-22 B B 2

Inspection for Installation and Fixation of Shutter & Formworks and Surveying Works and Setting-out of Capping Beam Pile 135
186 ADN-AFC-WIR-CIV-162 00 Latest
to 167
CVL Al Firas 1-Aug-22 3-Aug-22 B B 2

187 ADN-AFC-WIR-CIV-163 00 Latest Inspection for Installation of Construction Joint for Capping Beam Pile 191 - 167 CVL Al Firas 1-Aug-22 3-Aug-22 B B 2

188 ADN-AFC-WIR-CIV-164 00 Latest Inspection for Installation of Construction Joint for Capping Beam Pile 1001-135 CVL Al Firas 1-Aug-22 3-Aug-22 B B 2

189 ADN-AFC-WIR-CIV-165 00 Latest Inspection for Setting-out and Permanent Deep Well Drilling for DW-4 CVL Al Firas 3-Aug-22 5-Aug-22 B B 2

190 ADN-AFC-WIR-CIV-166 00 Latest Inspection for Setting-out and Permanent Deep Well Drilling for DW-5 CVL Al Firas 4-Aug-22 7-Aug-22 B B 3

191 ADN-AFC-WIR-CIV-167 00 Latest Inspection for Surface preparation of Bracket / Corbel Concrete prior to start form work for repairing work CVL Al Firas 4-Aug-22 8-Aug-22 B B 4

192 ADN-AFC-WIR-CIV-168 00 Latest Inspection for 1st and 2nd Stage Excavation up to bottom of capping beam CVL Al Firas 5-Aug-22 8-Aug-22 B B 3

193 ADN-AFC-WIR-CIV-169 00 Latest Inspection for Excavation up to -8.800m along grid line I-L/2-11 CVL Al Firas 5-Aug-22 9-Aug-22 B B 4

194 ADN-AFC-WIR-CIV-170 00 Superseded Inspection for Forwmwork of Bracket / Corbel Concrete Repair Work to Start Micro Concrete CVL Al Firas 7-Aug-22 9-Aug-22 C C 2

195 ADN-AFC-WIR-CIV-170 01 Latest Inspection for Forwmwork of Bracket / Corbel Concrete Repair Work to Start Micro Concrete CVL Al Firas 10-Aug-22 14-Aug-22 B B 4

196 ADN-AFC-WIR-CIV-171 00 Latest Inspection for Excavation form 8:00 M to -9.450 & -10.350M along grid line 2-13/C CVL Al Firas 12-Aug-22 16-Aug-22 B B 4

197 ADN-AFC-WIR-CIV-172 00 Superseded Inspection for marking of Cut Off Level for Center Pile (Pile No. 335 & 336) CVL Al Firas 12-Aug-22 16-Aug-22 C C 4

198 ADN-AFC-WIR-CIV-172 01 Latest Inspection for marking of Cut Off Level for Center Pile (Pile No. 335 & 336) CVL Al Firas 16-Aug-22 17-Aug-22 B B 1

199 ADN-AFC-WIR-CIV-173 00 Latest Inspection for Marking of Cut-off Levels for Center Piles 61,62,333,334,337,338,339,340,425,426 CVL Al Firas 15-Aug-22 17-Aug-22 B B 2

200 ADN-AFC-WIR-CIV-174 00 Superseded Inspection for Surface Preparation prior to start gunite mesh installation (Secant Pile 492-482) CVL Al Firas 17-Aug-22 19-Aug-22 C C 2

201 ADN-AFC-WIR-CIV-174 01 Latest Inspection for Surface Preparation prior to start gunite mesh installation (Secant Pile 492-482) CVL Al Firas 26-Aug-22 30-Aug-22 B B 4

202 ADN-AFC-WIR-CIV-175 00 Latest Inspection for Marking of Cut-off levels for Center Piles 410,411,412,413,414,415,416,417,418,419,420,421,422,423,425,426 CVL Al Firas 18-Aug-22 21-Aug-22 B B 3

203 ADN-AFC-WIR-CIV-176 00 Latest Inspection for Marking of Car Parking Shade Post Location CVL Al Firas 18-Aug-22 22-Aug-22 B B 4

204 ADN-AFC-WIR-CIV-177 00 Latest Inspection for Marking of Cut-off Levels for Center Piles CVL Al Firas 19-Aug-22 23-Aug-22 B B 4

205 ADN-AFC-WIR-CIV-178 00 Latest Inspection for Marking of Cut off Level for Center Pile (Pile No. 55 to 58, 325 to 332 & 393,394,398,399,403 &404 CVL Al Firas 21-Aug-22 23-Aug-22 B B 2

206 ADN-AFC-WIR-CIV-179 00 Latest Inspection for Rebar and Formwork of Car Park Foundations CVL Al Firas 25-Aug-22 28-Aug-22 B B 3

207 ADN-AFC-WIR-CIV-180 00 Superseded Inspection for Rebar, Anchor Bolts and Formwork of Car Park Shade Foundation Pedestal CVL Al Firas 26-Aug-22 28-Aug-22 C C 2

208 ADN-AFC-WIR-CIV-180 01 Latest Inspection for Rebar, Anchor Bolts and Formwork of Car Park Shade Foundation Pedestal CVL Al Firas 31-Aug-22 31-Aug-22 B B 0

209 ADN-AFC-WIR-CIV-181 00 Superseded Inspection for Surface Preparation prior to Start Gunite Mesh Installation (Secant Pile 461-446) CVL Al Firas 28-Aug-22 31-Aug-22 C C 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
210 ADN-AFC-WIR-CIV-181 01 Latest Inspection for Surface Preparation prior to Start Gunite Mesh Installation (Secant Pile 461-425) CVL Al Firas 1-Sep-22 5-Sep-22 B B 4

211 ADN-AFC-WIR-CIV-182 00 Latest Inspection for Mock-Up Gunite Mesh Installation CVL Al Firas 29-Aug-22 30-Aug-22 B B 1

212 ADN-AFC-WIR-CIV-183 00 Latest Inspection for Installation of Gunite Mesh prior to start guniting (grid line 2* to 6*) CVL Al Firas 31-Aug-22 4-Sep-22 B B 4

213 ADN-AFC-WIR-CIV-184 00 Latest Inspection for Marking of Cut Off level for center pile (Pile No. 90 & 94) CVL Al Firas 31-Aug-22 4-Sep-22 B B 4

214 ADN-AFC-WIR-CIV-185 00 Latest Inspection for Excavation up to -9.000M alond grid line D-M 7**-4** CVL Al Firas 31-Aug-22 4-Sep-22 B B 4

215 ADN-AFC-WIR-CIV-186 00 Latest Inspection for Excavation up to -9.000M, -11.000M, -11.350M & -9.450M along grid line F*-L*/4-13* CVL Al Firas 31-Aug-22 4-Sep-22 B B 4

216 ADN-AFC-WIR-CIV-187 00 Latest Inspection for Application of Gunite (grid line 2*-6*) CVL Al Firas 1-Sep-22 5-Sep-22 B B 4

217 ADN-AFC-WIR-CIV-188 00 Latest Inspection for marking of Cut Off Level for Center Pile (Pile No. 342, 343, 345, 346, 348, 349, 351, 352, 354, 355 & 356) CVL Al Firas 1-Sep-22 6-Sep-22 B B 5

218 ADN-AFC-WIR-CIV-189 00 Superseded Inspection for Surface preparation prior to start gunite mesh installation (grid line B*-X8/13*) CVL Al Firas 1-Sep-22 5-Sep-22 C C 4

219 ADN-AFC-WIR-CIV-189 01 Latest Inspection for Surface preparation prior to start gunite mesh installation (grid line B*-X8/13*) CVL Al Firas 7-Sep-22 11-Sep-22 B B 4

Inspection for Completion of Pile Breaking up to Cut-off level (Pile No. 54 to 63, 325 to 328, 330, 331, 333 to 339, 393 to 423 &
220 ADN-AFC-WIR-CIV-190 00 Latest
425)
CVL Al Firas 4-Sep-22 5-Sep-22 C C 1

221 ADN-AFC-WIR-CIV-191 00 Latest Inspection for Setting out, Level and Installation of Gunite Mesh prior to start guniting (grid line 6* to 12*) CVL Al Firas 5-Sep-22 6-Sep-22 B B 1

222 ADN-AFC-WIR-CIV-192 00 Latest Inspection for Marking of Cut-Off level for Center Pile (Pile No. 72 to 92, 94 & 95) CVL Al Firas 5-Sep-22 8-Sep-22 B B 3

223 ADN-AFC-WIR-CIV-193 00 Latest Inspection for Surface Preparation prior to Start Gunite Mesh Installation (grid line X*-V* / 13*) CVL Al Firas 5-Sep-22 8-Sep-22 A A 3

224 ADN-AFC-WIR-CIV-194 00 Latest Inspection for Completion of French Drain (60cmx80cm) CVL Al Firas 6-Sep-22 8-Sep-22 B B 2

225 ADN-AFC-WIR-CIV-195 00 Latest Inspection for Completiong of Gunite (grid line - 2* to 6*) CVL Al Firas 6-Sep-22 8-Sep-22 B B 2

226 ADN-AFC-WIR-CIV-196 00 Latest Inspection for Setting out, Level and Installation of Gunite Mesh Prior to Start Guniting (grid line B* V/13*) CVL Al Firas 8-Sep-22 11-Sep-22 B B 3

227 ADN-AFC-WIR-CIV-197 00 Latest Inspection for Completion of Gunite (grid line - 6* to 12*) CVL Al Firas 8-Sep-22 11-Sep-22 C C 3

228 ADN-AFC-WIR-CIV-198 00 Latest Inspection for Marking of Cut-off Level for Center Pile (Pile No. 48 to 52, 54 & 59) CVL Al Firas 8-Sep-22 11-Sep-22 B B 3

229 ADN-AFC-WIR-CIV-199 00 Latest Inspection for Marking of Cut Off Level for Center Pile (Pile No. 01, 02, 64 to 71, 96, 99 & 102) CVL Al Firas 8-Sep-22 11-Sep-22 B B 3

230 ADN-AFC-WIR-CIV-200 00 Latest Inspection for Completiong of French Drain (60cmx80cm) CVL Al Firas 8-Sep-22 11-Sep-22 B B 3

231 ADN-AFC-WIR-CIV-201 00 Latest Inspection for Surface Preparation Prior to Start Gunite Mesh Installation Grid Line - L*-J*, 12*-13*-B*, W-T CVL Al Firas 9-Sep-22 11-Sep-22 B B 2

Inspection for Marking of Cut-Off Levels for Center Piles Prior to Start Breaking Piles 633-72, 279, 280, 287, 288, 295, 296, 302-
232 ADN-AFC-WIR-CIV-202 00 Latest
304
CVL Al Firas 8-Sep-22 11-Sep-22 B B 3

233 ADN-AFC-WIR-CIV-203 00 Latest Inspection for Compeltiong of Gunite (grid line -B*V/13*) CVL Al Firas 9-Sep-22 11-Sep-22 B B 2

234 ADN-AFC-WIR-CIV-204 00 Latest Inspection for Checking of Levels Prior to Application of Anti-Termite and Casting of PCC at Pile 55 to 58 (PC-4) CVL Al Firas 9-Sep-22 11-Sep-22 C C 2

Inspection for Checking of Compacted Soil Level prior to Start Application of Anti-Termite and Casting of PCC at Pile Cap PC1 (2
235 ADN-AFC-WIR-CIV-205 00 Latest
Nos) & PC1B (2 Nos)
CVL Al Firas 11-Sep-22 18-Sep-22 B B 7

236 ADN-AFC-WIR-CIV-206 00 Superseded Inspection for Surface Preparation Prior to Start Gunite Mesh Installation (grid line J-G/13*) CVL Al Firas 11-Sep-22 18-Sep-22 C C 7

237 ADN-AFC-WIR-CIV-206 01 Latest Inspection for Surface Preparation Prior to Start Gunite Mesh Installation (grid line J-G/13*) CVL Al Firas 19-Sep-22 22-Sep-22 B B 3

238 ADN-AFC-WIR-CIV-207 00 Latest Inspection for Marking of Cut-Off Level for Tower Crane 4 Piles (TC4-1, TC4-2, TC4-3 & TC4-4) prior to start breaking CVL Al Firas 11-Sep-22 14-Sep-22 B B 3

239 ADN-AFC-WIR-CIV-208 00 Latest Inspection for Checking of Level prior to Start Casting of PCC for Tie Beam at PC13 Trench Area CVL Al Firas 12-Sep-22 18-Sep-22 B B 6
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
240 ADN-AFC-WIR-CIV-209 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at Pile Cap PC 7A, PC8 & TC4 CVL Al Firas 12-Sep-22 18-Sep-22 B B 6

241 ADN-AFC-WIR-CIV-210 00 Latest Inspection for Application of Anti-Termite prior to Start Casting of PCC at Pile Cap PC 7A, PC8 & TC4 CVL Al Firas 12-Sep-22 18-Sep-22 B B 6

242 ADN-AFC-WIR-CIV-211 00 Latest Inspection for Application of Anti-Termite prior to Start Casting of PCC at Pile Cap PC4, PC1 (2 nos) & PC1B CVL Al Firas 12-Sep-22 18-Sep-22 B B 6

243 ADN-AFC-WIR-CIV-212 00 Latest Inspection for Setting out, Level and Installation of Gunite Mesh prior to Start guniting (grid line V T/13* & K8-J*/2*) CVL Al Firas 12-Sep-22 18-Sep-22 B B 6

244 ADN-AFC-WIR-CIV-213 00 Latest Inspection for marking of Cut Off Level for Center Pile (Pile No. 275 to 278 & 283 to 286) CVL Al Firas 12-Sep-22 16-Sep-22 B B 4

245 ADN-AFC-WIR-CIV-214 00 Latest Inspection for marking of Cut-off Level for Tower Crane 01 Piles (TC1-1, TC1-2, TC1-3 & TC1-4) CVL Al Firas 13-Sep-22 18-Sep-22 B B 5

246 ADN-AFC-WIR-CIV-215 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at TC-01 CVL Al Firas 13-Sep-22 18-Sep-22 B B 5

247 ADN-AFC-WIR-CIV-216 00 Latest Inspection for Application of Anti-Termite at TC-01 Pile Cap Foundation prior to Start bliding CVL Al Firas 13-Sep-22 18-Sep-22 B B 5

248 ADN-AFC-WIR-CIV-217 00 Latest Inspection for Marking of Cut-off Level for Center Pile (pile No. 291 to 294, 300, 308, 309 & 42 to 47) prior to start breaking CVL Al Firas 13-Sep-22 16-Sep-22 B B 3

249 ADN-AFC-WIR-CIV-218 00 Latest Inspection for Block Wall Layout prior to Start Work at Pile Cap (PC4, PC1, PC1B & TC1) CVL Al Firas 13-Sep-22 16-Sep-22 B B 3

250 ADN-AFC-WIR-CIV-219 00 Latest Inspection for Surface Preparation prior ro Start Gunite Mesh Installation (grid line K*L*/2* & 12*-13*/C") CVL Al Firas 14-Sep-22 16-Sep-22 B B 2

251 ADN-AFC-WIR-CIV-220 00 Latest Inspection for Checking Block Wall Layout Coordinates prior to Start Work at Pile Cap (PC7A, PC8 & TC4) CVL Al Firas 14-Sep-22 16-Sep-22 B B 2

252 ADN-AFC-WIR-CIV-221 00 Latest Inspection for Installation of Gunite Mesh (grid line K*L*/2* & 12*-13*/C") CVL Al Firas 14-Sep-22 16-Sep-22 B B 2

253 ADN-AFC-WIR-CIV-222 00 Latest Inspection for Marking of Cut-off Level for Tower Crane - 02 Piles (TC2-1, TC2-2, TC2-3 & TC2-4) CVL Al Firas 14-Sep-22 16-Sep-22 B B 2

254 ADN-AFC-WIR-CIV-223 00 Latest Inspection for Rebar and Formwork of Tie Beam at PC13 prior to Start Concrete CVL Al Firas 14-Sep-22 19-Sep-22 B B 5

255 ADN-AFC-WIR-CIV-224 00 Latest Inspection for Surface Preparation prior to start gunite mesh installation (grid line J*-G*/2*) CVL Al Firas 18-Sep-22 19-Sep-22 B B 1

256 ADN-AFC-WIR-CIV-225 00 Superseded Inspection for Surface preparation prior to start gunite Mesh Installation (grid line G-D/7*) CVL Al Firas 18-Sep-22 19-Sep-22 C C 1

257 ADN-AFC-WIR-CIV-225 01 Latest Inspection for Surface preparation prior to start gunite Mesh Installation (grid line G-D/7*) CVL Al Firas 20-Sep-22 22-Sep-22 B B 2

258 ADN-AFC-WIR-CIV-226 00 Latest Inspection for marking of Cut-off level for Center Pile (97, 98, 100, 101, 341, 344, 347, 350 & 358) prior to start breaking CVL Al Firas 18-Sep-22 19-Sep-22 B B 1

259 ADN-AFC-WIR-CIV-227 00 Latest Inspection for Mock-Up of Block Wall (Dead Shutter Work) CVL Al Firas 18-Sep-22 19-Sep-22 B B 1

260 ADN-AFC-WIR-CIV-228 00 Superseded Inspection for Completion of French Drain (60cmx80cm) CVL Al Firas 18-Sep-22 20-Sep-22 C C 2

261 ADN-AFC-WIR-CIV-228 01 Latest Inspection for Completion of French Drain (60cmx80cm) CVL Al Firas 20-Sep-22 22-Sep-22 B B 2

262 ADN-AFC-WIR-CIV-229 00 Latest Inspection for marking of Cut-Off Level for Center Pile (Pile no. 42 to 47) prior to start breaking CVL Al Firas 18-Sep-22 20-Sep-22 B B 2

263 ADN-AFC-WIR-CIV-230 00 Latest Inspection for Marking of Cut-Off Level for Center Pile (Pile No. 357 to 385) prior to stat breaking CVL Al Firas 18-Sep-22 20-Sep-22 B B 2

264 ADN-AFC-WIR-CIV-231 00 Latest Inspection for Setting out, Level and Installation of Gunite Mesh prior to Start Guniting (grid line -l*J*/2*) CVL Al Firas 19-Sep-22 22-Sep-22 B B 3

265 ADN-AFC-WIR-CIV-232 00 Latest Inspection for Setting out, Level and Installation of Gunite Mesh prior to Start Guniting (grid line -G-J/7") CVL Al Firas 19-Sep-22 22-Sep-22 B B 3

266 ADN-AFC-WIR-CIV-233 00 Latest Inspection for Completion of Gunite (grid line - 12*-13*/C",C"-B"/13* & J*-L*/2*) CVL Al Firas 19-Sep-22 22-Sep-22 B B 3

267 ADN-AFC-WIR-CIV-234 00 Latest Inspection for Setting out, level and installation of gunite mesh prior to start guniting (grid line G-D/7*) CVL Al Firas 20-Sep-22 25-Sep-22 B B 5

268 ADN-AFC-WIR-CIV-235 00 Superseded Inspection for Completiong of French Drain (60cmx80cm) CVL Al Firas 20-Sep-22 22-Sep-22 C C 2

269 ADN-AFC-WIR-CIV-235 01 Latest Inspection for Completiong of French Drain (60cmx80cm) CVL Al Firas 25-Sep-22 27-Sep-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
Inspection for marking of Cut off level for center pile (Pile No. 273, 274, 281, 282, 289, 290, 297 to 299, 305, to 307, 310 to
270 ADN-AFC-WIR-CIV-236 00 Latest
324) prior to start breaking
CVL Al Firas 20-Sep-22 22-Sep-22 B B 2

271 ADN-AFC-WIR-CIV-237 00 Latest Inspection for Surface preparation prior to start gunite mesh installation (grid line I*-G*) CVL Al Firas 21-Sep-22 22-Sep-22 B B 1

272 ADN-AFC-WIR-CIV-238 00 Latest Inspection for Setting out Level and Installation of Gunite Mesh (grid line I*-G*/2*) CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

273 ADN-AFC-WIR-CIV-239 00 Latest Inspection for Completion of Gunite (grid line J*-I*/2*) CVL Al Firas 21-Sep-22 22-Sep-22 B B 1

274 ADN-AFC-WIR-CIV-240 00 Latest Inspection for Application of Anti-termite prior to start casting PCC at Pile Cap PC1B, PC1A, PC5 &PC6A CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

275 ADN-AFC-WIR-CIV-241 00 Latest Inspection for Checking of Compacted Soil Level to Start Anti-Termite PC/A-PC1B-PC5-PC6A CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

276 ADN-AFC-WIR-CIV-242 00 Latest Inspection for Surface preparation prior to start gunite mesh installation (grid line D-A/7**) CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

277 ADN-AFC-WIR-CIV-243 00 Latest Inspection for Rebar and Form Work of Stiffener Columns at PC13 prior to start concrete CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

278 ADN-AFC-WIR-CIV-244 00 Latest Inspection for Rebar and Form work of tie Beam at PC13 prior to start concrete CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

279 ADN-AFC-WIR-CIV-245 00 Latest Inspection for Mock-up of Re-profilling grout on pile head (ALSAN CAP C) CVL Al Firas 21-Sep-22 25-Sep-22 B B 4

280 ADN-AFC-WIR-CIV-246 00 Latest Inspection for Checking of Compacted Soil Level to Start Anti-Termite at PC13 CVL Al Firas 22-Sep-22 25-Sep-22 B B 3

281 ADN-AFC-WIR-CIV-247 00 Latest Inspection for Setting out, level and installation of Gunite Mesh prior to start guniting (grid line -D-B/7") CVL Al Firas 23-Sep-22 25-Sep-22 B B 2

282 ADN-AFC-WIR-CIV-248 00 Latest Inspection for Checking Block Wall Layout Coordinates prior to start work at pile cap (PC1B, PC5, PC6A) CVL Al Firas 23-Sep-22 25-Sep-22 C C 2

283 ADN-AFC-WIR-CIV-249 00 Superseded Inspection for Pile Head Re-Profiling Work for Pile No. 265 to 272 (10 nos) CVL Al Firas 25-Sep-22 26-Sep-22 C C 1

284 ADN-AFC-WIR-CIV-249 01 Latest Inspection for Surface Preparation prior to start re-profiling grout on Pile Head (ALSAN CAP C) CVL Al Firas 26-Sep-22 29-Sep-22 B B 3

285 ADN-AFC-WIR-CIV-250 00 Latest Inspection for Rebar and Form Work of Stiffener Beam at PC13 prior to start concrete CVL Al Firas 25-Sep-22 27-Sep-22 B B 2

286 ADN-AFC-WIR-CIV-251 00 Latest Inspection for Marking of Cut Off Level for Center Pile (Pile No. 424 & 427) prior to start breaking CVL Al Firas 25-Sep-22 25-Sep-22 B B 0

287 ADN-AFC-WIR-CIV-252 00 Latest Inspection for Marking of Cut Off Level for Center Pile (Pile no. 187 to 193) prior to start breaking CVL Al Firas 25-Sep-22 25-Sep-22 B B 0

288 ADN-AFC-WIR-CIV-253 00 Latest Inspection for the checking of compacted soil level prior to start anti-termite at PC13, TC-02, PC1B & PC6A CVL Al Firas 26-Sep-22 29-Sep-22 B B 3

289 ADN-AFC-WIR-CIV-254 00 Latest Inspection for Surface preparation prior to start gunite mesh installation grid line A-B/7** & 6**-7**/A CVL Al Firas 26-Sep-22 26-Sep-22 A A 0

290 ADN-AFC-WIR-CIV-255 00 Latest Inspection for Application of Anti-Termite at PC13, TC-02, PC1B & PC6A CVL Al Firas 26-Sep-22 29-Sep-22 B B 3

291 ADN-AFC-WIR-CIV-256 00 Latest Inspection for Setting out, level and installation of Gunite Mesh prior to start guniting (grid line A-B/7** & 7**-6**/A) CVL Al Firas 26-Sep-22 28-Sep-22 B B 2

292 ADN-AFC-WIR-CIV-257 00 Latest Inspection for Surface Preparation prior to start water Proofing primer application at TC-01 CVL Al Firas 27-Sep-22 28-Sep-22 B B 1

293 ADN-AFC-WIR-CIV-258 00 Latest Inspection for Mock Up of Primer Application prior to start water proorfing membrane at TC-01 CVL Al Firas 27-Sep-22 28-Sep-22 B B 1

294 ADN-AFC-WIR-CIV-259 00 Latest Inspection for Marking of Cut-Off Level for Center Pile (Pile No. 169 to 186) prior to start breaking CVL Al Firas 28-Sep-22 28-Sep-22 B B 0

295 ADN-AFC-WIR-CIV-260 00 Superseded Inspection for Surface Preparation prior to gunite mesh installation (grid line 4**06**/A) CVL Al Firas 27-Sep-22 29-Sep-22 C C 2

296 ADN-AFC-WIR-CIV-260 01 Latest Inspection for Surface Preparation prior to gunite mesh installation (grid line 4**06**/A) CVL Al Firas 3-Oct-22 4-Oct-22 B B 1

297 ADN-AFC-WIR-CIV-261 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC11, PC15 & PC1A CVL Al Firas 29-Sep-22 3-Oct-22 B B 4

298 ADN-AFC-WIR-CIV-262 00 Latest Inspection for Application of Anti-Termite at PC11, PC15 & PC1A CVL Al Firas 29-Sep-22 3-Oct-22 B B 4

299 ADN-AFC-WIR-CIV-263 00 Latest Inspection for Rebar and Form Work of Stiffner Column with Tie Beam (-9.350M) at PC13 prior to Start Concrete CVL Al Firas 29-Sep-22 3-Oct-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
300 ADN-AFC-WIR-CIV-264 00 Latest Inspection for Completion of Gunite (grid line -J-D/7** & J*-G*/2*) CVL Al Firas 29-Sep-22 30-Sep-22 B B 1

301 ADN-AFC-WIR-CIV-265 00 Latest Inspection for Surface preparation on Block Wall Prior to start waterproofing primer application at TC-01 CVL Al Firas 29-Sep-22 30-Sep-22 B B 1

302 ADN-AFC-WIR-CIV-266 00 Latest Inspection for Mock-upp of Primer Application on Block Wall prior to Start Waterproofing membrane at TC-01 CVL Al Firas 29-Sep-22 30-Sep-22 B B 1

303 ADN-AFC-WIR-CIV-267 00 Latest Inspection for Completion of French Drain (30x80cm) CVL Al Firas 30-Sep-22 2-Oct-22 B B 2

304 ADN-AFC-WIR-CIV-268 00 Latest Inspection for Surface Preparation on Floor and Wall prior to start waterproofing primer application at TC-04 CVL Al Firas 30-Sep-22 2-Oct-22 B B 2

305 ADN-AFC-WIR-CIV-269 00 Latest Inspection for Primer application on floor and block wall prior to start waterproofing membrane at TC-04 CVL Al Firas 30-Sep-22 3-Oct-22 B B 3

306 ADN-AFC-WIR-CIV-270 00 Superseded Inspection for Completion of Block Wall and Surface preparation prior to start water proofing primer application at PC13 CVL Al Firas 3-Oct-22 5-Oct-22 C C 2

307 ADN-AFC-WIR-CIV-270 01 Latest Inspection for Completion of Block Wall and Surface preparation prior to start water proofing primer application at PC13 CVL Al Firas 6-Oct-22 10-Oct-22 C C 4

308 ADN-AFC-WIR-CIV-271 00 Latest Inspection for marking of Cut Off Level for Center Pile (Pile No. 257 to 262) prior to start breaking CVL Al Firas 3-Oct-22 4-Oct-22 B B 1

309 ADN-AFC-WIR-CIV-272 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC5 & PC15 CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

310 ADN-AFC-WIR-CIV-273 00 Latest Inspection for Application of Anti-Termite at PC5 & PC15 CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

311 ADN-AFC-WIR-CIV-274 00 Latest Inspection for CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

Inspection for Completion of Water proofing membrane Installation prior to start protection screed and protection board at
312 ADN-AFC-WIR-CIV-275 00 Latest
TC-01
CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

313 ADN-AFC-WIR-CIV-276 00 Latest Inspection for Setting out, Level and Installation of Gunite Mesh Prior to Start Guniting (grid line 1** to 6**/A) CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

314 ADN-AFC-WIR-CIV-277 00 Latest Inspection for Completion of French Drain (60cmx80cm) prior to start blinding at PC14 CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

315 ADN-AFC-WIR-CIV-278 00 Superseded Inspection for Completion of Re-profilling on Pile Heads (ALSAN CAP C) CVL Al Firas 4-Oct-22 10-Oct-22 C C 6

316 ADN-AFC-WIR-CIV-278 01 Latest Inspection for Completion of Re-profilling on Pile Heads (ALSAN CAP C) CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

317 ADN-AFC-WIR-CIV-279 00 Latest Inspection for Surface preparation prior to start gunite mesh installation (grid line T-O/13**) CVL Al Firas 3-Oct-22 5-Oct-22 B B 2

318 ADN-AFC-WIR-CIV-280 00 Superseded Inspection for Surface preparation of Floor area prior to start water proofing primer applocation at PC13 CVL Al Firas 5-Oct-22 5-Oct-22 C C 0

319 ADN-AFC-WIR-CIV-280 01 Latest Inspection for Surface preparation of Floor area prior to start water proofing primer applocation at PC13 CVL Al Firas 6-Oct-22 9-Oct-22 B B 3

320 ADN-AFC-WIR-CIV-281 00 Superseded Inspection for Primer application on wall and floor at PC13 prior to start water proofing membrane CVL Al Firas 5-Oct-22 5-Oct-22 C C 0

321 ADN-AFC-WIR-CIV-281 01 Latest Inspection for Primer application on wall and floor at PC13 prior to start water proofing membrane CVL Al Firas 9-Oct-22 11-Oct-22 B B 2

322 ADN-AFC-WIR-CIV-282 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP-E) CVL Al Firas 4-Oct-22 10-Oct-22 B B 6

Inspection for Completion of Water Proofing Membrane Installation prior to start Protection Screed and Protection Board at
323 ADN-AFC-WIR-CIV-283 00 Latest
TC-04
CVL Al Firas 5-Oct-22 9-Oct-22 B B 4

324 ADN-AFC-WIR-CIV-284 00 Latest Inspection for Installation of Protection Board and Water Stopper at TC-01 CVL Al Firas 5-Oct-22 5-Oct-22 B B 0

325 ADN-AFC-WIR-CIV-285 00 Latest Inspection for marking if Cut-Off Level for Center Pile (Pile No. 03 to 08, 11, 116 to 124) prior to start breaking CVL Al Firas 5-Oct-22 5-Oct-22 B B 0

326 ADN-AFC-WIR-CIV-286 00 Superseded Inspection for Setting out, Level and Installation of Gunite Mesh prior to Start Guniting (grid line T-O/13**) CVL Al Firas 5-Oct-22 5-Oct-22 C C 0

327 ADN-AFC-WIR-CIV-286 01 Latest Inspection for Setting out, Level and Installation of Gunite Mesh prior to Start Guniting (grid line T-O/13**) CVL Al Firas 6-Oct-22 9-Oct-22 B B 3

328 ADN-AFC-WIR-CIV-287 00 Superseded Inspection for Rebar and Form Work of Tie Beam at PC14 prior to Start conrete CVL Al Firas 5-Oct-22 5-Oct-22 C C 0

329 ADN-AFC-WIR-CIV-287 01 Latest Inspection for Rebar and Form Work of Tie Beam at PC14 prior to Start conrete CVL Al Firas 6-Oct-22 10-Oct-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
330 ADN-AFC-WIR-CIV-288 00 Latest Inspection for Surface Preparation prior to start re-profiling grout on Pile Head (ALSAN CAP C) CVL Al Firas 5-Oct-22 9-Oct-22 B B 4

331 ADN-AFC-WIR-CIV-289 00 Latest Inspection for Completion of French Drain (60cmx80cm) prior to start blinding at PC14 CVL Al Firas 5-Oct-22 9-Oct-22 B B 4

332 ADN-AFC-WIR-CIV-290 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation at PC-04 (ALSAN CAP-E) CVL Al Firas 5-Oct-22 9-Oct-22 B B 4

333 ADN-AFC-WIR-CIV-291 00 Latest Inspection for Marking of Cut Off Level for Center Pile (Pile No. 103 to 108) prior to Start Breaking CVL Al Firas 6-Oct-22 10-Oct-22 B B 4

334 ADN-AFC-WIR-CIV-292 00 Latest Inspection for Surface Preparation prior to Start Gunite Mesh Installation (grid lime N-J/13**) CVL Al Firas 6-Oct-22 10-Oct-22 B B 4

335 ADN-AFC-WIR-CIV-293 00 Latest Inspection for 1st layer of Waterproofing Membrane on Floor and Wall prior to start 2nd layer CVL Al Firas 9-Oct-22 11-Oct-22 B B 2

336 ADN-AFC-WIR-CIV-294 00 Superseded Inspection for Rebar and Installation of Tower Crane Sections prior to Start Concrete at TC-01 CVL Al Firas 9-Oct-22 10-Oct-22 C C 1

337 ADN-AFC-WIR-CIV-294 01 Latest Inspection for Rebar and Installation of Tower Crane Sections prior to Start Concrete at TC-01 CVL Al Firas 10-Oct-22 11-Oct-22 B B 1

338 ADN-AFC-WIR-CIV-295 00 Latest Inspection for 2nd Layer Waterproofing Membrane on Floor and Wall at PC13 CVL Al Firas 10-Oct-22 12-Oct-22 B B 2

339 ADN-AFC-WIR-CIV-296 00 Latest Inspection for Rebar and Form Work of Tie Beam at PC14 prior to Start conrete CVL Al Firas 10-Oct-22 11-Oct-22 B B 1

340 ADN-AFC-WIR-CIV-297 00 Latest Inspection for Setting-out, Level and Installation of Gunite Mesh prior to Start Guniting (grid line J-N/13**) CVL Al Firas 10-Oct-22 11-Oct-22 B B 1

341 ADN-AFC-WIR-CIV-298 00 Latest Inspection for Surface Preparation prior to Start Re-profilling grout on Pile Head (ALSAN CAP C) CVL Al Firas 10-Oct-22 11-Oct-22 B B 1

342 ADN-AFC-WIR-CIV-299 00 Latest Inspection for Completion of Block Wall and Surface preparation prior to start water proofing primer application at PC13 CVL Al Firas 10-Oct-22 12-Oct-22 B B 2

