PROJECT MANAGEMENT Lesson 12
PROJECT MANAGEMENT Lesson 12
MANAGEMENT
OM202
Project Management
LESSON 12 LESSON 13
NETWORK SCHEDULING TECHNIQUE PROJECT GRAPHICS
Management is continually seeking new and better control
techniques to cope with the complexities, masses of data,
and tight deadlines that are characteristic of highly
competitive industries. Managers also want better methods
for presenting technical and cost data to customers.
COMMON SCHEDULING TECHNIQUES
◦● Gantt or bar charts
◦● Milestone charts
◦● Line of balance
◦● Networks
◦ ● Program Evaluation and Review Technique (PERT)
◦ ● Arrow Diagram Method (ADM) [Sometimes called the Critical Path Method (CPM)]
◦ ● Precedence Diagram Method (PDM)
◦ ● Graphical Evaluation and Review Technique (GERT)
Advantages of Network Scheduling
◦ ● They form the basis for all planning and predicting and help management
decide how to use its resources to achieve time and cost goals.
◦ ● They provide visibility and enable management to control “one-of-a-kind”
programs.
◦ ● They