343 ADN-AFC-WIR-CIV-300 00 Latest Inspection for Surface preparation of Floor area prior to start water proofing primer applocation at PC13 CVL Al Firas 10-Oct-22 12-Oct-22 B B 2

344 ADN-AFC-WIR-CIV-301 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation at Pile No. 263 to 272 (Epoxy Mortar - ALSAN CAP-E) CVL Al Firas 10-Oct-22 13-Oct-22 B B 3

345 ADN-AFC-WIR-CIV-302 00 Latest Inspection for Rebar and Form Work of Stiffner Columns and Beam at PC14 prior to Start Concrete CVL Al Firas 10-Oct-22 12-Oct-22 B B 2

346 ADN-AFC-WIR-CIV-303 00 Latest Inspection for Checking As-Built Center Pile Location at PC13 & TC-04 CVL Al Firas 11-Oct-22 24-Oct-22 A A 13

347 ADN-AFC-WIR-CIV-304 00 Latest Inspection for Surface Preparation prior to Start Re-profilling grout on Pile Head (ALSAN CAP C) CVL Al Firas 11-Oct-22 13-Oct-22 B B 2

348 ADN-AFC-WIR-CIV-305 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC16, PC6, PC1A & PC14 CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

349 ADN-AFC-WIR-CIV-306 00 Superseded Inspection for Application of Anti-Termite at PC16, PC6, PC1A & PC14 CVL Al Firas 11-Oct-22 13-Oct-22 C C 2

350 ADN-AFC-WIR-CIV-306 01 Latest Inspection for Application of Anti-Termite at PC16, PC6, PC1A & PC14 CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

351 ADN-AFC-WIR-CIV-307 00 Latest Inspection for Rebar and Installation of Tower Crane Section prior to Start Concrete at TC-04 CVL Al Firas 11-Oct-22 13-Oct-22 B B 2

352 ADN-AFC-WIR-CIV-308 00 Latest Inspection for marking of Cut Off Level for Center Pile (Pile No. 194 to 198 & 203, 208, 213, 218, 223 & 228) CVL Al Firas 11-Oct-22 13-Oct-22 B B 2

353 ADN-AFC-WIR-CIV-309 00 Latest Inspection for Checking of Compacted Soil level prior to Start Anti-Termite CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

354 ADN-AFC-WIR-CIV-310 00 Latest Inspection for Application of Anti-Termite CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

355 ADN-AFC-WIR-CIV-311 00 Latest Inspection for Checking of As-Built Center Pile Location CVL Al Firas 13-Oct-22 24-Oct-22 A A 11

356 ADN-AFC-WIR-CIV-312 00 Latest Inspection for Completion of Re-profilling on Pile Heads (ALSAN CAP C) CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

357 ADN-AFC-WIR-CIV-313 00 Superseded Inspection for Surface preparation on Floor and Wall prior to Start waterproofing primer application at TC-02 CVL Al Firas 13-Oct-22 14-Oct-22 C C 1

Inspection for Surface preparation on Floor and Wall prior to Start waterproofing primer application at TC-02, PC1, PC1A, PC1B
358 ADN-AFC-WIR-CIV-313 01 Superseded
& PC4
CVL Al Firas 16-Oct-22 17-Oct-22 C C 1

Inspection for Completion of Block Wall and Surface Preparation on Floor and Wall prior to Start Waterproofing Primer
359 ADN-AFC-WIR-CIV-313 02 Latest
Application at TC-02, PC1, PC1A, PC1B & PC4
CVL Al Firas 19-Oct-22 23-Oct-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
360 ADN-AFC-WIR-CIV-314 00 Superseded Inspection for Rebar and Form Work of Stiffner Columns and Beam at PC14 prior to Start Concrete CVL Al Firas 13-Oct-22 14-Oct-22 C C 1

361 ADN-AFC-WIR-CIV-314 01 Latest Inspection for Rebar and Form Work ofTie Beamn Stiffner Columns and Beam at PC14 prior to start Concrete CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

362 ADN-AFC-WIR-CIV-315 00 Latest Inspection for Primer application on wall and floor at PC13 prior to start water proofing membrane CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

363 ADN-AFC-WIR-CIV-316 00 Latest Inspection for 1st Layer Water proofing membrane on Floor and Wall prior to Start 2nd Layer CVL Al Firas 13-Oct-22 14-Oct-22 B B 1

364 ADN-AFC-WIR-CIV-317 00 Latest Inspection for 2nd Layer Waterproofing Membrane on Floor and Wall prior to start protection screed and protection board CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

365 ADN-AFC-WIR-CIV-318 00 Latest Inspection for Primer Application on Wall and Floor at PC13 prior to start waterproofing membrane CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

366 ADN-AFC-WIR-CIV-319 00 Latest Inspection for 1st Layer of Waterproofing membrane on floor and wall prior to start 2nd layer CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

367 ADN-AFC-WIR-CIV-320 00 Latest Inspection for marking of Cut-Off Level for Concrete Pile (Pile No. 09, 10, 12, 13, 14 to 19) prior to start breaking CVL Al Firas 16-Oct-22 19-Oct-22 B B 3

368 ADN-AFC-WIR-CIV-321 00 Latest Inspection for Completion of French Drain (60cmx80cm) prior to start blinding at PC14 & PC12 CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

369 ADN-AFC-WIR-CIV-322 00 Latest Inspection for 2nd Layer Waterproofing membrane on Floorand Wall prior to Start protection Screed and Protection Board CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

370 ADN-AFC-WIR-CIV-323 00 Latest Inspection for Application and Completion of Pile Top Endcalsulation (Epoxy Mortar - ALSAN CAP - E) CVL Al Firas 16-Oct-22 20-Oct-22 B B 4

371 ADN-AFC-WIR-CIV-324 00 Latest Inspection for Primer Application on Wall at PC13 prior to Start Waterproofing Membrane CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

372 ADN-AFC-WIR-CIV-325 00 Latest Inspection for 1st Layer Water proofing Membrane on Wall prior to Start 2nd Layer CVL Al Firas 16-Oct-22 17-Oct-22 B B 1

373 ADN-AFC-WIR-CIV-326 00 Latest Inspection for 2nd Layer Waterproofing Membrane on Wall prior to Start Protection Board CVL Al Firas 16-Oct-22 19-Oct-22 B B 3

374 ADN-AFC-WIR-CIV-327 00 Latest Inspection for Checking of Compacted Soil Level prior to Start anti-Termite CVL Al Firas 17-Oct-22 19-Oct-22 B B 2

375 ADN-AFC-WIR-CIV-328 00 Latest Inspection for Application of Anti-Termite CVL Al Firas 17-Oct-22 19-Oct-22 B B 2

376 ADN-AFC-WIR-CIV-329 00 Latest Inspection for Marking of Cut-Off Level for Center Pile (Pile No. 204, 205, 206, 210, 211, 212, 218, 223 & 228) CVL Al Firas 17-Oct-22 19-Oct-22 B B 2

377 ADN-AFC-WIR-CIV-330 00 Superseded Inspection for Surface Preparation prior to start re-profiling grout on Pile Head (ALSAN CAP C) CVL Al Firas 17-Oct-22 19-Oct-22 C C 2

378 ADN-AFC-WIR-CIV-330 01 Latest Inspection for Surface Preparation and Completion of Re-profiling re-profiling grout on Pile Head (ALSAN CAP C) CVL Al Firas 21-Oct-22 24-Oct-22 B B 3

379 ADN-AFC-WIR-CIV-331 00 Latest Inspection for Checking of Completed Soil Level prior to Start Anti-Termite CVL Al Firas 18-Oct-22 20-Oct-22 B B 2

380 ADN-AFC-WIR-CIV-332 00 Latest Inspection for Application of Anti-Termite CVL Al Firas 18-Oct-22 20-Oct-22 B B 2

381 ADN-AFC-WIR-CIV-333 00 Latest Inspection for Installation of Protection Board at PC13 CVL Al Firas 19-Oct-22 20-Oct-22 B B 1

382 ADN-AFC-WIR-CIV-334 00 Latest Inspection for Primer Application on Wall at PC13 priro to Start Waterproofing Membrane CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

383 ADN-AFC-WIR-CIV-335 00 Latest Inspection for 1st Layer Waterproofing Membrane on Wall prior to Start 2nd Layer CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

384 ADN-AFC-WIR-CIV-336 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC6A & PC15 CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

385 ADN-AFC-WIR-CIV-337 00 Latest Inspection for Application of Anti-Termite prior to Start Blinding at PC6A & PC15 CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

386 ADN-AFC-WIR-CIV-338 00 Superseded Inspection for Completion of Block Wall and Surface preparation prior to Start waterpoofing primer application at PC14 CVL Al Firas 19-Oct-22 23-Oct-22 C C 4

387 ADN-AFC-WIR-CIV-338 01 Latest Inspection for Completion of Block Wall and Surface preparation of wall and floor prior to Start Waterproofing CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

388 ADN-AFC-WIR-CIV-339 00 Latest Inspection for Rebar and Form Work of Stiffner Columns and Beam at PC14 prior to Start Concrete CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

389 ADN-AFC-WIR-CIV-340 00 Superseded Inspection for Rebar and Form Work of Tie Beam at PC12 prior to Start Concrete CVL Al Firas 19-Oct-22 23-Oct-22 C C 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
390 ADN-AFC-WIR-CIV-340 01 Latest Inspection for Rebar and Form Work of Tie Beam at PC12 prior to Start Concrete CVL Al Firas 24-Oct-22 26-Oct-22 B B

Inspection for Primer Application on Floor and Wall prior to Start 1st layer Waterpoofing Membrane at TC-02, PC1, PC1A, PC1B
391 ADN-AFC-WIR-CIV-341 00 Latest
& PC4
CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

392 ADN-AFC-WIR-CIV-342 00 Latest Inspection for Surface Preparation prior to start re-profiling grout on Pile Head (ALSAN CAP C) CVL Al Firas 19-Oct-22 20-Oct-22 B B 1

393 ADN-AFC-WIR-CIV-343 00 Latest Inspection for 2nd Layer Water Proofing Membrane on Wall prior to Start protection Board CVL Al Firas 19-Oct-22 23-Oct-22 B B 4

Inspection for Marking of Cut-Off Level for Center Pile (Pile No. 214, 215, 216, 217, 219, 220, 221, 222, 224, 225, 226 & 227)
394 ADN-AFC-WIR-CIV-344 00 Latest
prior to Start breaking
CVL Al Firas 19-Oct-22 20-Oct-22 B B 1

395 ADN-AFC-WIR-CIV-345 00 Latest Inspection for Installation of Protection Board CVL Al Firas 19-Oct-22 24-Oct-22 B B 5

396 ADN-AFC-WIR-CIV-346 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC2 & PC7A CVL Al Firas 20-Oct-22 23-Oct-22 B B 3

397 ADN-AFC-WIR-CIV-347 00 Latest Inspection for Application of Anti-Termite at PC2 & PC7A prior to Start Blinding CVL Al Firas 20-Oct-22 23-Oct-22 B B 3

398 ADN-AFC-WIR-CIV-348 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC14 & PC7 CVL Al Firas 20-Oct-22 24-Oct-22 B B 4

399 ADN-AFC-WIR-CIV-349 00 Latest Inspection for Application of Anti-Termite at PC14 & PC7 prior to Start Blinding CVL Al Firas 20-Oct-22 24-Oct-22 B B 4

400 ADN-AFC-WIR-CIV-350 00 Superseded Inspection for Surface preparation on Blinding Area prior to Start Water Proofing primer Application CVL Al Firas 20-Oct-22 23-Oct-22 C C 3

401 ADN-AFC-WIR-CIV-350 01 Latest Inspection for Surface preparation on Blinding Area prior to Start Water Proofing primer Application CVL Al Firas 24-Oct-22 26-Oct-22 B B 2

402 ADN-AFC-WIR-CIV-351 00 Latest Inspection for 1st Layer Water proofing membrane on Floor & Wall at PC1, PC1A, PC1B & PC4 prior to Start 2nd Layer CVL Al Firas 20-Oct-22 24-Oct-22 B B 4

403 ADN-AFC-WIR-CIV-352 00 Latest Inspection for 2nd Layer Water proofing Membrane on Floor & Wall at TC-2, PC1, PC1A, PC1B & PC4 prior to start 2nd Layer CVL Al Firas 21-Oct-22 24-Oct-22 B B 3

404 ADN-AFC-WIR-CIV-353 00 Latest Inspection for Rebar Bottom Layers of PC13 Foundation CVL Al Firas 21-Oct-22 25-Oct-22 B B 4

405 ADN-AFC-WIR-CIV-354 00 Latest Inspection for marking of Cur-Off Level for Center Pile (Pile No. 229 to 238) prior to Start breaking CVL Al Firas 23-Oct-22 24-Oct-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
406 ADN-AFC-WIR-CIV-355 00 Latest Inspection for Installation of protection Board on Wall at TC-2, PC1, PC1A, PC1B & PC4 CVL Al Firas 23-Oct-22 26-Oct-22 B B 3

407 ADN-AFC-WIR-CIV-356 00 Latest Inspection for Checking of Compacted Soil Level prior to Start anti-termite CVL Al Firas 23-Oct-22 26-Oct-22 B B 3

408 ADN-AFC-WIR-CIV-357 00 Latest Inspection for Application of Anti-Termite CVL Al Firas 23-Oct-22 26-Oct-22 B B 3

409 ADN-AFC-WIR-CIV-358 00 Superseded Inspection for Rebar of PC13 Foundation prior to Start Concrete CVL Al Firas 24-Oct-22 26-Oct-22 C C 2

410 ADN-AFC-WIR-CIV-358 01 Latest Inspection for Rebar of PC13 Foundation prior to Start Concrete CVL Al Firas 27-Oct-22 28-Oct-22 B B 1

411 ADN-AFC-WIR-CIV-359 00 Latest Inspection for Surface preparation and Completion of Re-profilling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 24-Oct-22 26-Oct-22 B B 2

412 ADN-AFC-WIR-CIV-360 00 Latest Inspection for Completion of French Drain (60cmx80cm) prior to start Blinding CVL Al Firas 24-Oct-22 26-Oct-22 B B 2

413 ADN-AFC-WIR-CIV-361 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite at PC17 CVL Al Firas 24-Oct-22 26-Oct-22 B B 2

414 ADN-AFC-WIR-CIV-362 00 Latest Inspection for Application of Anti-Termite at PC17 prior to Start Blinding CVL Al Firas 24-Oct-22 26-Oct-22 B B 2

415 ADN-AFC-WIR-CIV-363 00 Latest Inspection for Rebar and Form Work of Stiffner Columns and Beam at PC14 prior to Start Concrete CVL Al Firas 24-Oct-22 28-Oct-22 B B 4

416 ADN-AFC-WIR-CIV-364 00 Superseded Inspection for Surface preparation and Completion of Re-profilling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 24-Oct-22 26-Oct-22 C C 2

417 ADN-AFC-WIR-CIV-364 01 Latest Inspection for Surface preparation and Completion of Re-profilling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

418 ADN-AFC-WIR-CIV-365 00 Latest Inspection for primer application on blinding area prior to start 1st layer of Waterproofing membrane CVL Al Firas 25-Oct-22 26-Oct-22 B B 1

Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP E) at TC-2, PC1, PC1A, PC1B &
419 ADN-AFC-WIR-CIV-366 00 Latest
PC4
CVL Al Firas 25-Oct-22 28-Oct-22 B B 3

420 ADN-AFC-WIR-CIV-367 00 Latest Inspection for Installation of Water proofing Compartment System at PC13 (Water Stopper & Injection Hose) CVL Al Firas 25-Oct-22 28-Oct-22 B B 3

421 ADN-AFC-WIR-CIV-368 00 Latest Inspection for Surface Preparation on Floor and Wall prior to Start Waterproofing Primer Application CVL Al Firas 25-Oct-22 28-Oct-22 B B 3

422 ADN-AFC-WIR-CIV-369 00 Latest Inspection for Checking of Compacted Soil level at below the Raft Foundation prior to Start Anti-Termite CVL Al Firas 25-Oct-22 28-Oct-22 B B 3

423 ADN-AFC-WIR-CIV-370 00 Latest Inspection for Application of Anti-Termite at below the Raft Foundation prior to Start Blinding CVL Al Firas 25-Oct-22 28-Oct-22 B B 3

424 ADN-AFC-WIR-CIV-371 00 Superseded Inspection for Surface Preparation prior to Start Gunite Mesh Installation (grid line A* - D*/2*) CVL Al Firas 26-Oct-22 26-Oct-22 C C 0

425 ADN-AFC-WIR-CIV-371 01 Latest Inspection for Surface Preparation prior to Start Gunite Mesh Installation (grid line A* - D*/2*) CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

426 ADN-AFC-WIR-CIV-372 00 Latest Inspection for Installation of 1st Layer Water proofing Membrane on Floor prior to Start 2nd layer Membrane CVL Al Firas 26-Oct-22 28-Oct-22 B B 2

427 ADN-AFC-WIR-CIV-373 00 Latest Inspection for Primer Application on Wall Area (gunite surface) prior to Start 1st layer waterproofing Membrane CVL Al Firas 26-Oct-22 28-Oct-22 B B 2

428 ADN-AFC-WIR-CIV-374 00 Latest Inspection for Installation of 2nd layer Waterproofing Membrane prior to Start 2nd protection Screed CVL Al Firas 26-Oct-22 28-Oct-22 B B 2

429 ADN-AFC-WIR-CIV-375 00 Latest Inspection for Checking of Compacted Soil Level at Below the Raft Foundation prior to Start Anti-Termite CVL Al Firas 28-Oct-22 30-Oct-22 B B 2

430 ADN-AFC-WIR-CIV-376 00 Latest Inspection for Application of Anti-Termite prior to Start Blinding CVL Al Firas 28-Oct-22 30-Oct-22 B B 2

431 ADN-AFC-WIR-CIV-377 00 Superseded Inspection for Witness of Spark Test for Water Proofing Membrane Work CVL Al Firas 27-Oct-22 30-Oct-22 C C 3

432 ADN-AFC-WIR-CIV-377 01 Latest Inspection for Witness of Spark Test for Water Proofing Membrane Work CVL Al Firas 6-Dec-22 11-Dec-22 B B 5

433 ADN-AFC-WIR-CIV-378 00 Latest Inspection for Primer Application on Floor and Wall prior to Start 1st Layer Waterproofing Membrane CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

434 ADN-AFC-WIR-CIV-379 00 Latest Inspection for Installation of 1st Later Water Proofing membrane on Wall Area prior to Start 2nd Layer membrane CVL Al Firas 30-Oct-22 30-Oct-22 B B 0

435 ADN-AFC-WIR-CIV-380 00 Latest Inspection for Installation of 1st layer Waterproofing Membrane on Floor and Wall Area prior to Start 2nd Layer membrane CVL Al Firas 30-Oct-22 31-Oct-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
436 ADN-AFC-WIR-CIV-381 00 Latest Inspection for Installation of 2nd Layer Water Proofing membrane on Wall Area prior to Start protection Screed CVL Al Firas 30-Oct-22 30-Oct-22 B B 0

437 ADN-AFC-WIR-CIV-382 00 Latest Inspection for Setting out, Level and Installation of Gunite mesh prior to Start Guniting (grid line A*-D*/2*) CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

438 ADN-AFC-WIR-CIV-383 00 Latest Inspection for Rebar and Form Work of Tie Beam and Stiffner Column with Beam at PC12 prior to Start Concrete CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

439 ADN-AFC-WIR-CIV-384 00 Latest Inspection for Primer Application on Floor and Wall prior to Start 1st Layer Waterproofing Membrane at PC14 CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

440 ADN-AFC-WIR-CIV-385 00 Latest Inspection for Installation of 1st layer Waterproofing Membrane on Floor and Wall Area prior to Start 2nd Layer at PC14 CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

441 ADN-AFC-WIR-CIV-386 00 Latest Inspection for Installation of 2nd Layer Waterpoofing Membrane on Floor and Wall at PC14 CVL Al Firas 30-Oct-22 2-Nov-22 B B 3

442 ADN-AFC-WIR-CIV-387 00 Latest Inspection for Installation of protection Board on Wall Area CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

Inspection for Installation of 2nd Layer Waterpoofing Membrane on Floor and Wall Area prior to Start Screed and protection
443 ADN-AFC-WIR-CIV-388 00 Latest
Board
CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

444 ADN-AFC-WIR-CIV-389 00 Latest Inspection for Checking of Compacted Soil Level at Below the Raft Foundation prior to Start Anti-Termite CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

445 ADN-AFC-WIR-CIV-390 00 Latest Inspection for Application of Anti-Termite below the Raft Foundation Area prior to Start Blinding CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

Inspection for Marking of Cut-off Level for Center Pile (Pile No. 36 to 41, 143 to 146, 165 to 168, 239 to 256) prior to start
446 ADN-AFC-WIR-CIV-391 00 Latest
breaking
CVL Al Firas 30-Oct-22 31-Oct-22 B B 1

447 ADN-AFC-WIR-CIV-392 00 Latest Inspection for Checking of Compacted Soil Level at below the Raft Foundation prior to sStart Anti-Termite CVL Al Firas 31-Oct-22 2-Nov-22 B B 2

448 ADN-AFC-WIR-CIV-393 00 Latest Inspection for Application of Anti-Termite below the Raft Foundation Area prior to Start blinding CVL Al Firas 31-Oct-22 2-Nov-22 B B 2

449 ADN-AFC-WIR-CIV-394 00 Latest Inspection for Installation of Protection Board on Wall Area CVL Al Firas 1-Nov-22 2-Nov-22 B B 1

450 ADN-AFC-WIR-CIV-395 00 Latest Inspection for Installation of Protection Board on Wall at PC14 CVL Al Firas 1-Nov-22 2-Nov-22 B B 1

451 ADN-AFC-WIR-CIV-396 00 Latest Inspection for Surface Preparation on Floor and Wall Area CVL Al Firas 1-Nov-22 2-Nov-22 B B 1

452 ADN-AFC-WIR-CIV-397 00 Latest Inspection for Primer Application on Floor and Wall prior to Start 1st Layer Waterproofing Membrane CVL Al Firas 1-Nov-22 2-Nov-22 B B 1

453 ADN-AFC-WIR-CIV-398 00 Latest Inspection for Rebar Installation at Tower Crane 2 PILE CAP Foundation prior to Start Concreting Works CVL Al Firas 1-Nov-22 4-Nov-22 B B 3

454 ADN-AFC-WIR-CIV-399 00 Superseded Inspection for Rebar of Core Wall 03 at PC13 prior to Start Formwork CVL Al Firas 1-Nov-22 3-Nov-22 C C 2

455 ADN-AFC-WIR-CIV-399 01 Latest Inspection for Rebar of Core Wall 03 at PC13 prior to Start Formwork CVL Al Firas 7-Nov-22 10-Nov-22 B B 3

456 ADN-AFC-WIR-CIV-400 00 Latest Inspection for Marking of Cut Off Level for Center Pile (Pile No. 131 to 134 & 147 to 152) prior to Start breaking CVL Al Firas 2-Nov-22 4-Nov-22 B B 2

457 ADN-AFC-WIR-CIV-401 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor and Wall prior to Start 2nd Layer at PC1B CVL Al Firas 2-Nov-22 4-Nov-22 B B 2

458 ADN-AFC-WIR-CIV-402 00 Latest Inspection for Installation of 2nd Layer Waterpoofing Membrane on Floor and Wall prior to Start protection Screed at PC1B CVL Al Firas 2-Nov-22 6-Nov-22 B B 4

459 ADN-AFC-WIR-CIV-403 00 Latest Inspection for Checking of Compacted Soil level at below the Raft Foundation prior to Start Anti-Termite CVL Al Firas 2-Nov-22 4-Nov-22 B B 2

460 ADN-AFC-WIR-CIV-404 00 Latest Inspection for Application of Anti-Termite below the Raft Foundation Area prior to Start Blinding CVL Al Firas 2-Nov-22 4-Nov-22 B B 2

461 ADN-AFC-WIR-CIV-405 00 Latest Inspection for Surface preparation and Completion of Re-profilling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 2-Nov-22 6-Nov-22 B B 4

462 ADN-AFC-WIR-CIV-406 00 Latest Inspection for Installation of 1st layer Waterproofing Membrane on Floor and Wall prior to Start 2nd Layer at PC11 CVL Al Firas 2-Nov-22 6-Nov-22 B B 4

463 ADN-AFC-WIR-CIV-407 00 Latest Inspection for Installation of 2nd Layer Waterproofing membrane on Floor and Wall prior to Start Protection Screed at PC11 CVL Al Firas 2-Nov-22 6-Nov-22 B B 4

464 ADN-AFC-WIR-CIV-408 00 Latest Inspection for Checking As-Built of Center Pile Location CVL Al Firas 2-Nov-22 6-Nov-22 B B 4

465 ADN-AFC-WIR-CIV-409 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP-E) CVL Al Firas 2-Nov-22 6-Nov-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
466 ADN-AFC-WIR-CIV-410 00 Latest Inspection for Surface Preparation on Floor and Wall at PC15 and Blinding Surface Area prior to Start Primer CVL Al Firas 4-Oct-22 6-Nov-22 B B 33

467 ADN-AFC-WIR-CIV-411 00 Latest Inspection for Application of Primer on Floor and Wall at PC15 and blinding Surface Area prior to Start 1st layer Membrane CVL Al Firas 4-Nov-22 6-Nov-22 B B 2

468 ADN-AFC-WIR-CIV-412 00 Superseded Inspection for Completion of block Wall and Surface Preparation on Wall and Floor at PC14 prior to Start primer CVL Al Firas 4-Nov-22 6-Nov-22 C C 2

469 ADN-AFC-WIR-CIV-412 01 Latest Inspection for Completion of block Wall and Surface Preparation on Wall and Floor at PC14 prior to Start primer CVL Al Firas 8-Nov-22 8-Nov-22 B B 0

470 ADN-AFC-WIR-CIV-413 00 Latest Inspection for Rebar and Formwork to Tie Beam and Stiffner Column with Beam at PC12 prior to Start Concrete CVL Al Firas 4-Nov-22 7-Nov-22 B B 3

Inspection for Installation of 1st and 2nd Layer Waterproofing membrane on Floor and Wall prior to Start Protection Board at
471 ADN-AFC-WIR-CIV-414 00 Latest
PC13
CVL Al Firas 4-Nov-22 7-Nov-22 B B 3

472 ADN-AFC-WIR-CIV-415 00 Latest Inspection for Completion of French Drain and Checking of Compacted Soil level at Sump Pit Area prior to Start Anti-Termite CVL Al Firas 4-Nov-22 7-Nov-22 B B 3

473 ADN-AFC-WIR-CIV-416 00 Latest Inspection for Application of Anti-Termite at Sump Pit prior t oStart blinding CVL Al Firas 4-Nov-22 7-Nov-22 B B 3

474 ADN-AFC-WIR-CIV-417 00 Superseded Inspection for Formwork of Core Wall -03 prior to Start Concrete CVL Al Firas 4-Nov-22 7-Nov-22 C C 3

475 ADN-AFC-WIR-CIV-417 01 Latest Inspection for Formwork of Core Wall -03 prior to Start Concrete CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

476 ADN-AFC-WIR-CIV-418 00 Latest Inspection for marking of Cut off Level for Center Pile (Pile No. 153 to 158) prior to Start Breaking CVL Al Firas 6-Nov-22 7-Nov-22 B B 1

477 ADN-AFC-WIR-CIV-419 00 Latest Inspection for Primer Application on Wall prior to Start 1st Layer Waterproofing membrane at PC14 CVL Al Firas 6-Nov-22 7-Nov-22 B B 1

478 ADN-AFC-WIR-CIV-420 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor and Wall prior to Start 2nd Layer at PC15 CVL Al Firas 6-Nov-22 7-Nov-22 B B 1

479 ADN-AFC-WIR-CIV-421 00 Latest Inspection for Installation of Protection Board on Wall at PC1B, PC2 & PC5 CVL Al Firas 6-Nov-22 7-Nov-22 B B 1

480 ADN-AFC-WIR-CIV-422 00 Latest Inspection for Surface Preparation and Completion of Re-profilling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 4-Nov-22 7-Nov-22 B B 3

481 ADN-AFC-WIR-CIV-423 00 Latest Inspection for Checking of Compacted Soil Level at PC4, PC5, PC7 & PC1A prior to Start Anti Termite CVL Al Firas 7-Nov-22 7-Nov-22 B B 0

482 ADN-AFC-WIR-CIV-424 00 Latest Inspection for Application of Anti-Termite at PC4, PC5, PC7 & PC1A prior to Start blinding CVL Al Firas 7-Nov-22 7-Nov-22 B B 0

483 ADN-AFC-WIR-CIV-425 00 Latest Inspection for Application and Completion of Pile Top Endcalsulation (Epoxy Mortar - ALSAN CAP - E) at PC1B, PC2 & PC5 CVL Al Firas 7-Nov-22 7-Nov-22 B B 0

484 ADN-AFC-WIR-CIV-426 00 Latest Inspection for Installation of 2nd Layer Water proofing Membrane on Floor and Wall prior to Start Protection Screed at PC15 CVL Al Firas 7-Nov-22 10-Nov-22 B B 3

485 ADN-AFC-WIR-CIV-427 00 Latest Inspection for Surface Preparation on Floor and Wall at PC7A, PC1B and Blinding Surface Area prior to Start Primer CVL Al Firas 7-Nov-22 7-Nov-22 B B 0

486 ADN-AFC-WIR-CIV-428 00 Latest Inspection for Primer Application on Floor and Wall at PC7A, PC1B and Blinding Surface Area prior to Start Primer CVL Al Firas 7-Nov-22 7-Nov-22 B B 0

487 ADN-AFC-WIR-CIV-429 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor prior to Start 2nd Layer CVL Al Firas 7-Nov-22 8-Nov-22 B B 1

488 ADN-AFC-WIR-CIV-430 00 Latest Inspection for Checking of Compacted Soil Level at PC & PC7A prior to Start Anti-Termite CVL Al Firas 7-Nov-22 8-Nov-22 B B 1

489 ADN-AFC-WIR-CIV-431 00 Latest Inspection for Application of Anti-Termite at PC4 & PC7A prior to Start Blinding CVL Al Firas 7-Nov-22 8-Nov-22 B B 1

490 ADN-AFC-WIR-CIV-432 00 Latest Inspection for Installation of 1st Layer Membrane on Wall prior to Start 2nd Layer Waterpoofing Membrane at PC14 CVL Al Firas 8-Nov-22 8-Nov-22 B B 0

491 ADN-AFC-WIR-CIV-433 00 Latest Inspection for Rebar of Corewall 04 at PC13 prior to Start Formwork CVL Al Firas 8-Nov-22 10-Nov-22 B B 2

492 ADN-AFC-WIR-CIV-434 00 Latest Inspection for Installation of 2nd Layer Membrane on Wall prior to Start protection Board at PC14 CVL Al Firas 8-Nov-22 8-Nov-22 B B 0

493 ADN-AFC-WIR-CIV-435 00 Latest Inspection for Completion of Block Wall and Surface Preparation prior to Start primer Application on Wall PC12 CVL Al Firas 8-Nov-22 8-Nov-22 B B 0

494 ADN-AFC-WIR-CIV-436 00 Latest Inspection for Completion of Block Wall and Surface preparation prior to Start primer Application on Wall at PC3, PC1A, PC7A CVL Al Firas 8-Nov-22 10-Nov-22 B B 2

495 ADN-AFC-WIR-CIV-437 00 Latest Inspection for Checking of Compacted Soil Level at below the Raft Foundation to Start Anti-Termite CVL Al Firas 8-Nov-22 8-Nov-22 B B 0
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
496 ADN-AFC-WIR-CIV-438 00 Latest Inspection for Application of Anti-Termite at below the Raft Foundation CVL Al Firas 8-Nov-22 8-Nov-22 B B 0
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
497 ADN-AFC-WIR-CIV-439 00 Latest Inspection for Surface preparation on Floor at PC14 prior to Start Primer CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

498 ADN-AFC-WIR-CIV-440 00 Latest Inspection for Application of Primer on Floor PC14 prior to Start 1st layer Water Proofing membrane CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

499 ADN-AFC-WIR-CIV-441 00 Latest Inspection for Installation of Protection Board on Wall at PC14 CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

500 ADN-AFC-WIR-CIV-442 00 Latest Inspection for Installation of 1st Layer Water proofing Membrane on Floor and Wall at PC14 prior to Stat 2nd Layer Membrane CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

501 ADN-AFC-WIR-CIV-443 00 Latest Inspection for Installation of 1st & 2nd Layer Waterproofing Membrane on Wall at PC13 prior to Start protection Board CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

502 ADN-AFC-WIR-CIV-444 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor prior to Start 2nd Layer Membrane CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

503 ADN-AFC-WIR-CIV-445 00 Latest Inspection for Checking of Compacted Soil Level at Below the Raft Foundation prior to Start Anti-Termite CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

504 ADN-AFC-WIR-CIV-446 00 Latest Inspection for Application of Anti-Termite prior to Start Blinding at Below Raft Foundation Area CVL Al Firas 9-Nov-22 10-Nov-22 B B 1

505 ADN-AFC-WIR-CIV-447 00 Superseded Inspection for Rebar Works of PC13 retaining Walls prior to Start Formwork CVL Al Firas 9-Nov-22 10-Nov-22 C C 1

506 ADN-AFC-WIR-CIV-447 01 Latest Inspection for Rebar Works of PC13 retaining Walls prior to Start Formwork CVL Al Firas 11-Nov-22 16-Nov-22 B B 5

507 ADN-AFC-WIR-CIV-448 00 Latest Inspection for Installation of Protection Board on Wall at PC11 and PC13 (-12.300 to -9.300) CVL Al Firas 10-Nov-22 11-Nov-22 B B 1

508 ADN-AFC-WIR-CIV-449 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

509 ADN-AFC-WIR-CIV-450 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall CVL Al Firas 10-Nov-22 11-Nov-22 B B 1

510 ADN-AFC-WIR-CIV-451 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Wall prior to Start 2nd Layer Membrane (up to -6.50m) CVL Al Firas 10-Nov-22 11-Nov-22 B B 1

511 ADN-AFC-WIR-CIV-452 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Wall prior to Start Protection Board (up to -6.500m) CVL Al Firas 10-Nov-22 11-Nov-22 B B 1

Inspection for Installation of Water Stop, Injection Hose and Swellable Bars on Retaining Wall Construction Joint Area prior to
512 ADN-AFC-WIR-CIV-453 00 Latest
Start Form Work
CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

513 ADN-AFC-WIR-CIV-454 00 Latest Inspection for Checking of Compacted Soil Level as below the Raft Foundation and PC5 prior to Start Anti-Termite CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

514 ADN-AFC-WIR-CIV-455 00 Latest Inspection for Application of Anti-Termite at PC5 and below the Raft Foundation prior to start blinding CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

515 ADN-AFC-WIR-CIV-456 00 Latest Inspection for Formwork of Retaining Wall at PC13 prior to Start Concrete CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

516 ADN-AFC-WIR-CIV-457 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP-E) at PC11 & PC15 CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

517 ADN-AFC-WIR-CIV-458 00 Latest Inspection for Surface Preparation and Completion of Re-profiling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

Inspection for Application of Primer on Floor and Wall at PC3, PC7A, PC8 & PC1A prior to Start 1st Layer Waterproofing
518 ADN-AFC-WIR-CIV-459 00 Latest
Membrane
CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

519 ADN-AFC-WIR-CIV-460 00 Latest Inspection for Installation of Protection Board on Wall at PC14 CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

520 ADN-AFC-WIR-CIV-461 00 Latest Inspection for Surface Preparation prior to Start primer Application CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

521 ADN-AFC-WIR-CIV-462 00 Latest Inspection for Formwork of Core Wall - 04 prior to Start Concrete CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

522 ADN-AFC-WIR-CIV-463 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor and Wall at PC7A & PC5 prior to Start 2nd Layer CVL Al Firas 10-Nov-22 13-Nov-22 B B 3

523 ADN-AFC-WIR-CIV-464 00 Latest Inspection for Installation of Protection Board on Wall at PC6A, PC15 and Gunite Wall Area CVL Al Firas 10-Nov-22 13-Nov-22 B B 3

524 ADN-AFC-WIR-CIV-465 00 Latest Inspection for Rebar Works of Retaining Wall at PC13 prior to Start Formwork CVL Al Firas 10-Nov-22 14-Nov-22 B B 4

525 ADN-AFC-WIR-CIV-466 00 Superseded Inspection for Rebar Works of Water Tank Wall at PC13 prior to Start Formwork CVL Al Firas 10-Nov-22 14-Nov-22 C C 4

526 ADN-AFC-WIR-CIV-466 01 Latest Inspection for Rebar Works of Water Tank Wall at PC13 prior to Start Formwork CVL Al Firas 17-Nov-22 20-Nov-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
Inspection for Installation of 2nd Layer Waterpoofing Membrane on Floor and Wall at PC7A & PC5 prior to start Protection
527 ADN-AFC-WIR-CIV-467 00 Latest
Screed and Board
CVL Al Firas 13-Nov-22 14-Nov-22 B B 1

528 ADN-AFC-WIR-CIV-468 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor and Wall at PC7A & PC8 prior to Start 2nd Layer CVL Al Firas 13-Nov-22 14-Nov-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
529 ADN-AFC-WIR-CIV-469 00 Latest Inspection for Application of Primer on Wall prior to Start 1st Layer Waterproofing Membrane at PC12 CVL Al Firas 13-Nov-22 14-Nov-22 B B 1

530 ADN-AFC-WIR-CIV-470 00 Latest Inspection for Application of Primer on Floor prior to Start 1st Layer Waterproofing Membrane CVL Al Firas 13-Nov-22 14-Nov-22 B B 1

531 ADN-AFC-WIR-CIV-471 00 Latest Inspection for Surface Preparation and Completion of Re-profilling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 13-Nov-22 16-Nov-22 B B 3

Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall at PC7A & PC8 prior to Start protection
532 ADN-AFC-WIR-CIV-472 00 Latest
Screed
CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

533 ADN-AFC-WIR-CIV-473 00 Latest Inspection for Surface Preparation on Floor and Wall at PC12 prior to Start primer Application CVL Al Firas 13-Nov-22 14-Nov-22 B B 1

534 ADN-AFC-WIR-CIV-474 00 Latest Inspection for Application of primer on Floor and Wall at PC12 prior to Start 1st Layer Waterproofing Membrane CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

Inspection for Marking of Cut Off Level for Center Pile (Pile No. 139 to 142, 159 to 164, 26 to 35 & TC3-01 to TC3-04) prior to
535 ADN-AFC-WIR-CIV-475 00 Latest
Start Breaking
CVL Al Firas 13-Nov-22 16-Nov-22 B B 3

536 ADN-AFC-WIR-CIV-476 00 Latest Inspection for Installation Board on Wall at PC5 & PC7A CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

537 ADN-AFC-WIR-CIV-477 00 Latest Inspection for Installation of 1st Layer Waterpoofing Membrane on Floor and Wall at PC12 prior to Start 2nd Layer Membrane CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

538 ADN-AFC-WIR-CIV-478 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP-E) at PC5, PC7A & PC8 CVL Al Firas 13-Nov-22 16-Nov-22 B B 3

539 ADN-AFC-WIR-CIV-479 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor Area piror to Start 2nd Layer Membrane CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

540 ADN-AFC-WIR-CIV-480 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor Area prior to Start protection Screed CVL Al Firas 13-Nov-22 16-Nov-22 B B 3

541 ADN-AFC-WIR-CIV-481 00 Latest Inspection for Application of primer on gunite Wall prior to Start 1st Layer Waterproofing membrane CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

542 ADN-AFC-WIR-CIV-482 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Gunite Wall prior to Start 2nd Layer Membrane CVL Al Firas 13-Nov-22 15-Nov-22 B B 2

543 ADN-AFC-WIR-CIV-483 00 Latest Inspection for Rebar Works PC14 Foundation prior to Start Concrete CVL Al Firas 13-Nov-22 20-Nov-22 B B 7

544 ADN-AFC-WIR-CIV-484 00 Latest Inspection for Form Work of Retaining Wall at PC13 prior to Start Concrete CVL Al Firas 14-Nov-22 16-Nov-22 B B 2

545 ADN-AFC-WIR-CIV-485 00 Superseded Inspection for Form Work of Retaining and Fire Water Tank Wall at PC13 prior to Start Concrete CVL Al Firas 14-Nov-22 15-Nov-22 C C 1

546 ADN-AFC-WIR-CIV-485 01 Latest Inspection for Form Work of Retaining and Fire Water Tank Wall at PC13 prior to Start Concrete CVL Al Firas 6-Dec-22 11-Dec-22 A A 5

547 ADN-AFC-WIR-CIV-486 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on gunite Wall prior to Start Protection Board CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

Inspection for Installation of 2nd layer Waterproofing Membrane on Floor and Wall at PC12 prior to Start protection Screed
548 ADN-AFC-WIR-CIV-487 00 Latest
and protection Board
CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

549 ADN-AFC-WIR-CIV-488 00 Latest Inspection for Checking of Compacted Soil Level at PC4, PC5 & TC3 prior to Start Anti-Termite CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

550 ADN-AFC-WIR-CIV-489 00 Latest Inspection for Application of Anti-Termite at PC4, PC5 & TC3 prior to Start Blinding CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

551 ADN-AFC-WIR-CIV-490 00 Latest Inspection for Surface preparation on Floor and Wall at PC6, PC7B, PC16, PC6A & Gunite Wall prior to Start primer Application CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

Inspection for Application of Primer on Floor and Wall at PC7B, PC6, PC16, PC6A & Gunite Wall prior to Start 1st Layer
552 ADN-AFC-WIR-CIV-491 00 Latest
Waterproofing Membrane
CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

553 ADN-AFC-WIR-CIV-492 00 Latest Inspection for Application of Primer on Floor to Start 1st Layer Waterproofing Membrane CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

554 ADN-AFC-WIR-CIV-493 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor prior to Start 2nd Layer Membrane CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

555 ADN-AFC-WIR-CIV-494 00 Latest Inspection for Rebar Works of Retaining Wall at PC13 prior to Start Formwork CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

556 ADN-AFC-WIR-CIV-495 00 Latest Inspection for Form Work of Retianing Wall at PC13 prior to Start Concrete CVL Al Firas 14-Nov-22 17-Nov-22 B B 3

557 ADN-AFC-WIR-CIV-496 00 Superseded Inspection for Bottom Layer Rebards of Pile Cap (PC1, PC1A, PC1B, PC3, PC4, PC6A, PC7A, PC11& PC15) and Raft Foundation CVL Al Firas 16-Nov-22 20-Nov-22 C C 4

558 ADN-AFC-WIR-CIV-496 01 Latest Inspection for Bottom Layer Rebards of Pile Cap (PC1, PC1A, PC1B, PC3, PC4, PC6A, PC7A, PC11& PC15) and Raft Foundation CVL Al Firas 24-Nov-22 27-Nov-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
559 ADN-AFC-WIR-CIV-497 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor prior to Start protection Screed CVL Al Firas 16-Nov-22 17-Nov-22 B B 1

Inspection for Installation of 1st layer Waterproofing Membrane on Gunite Wall (2nd Stage up to -6.500m) prior to Start 2nd
560 ADN-AFC-WIR-CIV-498 00 Latest
Layer Membrane
CVL Al Firas 16-Nov-22 17-Nov-22 B B 1

Inspection for Installation of 2nd Layer Waterproofing Membrane on Gunite Wall (2nd Stage up to -6.500M) prior to Start
561 ADN-AFC-WIR-CIV-499 00 Superseded
Protection Board
CVL Al Firas 16-Nov-22 17-Nov-22 C C 1

Inspection for Installation of 2nd Layer Waterproofing Membrane on Gunite Wall (2nd Stage up to -6.500M) prior to Start
562 ADN-AFC-WIR-CIV-499 01 Latest
Protection Board
CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

563 ADN-AFC-WIR-CIV-500 00 Latest Inspection for Installation of Protection Board on Wall (2nd Stage up to -6.500M) CVL Al Firas 16-Nov-22 17-Nov-22 B B 1

564 ADN-AFC-WIR-CIV-501 00 Latest Inspection for Rebar of retaining Wall at PC13 prior to Start Formwork CVL Al Firas 16-Nov-22 17-Nov-22 B B 1

565 ADN-AFC-WIR-CIV-502 00 Latest Inspection for Formworks of Retaining Wall at PC13 prior to Start Concrete CVL Al Firas 16-Nov-22 17-Nov-22 B B 1

566 ADN-AFC-WIR-CIV-503 00 Latest Inspection for Installation of Water Stop, Injection Hose and Swellable bars on Retianing Wall Construction Joint Area CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

567 ADN-AFC-WIR-CIV-504 00 Latest Inspection for Installation of Protection Board on Gunite Wall (2nd Stage up to -6.500M) CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

568 ADN-AFC-WIR-CIV-505 00 Latest Inspection for Surface Preparation on Floor piror to Start Primer Application CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

569 ADN-AFC-WIR-CIV-506 00 Latest Inspection for Marking of Cut Off Level for Center Pile (Pile No. 135 to 138) prior to Start Breaking CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

570 ADN-AFC-WIR-CIV-507 00 Latest Inspection for Surface Preparation on Floor and Wall at PC6A, PC6B & PC15 prior to Start Primer Application CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

571 ADN-AFC-WIR-CIV-508 00 Latest Inspection for Installation of Protection Board on Wall at PC 12 CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

572 ADN-AFC-WIR-CIV-509 00 Latest Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP-E) at PC12 CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

573 ADN-AFC-WIR-CIV-510 00 Latest Inspection for Checking As Built Center Pile Location at PC12 CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

574 ADN-AFC-WIR-CIV-511 00 Latest Inspection for Rebar Works of Retaining Wall at PC13 prior to Start Formwork CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

575 ADN-AFC-WIR-CIV-512 00 Latest Inspection for Formwork of Retaining Wall and Water Tank Wall at PC13 prior to Start Concrete CVL Al Firas 17-Nov-22 23-Nov-22 B B 6

Inspection for Installation of 1st Layer Waterproofing Membrane on Gunite Wall (up to -6.500M) prior to Start 2nd Layer
576 ADN-AFC-WIR-CIV-513 00 Latest
Membrane
CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

577 ADN-AFC-WIR-CIV-514 00 Latest Inspection for Installation of Water Stop & Injection Hose at PC14, PC4, PC5 & PC17 Foundation CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

578 ADN-AFC-WIR-CIV-515 00 Latest Inspection for Installation of Steel Section for Composite Column C6 at PC14 CVL Al Firas 17-Nov-22 20-Nov-22 B B 3

579 ADN-AFC-WIR-CIV-516 00 Latest Inspection for Installation of 2nd Layer Water proofing Membrane on Gunite Wall (up to -6.50M) prior to Start Protection Board CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

580 ADN-AFC-WIR-CIV-517 00 Latest Inspection for Installation of Protection Board on Gunite Wall (up to -6.500M) CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

581 ADN-AFC-WIR-CIV-518 00 Superseded Inspection for Bottom Layer Rebar of PC12 CVL Al Firas 17-Nov-22 23-Nov-22 C C 6

582 ADN-AFC-WIR-CIV-518 01 Latest Inspection for Bottom Layer Rebar of PC12 CVL Al Firas 25-Nov-22 27-Nov-22 B B 2

583 ADN-AFC-WIR-CIV-519 00 Latest Inspection for Surface preparation on Floor Area prior to Start Primer Application CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

584 ADN-AFC-WIR-CIV-520 00 Latest Inspection for Primer Application on Floor Area prior to Start 1st Layer Water proofing Membrane CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

585 ADN-AFC-WIR-CIV-521 00 Latest Inspection for Checking of Compacted Soil Level below the Raft Foundation prior to Start Anti-Termite CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

586 ADN-AFC-WIR-CIV-522 00 Latest Inspection for Application of Anti-Termite at below the Raft Foundation prior to Start Blinding CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

587 ADN-AFC-WIR-CIV-523 00 Latest Inspection for Primer Application on Floor Area prior to Start 1st Layer Water proofing Membrane CVL Al Firas 18-Nov-22 20-Nov-22 B B 2

588 ADN-AFC-WIR-CIV-524 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor Area CVL Al Firas 18-Nov-22 20-Nov-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
589 ADN-AFC-WIR-CIV-525 00 Latest Inspection for Surface Preparation on Floor Area prior to Start Primer Application CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

590 ADN-AFC-WIR-CIV-526 00 Latest Inspection for Primer Application on Floor and Wall Area prior to Start 1st Layer Waterproofing Membrane CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

591 ADN-AFC-WIR-CIV-527 00 Latest Inspection for Installation of 1st Layer Waterproofing Membrane on Floor Area CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

592 ADN-AFC-WIR-CIV-528 00 Latest Inspection for Surface Preparation and Completion of Re-profiling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 20-Nov-22 24-Nov-22 B B 4

593 ADN-AFC-WIR-CIV-529 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor Area prior to Start protection Screed CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

594 ADN-AFC-WIR-CIV-530 00 Latest Inspection for Rebar of Retaining Wall at PC14 CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

595 ADN-AFC-WIR-CIV-531 00 Latest Inspection for FormWork of Retaining Wall prior to Start Concrete CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

596 ADN-AFC-WIR-CIV-532 00 Latest Inspection for Primer Application on Gunite Wall Area (up to -3.00M) prior to Start 1st Layer Waterproofing Membrane CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

Inspection for Installation of 1st Layer Waterproofing membrane on Gunite Wall (up to -3.00M) prior to Start 2nd Layer
597 ADN-AFC-WIR-CIV-533 00 Latest
Membrane
CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

598 ADN-AFC-WIR-CIV-534 00 Latest Inspection for Installation of Water stop, Injection Hose and Swellable Tape at Fire Water Tank Wall Construction Joint Area CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

599 ADN-AFC-WIR-CIV-535 00 Latest Inspection for Formwork of Fire Water Tank wall prior to Start Concrete CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

600 ADN-AFC-WIR-CIV-536 00 Latest Inspection for Installation of Water Stop, Injection Hose and Swellable Bar at PC14 Retaining Wall Construction Joint Area CVL Al Firas 20-Nov-22 23-Nov-22 B B 3

601 ADN-AFC-WIR-CIV-537 00 Superseded Inspection for Rebar of Pile Cap PC12 prior to Start Concrete (up to -11.900M) CVL Al Firas 21-Nov-22 23-Nov-22 C C 2

602 ADN-AFC-WIR-CIV-537 01 Latest Inspection for Rebar of Pile Cap PC12 prior to Start Concrete (up to -11.900M) CVL Al Firas 25-Nov-22 27-Nov-22 B B 2

603 ADN-AFC-WIR-CIV-538 00 Latest Inspection for Installation of Water Stop & Injection Hose at PC12 Foundation Construction Joint Area CVL Al Firas 21-Nov-22 24-Nov-22 B B 3

604 ADN-AFC-WIR-CIV-539 00 Latest Inspection for FormWork of Domestic Water Tank Wall prior to Start Concrete CVL Al Firas 21-Nov-22 23-Nov-22 B B 2

Inspection for Installation of Water Stop, Injection Hose and Swellable Tape at Domestic Water Tank Wall Construction Joint
605 ADN-AFC-WIR-CIV-540 00 Latest
Area
CVL Al Firas 21-Nov-22 23-Nov-22 B B 2

606 ADN-AFC-WIR-CIV-541 00 Superseded Inspection for Rebar of Retaining Wall at PC14 CVL Al Firas 21-Nov-22 23-Nov-22 C C 2

607 ADN-AFC-WIR-CIV-541 01 Latest Inspection for Rebar of Retaining Wall, Fire Water Tank and Domestic Water Tank Wall at PC14 CVL Al Firas 24-Nov-22 27-Nov-22 B B 3

608 ADN-AFC-WIR-CIV-542 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Gunite Wall (up to -3.00M) prior to Start Protection Board CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

609 ADN-AFC-WIR-CIV-543 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor Area prior to Start Protection Screed CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

610 ADN-AFC-WIR-CIV-544 00 Latest Inspection for Installation of protection Board on Gunite Wall (up to -3.00M) CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

Inspection for Installation of 1st Layer Waterproofing Membrane on Floor and Wall at PC 1A, PC3, PC7B, PC6 & PC16 prior to
611 ADN-AFC-WIR-CIV-545 00 Latest
Start 2nd Layer Membrane
CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall at PC 1A. PC3. PC7B. PC6 & PC16 prior to
612 ADN-AFC-WIR-CIV-546 00 Latest
Start protection Screed
CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

613 ADN-AFC-WIR-CIV-547 00 Latest Inspection for Surface preparation of Gunite Wall (up to -3.00M) prior to Start primer application CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

614 ADN-AFC-WIR-CIV-548 00 Latest Inspection for Application of Primer on Gunite Wall (up to -3.00M) prior to Start 1st Layer membrane CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

615 ADN-AFC-WIR-CIV-549 00 Latest Inspection for Installation of 1st layer Waterproofing Membrane on Floor Area prior to Start 2nd layer membrane CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

616 ADN-AFC-WIR-CIV-550 00 Latest Inspection for Completion of Block Wall and Surface preparation on Floor and Wall at TC-03 prior to Start primer Application CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

617 ADN-AFC-WIR-CIV-551 00 Latest Inspection for Application of Primer on Floor and Wall at TC-03 prior to Start 1st Layer Water Proofing Membrane CVL Al Firas 22-Nov-22 23-Nov-22 B B 1

618 ADN-AFC-WIR-CIV-552 00 Latest Inspection for Rebar of Shear Wall SW24 at PC13 prior to Start Form Work CVL Al Firas 22-Nov-22 23-Nov-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
619 ADN-AFC-WIR-CIV-553 00 Latest Inspection for Formwork of Shear Wall SW24 at PC13 prior to Start Concrete CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

Inspection for Application and Completion of Pile Top Endcapsulation (Epoxy Mortar - ALSAN CAP-E) at PC1A, PC3, PC7B, PC6 &
620 ADN-AFC-WIR-CIV-554 00 Latest
PC16
CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

621 ADN-AFC-WIR-CIV-555 00 Latest Inspection for Installation of Protection Board at PC1A, PC3, PC7B, PC6 & PC16 CVL Al Firas 22-Nov-22 27-Nov-22 B B 5

622 ADN-AFC-WIR-CIV-556 00 Latest Inspection for Installation of 1st Layer Waterpoofing Membrane on Floor and Wall at PC03 prior to Start 2nd Layer Membrane CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

623 ADN-AFC-WIR-CIV-557 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall at TC-03 prior to Start Protection Screed CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

624 ADN-AFC-WIR-CIV-558 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor Area prior to Start Protection Screed CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

Inspection for Installation of 1st Layer Waterproofing membrane on Gunite Wall (up to -3.00M) prior to Start 2nd Layer
625 ADN-AFC-WIR-CIV-559 00 Latest
Membrane
CVL Al Firas 22-Nov-22 24-Nov-22 B B 2

626 ADN-AFC-WIR-CIV-560 00 Latest Inspection for Surface preparation prior to Start gunite mesh installation (grid line F*-H/2*) CVL Al Firas 23-Nov-22 28-Nov-22 A A 5

627 ADN-AFC-WIR-CIV-561 00 Latest Inspection for Gunite Mesh Installation (grid line F*-H*/2) prior to start gunite CVL Al Firas 23-Nov-22 28-Nov-22 B B 5

628 ADN-AFC-WIR-CIV-562 00 Latest Inspection for Rebar Works of Plot C12 Full Raft Slab and Pile Caps prior to Casting Concrete CVL Al Firas 23-Nov-22 29-Nov-22 B B 6

629 ADN-AFC-WIR-CIV-563 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on gunite Wall (up to -3.00M) prior to start protection board CVL Al Firas 24-Nov-22 27-Nov-22 B B 3

630 ADN-AFC-WIR-CIV-564 00 Latest Inspection for Installation of protection board on Wall at TC-03 CVL Al Firas 24-Nov-22 27-Nov-22 B B 3

631 ADN-AFC-WIR-CIV-565 00 Latest Inspection for Checking of As-Built Center Pile Location (Pile No. 64 to 102, 341 to 355 & TC3-1 to 4) CVL Al Firas 24-Nov-22 27-Nov-22 B B 3

632 ADN-AFC-WIR-CIV-566 00 Latest Inspection for Rebar of Columns (C3, C4 & C6) and Shear Wall (SW5) at PC14 prior to Start Formwork CVL Al Firas 24-Nov-22 4-Dec-22 B B 10

633 ADN-AFC-WIR-CIV-567 00 Latest Inspection for Form Work of Retaining Wall & Domestic Water Tank with Pump Room Wall prior to Start Concrete at PC14 CVL Al Firas 24-Nov-22 28-Nov-22 B B 4

634 ADN-AFC-WIR-CIV-568 00 Latest Inspection for Installation of protection Board on gunite Wall up to -3.000M CVL Al Firas 24-Nov-22 27-Nov-22 B B 3

635 ADN-AFC-WIR-CIV-569 00 Latest Inspection for Installation of 1st Layer Water Proofing Membrane on Floor Area prior to Start 2nd Layer Membrane CVL Al Firas 25-Nov-22 27-Nov-22 B B 2

636 ADN-AFC-WIR-CIV-570 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor Area prior to Start protection Screed CVL Al Firas 25-Nov-22 27-Nov-22 B B 2

637 ADN-AFC-WIR-CIV-571 00 Latest Inspection for Installation of Protection Board (2 Layers) on Pipe Incasement Trench Side Wall CVL Al Firas 25-Nov-22 27-Nov-22 B B 2

638 ADN-AFC-WIR-CIV-572 00 Latest Inspection for Rebar of Tower Crane (TC-3) Foundation prior to Start Concrete CVL Al Firas 25-Nov-22 27-Nov-22 B B 2

639 ADN-AFC-WIR-CIV-573 00 Latest Inspection for Bottom Layer Rebar of PC1A, PC3, PC7A, PC7B, PC6, PC8 & PC16 CVL Al Firas 25-Nov-22 29-Nov-22 B B 4

640 ADN-AFC-WIR-CIV-574 00 Latest Inspection for Completion of Excavation at Plot C11 & C12 CVL Al Firas 25-Nov-22 27-Nov-22 A A 2

641 ADN-AFC-WIR-CIV-575 00 Latest Inspection for Installation of Waterstop & Injection Hose at Plot C12 Raft Slab Foundation CVL Al Firas 27-Nov-22 28-Nov-22 B B 1

642 ADN-AFC-WIR-CIV-576 00 Latest Inspection for Rebar of Retaining Wall, Shear Wall (SW6) and Column (C21) prior to start Form Work CVL Al Firas 28-Nov-22 4-Dec-22 B B 6

643 ADN-AFC-WIR-CIV-577 00 Latest Inspection for Rebar of Fire Water Tank Wall prior to Start Formwork CVL Al Firas 28-Nov-22 4-Dec-22 B B 6

644 ADN-AFC-WIR-CIV-578 00 Latest Inspection for Form Work of Retaining Wall, Shear Wall (SW26) and Column (C21) prior to Start Concrete CVL Al Firas 28-Nov-22 4-Dec-22 B B 6

645 ADN-AFC-WIR-CIV-579 00 Latest Inspection for Completion of French Drain (60cmx80cm) CVL Al Firas 28-Nov-22 4-Dec-22 B B 6

Inspection for Completion of Block Wall and Surface Preparation on Floor and Wall at Pile Caps and Blinding Floor Area prior to
646 ADN-AFC-WIR-CIV-580 00 Latest
Start Primer Application
CVL Al Firas 28-Nov-22 4-Dec-22 B B 6

647 ADN-AFC-WIR-CIV-581 00 Latest Inspection for primer application on floor and Wall at Pile Caps and Blinding Floor Area prior to Start 1st Later Membrane CVL Al Firas 28-Nov-22 4-Dec-22 B B 6

648 ADN-AFC-WIR-CIV-582 00 Latest Inspection for Installation of 1st layer Waterproofing Membrane on Floor and Wall Area prior to Start 2nd Layer membrane CVL Al Firas 28-Nov-22 4-Dec-22 B B 6
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
649 ADN-AFC-WIR-CIV-583 00 Latest Inspection for Form Work of Fire Water Tank and Retaining Wall at PC14 prior to Start Concrete CVL Al Firas 28-Nov-22 29-Nov-22 B B 1

650 ADN-AFC-WIR-CIV-584 00 Latest Inspection for Installation of protection Board on Gunite Wall up to -3.000M CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

651 ADN-AFC-WIR-CIV-585 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall Area prior to Start Screed CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

652 ADN-AFC-WIR-CIV-586 00 Latest Inspection for Completion of Gunite (grid line D-A/7**, 7**-1**/A & A*-G*/2) CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

653 ADN-AFC-WIR-CIV-587 00 Latest Inspection for Surface Preparation and Completion of Re-profiling Grout on Pile Heads (ALSAN CAP C) CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

Inspection for Rebar and all other embedment items (water stop, injection hose & swellable bar) of retaining wall from B2 to
654 ADN-AFC-WIR-CIV-588 00 Latest
B1 prior to start form work
CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

655 ADN-AFC-WIR-CIV-589 00 Latest Inspection for Form Work of retaining Wall form B2 to B1 prior to start concrete CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

656 ADN-AFC-WIR-CIV-590 00 Latest Inspection for FormWork of Fire Water Tank wall from B2 to B1 prior to start concrete CVL Al Firas 29-Nov-22 6-Dec-22 B B 7

Inspection for Installation of 1st Layer Waterproofing membrane on Floor and Wall Area at Pile Cap PC6A and PC15 to Start
657 ADN-AFC-WIR-CIV-591 00 Latest
2nd layer Membrane
CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

Inspection for Installation of 2nd Layer Waterproofing Membrane on Floor and Wall Area at Pile Cap PC6A and PC15 prior to
658 ADN-AFC-WIR-CIV-592 00 Latest
Start protection screed
CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

659 ADN-AFC-WIR-CIV-593 00 Latest Inspection for Rebar of Core Wall at PC12 prior to Start Form Work CVL Al Firas 29-Nov-22 5-Dec-22 B B 6

660 ADN-AFC-WIR-CIV-594 00 Latest Inspection for Form Work of Core Wall at PC12 prior to Start Concrete CVL Al Firas 29-Nov-22 4-Dec-22 C C 5

661 ADN-AFC-WIR-CIV-595 00 Latest Inspection for Rebar of Shear Wall (SW5) and Column (C6) prior to Start Form Work CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

662 ADN-AFC-WIR-CIV-596 00 Latest Inspection for Form Work of Shear Wall (SW5) and Column (C6) prior to Start Concrete CVL Al Firas 29-Nov-22 4-Dec-22 B B 5

663 ADN-AFC-WIR-CIV-597 00 Latest Inspection for Rebar of Water Tank Wall prior to start form work CVL Al Firas 29-Nov-22 5-Dec-22 B B 6

664 ADN-AFC-WIR-CIV-598 00 Latest Inspection for Rebar of Core Wall 04 prior to start form work CVL Al Firas 29-Nov-22 5-Dec-22 B B 6

665 ADN-AFC-WIR-CIV-599 00 Latest Inspection for Checking of Compacted Soil Level prior to Start Anti-Termite CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

666 ADN-AFC-WIR-CIV-600 00 Latest Inspection for Application of Anti-Termite prior to Start Blinding CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

Inspection for Installation of 1st Layer Waterproofing Membrane on Gunite Wall (up to -6.500M) prior to Start 2nd Layer
667 ADN-AFC-WIR-CIV-601 00 Latest
Membrane
CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

668 ADN-AFC-WIR-CIV-602 00 Latest Inspection for Installation of 2nd Layer Waterproofing membrane on Gunite Wall (up to -6.500M) prior to Start protection Board CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

Inspection for Installation of 1st Layer Waterpoofing Membrane on Pile Caps Floor and Wall & blinding Floor Area prior to Start
669 ADN-AFC-WIR-CIV-603 00 Latest
2nd Layer Membrane
CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

Inspection for Installation of 2nd Layer Waterproofing Membrane on Pile caps Floor and Wall & Blinding Floor Area prior to
670 ADN-AFC-WIR-CIV-604 00 Latest
Start protection Screed
CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

671 ADN-AFC-WIR-CIV-605 00 Latest Inspection for Installation of Protection Board on Wall at Pile Cap CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

672 ADN-AFC-WIR-CIV-606 00 Latest Inspection for Rebar of Retaining Wall & Shear Wall prior to Start Form Work CVL Al Firas 30-Nov-22 5-Dec-22 B B 5

673 ADN-AFC-WIR-CIV-607 00 Latest Inspection for Rebar of Core Wall 03 prior to start Form Work CVL Al Firas 30-Nov-22 6-Dec-22 B B 6

674 ADN-AFC-WIR-CIV-608 00 Latest Inspection for Application and Completion of Pile Top Encapsulation (Epoxy Mortar - ALSAN CAP-E) at PC4, PC10, PC6A & PC15 CVL Al Firas 30-Nov-22 4-Dec-22 B B 4

675 ADN-AFC-WIR-CIV-609 00 Latest Inspection for Installation of Protection Board on Gunite Wall (up to -6.500M) CVL Al Firas 30-Nov-22 5-Dec-22 B B 5

676 ADN-AFC-WIR-CIV-610 00 Latest Inspection for Completion of Block Wall and Surface Preparation on Pile Cap and Blinding Area prior to Start Primer CVL Al Firas 30-Nov-22 5-Dec-22 B B 5

677 ADN-AFC-WIR-CIV-611 00 Latest Inspection for Application of Primer on Floor and Wall at Pile Cap and Blinding Area prior to start 1st layer Membrane CVL Al Firas 30-Nov-22 5-Dec-22 B B 5

Inspection for Installation of 1st layer Waterpoofing membrane on Floor and Wall at Pile Cap, Sump Pit & Blinding Floor Area
678 ADN-AFC-WIR-CIV-612 00 Latest
Prior to Start 2nd Layer membrane
CVL Al Firas 30-Nov-22 5-Dec-22 B B 5
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
Inspection for Installation of 2nd Layer Waterproofing membrane on Floor and Wall at Pile Cap, Sump Pit & Blinding floor Area
679 ADN-AFC-WIR-CIV-613 00 Latest
prior to Start protection Screed
CVL Al Firas 30-Nov-22 5-Dec-22 B B 5

Inspection for Form Work and All Other Embedments (Water Stop, Injection Hose & Swellable Bar) of Retianing Wall &
680 ADN-AFC-WIR-CIV-614 00 Latest
Shearwalls from B2 to B1 prior to Start Concrete
CVL Al Firas 4-Dec-22 6-Dec-22 B B 2

681 ADN-AFC-WIR-CIV-615 00 Latest Inspection for Form Work of Core Wall -04 from B2 to B1 prior to Start Concrete CVL Al Firas 4-Dec-22 11-Dec-22 B B 7

682 ADN-AFC-WIR-CIV-616 00 Superseded Inspection for Bottom and Top Layer Rebar of PC1A, PC7A, PC8, PC3, PC7B, PC6, PC16 & PC6A CVL Al Firas 4-Dec-22 6-Dec-22 C C 2

683 ADN-AFC-WIR-CIV-616 01 Latest Inspection for Bottom and Top Layer Rebar of Pile Caps PC1A, PC3, PC4, PC5, PC6, PC7, PC7A, PC7B, PC8, PC10, PC15 & PC16 CVL Al Firas 8-Dec-22 9-Dec-22 B B 1

684 ADN-AFC-WIR-CIV-617 00 Latest Inspection for Rebar of Retaining Wall and Shear Walls from B2 to B1 prior to Start Form Work CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

Inspection for Form Work and All Other Embedment Items (water Stop, Injection Hose & Swellable Bar) of Retaining Wall &
685 ADN-AFC-WIR-CIV-618 00 Latest
Shear Walls from B2 to B1 prior to Start Concrete
CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

686 ADN-AFC-WIR-CIV-619 00 Latest Inspection for Completion fo Block Wall and Surface preparation on Pile Cap and Blinding Area prior to Start Primer CVL Al Firas 5-Dec-22 6-Dec-22 B B 1

687 ADN-AFC-WIR-CIV-620 00 Latest Inspection for Application of Primer on Floor and Wall at Pile Cap and Blinding Area prior to start 1st layer Membrane CVL Al Firas 5-Dec-22 6-Dec-22 B B 1

688 ADN-AFC-WIR-CIV-621 00 Latest Inspection for the Rectification Works Done in Core Wall 04 CVL Al Firas 5-Dec-22 11-Dec-22 A A 6

Inspection for Installation of 1st Layer Water Proofing Memebrane on Floor and Wall at Pile Cap & Blinding Floor Area Prior to
689 ADN-AFC-WIR-CIV-622 00 Latest
Start 2nd Layer Membrane
CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

Inspection for Installation of 2nd layer Water Proofing Membrane on Floor and Wall Pile Cap & Blinding Floor Area prior to
690 ADN-AFC-WIR-CIV-623 00 Latest
Start Protection Screed
CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

691 ADN-AFC-WIR-CIV-624 00 Latest Inspection for Surface Preparation of Gunite Wall (up to bottom of Capping Beam -1.550 & -3.050m) prior to Start primer CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

Inspection for Application of Primer on Gunite Wall (up to Bottom of capping beam -1.550 & -3.050m) prior to start 1st layer
692 ADN-AFC-WIR-CIV-625 00 Latest
waterproofing membrane
CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

693 ADN-AFC-WIR-CIV-626 00 Latest Inspection for Form Work of Core Wall -03 from B2 to B1 prior to Start Concrete CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

694 ADN-AFC-WIR-CIV-627 00 Latest Inspection for Rebar of Shear Wall (SW-24) from B2 to B1 prior to Start Form Work CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

Inspection for Form Work and All Other Embedment Items (water Stop, Swellable bar and injection Hose) of Retaining Wall
695 ADN-AFC-WIR-CIV-628 00 Latest
with shear walls and shear wall (SW-24) from B2 to B1 priot to Start Concrete
CVL Al Firas 5-Dec-22 11-Dec-22 B B 6

696 ADN-AFC-WIR-CIV-629 00 Latest Inspection for Installation of Protection Board on Wall at Pile Cap CVL Al Firas 6-Dec-22 11-Dec-22 B B 5

697 ADN-AFC-WIR-CIV-630 00 Latest Inspection for Application and Completion of Pile Top Encapsulation (Epoxy Mortar - ALSAN CAP-E) at PC1A, PC9, PC4, PC5, PC7 CVL Al Firas 6-Dec-22 11-Dec-22 B B 5

698 ADN-AFC-WIR-CIV-631 00 Latest Inspection for Checking As Built Center Pile Location (Pile No. 01 to 41, 131 to 168, 239 to 255 & 357 to 391 CVL Al Firas 6-Dec-22 11-Dec-22 B B 5

Inspection for Installation of 1st Layer Water Proofing Memebrane on Floor and Wall at Pile Cap & Blinding Floor Area Prior to
699 ADN-AFC-WIR-CIV-632 00 Latest
Start 2nd Layer Membrane
CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

Inspection for Installation of 2nd Layer Water proofing Membrane on Floor and Wall at Pile Cap & Blinding Floor Area prior to
700 ADN-AFC-WIR-CIV-633 00 Latest
Start protection Screed
CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

Inspection for Installation of 1st Layer Waterproofing Membrane on Gunite Wall (up to -3.050m) prior to start 2nd Layer
701 ADN-AFC-WIR-CIV-634 00 Latest
Membrane
CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

702 ADN-AFC-WIR-CIV-635 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Gunite Wall (up to -3.050m) prior to start protection board CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

703 ADN-AFC-WIR-CIV-636 00 Latest Inspection for Installation of Protection Board (2 Layers) on pipe incasement Trench Side Wall CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

704 ADN-AFC-WIR-CIV-637 00 Latest Inspection for Rebar of Water Tank and Ramp Wall from B2 to B1 prior to Start Form Work CVL Al Firas 7-Dec-22 9-Dec-22 B B 2

Inspection for Form Work and All other embedment Items (water Stops, Swellable Bar and Injection Hose) of retaining wall
705 ADN-AFC-WIR-CIV-638 00 Latest
with shear walls from B2 to B1 prior to Start concrete
CVL Al Firas 7-Dec-22 11-Dec-22 B B 4

706 ADN-AFC-WIR-CIV-639 00 Latest Inspection for Installation of protection Board on Pile Caps and Gunite Wall Area CVL Al Firas 8-Dec-22 11-Dec-22 B B 3

707 ADN-AFC-WIR-CIV-640 00 Latest Inspection for Surface preparation of Gunite Wall (-3.050m) prior to Start Primer CVL Al Firas 8-Dec-22 11-Dec-22 B B 3

Inspection for Application of Primer on Gunite Wall (up to bottom of capping beam -3.050m) prior to Start 1st Layer
708 ADN-AFC-WIR-CIV-641 00 Latest
Waterproofing Membrane
CVL Al Firas 8-Dec-22 11-Dec-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
Inspection for Installation of 1st Layer Waterproofing Membrane on Gunite Wall (up to -3.050m) prior to start 2nd Layer
709 ADN-AFC-WIR-CIV-642 00 Latest
Membrane
CVL Al Firas 8-Dec-22 11-Dec-22 B B 3

710 ADN-AFC-WIR-CIV-643 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Gunite Wall (up to -3.050m) prior to start protection board CVL Al Firas 8-Dec-22 11-Dec-22 B B 3

711 ADN-AFC-WIR-CIV-644 00 Latest Inspection for Installation of protection Board on Gunite Wall (up to -3.050m) CVL Al Firas 8-Dec-22 11-Dec-22 B B 3

Inspection for Form Work and All Other Embedment Items (Water stop, swellable bar and injection Hose) of Retaining Wall
712 ADN-AFC-WIR-CIV-645 00 Latest
with shear wall and ramp wall from B2 to B1 prior to Start concrete
CVL Al Firas 8-Dec-22 12-Dec-22 B B 4

Inspection for Form Work and All Other Embedment Items (water stop, swellable bar and injection hose) of Water Tank Wall
713 ADN-AFC-WIR-CIV-646 00 Latest
and Ramp Wall from B2 to B1 prior to Start Concrete
CVL Al Firas 8-Dec-22 12-Dec-22 A A 4

714 ADN-AFC-WIR-CIV-647 00 Latest Inspection for Completion of Pile and Raft Foundation Rebar prior to Start Concrete CVL Al Firas 9-Dec-22 12-Dec-22 B B 3

715 ADN-AFC-WIR-CIV-648 00 Latest Inspection for Installation of Waterproofing System (Water stop, injection hose and swellable car) at plot c11 raft foundation CVL Al Firas 9-Dec-22 12-Dec-22 B B 3

716 ADN-AFC-WIR-CIV-649 00 Latest Inspection for Installation of protection board on Gunite Wall (up to -3.050m) CVL Al Firas 9-Dec-22 12-Dec-22 B B 3

Inspection for Form Work and All Other Embedment Items (Water stop, swellable bar and injection hose) of Water Tank Wall
717 ADN-AFC-WIR-CIV-650 00 Latest
from B2 to B1 prior to start concrete
CVL Al Firas 9-Dec-22 12-Dec-22 A A 3

718 ADN-AFC-WIR-CIV-651 00 Latest Inspection for Rebar of Retaining Wall & Column from B2 to B1 prior to Start Form Work CVL Al Firas 12-Dec-22 18-Dec-22 C C 6

719 ADN-AFC-WIR-CIV-651 01 Latest Inspection for Rebar of Retaining Wall & Column from B2 prior to Start Form Work CVL Al Firas 19-Dec-22 25-Dec-22 B B 6

720 ADN-AFC-WIR-CIV-652 00 Latest Inspection for Rebar of Water Tank Wall from B2 to B1 prior to Start Form Work CVL Al Firas 12-Dec-22 18-Dec-22 B B 6

Inspection for Form Work and All Other Embedment Items (water stop, swellable bar and injection hose) of retaining Wall from
721 ADN-AFC-WIR-CIV-653 00 Latest
B2 to B1 prior to start concrete
CVL Al Firas 12-Dec-22 18-Dec-22 C C 6

Inspection for Form Work and All Other Embedment Items (water stop, swellable bar and injection hose) of retaining Wall from
722 ADN-AFC-WIR-CIV-653 01 Latest
B2 prior to start concrete
CVL Al Firas 19-Dec-22 25-Dec-22 B B 6

723 ADN-AFC-WIR-CIV-654 00 Latest Inspection for Application and Completion of Pile Top Encapsulation (Epoxy Mortar - ALSAN CAP-E) at PC2 & PC7A CVL Al Firas 12-Dec-22 18-Dec-22 B B 6

724 ADN-AFC-WIR-CIV-655 00 Latest Inspection for Installation of Protection Board on Pile Cap and Sum Pit Wall CVL Al Firas 12-Dec-22 18-Dec-22 B B 6

725 ADN-AFC-WIR-CIV-656 00 Latest Inspection for Rebar of basement 01 Slab CVL Al Firas 12-Dec-22 15-Dec-22 B B 3

726 ADN-AFC-WIR-CIV-657 00 Latest Inspection for Form Work of Basement 01 Slab prior to Start Concrete CVL Al Firas 12-Dec-22 15-Dec-22 B B 3

727 ADN-AFC-WIR-CIV-658 00 Latest Inspection for Installation of Protection Board (2 Layers) on pipe incasement Trench Side Wall CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

728 ADN-AFC-WIR-CIV-659 00 Latest Inspection for Surface preparation of Gunite Wall (-3.050m) prior to Start Primer CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

729 ADN-AFC-WIR-CIV-660 00 Latest Inspection for Application of Primer on Gunite Wall (-3.050m) prior to Start 1st Layer Water Proofing Membrane CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

Inspection for Installation of 1st Layer Water Proofing membrane on Guntie Wall (up to -3.050m) prior to Start 2nd Layer
730 ADN-AFC-WIR-CIV-661 00 Latest
membrane)
CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

731 ADN-AFC-WIR-CIV-662 00 Latest Inspection for Rebar and Other embedded Items (water stop & injection hose) of sump pit bottom slab prior to start concrete CVL Al Firas 13-Dec-22 15-Dec-22 B B 2

732 ADN-AFC-WIR-CIV-663 00 Latest Inspection for Rebar and Form Work of Suspended Slab at Lift Area prior to Start Concrete CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

Inspection for Form Work and All other Embedment items (water Stop, injection Hose and Swellable bar) of Fire Water Tank
733 ADN-AFC-WIR-CIV-664 00 Latest
Wall from B2 to B1 prior to tart Concrete
CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

Inspection for Installation of 2nd Layer Water Proofing Membrane on Gunite Wall (up to -3.050m) prior to Start protection
734 ADN-AFC-WIR-CIV-665 00 Latest
Board
CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

735 ADN-AFC-WIR-CIV-666 00 Latest Inspection for Installation of Protection Board on Gunite Wall (up to -3.050m) CVL Al Firas 13-Dec-22 18-Dec-22 B B 5

Inspection for Form Work and All Other Embedment Items (water Stop, Injection Hose and Swellable bar) of Domestic Water
736 ADN-AFC-WIR-CIV-667 00 Latest
Tank Wall & Shear Wall SW7 from B2 to B1 prior to Start Concrete
CVL Al Firas 13-Dec-22 16-Dec-22 B B 3

737 ADN-AFC-WIR-CIV-668 00 Superseded Inspection for Rebar and Form Work of Ramp Slab B2 to B1 prior to Start Concrete CVL Al Firas 15-Dec-22 18-Dec-22 C C 3

738 ADN-AFC-WIR-CIV-668 01 Latest Inspection for Rebar and Form Work of Ramp Slab B2 prior to Start Concrete CVL Al Firas 19-Dec-22 25-Dec-22 B B 6
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
739 ADN-AFC-WIR-CIV-669 00 Latest Inspection for Rebar of Retaining Wall, Column and Shear Wall from B2 to B1 prior to Start Form Work CVL Al Firas 15-Dec-22 18-Dec-22 B B 3

740 ADN-AFC-WIR-CIV-670 00 Latest Inspection for Form Work of Retaining Wall, Column and Shear Wall from B2 to B1 prior to Start Concrete CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

741 ADN-AFC-WIR-CIV-671 00 Latest Inspection for Rebar of Shear Wall and Columns from B1 to GF prior to Start Form Work CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

742 ADN-AFC-WIR-CIV-672 00 Latest Inspection for Form Work of Shear Wall & Columns from B1 to GF prior to Start Concrete CVL Al Firas 15-Dec-22 18-Dec-22 C C 3

743 ADN-AFC-WIR-CIV-672 00 Latest Inspection for Form Work of Shear Wall & Columns from B1 prior to Start Concrete CVL Al Firas 19-Dec-22 25-Dec-22 B B 6

Inspection for Installation of 1st layer Waterproofing membrane on Gunite Wall (up to -3.05m) prior to Start 2nd Layer
744 ADN-AFC-WIR-CIV-673 00 Latest
membrane
CVL Al Firas 15-Dec-22 16-Dec-22 B B 1

745 ADN-AFC-WIR-CIV-674 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane on Gunite Wall (up to -3.050m) prior to start protection board CVL Al Firas 15-Dec-22 16-Dec-22 B B 1

746 ADN-AFC-WIR-CIV-675 00 Latest Inspection for Installation of Protection Board on Gunite Wall (up to -3.050m) CVL Al Firas 15-Dec-22 16-Dec-22 B B 1

747 ADN-AFC-WIR-CIV-676 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall and Columns from B2 to B1 prior to Start Form Work CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

Inspection for Form Work and All Other Embedments (Water Stop, Injection Hose & Swellable Bar) of Retianing Wall with
748 ADN-AFC-WIR-CIV-677 00 Latest
Shearwalls and Columns from B2 to B1 prior to Start Concrete
CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

749 ADN-AFC-WIR-CIV-678 00 Latest Inspection for Rebar of Retaining Wall with Core Wall 05 and Shear Wall from B2 to B1 prior to Start Form Work CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of Retaining Wall with
750 ADN-AFC-WIR-CIV-679 00 Latest
core wall 05 and Shear Wall from B2 to B1 prior to Start Concrete
CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

751 ADN-AFC-WIR-CIV-680 00 Latest Inspection for Bottom and Top Layer Rebar of Pile Caps PC2, PC4, PC5 & PC7A at C11 CVL Al Firas 15-Dec-22 19-Dec-22 B B 4

752 ADN-AFC-WIR-CIV-681 00 Latest Inspection for Rebar and Form Work of Staircase -03 & 04 from B1 CVL Al Firas 18-Dec-22 21-Dec-22 B B 3

753 ADN-AFC-WIR-CIV-682 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall (SW2 & SW2A) from B2 to B1 prior to Start Form Works CVL Al Firas 18-Dec-22 21-Dec-22 B B 3

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of Retaining Wall with
754 ADN-AFC-WIR-CIV-683 00 Latest
Shear Wall (SW1, SW2 & SW2A) from B2 to B1 prior to Start Concrete
CVL Al Firas 18-Dec-22 25-Dec-22 B B 7

755 ADN-AFC-WIR-CIV-684 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall (SW-14) from B2 to B1 prior to Start Form Work CVL Al Firas 18-Dec-22 25-Dec-22 B B 7

Inspection for FormWork and All other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of Retaining Wall with
756 ADN-AFC-WIR-CIV-685 00 Latest
Shear Wall (SW14) from B2 to B1 prior to Start Concrete
CVL Al Firas 18-Dec-22 25-Dec-22 B B 7

Inspection for Completion of Rebar, Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar)
757 ADN-AFC-WIR-CIV-686 00 Latest
of Raft Foundation at C11
CVL Al Firas 18-Dec-22 25-Dec-22 B B 7

758 ADN-AFC-WIR-CIV-687 00 Latest Inspection for Rebar of Shear Wall and Columns from B2 to B1 at C11 prior to Start Form Work CVL Al Firas 18-Dec-22 21-Dec-22 B B 3

759 ADN-AFC-WIR-CIV-688 00 Latest Inspection for Form Work of Shear Wall and Columns from B2 to B1 at C11 prior to Start Form Work CVL Al Firas 18-Dec-22 25-Dec-22 B B 7

760 ADN-AFC-WIR-CIV-689 00 Latest Inspection for Rebar of Core Wall 01 fron B2 to B1 at C11 prior to start Form Work CVL Al Firas 18-Dec-22 25-Dec-22 B B 7

761 ADN-AFC-WIR-CIV-690 00 Latest Inspection for Rebar of Core Wall -03 from B1 to GF prior to Start Form Work CVL Al Firas 18-Dec-22 21-Dec-22 B B 3

762 ADN-AFC-WIR-CIV-691 00 Latest Inspection for Rebar of Shear Wall SW24 at Basement 1 prior to Start Form Work CVL Al Firas 19-Dec-22 25-Dec-22 B B 6

763 ADN-AFC-WIR-CIV-692 00 Latest Inspection for Form Work of Shear Wall SW24 at B1 prior to Start Concrete CVL Al Firas 19-Dec-22 25-Dec-22 B B 6

764 ADN-AFC-WIR-CIV-693 00 Superseded Inspection for Rebar of Retaining Wall with Shear Wall (SW-1, SW4 & SW15) CVL Al Firas 19-Dec-22 25-Dec-22 C C 6

765 ADN-AFC-WIR-CIV-693 01 Latest Inspection for Rebar of Retaining Wall with Shear Wall (SW-1, SW4 & SW15) at Basement 2 prior to Start Form Work CVL Al Firas 25-Dec-22 26-Dec-22 B B 1

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of Retaining Wall with
766 ADN-AFC-WIR-CIV-694 00 Superseded
Shear Wall (SW1, SW4 & SW15) from B2 to B1 prior to Start Concrete
CVL Al Firas 19-Dec-22 25-Dec-22 C C 6

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of Retaining Wall with
767 ADN-AFC-WIR-CIV-694 01 Latest
Shear Wall (SW1, SW4 & SW15) from B2 prior to Start Concrete
CVL Al Firas 25-Dec-22 26-Dec-22 B B 1

768 ADN-AFC-WIR-CIV-695 00 Latest Inspection for Form Work of Core Wall 03 at B1 prior to Start Concrete CVL Al Firas 19-Dec-22 25-Dec-22 B B 6
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
769 ADN-AFC-WIR-CIV-696 00 Latest Inspection for Rebar of Core Wall 04 at Basement 1 prior to Start Form Work CVL Al Firas 21-Dec-22 25-Dec-22 B B 4

770 ADN-AFC-WIR-CIV-697 00 Superseded Inspection for FormWork of Core Wall 01 at Basement 1 prior to Start Concrete CVL Al Firas 21-Dec-22 25-Dec-22 C C 4

771 ADN-AFC-WIR-CIV-697 01 Latest Inspection for FormWork and other embedment items (injection hose) of corewall 01 at Basement 2 prior to Start Concrete CVL Al Firas 25-Dec-22 26-Dec-22 B B 1

772 ADN-AFC-WIR-CIV-698 00 Latest Inspection for Rebar of Shear Wall (SW8) & Column (C4) at B1 prior to Start Form Work CVL Al Firas 21-Dec-22 25-Dec-22 B B 4

773 ADN-AFC-WIR-CIV-699 00 Latest Inspection for Form Work of Shear Wall (SW8) & Column (C4) at B1 prior to Start Concrete CVL Al Firas 21-Dec-22 25-Dec-22 B B 4

774 ADN-AFC-WIR-CIV-700 00 Latest Inspection for Form Work of Core Wall 04 at Basement 1 prior to Start Concrete CVL Al Firas 22-Dec-22 25-Dec-22 B B 3

775 ADN-AFC-WIR-CIV-701 00 Latest Inspection for Rebar of Corewall 02 at B1 prior to Start Form Work CVL Al Firas 22-Dec-22 25-Dec-22 B B 3

776 ADN-AFC-WIR-CIV-702 00 Latest Inspection for Rebar of Retaining Wall with Shear Walls (SW-14 & 26) and Column (C2A) at Basement 2 prior to Start Form Work CVL Al Firas 22-Dec-22 22-Dec-22 B B 0

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & swellable Bar) of Retaining Wall with
777 ADN-AFC-WIR-CIV-703 00 Latest
Shear Wall (SW-14 & 26) and Columns (C2A) at Basement 2 prior to Start Concrete
CVL Al Firas 22-Dec-22 25-Dec-22 B B 3

778 ADN-AFC-WIR-CIV-704 00 Latest Inspection for Rebar of Shear Walls & Columns at B2 prior to Start Form Work CVL Al Firas 22-Dec-22 25-Dec-22 B B 3

779 ADN-AFC-WIR-CIV-705 00 Latest Inspection for Form Work and Other Embedment Item (Injection Hose) of Shear Walls & Columns at B2 prior to Start Concrete CVL Al Firas 22-Dec-22 26-Dec-22 B B 4

Inspection for Completion of Block Wall (-2.050 to 0.000M) and Surface preparation on capping beam and block wall prior to
780 ADN-AFC-WIR-CIV-706 00 Superseded
Start primer (from -3.050M to 0.000M)
CVL Al Firas 22-Dec-22 26-Dec-22 C C 4

Inspection for Completion of Block Wall (-2.050 to -0.42m & -0.20M) and Surface preparation on capping beam and block wall
781 ADN-AFC-WIR-CIV-706 01 Latest
prior to Start primer (from -3.050M to -0.42m & -0.20M)
CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

782 ADN-AFC-WIR-CIV-707 00 Latest Inspection for Form Work and Other Embedment Item (injection hose) of Core Wall 02 at B2 prior to Start Concrete CVL Al Firas 25-Dec-22 28-Dec-22 B B 3

783 ADN-AFC-WIR-CIV-708 00 Latest Inspection for Rebar of Shear Wall (SW 6) at Basement 2 prior to Start Form Work CVL Al Firas 25-Dec-22 26-Dec-22 B B 1

Inspection for Form Work and Other Embedment Item (injection hose) of Shear Walls (SW 6) at Basement 2 prior to Start
784 ADN-AFC-WIR-CIV-709 00 Latest
Concrete
CVL Al Firas 25-Dec-22 26-Dec-22 B B 1

785 ADN-AFC-WIR-CIV-710 00 Latest Inspection for Rebar of Shear Wall SW25 at Basement 1 prior to Start Form Work CVL Al Firas 25-Dec-22 26-Dec-22 B B 1

786 ADN-AFC-WIR-CIV-711 00 Latest Inspection for Form Work of Shear Wall Sw25 at Basement 1 prior to Start Concrete CVL Al Firas 25-Dec-22 29-Dec-22 B B 4

787 ADN-AFC-WIR-CIV-712 00 Latest Inspection for Rebar of Corewall 03 at GF (from 0.000 to 1.600M) prior to start form work CVL Al Firas 26-Dec-22 29-Dec-22 B B 3

788 ADN-AFC-WIR-CIV-713 00 Latest Inspection for Form Work of Core Wall 03 at GF (from -2.000 to 1.60M) prior to start concrete CVL Al Firas 27-Dec-22 5-Jan-23 B B 9

789 ADN-AFC-WIR-CIV-714 00 Latest Inspection for Rebar of Core Wall 04 at GF (from 0.000 to 1.600M) prior to Start Form Work CVL Al Firas 27-Dec-22 2-Jan-23 B B 6

790 ADN-AFC-WIR-CIV-715 00 Latest Inspection for Bottom Rebar of Basement 01 Slab at C11 CVL Al Firas 28-Dec-22 29-Dec-22 B B 1

791 ADN-AFC-WIR-CIV-716 00 Latest Inspection for Completion of Rebar Rowk basement 01 Slab at C11 CVL Al Firas 28-Dec-22 2-Jan-23 B B 5

Inspection for Form Work and other Embedment Items (water Stop, Swellable Bar & injection Hose) of Basement 01 Slab prior
792 ADN-AFC-WIR-CIV-717 00 Latest
to Start Concrete
CVL Al Firas 28-Dec-22 5-Jan-23 B B 8

793 ADN-AFC-WIR-CIV-718 00 Superseded Inspection for Form Work of Corewall 04 at GF (Ffrom -2.000 to 1.60M) prior to Start Concrete CVL Al Firas 29-Dec-22 5-Jan-23 C C 7

794 ADN-AFC-WIR-CIV-718 01 Latest Inspection for Form Work of Corewall 04 at GF (Ffrom -2.000 to 1.60M) prior to Start Concrete CVL Al Firas 8-Jan-23 8-Jan-23 B B 0

795 ADN-AFC-WIR-CIV-719 00 Superseded Inspection for Rebar of Ramp Wall with Shear Wall (SW19 & SW21) at B1 prior to Start Form Work CVL Al Firas 29-Dec-22 5-Jan-23 C C 7

796 ADN-AFC-WIR-CIV-719 01 Latest Inspection for Rebar of Ramp Wall with Shear Wall (SW19 & SW21) at B1 prior to Start Form Work CVL Al Firas 8-Jan-23 8-Jan-23 B B 0

797 ADN-AFC-WIR-CIV-720 00 Latest Inspection for Rebar of Column (C23) & Shear Wall (SW20 & SW22) at B1 prior to Start Form Work CVL Al Firas 29-Dec-22 2-Jan-23 B B 4

798 ADN-AFC-WIR-CIV-721 00 Latest Inspection for Form Work of Column (C23) & Shear Wall (SW20 & SW22) at B1 prior to Start concrete CVL Al Firas 29-Dec-22 3-Jan-23 B B 5
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
799 ADN-AFC-WIR-CIV-722 00 Latest Inspection for Rebar of Columns & Shear Walls at B1 prior to Start Form Work CVL Al Firas 2-Jan-23 5-Jan-23 B B 3

800 ADN-AFC-WIR-CIV-723 00 Latest Inspection for Form Work of Columns & Shear Wall at B1 prior to Start Concrete CVL Al Firas 2-Jan-23 5-Jan-23 B B 3

801 ADN-AFC-WIR-CIV-724 00 Latest Inspection for Rebar and Form Work for Staircase 01 at B2 prior to Start Concrete CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

Inspection for Primer Application on Capping beam and Block Wall (from -3.00m to 0.000M) prior to start 1st Layer
802 ADN-AFC-WIR-CIV-725 00 Latest
waterproofing membrane
CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

Inspection for Installation of 1st Layer Waterpoofing Membrane on Capping Beam and Block Wall (from -3.000M to 0.000M)
803 ADN-AFC-WIR-CIV-726 00 Latest
prior to start 2nd Layer membrane
CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

804 ADN-AFC-WIR-CIV-727 00 Latest Inspection for Form Work (2nd Stage) of Shear Wall SW18 & SW25 and Column C21 & C13 at B1 prior to Start Concrete CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

805 ADN-AFC-WIR-CIV-728 00 Latest Inspection for Installation of Steel Section for Composite Column C6 at B1 (from -4.00m to 0.100M) prior to start concrete CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

806 ADN-AFC-WIR-CIV-729 00 Latest Inspection for Witnessing of UT Test at B1 Column C6 (Level -4.000M) CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

807 ADN-AFC-WIR-CIV-730 00 Superseded Inspection for Rebar and Form Work of Staircase -02 at B2 prior to start concrete CVL Al Firas 4-Jan-23 5-Jan-23 C C 1

808 ADN-AFC-WIR-CIV-730 01 Latest Inspection for Rebar and Form Work of Staircase -02 at B2 prior to start concrete CVL Al Firas 8-Jan-23 11-Jan-23 B B 3

809 ADN-AFC-WIR-CIV-731 00 Latest Inspection for Rebar and Form Work of Staircase -05 at B2 prior to start concrete CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

Inspection for Installation of 2nd Layer Waterproofing Membrane on Capping Beam and Block Wall (from -3.000m to 0.000M)
810 ADN-AFC-WIR-CIV-732 00 Latest
prior to start protection board
CVL Al Firas 4-Jan-23 5-Jan-23 B B 1

811 ADN-AFC-WIR-CIV-733 00 Latest Inspection for Form Work of Ramp Wall with Shear Wall (SW19 & SW21) at B1 prior to start concrete CVL Al Firas 4-Jan-23 8-Jan-23 B B 4

812 ADN-AFC-WIR-CIV-734 00 Latest Inspection for Rebar of Columns and Shear Walls at B1 prior to start Form Work CVL Al Firas 5-Jan-23 8-Jan-23 B B 3

813 ADN-AFC-WIR-CIV-735 00 Latest Inspection for Form Work of Columns & Shear Walls at B1 prior to Start Concrete CVL Al Firas 5-Jan-23 8-Jan-23 B B 3

814 ADN-AFC-WIR-CIV-736 00 Latest Inspection for Rebar of Retianing Wall with Shear Walls at B1 prior to start Form Work CVL Al Firas 5-Jan-23 8-Jan-23 B B 3

815 ADN-AFC-WIR-CIV-737 00 Latest Inspection for Installation of Protection board on Capping Beam and Block Wall (from -3.000m to 0.000m) CVL Al Firas 5-Jan-23 5-Jan-23 B B 0

816 ADN-AFC-WIR-CIV-738 00 Latest Inspection for Application of Anti-Termite at below the GF Slab prior to Start Blinding CVL Al Firas 5-Jan-23 8-Jan-23 B B 3

817 ADN-AFC-WIR-CIV-739 00 Latest Inspection for Rebar of Corewall 02 at B1 (from 5.100 to -2.000M) prior to start Form Work CVL Al Firas 5-Jan-23 11-Jan-23 B B 6

818 ADN-AFC-WIR-CIV-740 00 Latest Inspection for Form Work of Retaining Wall with Shear Walls at B1 prior to Start Concrete CVL Al Firas 8-Jan-23 11-Jan-23 B B 3

819 ADN-AFC-WIR-CIV-741 00 Latest Inspection for Rebar of Core Wall 01 at B1 (from -5.100 to -2.000M) prior to start form work CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

820 ADN-AFC-WIR-CIV-742 00 Latest Inspection for Form Work of Core Wall 02 at B1 (from -5.100 to -2.000M) prior to start concrete CVL Al Firas 8-Jan-23 11-Jan-23 B B 3

821 ADN-AFC-WIR-CIV-743 00 Latest Inspection for Surface preparation prior to start primer at B2 King Post Opening Area CVL Al Firas 8-Jan-23 8-Jan-23 B B 0

822 ADN-AFC-WIR-CIV-744 00 Latest Inspection for Primer Application at B2 King Post Opening Area prior to Start 1st Layer of Waterproofing Membrane CVL Al Firas 8-Jan-23 15/15 B B #VALUE!

Inspection for Installation of 1st Layer Membrane at B2 King Post Opening Area prior to Start 2nd Layer Waterproofing
823 ADN-AFC-WIR-CIV-745 00 Latest
Membrane
CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

824 ADN-AFC-WIR-CIV-746 00 Latest Inspection for Installation of 2nd Layer Waterproofing Membrane at Basement 2 King Post Opening Area prior to Start Screed CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

Inspection for Surface Preparation on Capping Beam, Block Wall and Blinding Surface (from -3.000m to -0.400M) prior to start
825 ADN-AFC-WIR-CIV-747 00 Latest
primer
CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

Inspection for primer application on capping beam, block wall and blinding surface (from -3.000M to -0.400m) prior to start 1st
826 ADN-AFC-WIR-CIV-748 00 Latest
layer waterproofing membrane
CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

Inspection for 1st Layer membrane on capping beam, block wall and blinding surface (from -3.000m to -0.400m) prior to start
827 ADN-AFC-WIR-CIV-749 00 Latest
2nd layer waterproofing membrane
CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

Inspection for 2nd Layer membrane on capping beam, block wall and blinding surface (from -3.000m to -0.400M) prior to start
828 ADN-AFC-WIR-CIV-750 00 Latest
2nd layer waterproofing membrane
CVL Al Firas 8-Jan-23 15-Jan-23 B B 7
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
829 ADN-AFC-WIR-CIV-751 00 Latest Inspection for Installation of protection Board on Capping Beam and Block Wall (from -3.000m to 0.400m) CVL Al Firas 8-Jan-23 13-Jan-23 B B 5

Inspection for 1st Layer membrane on capping beam, block wall and blinding surface (from -3.000m to -0.400m) prior to start
830 ADN-AFC-WIR-CIV-752 00 Latest
2nd layer waterproofing membrane
CVL Al Firas 8-Jan-23 13-Jan-23 B B 5

Inspection for 2nd Layer membrane on capping beam, block wall and blinding surface (from -3.000m to -0.400m) prior to start
831 ADN-AFC-WIR-CIV-753 00 Latest
protection board
CVL Al Firas 8-Jan-23 13-Jan-23 B B 5

832 ADN-AFC-WIR-CIV-754 00 Latest Inspection for Rebar of Retaining Wall at B1 prior to start Form Work CVL Al Firas 8-Jan-23 11-Jan-23 B B 3

Inspection for Form Work and All Other embedment Items (Water stop, Injection Hose & Swellable Bar) of Retaining Wall at B1
833 ADN-AFC-WIR-CIV-755 00 Latest
prior to start concrete
CVL Al Firas 8-Jan-23 15-Jan-23 B B 7

834 ADN-AFC-WIR-CIV-756 00 Latest Inspection for Rebar of Retaining Wall with Shear wall at B1 prior to Start Form Work CVL Al Firas 8-Jan-23 11-Jan-23 B B 3

Inspection for Form Work and All Other embedment Items (Water stop, Injection Hose & Swellable Bar) of Retaining Wall with
835 ADN-AFC-WIR-CIV-757 00 Latest
shear wall at B1 prior to start concrete
CVL Al Firas 8-Jan-23 11-Jan-23 B B 3

Inspection for Form Work (2nd Stage) of Ramp Wall with Shear Wall SW21 & SW19 (-2.000m to -0.750m) at basement 1 prior
836 ADN-AFC-WIR-CIV-758 00 Latest
to start concrete
CVL Al Firas 9-Jan-23 11-Jan-23 B B 2

Inspection for Form Work of Columns C2 & 2nd Stage Form Work of Shear Wall SW8 (-2.000M to -0.400M) and C4 (-2.000M ro
837 ADN-AFC-WIR-CIV-759 00 Latest
-0.700M) at Basement 1 prior to start concrete
CVL Al Firas 9-Jan-23 11-Jan-23 B B 2

838 ADN-AFC-WIR-CIV-760 00 Latest Inspection for Rebar of Columns at B1 prior to Start Form Work CVL Al Firas 9-Jan-23 13-Jan-23 B B 4

839 ADN-AFC-WIR-CIV-761 00 Superseded Inspection for Form Work of Columns at B1 prior to start concrete CVL Al Firas 9-Jan-23 11-Jan-23 C C 2

840 ADN-AFC-WIR-CIV-761 00 Latest Inspection for Form Work of Columns at C4 & C2 at B1 prior to start concrete CVL Al Firas 16-Jan-23 20-Jan-23 B B 4

841 ADN-AFC-WIR-CIV-762 00 Latest Inspection for Protection Board on Capping Beam, Block Wall and Blinding Surface (from -3.000m to -0.400m) CVL Al Firas 10-Jan-23 15-Jan-23 B B 5

842 ADN-AFC-WIR-CIV-763 00 Latest Inspection for Surface Preparation on Capping Beam and Block Wall (from -3.050m to 0.000m) prior to start primer CVL Al Firas 10-Jan-23 15-Jan-23 B B 5

843 ADN-AFC-WIR-CIV-764 00 Latest Inspection for primer application on capping beam and block wall (from -3.050m to 0.000m) prior to start 1st Layer membrane CVL Al Firas 10-Jan-23 15-Jan-23 B B 5

Inspection for 1st Layer waterproofing membrane on capping beam block wall (from -3.050m to 0.000m) prior to start 2nd
844 ADN-AFC-WIR-CIV-765 00 Latest
layer membrane
CVL Al Firas 10-Jan-23 13-Jan-23 B B 3

845 ADN-AFC-WIR-CIV-766 00 Latest Inspection for Rebar of Retaining Wall (2nd Stage from -2.000m to -0.350m) at B1 prior to start form work CVL Al Firas 10-Jan-23 15-Jan-23 C C 5

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of retaining wall 2nd
846 ADN-AFC-WIR-CIV-767 00 Latest
stage from -2.000m to -0.350m at B1 prior to start concrete
CVL Al Firas 10-Jan-23 15-Jan-23 C C 5

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of retaining wall with
847 ADN-AFC-WIR-CIV-768 00 Latest
shear wall at B1 prior to start concrete
CVL Al Firas 10-Jan-23 15-Jan-23 B B 5

848 ADN-AFC-WIR-CIV-769 00 Latest Inspection for Rebar of Retaining Wall with Ramp Wall at B1 prior to Start Form Work CVL Al Firas 10-Jan-23 11-Jan-23 B B 1

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of retaining wall with
849 ADN-AFC-WIR-CIV-770 00 Latest
ramp wall at B1 prior to start concrete
CVL Al Firas 10-Jan-23 13-Jan-23 B B 3

850 ADN-AFC-WIR-CIV-771 00 Superseded Inspection for Rebar of LV Room Slab (-0.9000 S.S.L) at Plot C11 CVL Al Firas 10-Jan-23 11-Jan-23 C C 1

851 ADN-AFC-WIR-CIV-771 00 Latest Inspection for Rebar of LV Room Slab (-0.9000 S.S.L) at Plot C11 CVL Al Firas 16-Jan-23 17-Jan-23 B B 1

Inspection for Installation of 2nd Layer Waterproofing Membrane on Capping Beam and Block Wall (from -3.050m to 0.000M)
852 ADN-AFC-WIR-CIV-772 00 Latest
prior to start protection board
CVL Al Firas 10-Jan-23 13-Jan-23 B B 3

853 ADN-AFC-WIR-CIV-773 00 Latest Inspection for Installation of Protection Board on Capping Beam and Block Wall (from -3.050m to 0.000m) CVL Al Firas 10-Jan-23 13-Jan-23 B B 3

854 ADN-AFC-WIR-CIV-774 00 Latest Inspection for Form Work of Core Wall 01 at B1 (from -5.100 to -2.000m) prior to start concrete CVL Al Firas 10-Jan-23 13-Jan-23 B B 3

Inspection for 2nd Stage of Columns C10 and Shear Wall SW7, SW9, SW10 & SW10A (-2.000M to -0.400) at B1 prior to start
855 ADN-AFC-WIR-CIV-775 00 Latest
concrete
CVL Al Firas 10-Jan-23 13-Jan-23 B B 3

856 ADN-AFC-WIR-CIV-776 00 Latest Inspection for Rebar of Retaining Wall at B1 prior to start Form Work CVL Al Firas 10-Jan-23 15-Jan-23 B B 5

Inspection for Form Work and All other Embedment Items (Water stop, injection hose & Swellable bar) of retaining wall at B1
857 ADN-AFC-WIR-CIV-777 00 Latest
prior t ostart concrete
CVL Al Firas 11-Jan-23 16-Jan-23 B B 5

858 ADN-AFC-WIR-CIV-778 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW26 at B1 prior to start Form Work CVL Al Firas 11-Jan-23 13-Jan-23 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
859 ADN-AFC-WIR-CIV-779 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW17 at B1 prior to start Form Work CVL Al Firas 11-Jan-23 13-Jan-23 B B 2

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of retaining wall with
860 ADN-AFC-WIR-CIV-780 00 Superseded
shear wall SW17 at B1 prior to start concrete
CVL Al Firas 11-Jan-23 13-Jan-23 C C 2

Inspection for Form Work and All Other Embedment Items (Water Stop, Injection Hose & Swellable Bar) of retaining wall with
861 ADN-AFC-WIR-CIV-780 01 Latest
shear wall SW17 & SW17B at B1 prior to start concrete
CVL Al Firas 17-Jan-23 UR UR 821

862 ADN-AFC-WIR-CIV-781 00 Latest Inspection for Rebar of Core wall 03 at GF 9from 1.600M to 5.200M) prior to start Form Work CVL Al Firas 11-Jan-23 17-Jan-23 B B 6

863 ADN-AFC-WIR-CIV-782 00 Latest Inspection for Surface Preparation on Capping Beam and Blinding Surface (from -3.050m to -0.400m) prior to start primer CVL Al Firas 11-Jan-23 13-Jan-23 B B 2

Inspection for Primer Application on Capping Beam and Blinding Surface (from -3.050m to 0.400m) prior to start 1st layer
864 ADN-AFC-WIR-CIV-783 00 Latest
membrane
CVL Al Firas 11-Jan-23 13-Jan-23 B B 2

Inspection for Installation of 1st Layer waterproofing membrane on capping beam and blinding surface (from -3.050M to -
865 ADN-AFC-WIR-CIV-784 00 Latest
0.400m) prior to start 2nd layer membrane
CVL Al Firas 11-Jan-23 13-Jan-23 B B 2

866 ADN-AFC-WIR-CIV-785 00 Latest Inspection for rebar of retaining wall with shear wall SW1 & SW4 at B1 prior to start form work CVL Al Firas 11-Jan-23 13-Jan-23 B B 2

Inspection for Form Work and All Other embedment items (Water stop, injection hose & swellable bar) of retaining wall with
867 ADN-AFC-WIR-CIV-786 00 Latest
shear wall SW1 & SW4 at B1 prior to start form work
CVL Al Firas 11-Jan-23 16-Jan-23 B B 5

868 ADN-AFC-WIR-CIV-787 00 Latest Inspection for Rebar of Retaining Wall (2nd Stage from -2.000m to -0.350m) at B1 prior to start form work CVL Al Firas 11-Jan-23 16-Jan-23 B B 5

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of retaining wall 2nd
869 ADN-AFC-WIR-CIV-788 00 Latest
stage from -2.000m to -0.350m at B1 prior to start concrete
CVL Al Firas 11-Jan-23 16-Jan-23 B B 5

870 ADN-AFC-WIR-CIV-789 00 Latest Inspection for Form Work of LV room Slab (-0.900 S.S.L) prior to start concrete at Plot C11 CVL Al Firas 11-Jan-23 16-Jan-23 B B 5

Inspection for Installation of 2nd Layer Waterproofing membrane on capping beam and blinding surface (from -3.050m to -
871 ADN-AFC-WIR-CIV-790 00 Latest
0.400m) prior to start protection board
CVL Al Firas 13-Jan-23 15-Jan-23 B B 2

872 ADN-AFC-WIR-CIV-791 00 Latest Inspection for Installation of Protection Board on Capping Beam (from -3.05m to -0.400m) prior to start protection board CVL Al Firas 13-Jan-23 15-Jan-23 B B 2

873 ADN-AFC-WIR-CIV-792 00 Superseded Inspection for Rebar of Corewall 02 at B1 (from -2.000m to 1.600m) prior to start form work CVL Al Firas 13-Jan-23 16-Jan-23 C C 3

874 ADN-AFC-WIR-CIV-792 01 Latest Inspection for Rebar of Corewall 02 at B1 (from -2.000m to 1.600m) prior to start form work CVL Al Firas 17-Jan-23 UR UR 821

875 ADN-AFC-WIR-CIV-793 00 Latest Inspection for Rebar of Retaining wall with Shear Wall SW26 at B1 prior to Start form work CVL Al Firas 13-Jan-23 16-Jan-23 B B 3

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of Retaining Wall with
876 ADN-AFC-WIR-CIV-794 00 Latest
Shear Wall SW26 at B1 prior to start Concrete
CVL Al Firas 13-Jan-23 16-Jan-23 B B 3

877 ADN-AFC-WIR-CIV-795 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW14 and Column C2 at B1 prior to Start Form Work CVL Al Firas 13-Jan-23 16-Jan-23 B B 3

Inspection for Form Work and All Other Embedment Items (Water stop, injection hose & Swellable Bar) of Retaining Wall with
878 ADN-AFC-WIR-CIV-796 00 Latest
Shear Wall SW14 and Column C2A at B1 prior to Start concrete
CVL Al Firas 13-Jan-23 17-Jan-23 B B 4

879 ADN-AFC-WIR-CIV-797 00 Latest Inspection for Rebar of Retaining Wall with Ramp Wall (2nd Stage from -2.000m to -0.350m) at B1 prior to start Form Work CVL Al Firas 13-Jan-23 16-Jan-23 B B 3

Inspection for Form Work and All Other Embedment Items (water stop, injection hose & swellable bar) of retaining Wall with
880 ADN-AFC-WIR-CIV-798 00 Latest
ramp wall 2nd Stage from -2.000MM to 0.350m) at B1 prior to start concrete
CVL Al Firas 13-Jan-23 17-Jan-23 B B 4

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of Retaining Wall with
881 ADN-AFC-WIR-CIV-799 00 Latest
Shear Wall SW26 at B1 prior to start Concrete
CVL Al Firas 13-Jan-23 17-Jan-23 B B 4

882 ADN-AFC-WIR-CIV-800 00 Latest Inspection for Rectification of Sump Pit and Dewatering Well Temporary Opening to Close SOR-039 CVL Al Firas 13-Jan-23 20-Jan-23 C C 7

883 ADN-AFC-WIR-CIV-801 00 Latest Inspection for Rectification of Retaining Wall to close SOR-037 CVL Al Firas 13-Jan-23 20-Jan-23 C C 7

884 ADN-AFC-WIR-CIV-802 00 Superseded Inspection for Form Work of Core Wall - 03 at GF (from 1.600M to 5.200M) prior to start concrete CVL Al Firas 13-Jan-23 16-Jan-23 C C 3

885 ADN-AFC-WIR-CIV-802 01 Latest Inspection for Form Work of Core Wall - 03 at GF (from 1.600M to 5.200M) prior to start concrete CVL Al Firas 17-Jan-23 UR UR 821

886 ADN-AFC-WIR-CIV-803 00 Latest Inspection for Surface Preparation on Capping Beam and Block Wall (from -3.050m to 0.000m) prior to start primer CVL Al Firas 15-Jan-23 16-Jan-23 B B 1

887 ADN-AFC-WIR-CIV-804 00 Latest Inspection for primer application on capping beam and block wall (from -3.050m to 0.000m) prior to start 1st Layer membrane CVL Al Firas 15-Jan-23 16-Jan-23 B B 1

Inspection for Installation of 1st Layer Waterpoofing membrane on Capping Beam and Block Wall (from -3.050M to 0.000M)
888 ADN-AFC-WIR-CIV-805 00 Latest
prior to start 2nd Layer membrane
CVL Al Firas 15-Jan-23 16-Jan-23 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
Inspection for Installation of 2nd Layer Water Proofing Membrane on Capping Beam and Block Wall (from -3.050m to 0.000m)
889 ADN-AFC-WIR-CIV-806 00 Latest
prior to start protection board
CVL Al Firas 15-Jan-23 18-Jan-23 B B 3

Inspection for Form Work and All Other Embedment items (water stop, injection hose & swellable bar) of Retaining Wall with
890 ADN-AFC-WIR-CIV-807 00 Latest
Shear Wall SW26 at B1 prior to start Concrete
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

891 ADN-AFC-WIR-CIV-808 00 Latest Inspection for Rebar of Retaining Wall (2nd Stage from -2.000m to -0.350m) at B1 prior to start form work CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

Inspection for Form Work and All Other Embedment Items (water stop, injection hose and swellable bar) of retaining wall (2nd
892 ADN-AFC-WIR-CIV-809 00 Latest
stage from -2.000M to -0.350m & -0.600M) at B1 prior to start concrete work
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

Inspection for Surface preparation on capping beam, block wall and blinding surface (from -3.050m to -0.400m) prior to start
893 ADN-AFC-WIR-CIV-810 00 Latest
primer
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

Inspection for Primer Application on Capping Beam, Block Wall and blinding surface (from -3.050M to -0.400m) prior to start
894 ADN-AFC-WIR-CIV-811 00 Latest
1st layer membrane
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

Inspection for Installation of 1st layer Membrane on capping beam, block wall and blinding surface (from -3.050m to -0.400m)
895 ADN-AFC-WIR-CIV-812 00 Latest
prior to start 2nd layer membrane
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

Inspection for Installation of 2nd layer membrane on Capping Beam, Block Wall and Blinding Surface (from -3.050m to -
896 ADN-AFC-WIR-CIV-813 00 Latest
0.400m) prior to start protection board
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

897 ADN-AFC-WIR-CIV-814 00 Latest Inspection for Installation of Protection Board on Capping Beam & Block Wall (from -3.050m to -0.400m) CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

898 ADN-AFC-WIR-CIV-815 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW14 at B1 prior to start From Work CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

Inspection for Form Work and All Other Embedment Items (water stop, injection hose & swellable bar) of retaining wall SW14
899 ADN-AFC-WIR-CIV-816 00 Latest
at B1 prior to start concrete
CVL Al Firas 15-Jan-23 20-Jan-23 B B 5

900 ADN-AFC-WIR-CIV-817 00 Latest Inspection for Rebar of Column C2 at B1 prior to Start Form Work CVL Al Firas 16-Jan-23 20-Jan-23 B B 4

901 ADN-AFC-WIR-CIV-818 00 Latest Inspection for Rebar of Core Wall 04 at GF (from 1.60m to 5.200m) prior to start form work CVL Al Firas 16-Jan-23 20-Jan-23 B B 4

902 ADN-AFC-WIR-CIV-819 00 Latest Inspection for Installation of Protection Board on Capping Beam and Block Wall (from -3.050m to 0.000m) CVL Al Firas 16-Jan-23 18-Jan-23 B B 2

903 ADN-AFC-WIR-CIV-820 00 Latest Inspection for Form Work of Core Wall 04 at GF (from 1.600m to 5.200m) prior to start concrete CVL Al Firas 17-Jan-23 UR UR 821

904 ADN-AFC-WIR-CIV-821 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall Sw15 & SW17B at B1 prior to start Form Work CVL Al Firas 17-Jan-23 UR UR 821

905 ADN-AFC-WIR-CIV-822 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW26 (2nd Stage from -2.000m to 0.600m) at B1 prior to start form work CVL Al Firas 17-Jan-23 UR UR 821

Inspection for Form Work and All Other Embedment Items (water stop, injection hose & swellable bar) of Retaining Wall with
906 ADN-AFC-WIR-CIV-823 00 Latest
Shear Wall SW26 2nd Stage from -2.000m to -0.600m at B1 prior to start concrete
CVL Al Firas 17-Jan-23 UR UR 821

907 ADN-AFC-WIR-CIV-824 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW1 at B1 prior to start Form Work CVL Al Firas 17-Jan-23 20-Jan-23 B B 3

Inspection for Form Work and All Other Embedment Items (water stop, Injection Hose & Swellable Bar) of Retaining Wall with
908 ADN-AFC-WIR-CIV-825 00 Latest
Shear Wall SW1 at B1 prior to start concrete
CVL Al Firas 17-Jan-23 UR UR 821

Inspection for Form Work and All Other Embedment Items (water stop, Injection hose &Swellable bar) of Retaining Wall with
909 ADN-AFC-WIR-CIV-826 00 Latest
Shear Wall SW26 2nd Stage from -2.000M to -0.350m at B1 prior to start concrete
CVL Al Firas 18-Jan-23 UR UR 820

910 ADN-AFC-WIR-CIV-827 00 Latest Inspection for Form Work of Corewall 02 at B1 (from -2.000M to 1.600M) prior to start concrete CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Form Work anf All embedment items (water stop, injection hose & swellable bar) of retaining wall with shear
911 ADN-AFC-WIR-CIV-828 00 Latest
wall SW14 and Column C2A 2nd Stage from -2.000M to -0.350M at B1 prior to start concrete
CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Surface Preparation on Capping Beam, Block Wall and Blinding Surface (from -3.050M to 0.000m) prior to start
912 ADN-AFC-WIR-CIV-829 00 Latest
primer
CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Primer Application on Capping Beam, Block Wall and blinding surface (from -3.050M to -0.400m) prior to start
913 ADN-AFC-WIR-CIV-830 00 Latest
1st layer membrane
CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Installation of 1st Layer Membrane on Capping beam, Block Wall and Blinding Surface (from -3.050m to 0.000M)
914 ADN-AFC-WIR-CIV-831 00 Latest
prior to start 2nd layer membrane
CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Form Work and All Other Embedment Items (water stop, injection hose & swellable bar) of retaining wall with
915 ADN-AFC-WIR-CIV-832 00 Latest
Shear Wall SW15 at B1 prior to start concrete
CVL Al Firas 18-Jan-23 UR UR 820

916 ADN-AFC-WIR-CIV-833 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW2 & SW2A at B1 prior to start Form Work CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Form Work and All Other Embedment Items (water stop, Injection Hose & Swellable Bar) of Retaining Wall with
917 ADN-AFC-WIR-CIV-834 00 Latest
Shear Wall SW2 & SW2A at B1 prior to start concrete
CVL Al Firas 18-Jan-23 UR UR 820

Inspection for Installation of 2nd Layer membrane on Capping Beam, Block Wall and Blinding Surface (from -3.050m to -
918 ADN-AFC-WIR-CIV-835 00 Latest
0.000m) prior to start protection Board
CVL Al Firas 19-Jan-23 UR UR 819
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 925 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 845 A = Approved 29

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 80 B = Approved as noted 775

Discipline
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 96 REMARKS
Closed 0 UR = Under Review 25
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
919 ADN-AFC-WIR-CIV-836 00 Latest Inspection for Installation of Protection Board on Capping Beam and Block Wall (from -3.050m to 0.000m) CVL Al Firas 19-Jan-23 UR UR 819

920 ADN-AFC-WIR-CIV-837 00 Latest Inspection for Surface Preparation on Capping Beam and Blinding Surface (from -3.050m to 0.000m) prior to start primer CVL Al Firas 19-Jan-23 UR UR 819

921 ADN-AFC-WIR-CIV-838 00 Latest Inspection for Applicaton of Primer on Capping Beam and Blinding Surface (from -3.050 to 0.000m) prior to start primer CVL Al Firas 19-Jan-23 UR UR 819

922 ADN-AFC-WIR-CIV-839 00 Latest Inspection for Rebar of Corewall 01 at B1 (from -2.000m to 1.600m) prior to start form work CVL Al Firas 19-Jan-23 UR UR 819

923 ADN-AFC-WIR-CIV-840 00 Latest Inspection for Rebar of Retaining Wall with Shear Wall SW3 and SW16 at B1 prior to start Form Work CVL Al Firas 19-Jan-23 UR UR 819

Inspection for Form Work and All Embedment Items (water stop, Injection Hose & Swellable Bar) of Retaining Wall with Shear
924 ADN-AFC-WIR-CIV-841 00 Latest
wall SW3 & SW16 at B1 prior to start concrete
CVL Al Firas 19-Jan-23 UR UR 819

Inspection for Form Work and All Embedment Items (water stop, Injection Hose & Swellable Bar) of Retaining Wall with Shear
925 ADN-AFC-WIR-CIV-842 00 Latest
Wall SW14 2nd Stage at B1 prior to start Concrete
CVL Al Firas 19-Jan-23 UR UR 819
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE

1 AF190-DUTCH-CVL-WIR-001 00 Latest Inspection Request for Driving the H-Beam CVL DUTCH 7-Apr-22 7-Apr-22 B B 0

2 AF190-DUTCH-CVL-WIR-002 00 Superseded Inspection Request for Driving the H-Beam CVL DUTCH 7-Apr-22 7-Apr-22 C C 0

3 AF190-DUTCH-CVL-WIR-002 01 Latest Inspection Request for Driving the H-Beam CVL DUTCH 19-Apr-22 21-Apr-22 B B 2

4 AF190-DUTCH-CVL-WIR-003 00 Latest Inspection Request for Setting Out og Primary Secant Piles CVL DUTCH 7-Apr-22 7-Apr-22 B B 0

5 AF190-DUTCH-CVL-WIR-004 00 Latest Inspection Request for Casting of 7 Primary Secant Piles CVL DUTCH 7-Apr-22 7-Apr-22 B B 0

6 AF190-DUTCH-CVL-WIR-005 00 Latest Inspection Request for Setting Out of 6 Secondary Secant Pile Number 1,3,5,7,491,489 CVL DUTCH 7-Apr-22 10-Apr-22 C C 3

7 AF190-DUTCH-CVL-WIR-006 00 Latest Inspection Request for Casting of 6 Secondary Secant Pile Number 1,3,5,7,491,489 CVL DUTCH 7-Apr-22 10-Apr-22 B B 3

8 AF190-DUTCH-CVL-WIR-007 00 Latest Inspection Request for Setting Out of 7 Primary Secant Pile Number 420, 422, 424, 426, 428, 430, 432 CVL DUTCH 7-Apr-22 11-Apr-22 B B 4

9 AF190-DUTCH-CVL-WIR-008 00 Latest Inspection Request for Casting of 7 Primary Secant Pile Number 420, 422, 424, 426, 428, 430, 432 CVL DUTCH 7-Apr-22 10-Apr-22 B B 3

10 AF190-DUTCH-CVL-WIR-008 01 Latest Inspection Request for Casting of 7 Primary Secant Pile Number 420, 422, 424, 426, 428, 430, 432 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

11 AF190-DUTCH-CVL-WIR-009 00 Latest Inspection Request for Setting Out of 7 Primary Secant Piles Number 10,12,14,16,18,20,22 CVL DUTCH 8-Apr-22 11-Apr-22 B B 3

12 AF190-DUTCH-CVL-WIR-010 00 Latest Inspection Request for Casting of 7 Primary Secant Piles Number 10,12,14,16,18,20,22 CVL DUTCH 8-Apr-22 11-Apr-22 B B 3

13 AF190-DUTCH-CVL-WIR-011 00 Latest Inspection Request for Setting Out and Steel Cages 5 Secondary Secant Piles Number 421,423,425,427,429 CVL DUTCH 8-Apr-22 11-Apr-22 B B 3

14 AF190-DUTCH-CVL-WIR-012 00 Latest Inspection Request for Casting of 5 Secondary Secant Piles Number 421,423,425,427,429 CVL DUTCH 8-Apr-22 11-Apr-22 B B 3

16 AF190-DUTCH-CVL-WIR-013 00 Superseded Inspection Request for Setting Out of 7 Primary Secant Pile Number 432,434,436,438,440,442,444 CVL DUTCH 10-Apr-22 12-Apr-22 C C 2

AF190-DUTCH-CVL-WIR-013 01 Latest Inspection Request for Setting Out of 7 Primary Secant Pile Number 432,434,436,438,440,442,444 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

17 AF190-DUTCH-CVL-WIR-014 00 Superseded Inspection Request for Casting of 7 Primary Secant Pile Number 432,434,436,438,440,442,444 CVL DUTCH 10-Apr-22 12-Apr-22 C C 2

18 AF190-DUTCH-CVL-WIR-014 01 Latest Inspection Request for Casting of 7 Primary Secant Pile Number 432,434,436,438,440,442,444 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

19 AF190-DUTCH-CVL-WIR-015 00 Superseded Inspection Request for Setting Out and Steel Cages of 7 Secondary Secant Pile Number 9,11,13,15,17,19&21 CVL DUTCH 10-Apr-22 12-Apr-22 C C 2

20 AF190-DUTCH-CVL-WIR-015 01 Latest Inspection Request for Setting Out and Steel Cages of 7 Secondary Secant Pile Number 9,11,13,15,17,19&21 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

21 AF190-DUTCH-CVL-WIR-016 00 Superseded Inspection Request for Casting of 7 Secondary Secant Pile Number 9,11,13,15,17,19&21 CVL DUTCH 10-Apr-22 12-Apr-22 C C 2

22 AF190-DUTCH-CVL-WIR-016 01 Superseded Inspection Request for Casting of 7 Secondary Secant Pile Number 9,11,13,15,17,19&21 CVL DUTCH 15-Apr-22 19-Apr-22 C C 4

23 AF190-DUTCH-CVL-WIR-016 02 Latest Inspection Request for Casting of 7 Secondary Secant Pile Number 9,11,13,15,17,19&21 CVL DUTCH 22-Apr-22 25-Apr-22 B B 3

24 AF190-DUTCH-CVL-WIR-017 00 Latest Inspection Request for Casting of 7 Secondary Secant Pile Number 431,433,439,441,443 CVL DUTCH 11-Apr-22 13-Apr-22 B B 2

25 AF190-DUTCH-CVL-WIR-018 00 Latest Inspection Request for Casting of 7 Primary Secant Pile Number 24,26,28,30,32,34,36 CVL DUTCH 11-Apr-22 13-Apr-22 B B 2

26 AF190-DUTCH-CVL-WIR-019 00 Latest Inspection Request for Casting of 7 Primary Secant Pile Number 24,26,28,30,32,34,36 CVL DUTCH 11-Apr-22 13-Apr-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
27 AF190-DUTCH-CVL-WIR-020 00 Latest Inspection Request for Setting Out of 7 Primary Secant Pile Number 431,433,435,437,439,441,443 CVL DUTCH 11-Apr-22 13-Apr-22 B B 2

28 AF190-DUTCH-CVL-WIR-021 00 Superseded Inspection Request fo Setting Out of 7 Primary Secant Pile Number 446,448,450,452,454,456,458 CVL DUTCH 12-Apr-22 13-Apr-22 C C 1

29 AF190-DUTCH-CVL-WIR-021 01 Latest Inspection Request fo Setting Out of 7 Primary Secant Pile Number 446,448,450,452,454,456,458 CVL DUTCH 15-Apr-22 19-Apr-22 A A 4

30 AF190-DUTCH-CVL-WIR-022 00 Superseded Inspection Request for Casting of 7 Primary Secant Pile Number 446,448,450,452,454,456,458 CVL DUTCH 12-Apr-22 13-Apr-22 C C 1

31 AF190-DUTCH-CVL-WIR-022 01 Latest Inspection Request for Casting of 7 Primary Secant Pile Number 446,448,450,452,454,456,458 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

32 AF190-DUTCH-CVL-WIR-023 00 Superseded Inspection Request for Setting Out of 7 Secondary Secant Pile Number 23,25,27,29,31,33,35 CVL DUTCH 12-Apr-22 13-Apr-22 C C 1

33 AF190-DUTCH-CVL-WIR-023 01 Latest Inspection Request for Setting Out of 7 Secondary Secant Pile Number 23,25,27,29,31,33,35 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

34 AF190-DUTCH-CVL-WIR-024 00 Superseded Inspection Request for Castng Out of 7 Secondary Secant Pile Number 23,25,27,29,31,33,35 CVL DUTCH 12-Apr-22 13-Apr-22 C C 1

35 AF190-DUTCH-CVL-WIR-024 01 Latest Inspection Request for Castng Out of 7 Secondary Secant Pile Number 23,25,27,29,31,33,35 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

36 AF190-DUTCH-CVL-WIR-025 00 Latest Inspection Request for Setting Out of 7 Primary Secant Piles Numbers 38,40,42,44,46,48,50 CVL DUTCH 13-Apr-22 17-Apr-22 B B 4

37 AF190-DUTCH-CVL-WIR-026 00 Latest Inspection Request for Casting of 7 Primary Secant Piles Numbers 38,40,42,44,46,48,50 CVL DUTCH 13-Apr-22 17-Apr-22 B B 4

38 AF190-DUTCH-CVL-WIR-027 00 Latest Inspection Request for Setting out and Steel Cages of 7 Secondary Secant Piles Numbers 445,447,449,451,453,455,457 CVL DUTCH 13-Apr-22 17-Apr-22 B B 4

39 AF190-DUTCH-CVL-WIR-028 00 Latest Inspection Request for Casting of 7 Secondary Secant Piles Numbers 445,447,449,451,453,455,457 CVL DUTCH 13-Apr-22 17-Apr-22 B B 4

40 AF190-DUTCH-CVL-WIR-029 00 Latest Inspection Request for Setting Out of 8 Primary Secant Piles numbers (460,462,464,466,468,470,472,474) CVL DUTCH 14-Apr-22 17-Apr-22 B B 3

41 AF190-DUTCH-CVL-WIR-030 00 Latest Inspection Request for Casing of 8 Primary Secant Piles numbers (460,462,464,466,468,470,472,474) CVL DUTCH 14-Apr-22 17-Apr-22 B B 3

42 AF190-DUTCH-CVL-WIR-031 00 Latest Inspection Request for Setting Out and Steel Cages of 7 Secondary Secant Piles numbers (37,39,41,43,45) CVL DUTCH 14-Apr-22 17-Apr-22 B B 3

43 AF190-DUTCH-CVL-WIR-032 00 Latest Inspection Request for Casting of 7 Secondary Secant Piles numbers (37,39,41,43,45) CVL DUTCH 14-Apr-22 17-Apr-22 B B 3

44 AF190-DUTCH-CVL-WIR-033 00 Latest Inspection Request for Setting Out of 8 Primary Secant Pile Number 70,72,74,76,78,80,82,84 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

45 AF190-DUTCH-CVL-WIR-034 00 Latest Inspection Request for Casting of 8 Primary Secant Pile Number 70,72,74,76,78,80,82,84 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

46 AF190-DUTCH-CVL-WIR-035 00 Latest Inspection Request for Setting Out of 8 Secondary Secant Pile Number 473,471,469,467,465,463,461,459 CVL DUTCH 15-Apr-22 19-Apr-22 A A 4

47 AF190-DUTCH-CVL-WIR-036 00 Latest Inspection Request for Casting of 8 Secondary Secant Pile Number 473,471,469,467,465,463,461,459 CVL DUTCH 15-Apr-22 19-Apr-22 B B 4

48 AF190-DUTCH-CVL-WIR-037 00 Latest Inspection Request for Setting Out of 6 Primary Secant Piles 476,478,480,482,484,486 CVL DUTCH 18-Apr-22 19-Apr-22 B B 1

49 AF190-DUTCH-CVL-WIR-038 00 Latest Inspection Request for Casting of 6 Primary Secant Piles 476,478,480,482,484,486 CVL DUTCH 18-Apr-22 19-Apr-22 B B 1

50 AF190-DUTCH-CVL-WIR-039 00 Latest Inspection Request for Setting Out and Steel Cages of 6 Secondary Secant Piles 71,73,75,77,79,81 CVL DUTCH 18-Apr-22 19-Apr-22 A A 1

51 AF190-DUTCH-CVL-WIR-040 00 Latest Inspection Request for Casting of 6 Secondary Secant Piles 71,73,75,77,79,81 CVL DUTCH 15-May-22 19-May-22 B B 4

52 AF190-DUTCH-CVL-WIR-041 00 Latest Inspection Request for Setting Out of 4 Primary Secant Piles 152,154,156,158 CVL DUTCH 18-Apr-22 21-Apr-22 B B 3

53 AF190-DUTCH-CVL-WIR-042 00 Latest Inspection Request for Casting of 4 Primary Secant Piles 152,154,156,158 CVL DUTCH 18-Apr-22 21-Apr-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
54 AF190-DUTCH-CVL-WIR-043 00 Latest Inspection Request for Setting Out of 8 Primary Secant Piles No. 84,86,88,90,92,94,86,98 CVL DUTCH 18-Apr-22 20-Apr-22 B B 2

55 AF190-DUTCH-CVL-WIR-044 00 Latest Inspection Request for Casting of 8 Primary Secant Piles No. 84,86,88,90,92,94,86,98 CVL DUTCH 18-Apr-22 19-Apr-22 B B 1

56 AF190-DUTCH-CVL-WIR-045 00 Latest Inspection Request for Setting Out and Steel Cages of 7 Secondary Secant Piles No. 475,477,479,481,483,485,487 CVL DUTCH 18-Apr-22 20-Apr-22 B B 2

57 AF190-DUTCH-CVL-WIR-046 00 Latest Inspection Request for Casting of 7 Secondary Secant Piles No. 475,477,479,481,483,485,487 CVL DUTCH 18-Apr-22 20-Apr-22 B B 2

58 AF190-DUTCH-CVL-WIR-047 00 Latest Inspection Request for Setting Out of 4 Primary Secant Piles 160,162,164,166 CVL DUTCH 19-Apr-22 21-Apr-22 B B 2

59 AF190-DUTCH-CVL-WIR-048 00 Latest Inspection Request for Casting of 4 Primary Secant Piles 160,162,164,166 CVL DUTCH 19-Apr-22 21-Apr-22 B B 2

60 AF190-DUTCH-CVL-WIR-049 00 Latest Inspection Request for Setting Out and Steel Cages of 7 Secondary Secant Piles 83,85,87,89,91,93,95 CVL DUTCH 19-Apr-22 21-Apr-22 B B 2

61 AF190-DUTCH-CVL-WIR-050 00 Latest Inspection Request for Casting of 7 Secondary Secant Piles 83,85,87,89,91,93,95 CVL DUTCH 19-Apr-22 21-Apr-22 B B 2

62 AF190-DUTCH-CVL-WIR-051 00 Latest Inspection Request for Setting Out of 7 Primary 98,100,102,104,106,108,110 CVL DUTCH 20-Apr-22 22-Apr-22 B B 2

63 AF190-DUTCH-CVL-WIR-052 00 Latest Inspection Request for Casting of 7 Primary 98,100,102,104,106,108,110 CVL DUTCH 20-Apr-22 22-Apr-22 B B 2

64 AF190-DUTCH-CVL-WIR-053 00 Latest Inspection Request for Setting Out and Steel Cages of 8 Secondary Secant Piles 151,153,155,157,159,16,163,165 CVL DUTCH 20-Apr-22 22-Apr-22 B B 2

65 AF190-DUTCH-CVL-WIR-054 00 Latest Inspection Request for Casting of 8 Secondary Secant Piles 151,153,155,157,159,16,163,165 CVL DUTCH 20-Apr-22 22-Apr-22 B B 2

66 AF190-DUTCH-CVL-WIR-055 00 Latest Inspection Request for Setting Out of 9 Primary Secant Piles 168,170,172,174,176,180,182,184,186 CVL DUTCH 22-Apr-22 24-Apr-22 B B 2

67 AF190-DUTCH-CVL-WIR-056 00 Latest Inspection Request for Casting of 9 Primary Secant Piles 168,170,172,174,176,180,182,184,186 CVL DUTCH 22-Apr-22 24-Apr-22 B B 2

68 AF190-DUTCH-CVL-WIR-057 00 Latest Inspection Request for Setting Out and Steel Cages of 5 Secondary Piles 101,103,105,107,109 CVL DUTCH 22-Apr-22 24-Apr-22 B B 2

69 AF190-DUTCH-CVL-WIR-058 00 Latest Inspection Request for Casting of 5 Secondary Piles 101,103,105,107,109 CVL DUTCH 22-Apr-22 24-Apr-22 B B 2

70 AF190-DUTCH-CVL-WIR-059 00 Latest Inspection Request for Setting Out of 7 Primary Secant Piles 48,50,52,54,56,58,60 CVL DUTCH 22-Apr-22 25-Apr-22 B B 3

71 AF190-DUTCH-CVL-WIR-060 00 Latest Inspection Request for Casting of 7 Primary Secant Piles 48,50,52,54,56,58,60 CVL DUTCH 22-Apr-22 25-Apr-22 B B 3

72 AF190-DUTCH-CVL-WIR-061 00 Latest Inspection Request for Setting out and Steel Cages of 9 Secondary Secant Piles 167,169,17,173,175,177,179,181,183 CVL DUTCH 22-Apr-22 25-Apr-22 B B 3

73 AF190-DUTCH-CVL-WIR-062 00 Latest Inspection Request for Casting of 9 Secondary Secant Piles 167,169,17,173,175,177,179,181,183 CVL DUTCH 22-Apr-22 25-Apr-22 B B 3

74 AF190-DUTCH-CVL-WIR-063 00 Latest Inspection Request for Setting Out and Steel Cages of 10 Primary Secant Piles 186,188,190,192,194,196,198,200,148,146 CVL DUTCH 24-Apr-22 26-Apr-22 B B 2

75 AF190-DUTCH-CVL-WIR-064 00 Latest Inspection Request for Casting of 10 Primary Secant Piles 186,188,190,192,194,196,198,200,148,146 CVL DUTCH 24-Apr-22 26-Apr-22 B B 2

76 AF190-DUTCH-CVL-WIR-065 00 Latest Inspection Request for Setting Out and Steel Cages of 10 Primary Secant Piles 186,188,190,192,194,196,198,200,148,146 CVL DUTCH 24-Apr-22 26-Apr-22 B B 2

77 AF190-DUTCH-CVL-WIR-066 00 Latest Inspection Request for Casting of 7 Secondary Secant Piles 47,49,51,53,55,59 CVL DUTCH 24-Apr-22 26-Apr-22 B B 2

78 AF190-DUTCH-CVL-WIR-067 00 Latest Inspection Request for Driving of H-Beam 36 to 75 CVL DUTCH 24-Apr-22 26-Apr-22 B B 2

79 AF190-DUTCH-CVL-WIR-068 00 Latest Inspection Request for Casting of 7 Primary Secant Piles 60,62,64,66,68,114,116 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

80 AF190-DUTCH-CVL-WIR-069 00 Latest Inspection Request for Setting Out and Steel Cages of 7 Primary Secant Piles 60,62,64,66,68,114,116 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
81 AF190-DUTCH-CVL-WIR-070 00 Latest Inspection Request for Setting Out and Steel Cages of 10 Secondary Secant Piles 145,147,149,197,195,193,191,189,197,185 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

82 AF190-DUTCH-CVL-WIR-071 00 Latest Inspection Request for Casting of 10 Secondary Secant Piles 145,147,149,197,195,193,191,189,197,185 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

83 AF190-DUTCH-CVL-WIR-072 00 Latest Inspection Request for Setting Out of 5 Center Piles 263,265,267,269,271 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

84 AF190-DUTCH-CVL-WIR-073 00 Latest Inspection Request for Steel Cages of 5 Center Piles 263,265,267,269,271 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

85 AF190-DUTCH-CVL-WIR-074 00 Superseded Inspection Request for Casting of 5 Center Piles 263,265,267,269,271 CVL DUTCH 26-Apr-22 27-Apr-22 C C 1

86 AF190-DUTCH-CVL-WIR-074 01 Latest Inspection Request for Casting of 5 Center Piles 263,265,267,269,271 CVL DUTCH 5-May-22 9-May-22 B B 4

87 AF190-DUTCH-CVL-WIR-075 00 Latest Inspection Request for Setting Out of 9 Primary Secant Piles 126,128,130,132,134,136,138,140,142 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

88 AF190-DUTCH-CVL-WIR-076 00 Latest Inspection Request for Setting Out of 9 Primary Secant Piles 126,128,130,132,134,136,138,140,142 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

89 AF190-DUTCH-CVL-WIR-077 00 Latest Inspection Request for Setting Out of 8 Primary Secant Piles 59,61,63,6,67,69,111,113 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

90 AF190-DUTCH-CVL-WIR-078 00 Latest Inspection Request for Casting of 8 Primary Secant Piles 59,61,63,6,67,69,111,113 CVL DUTCH 26-Apr-22 28-Apr-22 B B 2

91 AF190-DUTCH-CVL-WIR-079 00 Latest Inspection Request for Setting Out of 9 Primary Secant Piles Numbers (356, 358, 360, 362, 364, 366, 368, 370) CVL DUTCH 27-Apr-22 5-May-22 B B 8

92 AF190-DUTCH-CVL-WIR-080 00 Latest Inspection Request for Casting of 9 Primary Secant Piles 356, 358, 360, 362, 364, 366, 368, 370 CVL DUTCH 27-Apr-22 6-May-22 B B 9

93 AF190-DUTCH-CVL-WIR-081 00 Superseded Inspection Request for Setting out & Steel Cages 0f 10 Secondary Secant Piles 125, 127, 129, 131, 133, 135, 137, 139, 141, 143 CVL DUTCH 27-Apr-22 6-May-22 C C 9

94 AF190-DUTCH-CVL-WIR-081 01 Latest Inspection Request for Setting out & Steel Cages 0f 10 Secondary Secant Piles 125, 127, 129, 131, 133, 135, 137, 139, 141, 143 CVL DUTCH 9-May-22 12-May-22 A A 3

95 AF190-DUTCH-CVL-WIR-082 00 Latest Inspection Request for Casting 0f 10 Secondary Secant Piles 125, 127, 129, 131, 133, 135, 137, 139, 141, 144 CVL DUTCH 27-Apr-22 6-May-22 B B 9

96 AF190-DUTCH-CVL-WIR-083 00 Latest Inspection for Setting Out & Drilling Depth of 10 Primary Secant Piles 116, 118, 120, 122, CVL DUTCH 28-Apr-22 6-May-22 B B 8

97 AF190-DUTCH-CVL-WIR-084 00 Latest Inspection for Casting of 10 Primary Secant Piles 116, 118, 120, 122, 408, 410, 412, 414, 416, 418 CVL DUTCH 28-Apr-22 6-May-22 B B 8

98 AF190-DUTCH-CVL-WIR-085 00 Latest Inspection for Setting Out, Drilling Depth and Steel Cages of 8 Secondary Secant Piles 357, 359, 361, 363, 365, 367, 369 CVL DUTCH 28-Apr-22 6-May-22 B B 8

99 AF190-DUTCH-CVL-WIR-086 00 Latest Inspection for Casting of 10 Secondary Secant Piles 357, 359, 361, 363, 365, 367, 369 CVL DUTCH 28-Apr-22 6-May-22 B B 8

Inspection for Setting Out & Drilling Depth of 10 Primary Secant Piles
100 AF190-DUTCH-CVL-WIR-087 00 Latest
346,348,350,352,354,374,378,380,382,384,386,388,390,392
CVL DUTCH 30-Apr-22 9-May-22 B B 9

101 AF190-DUTCH-CVL-WIR-088 00 Latest Inspection for Casting of 10 Primary Secant Piles 346,348,350,352,354,374,376,378,380,382,384,386,388,390,392 CVL DUTCH 30-Apr-22 9-May-22 B B 9

Inspection for Setting Out, Drilling Depth & Steel Cages of 10 Secondary Secant Piles
102 AF190-DUTCH-CVL-WIR-089 00 Latest
115,117,119,121,123,347,349,351,353,355
CVL DUTCH 30-Apr-22 9-May-22 B B 9

103 AF190-DUTCH-CVL-WIR-090 00 Latest Inspection for Casting of 10 Secondary Secant Piles 115,117119,121,123,347,349,351,353,355 CVL DUTCH 30-Apr-22 9-May-22 B B 9

104 AF190-DUTCH-CVL-WIR-091 00 Latest Inspection for Setting Out & Drilling of 10 Primary Secant Pile 326,328,330,334,336,338,340,342,344 CVL DUTCH 4-May-22 9-May-22 B B 5

105 AF190-DUTCH-CVL-WIR-092 00 Latest Inspection for Casting of 10 Primary Secant Pile 326,328,330,332,334,336,338,340,342,344 CVL DUTCH 4-May-22 9-May-22 B B 5

106 AF190-DUTCH-CVL-WIR-093 00 Latest Inspection for Setting Out, Drilling & Steel Cages of 10 Secondary Secant Pile 373,375,377,379,381,383,385,387,389,391 CVL DUTCH 4-May-22 9-May-22 B B 5

107 AF190-DUTCH-CVL-WIR-094 00 Latest Inspection for Casting of 10 Secondary Secant Pile 373,375,377,379,381,383,385,387,391 CVL DUTCH 4-May-22 9-May-22 B B 5
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
108 AF190-DUTCH-CVL-WIR-095 00 Latest Inspection for Setting Out & Drilling Depth of 10 Primary Secant Pile 394,396,398,400,402,404,406,408,410,412 CVL DUTCH 4-May-22 9-May-22 B B 5

109 AF190-DUTCH-CVL-WIR-096 00 Latest Inspection for Casting of 10 Primary Secant Pile 394,396,398,400,402,404,406,408,410,412 CVL DUTCH 4-May-22 9-May-22 B B 5

110 AF190-DUTCH-CVL-WIR-097 00 Latest Inspection for Setting Out, Drilling Depth & Steel Cages of 10 Secondary Secant Pile 327,329,331,333,337,339,341,343,345 CVL DUTCH 4-May-22 9-May-22 B B 5

111 AF190-DUTCH-CVL-WIR-098 00 Latest Inspection for Casting of 10 Secondary Secant Pile 327,329,331,333,335,337,341,343,345 CVL DUTCH 4-May-22 9-May-22 B B 5

112 AF190-DUTCH-CVL-WIR-099 00 Latest Inspection for Setting Out & Drilling Depth of 10 Primary Secant Piles 306,308,310,312,314,316,318,320,322,324 CVL DUTCH 5-May-22 9-May-22 B B 4

113 AF190-DUTCH-CVL-WIR-100 00 Latest Inspection for Casting of 10 Primary Secant Piles 306,308,310,312,314,316,318,320,322,324 CVL DUTCH 5-May-22 9-May-22 B B 4

114 AF190-DUTCH-CVL-WIR-101 00 Latest Inspection for Setting Out, Drilling Depth & Steel Cages of 8 Secondary Secant Piles 389,391,393,395,397,399,401,403 CVL DUTCH 5-May-22 9-May-22 B B 4

115 AF190-DUTCH-CVL-WIR-102 00 Latest Inspection for Casting of 8 Secondary Secant Piles 389,391,393,395,397,399,401,403 CVL DUTCH 5-May-22 9-May-22 B B 4

116 AF190-DUTCH-CVL-WIR-103 00 Latest Inspection for Setting our and Drilling of 9 Primary Secant Piles 406,408,410,412,414,416,418 CVL DUTCH 8-May-22 9-May-22 B B 1

117 AF190-DUTCH-CVL-WIR-104 00 Latest Inspection for Casting og 7 primary Secant Piles 406,408,412,414,416,418 CVL DUTCH 8-May-22 9-May-22 B B 1

118 AF190-DUTCH-CVL-WIR-105 00 Latest Inspection for Setting Out, Drilling Depth andSteel Cages of 8 Secondary Secant Piles 311,313,315,317,319,321 CVL DUTCH 8-May-22 9-May-22 B B 1

119 AF190-DUTCH-CVL-WIR-106 00 Latest Inspection for Casting of 8 Secondary Secant Piles 311,313,315,317,319,321,323,325 CVL DUTCH 8-May-22 9-May-22 B B 1

120 AF190-DUTCH-CVL-WIR-107 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 303,296,280,278,276 CVL DUTCH 8-May-22 9-May-22 B B 1

121 AF190-DUTCH-CVL-WIR-108 00 Latest Inspection for Cages of 5 Center Piles 303,296,280,278,276 CVL DUTCH 8-May-22 9-May-22 B B 1

122 AF190-DUTCH-CVL-WIR-109 00 Latest Inspection for Casting of 5 Center Pile 303,296,280,278,276 CVL DUTCH 8-May-22 9-May-22 B B 1

123 AF190-DUTCH-CVL-WIR-110 00 Latest Inspection for Setting Out and Drilling of 10 Primary Secant Piles 290,292,294,298,300,302,304,306,308 CVL DUTCH 8-May-22 11-May-22 B B 3

124 AF190-DUTCH-CVL-WIR-111 00 Latest Inspection for Casting of 10 Primary Secant Piles 290,292,294,296,298,300,302,304,306,308 CVL DUTCH 8-May-22 11-May-22 B B 3

125 AF190-DUTCH-CVL-WIR-112 00 Latest Inspection for Setting out, drilling and steel cages of 8 secondary secant pile 405,407,409,411,413,415,417,419 CVL DUTCH 8-May-22 11-May-22 B B 3

126 AF190-DUTCH-CVL-WIR-113 00 Latest Inspection for casting of 8 secant pile 405,407,409,411,413,415,417,419 CVL DUTCH 8-May-22 11-May-22 B B 3

127 AF190-DUTCH-CVL-WIR-114 00 Latest Inspection for Setting out and drilling of 8 center pile 264,266,268,272,275,277,279,288 CVL DUTCH 8-May-22 11-May-22 B B 3

128 AF190-DUTCH-CVL-WIR-115 00 Latest Inspection for Steel cages of 8 center pile 264,266,268,272,275,277,279,288 CVL DUTCH 8-May-22 11-May-22 B B 3

129 AF190-DUTCH-CVL-WIR-116 00 Latest Inspection for Casting of 8 center pile 264,266,268,272,275,277,279,288 CVL DUTCH 8-May-22 11-May-22 B B 3

130 ADN-DUTCH-WIR-CIV-0117 00 Latest Inspection for Setting out, drilling depth and steel cages of 8 Secondary Secant Piles 295,297,299,301,305,307,309 CVL DUTCH 9-May-22 12-May-22 B B 3

131 ADN-DUTCH-WIR-CIV-0118 00 Latest Inspection for Casting og 8 Secondary Secant piles 295,297,299,301,305,307,309 CVL DUTCH 9-May-22 12-May-22 B B 3

132 ADN-DUTCH-WIR-CIV-0119 00 Latest Inspection for Setting out and drilling of 10 Center piles 266,272,277,279,288,415,417,423,427,425 CVL DUTCH 9-May-22 12-May-22 B B 3

133 ADN-DUTCH-WIR-CIV-0120 00 Latest Inspection for Steel cages of 10 center piles 266,272,277,279,288,415,417,423,427,425 CVL DUTCH 9-May-22 12-May-22 B B 3

134 ADN-DUTCH-WIR-CIV-0121 00 Latest Inspection for casting of 10 center pile numbers 266,272,277,279,288,415,417,423,427,425 CVL DUTCH 10-May-22 12-May-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
135 ADN-DUT-WIR-CIV-0122 00 Latest Inspection for Setting out and Drilling Delth of 10 Primary Secant Pile 274,276,278,280,282,284,286,288,290,292,98 CVL DUTCH 10-May-22 13-May-22 B B 3

136 ADN-DUT-WIR-CIV-0123 00 Latest Inspection for Casting ig 10 Primary Secant Pile 274,276,278,280,282,284,286,288,290,292,98 CVL DUTCH 10-May-22 13-May-22 B B 3

137 ADN-DUT-WIR-CIV-0124 00 Latest Inspection for Setting out, drilling depth and steel cages of 2 secondary secant piles 97 & 99 CVL DUTCH 10-May-22 13-May-22 B B 3

138 ADN-DUT-WIR-CIV-0125 00 Latest Inspection for Casting og 2 Secondary Secant pile 97 & 99 CVL DUTCH 10-May-22 13-May-22 B B 3

139 ADN-DUT-WIR-CIV-0126 00 Latest Setting out and drilling of 8 center pile 338,340,425,427,423,417,415,409 CVL DUTCH 10-May-22 13-May-22 B B 3

140 ADN-DUT-WIR-CIV-0127 00 Latest Inspection for Steel Cages of 8 Center Piles 338,340,425,427,423,417,415,409 CVL DUTCH 10-May-22 13-May-22 B B 3

141 ADN-DUT-WIR-CIV-0128 00 Latest Inspection for Casting of 8 Center Pile 338,340,425,427,423,417,415,409 CVL DUTCH 10-May-22 13-May-22 B B 3

142 ADN-DUT-WIR-CIV-0129 00 Latest Inspection for Setting out, Drilling and Steel Cages of 12 Secondary Secant Piles 271,273,275,277,279,281,283,285,289,291,293 CVL DUTCH 11-May-22 17-May-22 A A 6

143 ADN-DUT-WIR-CIV-0130 00 Latest Inspection for Casting of 12 Secondary Piles 271,273,275,277,279,281,283,285,287,289,291,293 CVL DUTCH 11-May-22 17-May-22 B B 6

144 ADN-DUT-WIR-CIV-0131 00 Latest Inspection for Setting out and Drilling of 10 Center Pile 281,283,285,303,309,319,323,338,340 CVL DUTCH 11-May-22 17-May-22 B B 6

145 ADN-DUT-WIR-CIV-0132 00 Latest Inspection for Steel Cages of 10 Center Piles 281,283,285,287,303,309,319,323,338,340 CVL DUTCH 11-May-22 17-May-22 B B 6

146 ADN-DUT-WIR-CIV-0133 00 Latest Inspection for Casting of 10 Center Piles 281,283,285,287,303,309,319,323,338,340 CVL DUTCH 11-May-22 17-May-22 B B 6

147 ADN-DUT-WIR-CIV-0134 00 Latest Inspection for Setting out and Drilling Depth of 12 primary Secant Pile 246,248,250,250,254,256,258,260,262,264,266,268 CVL DUTCH 13-May-22 17-May-22 A A 4

148 ADN-DUT-WIR-CIV-0135 00 Latest Inspection for casting of 12 primary Secant Pile 246,248,250,254,256,260,262,264,266,268 CVL DUTCH 13-May-22 17-May-22 B B 4

149 ADN-DUT-WIR-CIV-0136 00 Superseded Inspection for Setting out and drilling of 6 Center Piles 335,337,339,426,421,413 CVL DUTCH 13-May-22 17-May-22 C C 4

150 ADN-DUT-WIR-CIV-0136 01 Latest Inspection for Setting out and drilling of 7 Center Piles 335,336,392,403,405,424,426 CVL DUTCH 19-May-22 22-May-22 B B 3

151 ADN-DUT-WIR-CIV-0137 00 Superseded Inspection for Steel Cages of 6 Center Piles 335,337,339,426,421,413 CVL DUTCH 13-May-22 17-May-22 C C 4

152 ADN-DUT-WIR-CIV-0137 01 Latest Inspection for Steel Cages of 7 Center Piles 335,336,392,403,405,424,426 CVL DUTCH 19-May-22 22-May-22 B B 3

153 ADN-DUT-WIR-CIV-0138 00 Superseded Inspection for Casting of 6 Center Piles 335,337,339,426,421,413 CVL DUTCH 13-May-22 17-May-22 C C 4

154 ADN-DUT-WIR-CIV-0138 01 Latest Inspection for Casting of 7 Center Piles 335,336,392,403,405,424,426 CVL DUTCH 19-May-22 22-May-22 B B 3

Inspection for setting out, drilling and steel cages of 12 secondary secant piles
155 ADN-DUT-WIR-CIV-0139 00 Latest
247,249,251,253,255,257,259,261,263,265,267,269
CVL DUTCH 15-May-22 19-May-22 B B 4

156 ADN-DUT-WIR-CIV-0140 00 Latest Inspection for Casting of 12 Secondary Piles 247,249,251,253,255,257,259,261,263,265,267,269 CVL DUTCH 15-May-22 19-May-22 B B 4

157 ADN-DUT-WIR-CIV-0141 00 Latest Inspection for Setting out and drilling of 7 center piles 337,339,419,420,414,416,422 CVL DUTCH 15-May-22 19-May-22 B B 4

158 ADN-DUT-WIR-CIV-0142 00 Latest Inspection for Steel Cages of 7 Center Piles 337,339,419,420,414,416,422 CVL DUTCH 15-May-22 19-May-22 B B 4

159 ADN-DUT-WIR-CIV-0143 00 Latest Inspection for Casting of 7 center piles 337,339,419,420,414,416,422 CVL DUTCH 15-May-22 19-May-22 B B 4

160 ADN-DUT-WIR-CIV-0144 00 Latest Inspection for Setting out and Drilling of 12 primary Secant piles 222,224,226,228,230,232,234,236,238,240,242,244 CVL DUTCH 17-May-22 19-May-22 B B 2

161 ADN-DUT-WIR-CIV-0145 00 Latest Inspection for Casting of 12 Primary Secant Piles 222,224,226,228,230,232,234,236,238,240,242,244 CVL DUTCH 17-May-22 19-May-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
162 ADN-DUT-WIR-CIV-0146 00 Latest Inspection for Setting out and drilling of 9 Center Piles 54,59,299,312,404,406,408,413,421 CVL DUTCH 17-May-22 19-May-22 B B 2

163 ADN-DUT-WIR-CIV-0147 00 Latest Inspection for Steel Cages of 9 Center Piles 54,59,299,312,404,406,408,413,421 CVL DUTCH 17-May-22 19-May-22 B B 2

164 ADN-DUT-WIR-CIV-0148 00 Latest Inspection for Casting of 9 Center Piles 54,59,299,312,404,406,408,413,421 CVL DUTCH 17-May-22 19-May-22 B B 2

Inspection for Setting out, drilling depth and steel cages of 13 secondary secant piles
165 ADN-DUT-WIR-CIV-0149 00 Latest
223,225,227,229,231,233,235,237,239,241,243,245,247
CVL DUTCH 18-May-22 22-May-22 B B 4

166 ADN-DUT-WIR-CIV-0150 00 Latest Inspection for Casting ot 13 secondary secant piles 223,225,227,229,231,233,235,237,239,241,243,245,247 CVL DUTCH 18-May-22 22-May-22 B B 4

167 ADN-DUT-WIR-CIV-0151 00 Latest Inspection for setting out and drilling of 8 center piles 60,63,334,273,421,413,397,406 CVL DUTCH 18-May-22 23-May-22 B B 5

168 ADN-DUT-WIR-CIV-0152 00 Latest Inspection for steel cages of 8 center piles 60,63,334,273,421,413,397,406 CVL DUTCH 18-May-22 23-May-22 B B 5

169 ADN-DUT-WIR-CIV-0153 00 Latest Inspection for casting of 8 ceneter pile 60,63,334,273,421,413,397,406 CVL DUTCH 18-May-22 23-May-22 B B 5

170 ADN-DUT-WIR-CIV-0154 00 Superseded Inspection for Setting out and drilling of 8 center pile 333,269,186,402,411,412,419,420 CVL DUTCH 19-May-22 22-May-22 C C 3

171 ADN-DUT-WIR-CIV-0154 01 Latest Inspection for Setting out and drilling of 2 Center Piles 186,402 CVL DUTCH 25-May-22 30-May-22 B B 5

172 ADN-DUT-WIR-CIV-0155 00 Superseded Inspection for Steel Cages of 8 Center Piles 333,269,186,402,411,412,419,420 CVL DUTCH 19-May-22 22-May-22 C C 3

173 ADN-DUT-WIR-CIV-0155 01 Latest Inspection for Setting out and drilling of 2 Center Piles 186,402 CVL DUTCH 25-May-22 30-May-22 B B 5

174 ADN-DUT-WIR-CIV-0156 00 Superseded Inspection for Casting of 8 Center Piles 333,269,186,402,411,412,419,420 CVL DUTCH 19-May-22 22-May-22 C C 3

175 ADN-DUT-WIR-CIV-0156 01 Latest Inspection for Setting out and drilling of 2 Center Piles 186,402 CVL DUTCH 25-May-22 30-May-22 B B 5

176 ADN-DUT-WIR-CIV-0157 00 Latest Inspection for Setting out and drilling depth of 11 primary secant piles 200,202,204,206,208,210,212,214,216,218,220 CVL DUTCH 19-May-22 22-May-22 B B 3

177 ADN-DUT-WIR-CIV-0158 00 Latest Inspection for Casting of 11 primary secant piles 200,202,204,206,208,210,212,214,216,218,220 CVL DUTCH 19-May-22 22-May-22 B B 3

178 ADN-DUT-WIR-CIV-0159 00 Latest Inspection for Setting out, drilling depth and steel cages of 7 secondary secant piles 209,211,213,215,217,219,221 CVL DUTCH 20-May-22 24-May-22 A A 4

179 ADN-DUT-WIR-CIV-0160 00 Latest Inspection for Casting of 7 secondary secant piles 209,211,213,215,217,219,221 CVL DUTCH 20-May-22 24-May-22 B B 4

180 ADN-DUT-WIR-CIV-0161 00 Latest Inspection for setting out and drilling of 11 center piles 174,180,183,186,411,412,419,420,61,62,54 CVL DUTCH 20-May-22 23-May-22 B B 3

181 ADN-DUT-WIR-CIV-0162 00 Latest Inspection for steel cages of 11 Center Piles 174,180,183,186,411,412,419,420,61,62,54 CVL DUTCH 20-May-22 23-May-22 B B 3

182 ADN-DUT-WIR-CIV-0163 00 Latest Inspection for casting of 11 center piles 174,180,183,186,411,412,419,420,61,62,54 CVL DUTCH 20-May-22 24-May-22 B B 4

183 ADN-DUT-WIR-CIV-0164 00 Latest Inspection for setting out and drilling depth of 4 primary secant piles 200,202,204,206 CVL DUTCH 22-May-22 24-May-22 B B 2

184 ADN-DUT-WIR-CIV-0165 00 Latest Inspection for Casting of 4 Primary Secant Pile 200,202,204,206 CVL DUTCH 22-May-22 24-May-22 B B 2

185 ADN-DUT-WIR-CIV-0166 00 Superseded Inspection for Setting out and drilling of 19 center piles 404,396,269,183,186,321,323,314,301,303,45,43,47,51,49,53,54,55,58 CVL DUTCH 22-May-22 25-May-22 C C 3

186 ADN-DUT-WIR-CIV-0166 01 Latest Inspection for Setting out and drilling of 9 center piles 54,55,58,301,314,323,333,396,404 CVL DUTCH 29-May-22 30-May-22 B B 1

187 ADN-DUT-WIR-CIV-0167 00 Superseded Inspection for Steel Cages of 19 Center Piles 404,396,269,183,186,321,323,314,301,303,45,43,47,51,49,53,54,55,58 CVL DUTCH 22-May-22 25-May-22 C C 3

188 ADN-DUT-WIR-CIV-0167 01 Latest Inspection for Steel Cages of 9 Center Piles 54,55,58,301,314,323,333,396,404 CVL DUTCH 29-May-22 30-May-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
189 ADN-DUT-WIR-CIV-0168 00 Superseded Inspection for Casting of 19 Center Piles 404,396,269,183,186,321,323,314,301,303,45,43,47,51,49,53,54,55,58 CVL DUTCH 22-May-22 25-May-22 C C 3

190 ADN-DUT-WIR-CIV-0168 01 Latest Inspection for Casting of 9 Center Piles 54,55,58,301,314,323,333,396,404 CVL DUTCH 29-May-22 30-May-22 B B 1

191 ADN-DUT-WIR-CIV-0169 00 Latest Inspection for setting out, drilling depth and steel cages of 6 secondary piles 199,201,203,205,207,209 CVL DUTCH 23-May-22 25-May-22 B B 2

192 ADN-DUT-WIR-CIV-0170 00 Latest Inspection for Casting of 6 Secondary Secant Piles 199,201,203,205,207,209 CVL DUTCH 23-May-22 25-May-22 B B 2

Inspection for Setting out and Drilling of 19 Center Piles


193 ADN-DUT-WIR-CIV-0171 00 Superseded
42,46,44,48,52,56,57,270,281,297,302,309,310,320,410,413,402,418,421
CVL DUTCH 23-May-22 25-May-22 C C 2

194 ADN-DUT-WIR-CIV-0171 01 Latest Inspection for Setting out and Drilling of 10 Center Piles 47,49,51,269,282,287,303,413,418,421 CVL DUTCH 29-May-22 30-May-22 B B 1

195 ADN-DUT-WIR-CIV-0172 00 Superseded Inspection for Steel Cages of 19 center piles 42,46,44,48,52,56,57,270,281,297,302,309,310,320,410,413,402,418,421 CVL DUTCH 23-May-22 25-May-22 C C 2

196 ADN-DUT-WIR-CIV-0172 01 Latest Inspection for Steel Cages of 10 Center Piles 47,49,51,269,282,287,303,413,418,421 CVL DUTCH 29-May-22 30-May-22 B B 1

197 ADN-DUT-WIR-CIV-0173 00 Superseded Inspection for Casting og 19 Center Piles 42,46,44,48,52,56,57,270,281,297,302,309,310,320,410,413,402,418,421 CVL DUTCH 23-May-22 25-May-22 C C 2

198 ADN-DUT-WIR-CIV-0173 01 Latest Inspection for Casting of 10 Center Piles 47,49,51,269,282,287,303,413,418,421 CVL DUTCH 29-May-22 30-May-22 B B 1

199 ADN-DUT-WIR-CIV-0174 00 Superseded Inspection for setting out 8 H-Beams 89,90,264,265,165,166,258,259 CVL DUTCH 24-May-22 26-May-22 C C 2

200 ADN-DUT-WIR-CIV-0174 01 Latest Inspection for setting out 4 H-Beams 89,90,264,265 CVL DUTCH 1-Jun-22 2-Jun-22 B B 1

201 ADN-DUT-WIR-CIV-0175 00 Superseded Inspection for setting out and drilling of 21 center piles 42,46,44,48,52,56,57,183,186,270,281,297 CVL DUTCH 24-May-22 26-May-22 C C 2

202 ADN-DUT-WIR-CIV-0175 01 Latest Inspection for Setting out and drilling of 10 center piles 43,45,48,53,170,172,176,281,298,321 CVL DUTCH 29-May-22 30-May-22 B B 1

203 ADN-DUT-WIR-CIV-0176 00 Superseded Inspection for steel cages of 21 center piles 42,46,44,48,52,56,57,183,186,270,281,297,310,320,302,309,321,410,413,396,402 CVL DUTCH 24-May-22 26-May-22 C C 2

204 ADN-DUT-WIR-CIV-0176 01 Latest Inspection for Steel cages of 10 center piles 43,45,48,53,170,172,176,281,298,321 CVL DUTCH 29-May-22 30-May-22 B B 1

205 ADN-DUT-WIR-CIV-0177 00 Superseded Inspection for Casting of 21 center plies 42,46,44,48,52,56,57,183,186,270,281,297,310,320,302,309,321,410,413,396,402 CVL DUTCH 24-May-22 26-May-22 C C 2

206 ADN-DUT-WIR-CIV-0177 01 Latest Inspection for Casting of 10 center piles 43,45,48,53,170,172,176,281,298,321 CVL DUTCH 29-May-22 30-May-22 B B 1

207 ADN-DUT-WIR-CIV-0178 00 Superseded Inspection for Casting and drilling depth of 8 H-Beams 89,90,264,265,165,166,258,259 CVL DUTCH 24-May-22 26-May-22 C C 2

208 ADN-DUT-WIR-CIV-0178 01 Latest Inspection for Casting and drilling depth of 1 H-Beams 90 CVL DUTCH 1-Jun-22 2-Jun-22 B B 1

209 ADN-DUT-WIR-CIV-0179 00 Superseded Inspection for Installation of H-Beam prior to cast concrete 8 H-Beam 89,90,264,265,165,166,258,259 CVL DUTCH 24-May-22 26-May-22 C C 2

210 ADN-DUT-WIR-CIV-0179 01 Latest Inspection for Installation of H-Beam prior to cast concrete of 1 H-Beams 90 CVL DUTCH 1-Jun-22 2-Jun-22 B B 1

211 ADN-DUT-WIR-CIV-0180 00 Latest Inspection for Setting out and Drilling of 6 center piles 311,307,410,89,91,95 CVL DUTCH 25-May-22 27-May-22 B B 2

212 ADN-DUT-WIR-CIV-0181 00 Latest Inspection for Steel cages of 7 center piles 311,307,410,89,91,95 CVL DUTCH 25-May-22 27-May-22 B B 2

213 ADN-DUT-WIR-CIV-0182 00 Latest Inspection for Casting of 6 center piles 311,307,410,89,91,95 CVL DUTCH 25-May-22 30-May-22 B B 5

Inspection for Setting out and drilling of 19 center piles 270, 285, 316, 320, 72, 76, 77, 74, 42, 44, 46, 80, 82, 85, 87, 173, 175,
214 ADN-DUT-WIR-CIV-0183 00 Latest
179, 402
CVL DUTCH 26-May-22 30-May-22 B B 4

215 ADN-DUT-WIR-CIV-0184 00 Latest Inspection for Steel cages of 19 Center Piles 270, 285, 316, 320, 72, 76, 77, 74, 42, 44, 46, 80, 82, 85, 87, 173, 175, 179, 402 CVL DUTCH 26-May-22 30-May-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
216 ADN-DUT-WIR-CIV-0185 00 Latest Inspection for Casting of 19 Center Piles 270, 285, 316, 320, 72, 76, 77, 74, 42, 44, 46, 80, 82, 85, 87, 173, 175, 179, 402 CVL DUTCH 26-May-22 30-May-22 B B 4

217 ADN-DUT-WIR-CIV-0186 00 Latest Inspection for Setting out and drilling of 8 center piles 71, 75, 79, 81, 84, 88, 92, 94, CVL DUTCH 29-May-22 30-May-22 B B 1

218 ADN-DUT-WIR-CIV-0187 00 Latest Inspection for Steel Cages of 8 Center Piles 71, 75, 79, 81, 84, 88, 92, 94, CVL DUTCH 29-May-22 30-May-22 B B 1

219 ADN-DUT-WIR-CIV-0188 00 Latest Inspection for Casting of 8 Center Piles 71, 75, 79, 81, 84, 88, 92, 94 CVL DUTCH 29-May-22 30-May-22 B B 1

220 ADN-DUT-WIR-CIV-0189 00 Latest Inspection for Setting out and drilling of 10 Center Piles 52, 56, 57, 78, 186, 289, 305, 309, 318 CVL DUTCH 29-May-22 30-May-22 B B 1

221 ADN-DUT-WIR-CIV-0190 00 Latest Inspection for Steel Cages of 10 center piles 52, 56, 57, 65, 78, 186, 289, 305, 309, 318 CVL DUTCH 29-May-22 30-May-22 B B 1

222 ADN-DUT-WIR-CIV-0191 00 Latest Inspection for Casting of 10 center piles 52, 56, 57, 65, 78, 186, 289, 305, 309, 318 CVL DUTCH 29-May-22 30-May-22 B B 1

223 ADN-DUT-WIR-CIV-0192 00 Latest Inspection for Setting out and drilling of 8 Center piles 257,259,261,398,394,400,294,285 CVL DUTCH 30-May-22 2-Jun-22 A A 3

224 ADN-DUT-WIR-CIV-0193 00 Latest Inspection for Setting out and Drilling of 10 Center Piles 182,184,257,259,261,297,310,401,395,399 CVL DUTCH 25-May-22 1-Jun-22 B B 7

225 ADN-DUT-WIR-CIV-0194 00 Latest Inspection for Steel Cages of 10 Center Piles 182,184,257,259,261,297,310,401,395,399 CVL DUTCH 25-May-22 1-Jun-22 B B 7

226 ADN-DUT-WIR-CIV-0195 00 Latest Inspection for Casting of 10 Center Piles 182,184,257,259,261,297,310,401,395,399 CVL DUTCH 25-May-22 1-Jun-22 B B 7

227 ADN-DUT-WIR-CIV-0196 00 Latest Inspection for Setting out and drilling of 15 center piles 37,39,73,86,90,181,183,185,286,295,302,308,326,328,330 CVL DUTCH 25-May-22 30-May-22 A A 5

228 ADN-DUT-WIR-CIV-0197 00 Latest Inspection for Steel Cages of 15 Center Piles 37,39,73,86,90,181,183,185,286,295,302,308,326,328,330 CVL DUTCH 25-May-22 30-May-22 B B 5

229 ADN-DUT-WIR-CIV-0198 00 Latest Inspection for Casting of 15 Center Piles 37,39,73,86,90,181,183,185,286,295,302,308,326,328,330 CVL DUTCH 25-May-22 30-May-22 B B 5

230 ADN-DUT-WIR-CIV-0199 00 Latest Inspection for Steel Cages of 8 Center Piles 257,259,261,398,394,400,294,285 CVL DUTCH 30-May-22 2-Jun-22 B B 3

231 ADN-DUT-WIR-CIV-0200 00 Latest Inspection for Casting of 8 center piles 257,259,261,398,394,400,294,285 CVL DUTCH 30-May-22 2-Jun-22 B B 3

232 ADN-DUT-WIR-CIV-0201 00 Latest Inspection for Setting out and drilling of 12 center piles 2,4,7,9,11,64,131,325,327,329,331,332 CVL DUTCH 30-May-22 1-Jun-22 B B 2

233 ADN-DUT-WIR-CIV-0202 00 Latest Inspection for Steel cages of 12 center piles 2,4,7,9,11,64,131,325,327,329,331,332 CVL DUTCH 30-May-22 1-Jun-22 B B 2

234 ADN-DUT-WIR-CIV-0203 00 Latest Inspection for Casting of 12 center piles 2,4,7,9,11,64,131,325,327,329,331,332 CVL DUTCH 30-May-22 1-Jun-22 B B 2

235 ADN-DUT-WIR-CIV-0204 00 Latest Inspection for Setting out and Drilling of 10 Center Piles 83,93,70,387,388,391,50,38,27 CVL DUTCH 1-Jun-22 5-Jun-22 B B 4

236 ADN-DUT-WIR-CIV-0205 00 Latest Inspection for Steel Cages of 10 Center Piles 83,93,70,5,387,388,391,50,38,27 CVL DUTCH 1-Jun-22 5-Jun-22 B B 4

237 ADN-DUT-WIR-CIV-0206 00 Latest Inspection for Casting of 10 Center Piles 83,93,70,5,387,388,391,50,38,27 CVL DUTCH 1-Jun-22 5-Jun-22 B B 4

238 ADN-DUT-WIR-CIV-0207 00 Latest Inspection for Setting out and Drilling of 14 center piles 5,6,8,10,12,14,18,20,24,41,67,69,292,306 CVL DUTCH 1-Jun-22 5-Jun-22 B B 4

239 ADN-DUT-WIR-CIV-0208 00 Latest Inspection for Steel Cages of 14 Center Piles 3,6,8,10,12,14,18,20,24,41,67,69,292,306 CVL DUTCH 1-Jun-22 5-Jun-22 B B 4

240 ADN-DUT-WIR-CIV-0209 00 Latest Inspection for Casting of 14 Center Piles 3,6,8,10,12,14,18,20,24,41,67,69,292,306 CVL DUTCH 1-Jun-22 5-Jun-22 B B 4

241 ADN-DUT-WIR-CIV-0210 00 Latest Inspection for Setting out and Drilling of 8 Center Piles 22,26,28,30,310,313,384 CVL DUTCH 2-Jun-22 5-Jun-22 B B 3

242 ADN-DUT-WIR-CIV-0211 00 Latest Inspection for Steel Cages of 8 Center Piles 22,26,28,30,291,310,313,384 CVL DUTCH 2-Jun-22 5-Jun-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
243 ADN-DUT-WIR-CIV-0212 00 Latest Inspection for Casting of 8 Center Piles 22,26,28,30,291,310,313,384 CVL DUTCH 2-Jun-22 5-Jun-22 B B 3

244 ADN-DUT-WIR-CIV-0213 00 Latest Inspection for Setting out and Drilling of 12 Center Piles 13,15,17,19,23,29,157,258,262,290,317 CVL DUTCH 2-Jun-22 5-Jun-22 C C 3

245 ADN-DUT-WIR-CIV-0214 00 Latest Inspection for Steel Cages of 12 Center Piles 13,15,17,19,21,23,29,157,258,262,290,317 CVL DUTCH 2-Jun-22 5-Jun-22 C C 3

246 ADN-DUT-WIR-CIV-0215 00 Latest Inspection for Casting of 12 Center Piles 13,15,17,19,21,23,29,157,258,262,290,317 CVL DUTCH 2-Jun-22 5-Jun-22 C C 3

247 ADN-DUT-WIR-CIV-0216 00 Latest Inspection for Setting out and Drilling of 8 Center Piles 397,393,27,386,310,144,145,31 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

248 ADN-DUT-WIR-CIV-0217 00 Latest Inspection for Steel Cages of 8 Center Piles 397,393,27,386,310,144,145,31 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

249 ADN-DUT-WIR-CIV-0218 00 Latest Inspection for Casting of 8 Center Piles 397,393,27,386,310,144,145,31 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

250 ADN-DUT-WIR-CIV-0219 00 Latest Inspection for Setting out and Drilling of 12 Center Piles 5,13,29,33,40,70,300,315,378,382,389,390 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

251 ADN-DUT-WIR-CIV-0220 00 Latest Inspection for Steel Cages of 12 Center Piles 5,13,29,33,40,70,300,315,378,382,389,390 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

252 ADN-DUT-WIR-CIV-0221 00 Latest Inspection for Casting of 12 Center Piles 5,13,29,33,40,70,300,315,378,382,389,390 CVL DUTCH 5-Jun-22 5-Jun-22 B B 0

253 ADN-DUT-WIR-CIV-0222 00 Latest Inspection for Setting out and Drilling of 11 Center Piles 260,368,370,376,372,169,178,32,35,34,146 CVL DUTCH 5-Jun-22 7-Jun-22 B B 2

254 ADN-DUT-WIR-CIV-0223 00 Latest Inspection for Steel Cages of 11 Center Piles 260,368,370,376,372,169,178,32,35,34,146 CVL DUTCH 5-Jun-22 7-Jun-22 B B 2

255 ADN-DUT-WIR-CIV-0224 00 Latest Inspection for Casting of 11 Center Piles 260,368,370,372,169,178,32,35,34,146 CVL DUTCH 5-Jun-22 7-Jun-22 B B 2

256 ADN-DUT-WIR-CIV-0225 00 Latest Inspection for Setting out and Drilling of 15 Center Piles 107,110,132,133,136,137,140,141,155,156,377,379,381,383,385 CVL DUTCH 5-Jun-22 6-Jun-22 A A 1

257 ADN-DUT-WIR-CIV-0226 00 Latest Inspection for Steel Cages of 15 Center Piles 107,110,132,136,137,140,141,155,156,377,379,381,383,385 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

258 ADN-DUT-WIR-CIV-0227 00 Latest Inspection for Casting of 15 Center Piles 107,110,132,133,136,137,140,141,155,156,377,379,381,383,385 CVL DUTCH 5-Jun-22 6-Jun-22 B B 1

259 ADN-DUT-WIR-CIV-0228 00 Latest Inspection for Setting out and Drilling of 8 Center Piles 367,109,165,166,168,374,380,154 CVL DUTCH 6-Jun-22 7-Jun-22 B B 1

260 ADN-DUT-WIR-CIV-0229 00 Latest Inspection for Steel Cages of 8 Center Piles 367,109,165,166,168,374,380,154 CVL DUTCH 6-Jun-22 7-Jun-22 B B 1

261 ADN-DUT-WIR-CIV-0230 00 Latest Inspection for Casting of 8 Center Piles 367,109,165,166,168,374,380,154 CVL DUTCH 6-Jun-22 7-Jun-22 B B 1

262 ADN-DUT-WIR-CIV-0231 00 Latest Inspection for Setting out and Drilling of 10 Center Piles 364,369,372,373,375,246,247,160,162,164 CVL DUTCH 6-Jun-22 9-Jun-22 B B 3

263 ADN-DUT-WIR-CIV-0232 00 Latest Inspection for Steel Cages of 10 center piles 364,369,372,373,375,246,247,160,162,164 CVL DUTCH 6-Jun-22 9-Jun-22 B B 3

264 ADN-DUT-WIR-CIV-0233 00 Latest Inspection for Casting of 10 Center Piles 364,369,372,373,375,246,247,160,162,164 CVL DUTCH 6-Jun-22 9-Jun-22 B B 3

265 ADN-DUT-WIR-CIV-0234 00 Latest Inspection for Setting out and Drilling of 14 Center Piles 116,118,134,135,143,142,138,139,103,106,93,158,366,365 CVL DUTCH 8-Jun-22 12-Jun-22 B B 4

266 ADN-DUT-WIR-CIV-0235 00 Latest Inspection for Steel Cages of 14 Center Piles 116,118,134,135,143,142,138,139,103,106,93,158,366,365 CVL DUTCH 8-Jun-22 12-Jun-22 B B 4

267 ADN-DUT-WIR-CIV-0236 00 Latest Inspection for Casting of 14 Center Piles 116,118,134,135,143,142,138,139,103,106,93,158,366,365 CVL DUTCH 8-Jun-22 12-Jun-22 B B 4

268 ADN-DUT-WIR-CIV-0237 00 Latest Inspection for Setting out and Drilling of 12 Center Piles 120,121,123,124,162,250,252,256,345,349,351,356 CVL DUTCH 8-Jun-22 12-Jun-22 B B 4

269 ADN-DUT-WIR-CIV-0238 00 Latest Inspection for Steel Cages of 12 Center Piles 120,121,123,124,162,250,252,256,345,349,351,356 CVL DUTCH 8-Jun-22 12-Jun-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
270 ADN-DUT-WIR-CIV-0239 00 Latest Inspection for Casting of 12 Center Piles 120,121,123,124,162,250,252,256,345,349,351,356 CVL DUTCH 8-Jun-22 12-Jun-22 B B 4

271 ADN-DUT-WIR-CIV-0240 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 243,248,244,364,363,360 CVL DUTCH 9-Jun-22 12-Jun-22 B B 3

272 ADN-DUT-WIR-CIV-0241 00 Latest Inspection for Steel Cages of 6 Center Piles 243,248,244,364,363,360 CVL DUTCH 9-Jun-22 12-Jun-22 B B 3

273 ADN-DUT-WIR-CIV-0242 00 Latest Inspection for Casting of 6 Center piles 243,248,244,364,363,360 CVL DUTCH 9-Jun-22 12-Jun-22 B B 3

274 ADN-DUT-WIR-CIV-0243 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 117,239,249,251,353,361 CVL DUTCH 9-Jun-22 12-Jun-22 B B 3

275 ADN-DUT-WIR-CIV-0244 00 Latest Inspection for Steel Cages of 6 Center Piles 117,239,249,351,353,361 CVL DUTCH 9-Jun-22 12-Jun-22 B B 3

276 ADN-DUT-WIR-CIV-0245 00 Latest Inspection for Casting of 6 Center Piles 117,239,249,251,353,361 CVL DUTCH 9-Jun-22 12-Jun-22 B B 3

277 ADN-DUT-WIR-CIV-0246 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 363,348,350,354,122,346 CVL DUTCH 12-Jun-22 12-Jun-22 B B 0

278 ADN-DUT-WIR-CIV-0247 00 Latest Inspection for Steel Cages of 6 Center Piles 363,348,350,354,122,346 CVL DUTCH 12-Jun-22 12-Jun-22 B B 0

279 ADN-DUT-WIR-CIV-0248 00 Latest Inspection for Casting of 6 Center Piles 363,348,350,354,122,346 CVL DUTCH 12-Jun-22 14-Jun-22 B B 2

280 ADN-DUT-WIR-CIV-0249 00 Latest Inspection for Setting out and Drilling of 9 Center Piles 104,111,119,121,123,124,167,254,255 CVL DUTCH 12-Jun-22 12-Jun-22 B B 0

281 ADN-DUT-WIR-CIV-0250 00 Latest Inspection for Steel Cages of 9 Piles 104,111,119,121,124,167,254,255 CVL DUTCH 12-Jun-22 12-Jun-22 B B 0

282 ADN-DUT-WIR-CIV-0251 00 Latest Inspection for Casting of 9 center Piles 104,111,119,121,123,124,167,254,255 CVL DUTCH 12-Jun-22 12-Jun-22 B B 0

283 ADN-DUT-WIR-CIV-0252 00 Latest Inspection for Setting out and drilling of 6 Center Piles 113,122,350,355,358,359 CVL DUTCH 12-Jun-22 14-Jun-22 B B 2

284 ADN-DUT-WIR-CIV-0253 00 Latest Inspection for Steel Cages of 6 Center Piles 113,122,350,355,358,359 CVL DUTCH 12-Jun-22 14-Jun-22 B B 2

285 ADN-DUT-WIR-CIV-0254 00 Latest Inspection for Casting of 6 Center Piles 113,122,350,355,358,359 CVL DUTCH 12-Jun-22 15-Jun-22 B B 3

286 ADN-DUT-WIR-CIV-0255 00 Latest Inspection for Setting out and Drilling of 10 Center Piles 16,25,112,114,115,240,241,246,352,362 CVL DUTCH 12-Jun-22 14-Jun-22 B B 2

287 ADN-DUT-WIR-CIV-0256 00 Latest Inspection for Steel Cages of 10 Center Piles 16,25,112,114,115,240,241,246,352,362 CVL DUTCH 12-Jun-22 14-Jun-22 B B 2

288 ADN-DUT-WIR-CIV-0257 00 Latest Inspection for Casting of 10 Center Piles 16,25,112,114,115,240,241,246,352,362 CVL DUTCH 12-Jun-22 14-Jun-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
289 ADN-DUT-WIR-CIV-0258 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 234,230,236,232,238,242 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

290 ADN-DUT-WIR-CIV-0259 00 Latest Inspection for Steel Cages of 6 Center Piles 234,230,236,232,238,242 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

291 ADN-DUT-WIR-CIV-0260 00 Latest Inspection for Casting of 6 Center Piles 234,230,236,232,238,242 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

292 ADN-DUT-WIR-CIV-0261 00 Latest Inspection for Setting out and Drilling of 9 Center Piles 96,98,100,102,161,163,246,343,36 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

293 ADN-DUT-WIR-CIV-0262 00 Latest Inspection for Steel Cages of 9 Center Piles 96,98,100,102,161,163,245,343,36 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

294 ADN-DUT-WIR-CIV-0263 00 Latest Inspection for Casting of 9 Center Piles 96,98,100,102,161,163,245,343,36 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

295 ADN-DUT-WIR-CIV-0264 00 Latest Inspection for Setting out 4 H-Beams 92,97,101,264 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

296 ADN-DUT-WIR-CIV-0265 00 Latest Inspection for Installation of Casing and Drilling Depth of H-Beams 92,97,101,264 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

297 ADN-DUT-WIR-CIV-0266 00 Latest Inspection for Installation of H-Beam Prior to Cast Concrete of 4 H-Beams 92,97,101,264 CVL DUTCH 14-Jun-22 15-Jun-22 B B 1

298 ADN-DUT-WIR-CIV-0267 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 97,99,101,342,347,223 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

299 ADN-DUT-WIR-CIV-0268 00 Latest Inspection for Steel Cages of 6 Center Piles 97,99,101,342,347,223 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

300 ADN-DUT-WIR-CIV-0269 00 Latest Inspection for Casting of 6 Center Piles 97,99,101,342,347,223 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

301 ADN-DUT-WIR-CIV-0270 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 344,350,358,359,363 CVL DUTCH 15-Jun-22 15-Jun-22 B B 0

302 ADN-DUT-WIR-CIV-0271 00 Latest Inspection for Steel Cages of 5 Center Piles 344,350,358,359,363 CVL DUTCH 15-Jun-22 15-Jun-22 B B 0

303 ADN-DUT-WIR-CIV-0272 00 Latest Inspection for Casting of 5 Center Piles 344,350,358,359,363 CVL DUTCH 15-Jun-22 15-Jun-22 B B 0

304 ADN-DUT-WIR-CIV-0273 00 Latest Inspection for Setting out of 4 H-Beams 99,103,105,107 CVL DUTCH 15-Jun-22 15-Jun-22 B B 0

305 ADN-DUT-WIR-CIV-0274 00 Latest Inspection for Installation of Casing and Drilling Depth of 4 H-Beams 99,103,105,107 CVL DUTCH 15-Jun-22 15-Jun-22 B B 0

306 ADN-DUT-WIR-CIV-0275 00 Latest Inspection for Installation of H-Beam prior to Cast Concrete of 4 H-Beams 99,103,105,107 CVL DUTCH 15-Jun-22 15-Jun-22 B B 0

307 ADN-DUT-WIR-CIV-0276 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 341,357,208,218,233 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

308 ADN-DUT-WIR-CIV-0277 00 Latest Inspection for Steel Cages of 5 Center Pile 341,357,208,218,233 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

309 ADN-DUT-WIR-CIV-0278 00 Latest Inspection for Casting of 5 Center Piles 341,357,208,218,233 CVL DUTCH 15-Jun-22 19-Jun-22 B B 4

310 ADN-DUT-WIR-CIV-0279 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 217,219,225,227,237 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

311 ADN-DUT-WIR-CIV-0280 00 Latest Inspection for Steel Cages of 5 Center Piles 217,219,225,227,237 CVL DUTCH 15-Jun-22 17-Jun-22 B B 2

312 ADN-DUT-WIR-CIV-0281 00 Latest Inspection for Casting of 5 Center Piles 217,219,225,227,237 CVL DUTCH 15-Jun-22 19-Jun-22 B B 4

313 ADN-DUT-WIR-CIV-0282 00 Latest Inspection for Setting out of 9 H-Beam 89,98,100,102,104,95,109,160,162 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

314 ADN-DUT-WIR-CIV-0283 00 Latest Inspection for Installation of Casing and Drilling Depth of H-Beams 89, 98,100,102,104,95,109,160,162 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

315 ADN-DUT-WIR-CIV-0284 00 Latest Inspection for Installation of H-Beam Prior to Cast Concrete of 9 H-Beam 89,98,100,102,104,95,109,160,162 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
316 ADN-DUT-WIR-CIV-0285 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 218,222,228,231,235,229 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

317 ADN-DUT-WIR-CIV-0286 00 Latest Inspection for Steel Cages of 6 Center Piles 218,222,228,231,235,229 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

318 ADN-DUT-WIR-CIV-0287 00 Latest Inspection for Casting of 6 Center Piles 218,222,228,231,235,229 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

319 ADN-DUT-WIR-CIV-0288 00 Latest Inspection for Setting out of 5 H-Beam 152,154,156,158,106 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

320 ADN-DUT-WIR-CIV-0289 00 Latest Inspection for Installation of Casing and Drilling Depth of 5 H-Beam 152,154,156,158,106 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

321 ADN-DUT-WIR-CIV-0290 00 Latest Inspection for Installation of H-Beam prior to cast concrete of 5 H-Beam 152,154,156,158,106 CVL DUTCH 16-Jun-22 20-Jun-22 B B 4

322 ADN-DUT-WIR-CIV-0291 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 126,128,130,148,150 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

323 ADN-DUT-WIR-CIV-0292 00 Latest Inspection for Steel Cages of 5 Center Piles 126,128,130,148,150 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

324 ADN-DUT-WIR-CIV-0293 00 Latest Inspection for Casting of 5 Center Piles 126,128,130,148,150 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

325 ADN-DUT-WIR-CIV-0294 00 Latest Inspection for Setting out and Drilling of 3 Center Piles 193,211,341 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

326 ADN-DUT-WIR-CIV-0295 00 Latest Inspection for Steel Cages of 3 Center Piles 193,211,341 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

327 ADN-DUT-WIR-CIV-0296 00 Latest Inspection for Casting of 3 Center Piles 193,211,341 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

328 ADN-DUT-WIR-CIV-0297 00 Latest Inspection for Setting out of 5 H-Beams 265,91,93,94,96 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

329 ADN-DUT-WIR-CIV-0298 00 Latest Inspection for Installation of Casing and Drilling Depth of 5 H-Beams 265,91,93,94,96 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

330 ADN-DUT-WIR-CIV-0299 00 Latest Inspection for Installation of H-Beam prior to cast Concrete of 5 H-Beams 265,91,93,94,96 CVL DUTCH 19-Jun-22 20-Jun-22 B B 1

331 ADN-DUT-WIR-CIV-0300 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 188,191,197,203,207,213 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

332 ADN-DUT-WIR-CIV-0301 00 Latest Inspection for Steel Cages of 6 Center Piles 188,191,197,203,207,213 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

333 ADN-DUT-WIR-CIV-0302 00 Latest Inspection for Casting of 6 Center Piles 188,191,197,203,207,213 CVL DUTCH 19-Jun-22 23-Jun-22 B B 4

334 ADN-DUT-WIR-CIV-0303 00 Latest Inspection for Setting out and Drilling of 6 Center Piles 153,208,214,220,226,229 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

335 ADN-DUT-WIR-CIV-0304 00 Latest Inspection for Steel Cages of 6 Center Piles 153,208,214,220,226,229 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

336 ADN-DUT-WIR-CIV-0305 00 Latest Inspection for Casting of 6 Center Piles 153,208,214,220,226,229 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

337 ADN-DUT-WIR-CIV-0306 00 Latest Inspection for Setting out of 5 H-Beams 148,146,268,142 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

338 ADN-DUT-WIR-CIV-0307 00 Latest Inspection for Installation of Casing and Drilling Depth of 5 H-Beams 148,146,144,268,142 CVL DUTCH 19-Jun-22 22-Jun-22 B B 3

339 ADN-DUT-WIR-CIV-0308 00 Latest Inspection for Installation of H-Beam prior to Cast Concrete of 5 H-Beams 148,146,144,268,142 CVL DUTCH 19-Jun-22 23-Jun-22 B B 4

340 ADN-DUT-WIR-CIV-0309 00 Latest Inspection for Setting out and Drilling of 7 Center Pile 187,190,194,197,200,126,147 CVL DUTCH 20-Jun-22 23-Jun-22 B B 3

341 ADN-DUT-WIR-CIV-0310 00 Latest Inspection for Steel Cages of 7 Center Piles 187,190,194,197,200,126,147 CVL DUTCH 20-Jun-22 23-Jun-22 B B 3

342 ADN-DUT-WIR-CIV-0311 00 Latest Inspection for Casting of 7 Center Piles 187,190,194,197,200,126,147 CVL DUTCH 20-Jun-22 23-Jun-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
343 ADN-DUT-WIR-CIV-0312 00 Latest Inspection for Setting out 5 H-Beam 153,155,157,159,161 CVL DUTCH 20-Jun-22 23-Jun-22 B B 3

344 ADN-DUT-WIR-CIV-0313 00 Latest Inspection for Installation of Casing and Drilling Depth of 5 H-Beam 153,155,157,159,161 CVL DUTCH 20-Jun-22 23-Jun-22 C C 3

345 ADN-DUT-WIR-CIV-0314 00 Latest Inspection for Installation of H-Beam Prior to Cast Concrete of 5 H-Beam 153,155,157,159,161 CVL DUTCH 20-Jun-22 23-Jun-22 C C 3

346 ADN-DUT-WIR-CIV-0315 00 Latest Inspection for Setting out and Drilling of 11 Center Piles 283,319,182,184,395,399,401,297,01,66,68 CVL DUTCH 20-Jun-22 27-Jun-22 B B 7

347 ADN-DUT-WIR-CIV-0316 00 Latest Inspection for Steel Cages of 11 Center Piles 283,319,182,184,395,399,401,297,01,66,68 CVL DUTCH 20-Jun-22 27-Jun-22 B B 7

348 ADN-DUT-WIR-CIV-0317 00 Latest Inspection for Casting of 11 Center Piles 283,319,182,184,395,399,401,297,01,66,68 CVL DUTCH 20-Jun-22 27-Jun-22 B B 7

349 ADN-DUT-WIR-CIV-0318 00 Latest Inspection for Setting out and Drilling of 11 Center Piles 10,15,17,19,21,23,157,258,262,290,317 CVL DUTCH 20-Jun-22 27-Jun-22 B B 7

350 ADN-DUT-WIR-CIV-0319 00 Latest Inspection for Steel Cages of 11 Center Piles 10,15,17,19,21,23,157,258,262,290,317 CVL DUTCH 20-Jun-22 27-Jun-22 B B 7

351 ADN-DUT-WIR-CIV-0320 00 Latest Inspection for Casting of 11 Center Piles 10,15,17,19,21,23,157,258,262,290,317 CVL DUTCH 20-Jun-22 27-Jun-22 B B 7

352 ADN-DUT-WIR-CIV-0321 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 125,152,215,212,202 CVL DUTCH 21-Jun-22 23-Jun-22 B B 2

353 ADN-DUT-WIR-CIV-0322 00 Latest Inspection for Steel Cages of 5 Center Piles 125,152,215,212,202 CVL DUTCH 21-Jun-22 23-Jun-22 B B 2

354 ADN-DUT-WIR-CIV-0323 00 Latest Inspection for Casting of 5 Center Piles 125,152,215,212,202 CVL DUTCH 21-Jun-22 23-Jun-22 B B 2

355 ADN-DUT-WIR-CIV-0324 00 Latest Inspection for Setting out and Drilling of 3 Center Piles 127,129,149 CVL DUTCH 21-Jun-22 23-Jun-22 B B 2

356 ADN-DUT-WIR-CIV-0325 00 Latest Inspection for Steel Cages of 3 Center Piles 127,129,149 CVL DUTCH 21-Jun-22 23-Jun-22 B B 2

357 ADN-DUT-WIR-CIV-0326 00 Latest Inspection for Casting of Center Piles 127,129,149 CVL DUTCH 21-Jun-22 23-Jun-22 B B 2

358 ADN-DUT-WIR-CIV-0327 00 Latest Inspection for Setting out and Drilling of 5 Center Piles 195, 199,201,205,209 CVL DUTCH 22-Jun-22 26-Jun-22 B B 4

359 ADN-DUT-WIR-CIV-0328 00 Latest Inspection for Steel Cages of 6 Center Piles 195,199,201,205,209 CVL DUTCH 22-Jun-22 26-Jun-22 B B 4

360 ADN-DUT-WIR-CIV-0329 00 Latest Inspection for Casting of 5 Center Piles 195,199,201,205,209 CVL DUTCH 22-Jun-22 26-Jun-22 B B 4

361 ADN-DUT-WIR-CIV-0330 00 Latest Inspection for Setting out and Drilling of 4 Center Piles 192,196,198,200 CVL DUTCH 22-Jun-22 23-Jun-22 B B 1

362 ADN-DUT-WIR-CIV-0331 00 Latest Inspection for Steel Cages of 4 Center Piles 192,196,198,200 CVL DUTCH 22-Jun-22 23-Jun-22 B B 1

363 ADN-DUT-WIR-CIV-0332 00 Latest Inspection for Casting of 4 Center Piles 192,196,198,200 CVL DUTCH 22-Jun-22 23-Jun-22 B B 1

364 ADN-DUT-WIR-CIV-0333 00 Latest Inspection for Setting out of 12 H-Beams 126,127,128,129,130,131,132,133,134,135,136,137 CVL DUTCH 22-Jun-22 26-Jun-22 B B 4

365 ADN-DUT-WIR-CIV-0334 00 Latest Inspection for Installation of Casing and Drilling of Depth of 12 H-Beams 126,127,128,129,130,131,132,133,134,135,136,137 CVL DUTCH 22-Jun-22 26-Jun-22 B B 4

366 ADN-DUT-WIR-CIV-0335 00 Latest Inspection for Installation of H-Beams prior to cast concrete of 12 H-Beams 126,127,128,129,130,131,132,133,134,135,136,137 CVL DUTCH 22-Jun-22 26-Jun-22 B B 4

367 ADN-DUT-WIR-CIV-0336 00 Latest Inspection for Setting out and Drilling of 7 Center Piles 204,206,210,159,160,260,216 CVL DUTCH 23-Jun-22 27-Jun-22 B B 4

368 ADN-DUT-WIR-CIV-0337 00 Latest Inspection for Steel Cages of 7 Center Piles 204,206,210,159,160,260,216 CVL DUTCH 23-Jun-22 27-Jun-22 B B 4

369 ADN-DUT-WIR-CIV-0338 00 Latest Inspection for Casting of 7 Center Piles 204,206,210,159,160,260,216 CVL DUTCH 23-Jun-22 27-Jun-22 B B 4
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
370 ADN-DUT-WIR-CIV-0339 00 Latest Inspection for Setting out of 7 H-Beams 120,121,122,123,124,125,126 CVL DUTCH 23-Jun-22 27-Jun-22 B B 4

371 ADN-DUT-WIR-CIV-0340 00 Latest Inspection for Installation of Casing and Drilling Depth of 7 H-Beams 120,121,122,123,124,125,126 CVL DUTCH 23-Jun-22 27-Jun-22 B B 4

372 ADN-DUT-WIR-CIV-0341 00 Latest Inspection for Installation of H-Beam prior to cast concrete of 7 H-Beams 120,121,122,123,124,125,126 CVL DUTCH 23-Jun-22 27-Jun-22 B B 4

373 ADN-DUT-WIR-CIV-0342 00 Latest Inspection for Setting out of 8 H-Beams 117,116,115,114,267,265,113,112 CVL DUTCH 26-Jun-22 29-Jun-22 B B 3

374 ADN-DUT-WIR-CIV-0343 00 Latest Inspection for Installation of Casing and Drilling Depth of 8 H-Beams 117,116,115,114,267,265,113,112 CVL DUTCH 26-Jun-22 29-Jun-22 B B 3

375 ADN-DUT-WIR-CIV-0344 00 Latest Inspection for Installation of H-Beam prior to Cast Concrete of 8 H-Beams 117,116,115,114,267,265,113,112 CVL DUTCH 26-Jun-22 29-Jun-22 B B 3

376 ADN-DUT-WIR-CIV-0345 00 Latest Inspection for Setting out of 7 H-Beams 194,195,196,197,198,199,200 CVL DUTCH 26-Jun-22 28-Jun-22 C C 2

377 ADN-DUT-WIR-CIV-0346 00 Latest Inspection for Installation of Casing and Drilling Depth of 7 H-Beams 194,195,196,197,198,199,200 CVL DUTCH 26-Jun-22 28-Jun-22 C C 2

378 ADN-DUT-WIR-CIV-0347 00 Latest Inspection for Installation of H-Beams prior to cast concrete of 7 H-Beams 194,195,196,197,198,199,200 CVL DUTCH 26-Jun-22 28-Jun-22 C C 2

379 ADN-DUT-WIR-CIV-0348 00 Latest Inspection for Setting out of 8 H-Beams 266,188,189,190,191,192,260,261 CVL DUTCH 26-Jun-22 28-Jun-22 B B 2

380 ADN-DUT-WIR-CIV-0349 00 Latest Inspection for Installation of Casing and Drilling Depth of 8 H-Beams 266,188,189,190,191,192,260,261 CVL DUTCH 26-Jun-22 28-Jun-22 B B 2

381 ADN-DUT-WIR-CIV-0350 00 Latest Inspection for Installation of H-Beams prior to cast Concrete of 8 H-Beams 266,188,189,190,191,192,260,261 CVL DUTCH 26-Jun-22 28-Jun-22 B B 2

382 ADN-DUT-WIR-CIV-0351 00 Latest Inspection for Setting out of 14 H-Beams 111,110,108,143,149,153,151,147,187,186,185,184,183,182 CVL DUTCH 29-Jun-22 1-Jul-22 B B 2

Inspection for Installation of Casing and Drilling Depth of 14 H-Beams


383 ADN-DUT-WIR-CIV-0352 00 Latest
111,110,108,143,149,153,151,147,187,186,185,184,183,182
CVL DUTCH 29-Jun-22 1-Jul-22 B B 2

Inspection for Installation of H-Beams prior to cast concrete of 14 H-Beams


384 ADN-DUT-WIR-CIV-0353 00 Latest
111,110,108,143,149,153,151,147,187,186,185,184,183,182
CVL DUTCH 29-Jun-22 1-Jul-22 B B 2

385 ADN-DUT-WIR-CIV-0354 00 Latest Inspection for Setting out and Drilling of 4 Tower Crane Piles TC1-1, TC1-4, TC2-1, TC2-4 CVL DUTCH 29-Jun-22 1-Jul-22 C C 2

386 ADN-DUT-WIR-CIV-0355 00 Latest Inspection for Steel Cages of 4 Tower Crane Piles TC1-1, TC1-4, TC2-1, TC2-4 CVL DUTCH 29-Jun-22 1-Jul-22 C C 2

387 ADN-DUT-WIR-CIV-0356 00 Latest Inspection for Casting of 4 Tower Crane Piles TC1-1, TC1-4, TC2-1, TC2-4 CVL DUTCH 29-Jun-22 1-Jul-22 C C 2

388 ADN-DUT-WIR-CIV-0357 00 Superseded Inspection for Witness on Performing 7 Dynamic Test Piles 427,397,393,178,169,50,36 CVL DUTCH 29-Jun-22 3-Jul-22 C C 4

389 ADN-DUT-WIR-CIV-0357 01 Latest Inspection for Witness on Performing 4 Dynamic Test Piles 178,255,169,50 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

390 ADN-DUT-WIR-CIV-0358 00 Latest Inspection for Setting out of 5 H-Beams 145,141,140,139,138 CVL DUTCH 29-Jun-22 3-Jul-22 B B 4

391 ADN-DUT-WIR-CIV-0359 00 Latest Inspection for Installation of Casing and Drilling Depth of 5 H-Beams 145,141,140,139,138 CVL DUTCH 29-Jun-22 3-Jul-22 B B 4

392 ADN-DUT-WIR-CIV-0360 00 Latest Inspection for Installation of H-Beams prior to cast concrete of 5 H-Beams 145,141,140,139,138 CVL DUTCH 29-Jun-22 3-Jul-22 B B 4

393 ADN-DUT-WIR-CIV-0361 00 Latest Inspection for Setting-out of 13 H-Beams 193,194,195,198,197,196,181,180,179,178,177,176,175, CVL DUTCH 28-Jun-22 3-Jun-22 B B -25

394 ADN-DUT-WIR-CIV-0362 00 Latest Inspection for Installation of Casing and Drilling Depth of 13 H-Beams 193,194,195,198,197,196,181,180,179,178,177,176,175, CVL DUTCH 30-Jun-22 3-Jun-22 B B -27

Inspection for Installation of H-Beams prior to cast concrete of 13 H-Beams


395 ADN-DUT-WIR-CIV-0363 00 Latest
193,194,195,198,197,196,181,180,179,178,177,176,175,
CVL DUTCH 30-Jun-22 3-Jul-22 B B 3

396 ADN-DUT-WIR-CIV-0364 00 Latest Inspection for Setting out of 6 H-Beams 199,200,201,202,203,204 CVL DUTCH 3-Jul-22 4-Jul-22 B B 1
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
397 ADN-DUT-WIR-CIV-0365 00 Latest Inspection for Installation of Casing and Drilling Depth of 6 H-Beams 199,200,201,202,203,204 CVL DUTCH 3-Jul-22 4-Jul-22 B B 1

398 ADN-DUT-WIR-CIV-0366 00 Latest Inspection for Installation of H-Beams prior to Cast Concrete of 6 H-Beams 199,200,201,202,203,204 CVL DUTCH 3-Jul-22 4-Jul-22 B B 1

399 ADN-DUT-WIR-CIV-0367 00 Latest Inspection for Setting out and Drilling of 4 Tower Crane Piles TC3-1, TC3-4, TC3-1, TC3-4 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

400 ADN-DUT-WIR-CIV-0368 00 Latest Inspection for Steel Cages of 4 Tower Canes Piles TC3-1, TC3-4, TC3-1, TC3-4 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

401 ADN-DUT-WIR-CIV-0369 00 Latest Inspection for Casting of 4 Tower Crane Piles TC3-1, TC3-4, TC3-1, TC3-4 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

402 ADN-DUT-WIR-CIV-0370 00 Latest Inspection for Setting out 12 H-Beams 205,206,207,208,209,210,170,171,172,173,174,175 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

403 ADN-DUT-WIR-CIV-0371 00 Latest Inspection for Installation of Casing and Drilling Depth of 12 H-Beams 205,206,207,208,209,210,170,171,172,173,174,175 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

404 ADN-DUT-WIR-CIV-0372 00 Latest Inspection for installation of H-Beams prior to Cast Concrete of 12 H-Beams 205,206,207,208,209,210,170,171,172,173,174,175 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

405 ADN-DUT-WIR-CIV-0373 00 Latest Inspection for Setting out of 14 H-Beams 211,212,213,214,215,216,217,165,166,167,168,258,259 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

406 ADN-DUT-WIR-CIV-0374 00 Latest Inspection for Installation of Casing and Drilling oDepth of 14 H-beams 211,212,213,214,215,216,217,165,166,167,168,258,259 CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

Inspection for Installation of H-Beams prior to cast concrete of 14 H-Beams


407 ADN-DUT-WIR-CIV-0375 00 Latest
211,212,213,214,215,216,217,165,166,167,168,258,259
CVL DUTCH 4-Jul-22 6-Jul-22 B B 2

408 ADN-DUT-WIR-CIV-0376 00 Latest Inspection for Setting out and Drilling of 1 PTP Test Pile (PTP-1) CVL DUTCH 5-Jul-22 12-Jul-22 A A 7

409 ADN-DUT-WIR-CIV-0377 00 Latest Inspection for Steel Cages of 1 PTP Test Pile (PTP-1) CVL DUTCH 5-Jul-22 12-Jul-22 B B 7

410 ADN-DUT-WIR-CIV-0378 00 Latest Inspection for Casting of 1 PTP Test Pile (PTP-1) CVL DUTCH 5-Jul-22 13-Jul-22 B B 8

411 ADN-DUT-WIR-CIV-0379 00 Latest Inspection for Setting out of 10 H-Beams 218,219,220,221,223,262,263,167,169,166 CVL DUTCH 7-Jul-22 12-Jul-22 B B 5

412 ADN-DUT-WIR-CIV-0380 00 Latest Inspection for Installation of Casing and Drilling of Depth of 10 H-Beams 218,219,220,221,223,262,263,167,169,166 CVL DUTCH 7-Jul-22 12-Jul-22 A A 5

413 ADN-DUT-WIR-CIV-0381 00 Latest Inspection for Installation of H-Beams prior to cast concrete of 10 H-Beams 218,219,220,221,223,262,263,167,169,166 CVL DUTCH 7-Jul-22 12-Jul-22 B B 5

414 ADN-DUT-WIR-CIV-0382 00 Latest Inspection for Setting out of 6 H-Beams 258,259,224,225,226,227 CVL DUTCH 12-Jul-22 13-Jul-22 B B 1

415 ADN-DUT-WIR-CIV-0383 00 Latest Inspection for Installation of Casing and Drilling Depth of 6 H-Beams 258,259,224,225,226,227 CVL DUTCH 12-Jul-22 13-Jul-22 B B 1

416 ADN-DUT-WIR-CIV-0384 00 Latest Inspection for Installation of H-Beam prior to Cast Concrete of 6 H-Beams 258,259,224,225,226,227 CVL DUTCH 12-Jul-22 13-Jul-22 B B 1

417 ADN-DUT-WIR-CIV-0385 00 Latest Inspection for Setting out of 10 H-Beams 228,229,230,231,232,233,234,235,236,237 CVL DUTCH 12-Jul-22 13-Jul-22 B B 1

418 ADN-DUT-WIR-CIV-0386 00 Latest Inspection for Installation of Casing and Drilling Depth of 10 H-Beams 228,229,230,231,232,233,234,235,236,237 CVL DUTCH 12-Jul-22 13-Jul-22 B B 1

419 ADN-DUT-WIR-CIV-0387 00 Latest Inspection for Installation of H-Beams prior to Cast Concrete of 10 H-Beams 228,229,230,231,232,233,234,235,236,237 CVL DUTCH 12-Jul-22 13-Jul-22 B B 1

420 ADN-DUT-WIR-CIV-0388 00 Latest Inspection for Setting out 10 Permanent H-Beams 238,239,240,241,242,243,244,245,246,247 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

421 ADN-DUT-WIR-CIV-0389 00 Latest Inspection for Installation of Casing and Drilling Depth of 10 Permanent H-Beams 238,239,240,241,242,243,244,245,246,247 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

422 ADN-DUT-WIR-CIV-0390 00 Latest Inspection for Installation of H-Beam prior ro cast concrete 10 Permanent H-Beams 238,239,240,241,242,243,244,245,246,247 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

423 ADN-DUT-WIR-CIV-0391 00 Latest Inspection for Setting out of 12 H-Beams 163,164,248,249,250,251,252,253,254,255,256,257 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
424 ADN-DUT-WIR-CIV-0392 00 Latest Inspection for Installation of Casing and Drilling Depth of 12 H-Beams 163,164,248,249,250,251,252,253,254,255,256,257 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

425 ADN-DUT-WIR-CIV-0393 00 Latest Inspection for Installation of 12 H-Beams 163,164,248,249,250,251,252,253,254,255,256,257 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

426 ADN-DUT-WIR-CIV-0394 00 Latest Inspection for Setting out and Drilling of Static Test Pile 253 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

427 ADN-DUT-WIR-CIV-0395 00 Latest Inspection for Steel Cages of 1 Test Pile 253 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

428 ADN-DUT-WIR-CIV-0396 00 Latest Inspection for Casting of test Pile 253 CVL DUTCH 17-Jul-22 19-Jul-22 B B 2

429 ADN-DUT-WIR-CIV-0397 00 Superseded Inspection for Installation and Welding for Strut Pipe S01 & S02 CVL DUTCH 17-Jul-22 19-Jul-22 C C 2

430 ADN-DUT-WIR-CIV-0397 01 Superseded Inspection for Installation and Welding for Strut Pipe S01 CVL DUTCH 4-Aug-22 7-Aug-22 C C 3

431 ADN-DUT-WIR-CIV-0397 02 Latest Inspection for Installation and Welding for Strut Pipe S01 CVL DUTCH 8-Sep-22 11-Sep-22 B B 3

432 ADN-DUT-WIR-CIV-0398 00 Latest Inspection for Witness on Performing 7 Dynamic 2 test Pile 38,135,143,161,167,245,386 CVL DUTCH 19-Jul-22 21-Jul-22 B B 2

433 ADN-DUT-WIR-CIV-0399 00 Latest Inspection for Setting out 4 H-Beams 222,161,159,165 CVL DUTCH 19-Jul-22 21-Jul-22 B B 2

434 ADN-DUT-WIR-CIV-0400 00 Latest Inspection for Installation of Casing and Drilling Depth of 4 H-Beams 222,161,159,165 CVL DUTCH 19-Jul-22 21-Jul-22 B B 2

435 ADN-DUT-WIR-CIV-0401 00 Latest Inspection for Installation of H-Beam Prior to Cast Concrete of 4 H-Beam 22,161,159,165 CVL DUTCH 19-Jul-22 21-Jul-22 B B 2

436 ADN-DUT-WIR-CIV-0402 00 Superseded Inspection for Witness on Performing Magnetic particle Test for the Strut Pipes (S01) CVL DUTCH 19-Jul-22 21-Jul-22 C C 2

437 ADN-DUT-WIR-CIV-0402 01 Latest Inspection for Witnessing on Performing Magnetic particle Inspection for Strut Pipe (S01) CVL DUTCH 4-Aug-22 7-Aug-22 B B 3

438 ADN-DUT-WIR-CIV-0403 00 Latest Inspection for Witness on Performing Integrity Test (pile No. 427) CVL DUTCH 19-Jul-22 21-Jul-22 B B 2

439 ADN-DUT-WIR-CIV-0404 00 Latest Inspection for Setting -out 3 H-Beams 153,143,157 CVL DUTCH 20-Jul-22 21-Jul-22 B B 1

440 ADN-DUT-WIR-CIV-0405 00 Latest Inspection for Installation of Casing and Drilling Depth of 3 H-Beams 153,143,157 CVL DUTCH 20-Jul-22 21-Jul-22 B B 1

441 ADN-DUT-WIR-CIV-0406 00 Latest Inspection for Installation of H-Beams prior to Cast Concrete of 3 H-Beams 153,143,157 CVL DUTCH 20-Jul-22 21-Jul-22 B B 1

442 ADN-DUT-WIR-CIV-0407 00 Latest Inspection for Witness on Performing 4 Dynamic Test Piles 153,229,216,198 CVL DUTCH 21-Jul-22 22-Jul-22 B B 1

443 ADN-DUT-WIR-CIV-0408 00 Latest Inspection for Setting-out and Drilling of 4 Tower Crane Piles (TC2-1, TC2-2, TC2-3, TC2-4) CVL DUTCH 21-Jul-22 22-Jul-22 B B 1

444 ADN-DUT-WIR-CIV-0409 00 Latest Inspection for Steel Cages of 4 Tower Crane Piles (TC2-1, TC2-2, TC2-3, TC2-4) CVL DUTCH 21-Jul-22 22-Jul-22 B B 1

445 ADN-DUT-WIR-CIV-0410 00 Latest Inspection for Casting of 4 Tower Crane Piles (TC2-1, TC2-2, TC2-3, TC2-4) CVL DUTCH 21-Jul-22 22-Jul-22 B B 1

446 ADN-DUT-WIR-CIV-0411 00 Latest Inspection for Setting out and Drilling of 4 Tower Crane Piles (TC1-1, TC1-2, TC1-3, TC1-4) CVL DUTCH 22-Jul-22 25-Jul-22 B B 3

447 ADN-DUT-WIR-CIV-0412 00 Latest Inspection for steel Cages of 4 Tower Crane Piles (TC1-1, TC1-2, TC1-3, TC1-4) CVL DUTCH 22-Jul-22 25-Jul-22 B B 3

448 ADN-DUT-WIR-CIV-0413 00 Latest Inspection for Casting of 4 Tower Crane Piles (TC1-1, TC1-2, TC1-3, TC1-4) CVL DUTCH 22-Jul-22 25-Jul-22 B B 3

449 ADN-DUT-WIR-CIV-0414 00 Latest Inspection for Setting out and Drilling of 2 Tower Crane Piles (TC3-2, TC3-3) CVL DUTCH 22-Jul-22 25-Jul-22 B B 3

450 ADN-DUT-WIR-CIV-0415 00 Latest Inspection for Steel Cages of 2 Tower Crane Piles (TC3-2, TC3-3) CVL DUTCH 22-Jul-22 25-Jul-22 B B 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
451 ADN-DUT-WIR-CIV-0416 00 Latest Inspection for Casting of 2 Tower Crane Piles (TC3-2, TC3-3) CVL DUTCH 22-Jul-22 25-Jul-22 B B 3

452 ADN-DUT-WIR-CIV-0417 00 Latest Inspection for Setting out and Drilling of 1 Center Pile 152 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

453 ADN-DUT-WIR-CIV-0418 00 Latest Inspection for Steel Cages of 1 Center Pile 152 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

454 ADN-DUT-WIR-CIV-0419 00 Latest Inspection for Casting of 1 Center Piles 152 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

455 ADN-DUT-WIR-CIV-0420 00 Latest Inspection for Setting out of 2 H-Beams for King Post (S7-1, S7-2) CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

456 ADN-DUT-WIR-CIV-0421 00 Latest Inspection for Installation of Casting and Drilling of 2 H-Beams for King Post (S7-1, S7-2) CVL DUTCH 24-Jul-22 25-Jul-22 A A 1

457 ADN-DUT-WIR-CIV-0422 00 Latest Inspection for Installation of H-Beams prior to cast of 2 H-Beams for King Post (S7-1, S7-2) CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

458 ADN-DUT-WIR-CIV-0423 00 Latest Inspection for Setting out and Drilling of 4 Tower Crane Piles (TC4-1, TC-4-2, TC4-3, TC4-4) CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

459 ADN-DUT-WIR-CIV-0424 00 Latest Inspection for Steel Cages of 4 Tower Crane Piles (TC4-1, TC-4-2, TC4-3, TC4-4) CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

460 ADN-DUT-WIR-CIV-0425 00 Latest Inspection for Casting of 4 Tower Crane Piles (TC4-1, TC-4-2, TC4-3, TC4-4) CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

461 ADN-DUT-WIR-CIV-0426 00 Latest Inspection for Setting out of 2 H-Beams 121, 149 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

462 ADN-DUT-WIR-CIV-0427 00 Latest Inspection for Installation of Casing and Drilling Depth of 2 H-Beams 121, 149 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

463 ADN-DUT-WIR-CIV-0428 00 Latest Inspection for Installation of H-Beam Prior to Cast Concrete of 2 H-Beams 121, 149 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

464 ADN-DUT-WIR-CIV-0429 00 Latest Inspection for Setting out of 5 Additional H-Beams 40,41,42,43,44 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

465 ADN-DUT-WIR-CIV-0430 00 Latest Inspection for Installation of Casing and Drilling Depth of 5 Additional H-Beams 40,41,42,43,44 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

466 ADN-DUT-WIR-CIV-0431 00 Latest Inspection for Installation of H-Beams Prior to Cast Concrete of 5 Additional H-Beams 40,41,42,43,44 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

467 ADN-DUT-WIR-CIV-0432 00 Latest Inspection for for Witness on Performing 7 Dynamic Test Piles 16,24,27,129,134,393,397 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

468 ADN-DUT-WIR-CIV-0433 00 Latest Inspection for Witness on Performing 1 Dynamic Test Pile 427 CVL DUTCH 24-Jul-22 25-Jul-22 B B 1

469 ADN-DUT-WIR-CIV-0434 00 Latest Inspection for Setting out and Drilling of 1 Center Piles 260 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

470 ADN-DUT-WIR-CIV-0435 00 Latest Inspection for Steel Cages of 1 Center Pile 260 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

471 ADN-DUT-WIR-CIV-0436 00 Latest Inspection for Casting of 1 Center Piles 260 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

472 ADN-DUT-WIR-CIV-0437 00 Latest Inspection for Setting out of 4 H-Beams 159,161,165,222 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

473 ADN-DUT-WIR-CIV-0438 00 Latest Inspection for Installation of Casing and Drilling Depth of 4 H-Beams 159,161,165,222 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

474 ADN-DUT-WIR-CIV-0439 00 Latest Inspection for Installation of H-Beams prior to Cast Concrete of 4 H-Beams 159,161,165,222 CVL DUTCH 24-Jul-22 26-Jul-22 B B 2

475 ADN-DUT-WIR-CIV-0440 00 Latest Inspection for Setting out 9 Additional H-Beams 31,32,33,34,35,36,37,38,39 CVL DUTCH 25-Jul-22 27-Jul-22 B B 2

476 ADN-DUT-WIR-CIV-0441 00 Latest Inspection for Installation of Casing and Drilling Depth of 9 Additional H-Beams 31,32,33,34,35,36,37,38,39 CVL DUTCH 25-Jul-22 27-Jul-22 B B 2

477 ADN-DUT-WIR-CIV-0442 00 Latest Inspection for Installation of H-Beams prior to Cast Concrete of 9 Additional H-Beams 31,32,33,34,35,36,37,38,39 CVL DUTCH 25-Jul-22 27-Jul-22 B B 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
478 ADN-DUT-WIR-CIV-0443 00 Latest Inspection for Setting out and Drilling of 1 Center Pile 371 CVL DUTCH 25-Jul-22 27-Jul-22 B B 2

479 ADN-DUT-WIR-CIV-0444 00 Latest Inspection for Steel Cages of 1 Center Pile 371 CVL DUTCH 25-Jul-22 27-Jul-22 B B 2

480 ADN-DUT-WIR-CIV-0445 00 Latest Inspection for Casting of 1 Center Pile 371 CVL DUTCH 25-Jul-22 27-Jul-22 B B 2

481 ADN-DUT-WIR-CIV-0446 00 Latest Inspection for Setting out and Drilling of 1 Center Pile 105 CVL DUTCH 28-Jul-22 29-Jul-22 B B 1

482 ADN-DUT-WIR-CIV-0447 00 Latest Inspection for Steel Cages of 1 Center Pile 105 CVL DUTCH 28-Jul-22 29-Jul-22 B B 1

483 ADN-DUT-WIR-CIV-0448 00 Latest Inspection for Casting of 1 Center Pile 105 CVL DUTCH 28-Jul-22 29-Jul-22 B B 1

484 ADN-DUT-WIR-CIV-0449 00 Latest Inspection for Setting out of 10 Additional H-Beams 46,47,48,49,25,26,27,28,29,30 CVL DUTCH 28-Jul-22 29-Jul-22 B B 1

485 ADN-DUT-WIR-CIV-0450 00 Latest Inspection for Installation of Casing and Drilling Depth of 10 Additional H-Beams 46,47,48,49,25,26,27,28,29,30 CVL DUTCH 28-Jul-22 29-Jul-22 B B 1

486 ADN-DUT-WIR-CIV-0451 00 Latest Inspection for Installation of H-Beams prior to cast Concrete of 10 H-Beams 46,47,48,49,25,26,27,28,29,30 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

487 ADN-DUT-WIR-CIV-0452 00 Latest Inspection for Setting out and Drilling of 1 Center Pile 189 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

488 ADN-DUT-WIR-CIV-0453 00 Latest Inspection for Steel Cages of 1 Center Pile 189 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

489 ADN-DUT-WIR-CIV-0454 00 Latest Inspection for Casting of 1 Center Pile 189 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

490 ADN-DUT-WIR-CIV-0455 00 Latest Inspection for Witness on Performing Magnetic Particle Test for the Strut Pipes (S01, S03, S04, S05, S06) CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

491 ADN-DUT-WIR-CIV-0456 00 Latest Inspection for Setting out of 11 Additional H-Beams 01,02,03,04,05,06,21,22,23,24,45 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

492 ADN-DUT-WIR-CIV-0457 00 Latest Inspection for Installation fo Casing and Drilling Depth of 11 Additional H-Beams 01,02,03,04,05,06,21,22,23,24,45 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

493 ADN-DUT-WIR-CIV-0458 00 Latest Inspection for Installation of H-Beams prior to Cast Concrete of 11 Additional H-Beams 01,02,03,04,05,06,21,22,23,24,45 CVL DUTCH 28-Jul-22 1-Aug-22 B B 4

494 ADN-DUT-WIR-CIV-0459 00 Latest Inspection for Setting out 7 Additional H-Beams 07,08,09,10,11,12,13 CVL DUTCH 31-Jul-22 1-Aug-22 B B 1

495 ADN-DUT-WIR-CIV-0460 00 Latest Inspection for Installation of Casing and Drilling Depth of 7 Additional H-Beams 07,08,09,10,11,12,13 CVL DUTCH 31-Jul-22 1-Aug-22 B B 1

496 ADN-DUT-WIR-CIV-0461 00 Latest Inspection for Installation of H-Beam prior to Cast Concrete of 7 Additional H-Beams 07,08,09,10,11,12,13 CVL DUTCH 31-Jul-22 1-Aug-22 B B 1

497 ADN-DUT-WIR-CIV-0462 00 Latest Inspection for Inspection for Static Load Test of Preliminary Test Pile (PTP) CVL DUTCH 1-Aug-22 4-Aug-22 B B 3

498 ADN-DUT-WIR-CIV-0463 00 Latest Inspection for Setting-out and Drilling of 7 Additional H-Beams 14,15,16,17,18,19,20 CVL DUTCH 2-Aug-22 4-Aug-22 B B 2

499 ADN-DUT-WIR-CIV-0464 00 Latest Inspection for Steel Cages of 7 Additional H-Beams 14,15,16,17,18,19,20 CVL DUTCH 2-Aug-22 4-Aug-22 B B 2

500 ADN-DUT-WIR-CIV-0465 00 Latest Inspection for Casting of 7 Additional H-Beams 14,15,16,17,18,19,20 CVL DUTCH 2-Aug-22 4-Aug-22 B B 2

501 ADN-DUT-WIR-CIV-0466 00 Latest Inspection for Setting-out and Drilling of 2 King Posts S12-1, S12-2 CVL DUTCH 2-Aug-22 4-Aug-22 B B 2

502 ADN-DUT-WIR-CIV-0467 00 Latest Inspection for Steel Cages of 2 King Posts S12-1, S12-2 CVL DUTCH 2-Aug-22 4-Aug-22 B B 2

503 ADN-DUT-WIR-CIV-0468 00 Latest Inspection for Casting of 2 King Posts S12-1, S12-2 CVL DUTCH 2-Aug-22 4-Aug-22 B B 2

504 ADN-DUT-WIR-CIV-0469 00 Superseded Inspection for Installation of 7 Struts S01,S03,S04,S05,S06,S07,S15,S18 CVL DUTCH 4-Aug-22 7-Aug-22 C C 3
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
505 ADN-DUT-WIR-CIV-0469 01 Latest Inspection for Installation of 7 Struts S02,S03,S04,S05,S06,S07,S15,S18 CVL DUTCH 8-Sep-22 11-Sep-22 B B 3

506 ADN-DUT-WIR-CIV-0470 00 Latest Inspection for Setting out and Drilling of 10 King Posts S20-1, S20-2, S8-1, S8-2, S9-1, S9-2, S10-1, S10-2, S11-1, S11-2 CVL DUTCH 4-Aug-22 7-Aug-22 B B 3

507 ADN-DUT-WIR-CIV-0471 00 Latest Inspection for Installation of H-Beams of 10 King Posts S20-1, S20-2, S8-1, S8-2, S9-1, S9-2, S10-1, S10-2, S11-1, S11-2 CVL DUTCH 4-Aug-22 7-Aug-22 B B 3

508 ADN-DUT-WIR-CIV-0472 00 Latest Inspection for Casting of 10 King Posts S20-1, S20-2, S8-1, S8-2, S9-1, S9-2, S10-1, S10-2, S11-1, S11-2 CVL DUTCH 4-Aug-22 7-Aug-22 B B 3

509 ADN-DUT-WIR-CIV-0473 00 Latest Inspection for Winessing of Static Load Test Pile P253 CVL DUTCH 4-Aug-22 7-Aug-22 B B 3

510 ADN-DUT-WIR-CIV-0474 00 Latest Inspection for Witnessing of magnetic particle Inspection Weliding of Strut Pipe S07 CVL DUTCH 4-Aug-22 7-Aug-22 B B 3

511 ADN-DUT-WIR-CIV-0475 00 Latest Inspection for Witnessing of Static Load Test Pile 371 CVL DUTCH 8-Aug-22 11-Aug-22 B B 3

512 ADN-DUT-WIR-CIV-0476 00 Superseded Inspection for Installation and Welding of Strut Pipe No. S08 CVL DUTCH 8-Aug-22 11-Aug-22 C C 3

513 ADN-DUT-WIR-CIV-0476 01 Latest Inspection for Installation and Welding of Strut Pipe No. S08 CVL DUTCH 8-Sep-22 11-Sep-22 B B 3

514 ADN-DUT-WIR-CIV-0477 00 Latest Inspection for Witnessing of Magnetic Particle Inspection for Welding of Strut Pipe S08, S15, S18 CVL DUTCH 8-Aug-22 12-Aug-22 C C 4

515 ADN-DUT-WIR-CIV-0478 00 Latest Inspection for Witnessing of Static Load Test Pile P152 CVL DUTCH 10-Aug-22 14-Aug-22 B B 4

516 ADN-DUT-WIR-CIV-0479 00 Latest Inspection for Witnessing of Magnetic Particle Inspection for Welding of Strut Pipe S09, S19, S13 CVL DUTCH 11-Aug-22 16-Aug-22 B B 5

517 ADN-DUT-WIR-CIV-0480 00 Latest Inspection for Witnessing of magnetic Particle Inspection for Welding of Strut Pipe No. S10, S16, S14, S17 CVL DUTCH 12-Aug-22 16-Aug-22 B B 4

518 ADN-DUT-WIR-CIV-0481 00 Latest Inspection for Witnessing of Static Load Test Pile P105 CVL DUTCH 14-Aug-22 17-Aug-22 B B 3

519 ADN-DUT-WIR-CIV-0482 00 Latest Inspection for Witnessing of Static Load Test Pile P189 CVL DUTCH 16-Aug-22 19-Aug-22 B B 3

520 ADN-DUT-WIR-CIV-0483 00 Latest Inspection for Grouting of Static Test Piles 371,152,253,105,189 CVL DUTCH 17-Aug-22 19-Aug-22 B B 2

521 ADN-DUT-WIR-CIV-0484 00 Superseded Inspection for Witnessing of Magnetic Particle Inspection for Welding of Strut Pipe No. S20 CVL DUTCH 17-Aug-22 21-Aug-22 C C 4

522 ADN-DUT-WIR-CIV-0484 01 Latest Inspection for Witnessing of Magnetic Particle Inspection for Welding of Strut Pipe No. S20, S12, S11 CVL DUTCH 22-Aug-22 23-Aug-22 B B 1

523 ADN-DUT-WIR-CIV-0485 00 Latest Inspection for Witnessing Integrity Test (P-340) CVL DUTCH 18-Aug-22 21-Aug-22 B B 3

524 ADN-DUT-WIR-CIV-0486 00 Latest Inspection for Grouting of Static Test Pile 371 CVL DUTCH 19-Aug-22 23-Aug-22 B B 4

525 ADN-DUT-WIR-CIV-0487 00 Latest Inspection for Witness on Performing 1 Dynamic Test Pile 427 CVL DUTCH 5-Sep-22 6-Sep-22 B B 1

526 ADN-DUT-WIR-CIV-0488 00 Latest Inspection for Witnessing Integrity Test of Working Piles (44 Piles) CVL DUTCH 5-Sep-22 6-Sep-22 B B 1

524 ADN-DUT-WIR-CIV-0489 00 Latest Inspection for Witnessing Pile Integrity Profile Test of Working Pile (pile No. 340) by Transient Response method CVL DUTCH 13-Sep-22 18-Sep-22 B B 5

525 ADN-DUT-WIR-CIV-0490 00 Latest Inspection for Witnessing Integrity Test of Working Piles (35 Piles) & Tower Crane Piles (08 Piles) CVL DUTCH 18-Sep-22 20-Sep-22 B B 2

526 ADN-DUT-WIR-CIV-0491 00 Latest Inspection for Witnessing Integrity Test Working Piles (71 Piles) & Tower Crane Piles (4 Piles) CVL DUTCH 26-Sep-22 27-Sep-22 B B 1

527 ADN-DUT-WIR-CIV-0492 00 Latest Inspection for Witnessing Integrity Test of Working Piles CVL DUTCH 3-Oct-22 5-Oct-22 B B 2

528 ADN-DUT-WIR-CIV-0493 00 Superseded Inspection for Witnessing the Pile Repairing Works and Application of Fosroc Supercast PC (pile No. 329 & 332) CVL DUTCH 9-Oct-22 11-Oct-22 C C 2
AF190 - ADNEC-Residences Plot 11 & 12

TOTAL RIA's = 543 Work Inspection Request Register - Civil Subcontractor's


Valid Status Qty Action Code QTY

CURRENT STATUS
Latest 505 A = Approved 13

DAYS ELAPSED
VALID STATUS

ORIGINATOR
Superseded 38 479

Discipline
B = Approved as noted
Sr.No

REV.
SUBMITTAL NO. Cancelled 0 C = Revise and Resubmit 51 REMARKS
Closed 0 UR = Under Review 0
D = D-Rejected 0
DESCRIPTION SUBMITTED
Date
RETURNED By
Engineer
ACTION
CODE
529 ADN-DUT-WIR-CIV-0493 01 Latest Inspection for Witnessing the Pile Repairing Works and Application of Fosroc Supercast PC (pile No. 329 & 332) CVL DUTCH 31-Oct-22 2-Nov-22 B B 2

530 ADN-DUT-WIR-CIV-0494 00 Latest Inspection for Witnessing Integrity Test of Working Piles CVL DUTCH 13-Oct-22 14-Oct-22 B B 1

531 ADN-DUT-WIR-CIV-0495 00 Latest Inspection for Witnessing Integrity Test of Working Piles CVL DUTCH 24-Oct-22 26-Oct-22 B B 2

Inspection for Witnessing the Pile Repairing Works


532 ADN-DUT-WIR-CIV-0496 00 Latest Pile 53, 93, 340 - Concrete Cast up to Cut-Off level CVL DUTCH 31-Oct-22 2-Nov-22 B B 2
Pile 72, 82 - Repairing by Fosroc Supercast PC

533 ADN-DUT-WIR-CIV-0497 00 Latest Inspection for Witnessing Pile Integrity Test for Working Piles CVL DUTCH 1-Nov-22 4-Nov-22 B B 3

534 ADN-DUT-WIR-CIV-0498 00 Latest Inspection for Witnessing Pile Integrity Test for Working Piles CVL DUTCH 8-Nov-22 10-Nov-22 B B 2

535 ADN-DUT-WIR-CIV-0499 00 Latest Inspection for Witnessing the Pile 189 Repairing Works for Application of Fosroc Supercast PC CVL DUTCH 8-Nov-22 10-Nov-22 B B 2

536 ADN-DUT-WIR-CIV-0500 00 Latest Inspection for Completion of Pile 105 Rectification and Repairing Works CVL DUTCH 8-Nov-22 10-Nov-22 B B 2

537 ADN-DUT-WIR-CIV-0501 00 Latest Inspection for Witnessing the Pile-79 Repairing Works for and Application of Fosroc Supercast PC CVL DUTCH 11-Nov-22 14-Nov-22 B B 3

538 ADN-DUT-WIR-CIV-0502 00 Latest Inspection for Completion of Water Leakage Repairing Works at Shoring Walls Gridline K-L/13* CVL DUTCH 13-Nov-22 16-Nov-22 B B 3

539 ADN-DUT-WIR-CIV-0503 00 Latest Inspection for Witnessing Pile Integrity Test for Working Piles CVL DUTCH 22-Nov-22 23-Nov-22 B B 1

540 ADN-DUT-WIR-CIV-0504 00 Latest Inspection for Witnessing Pile Integrity Test for Working Piles CVL DUTCH 28-Nov-22 4-Dec-22 B B 6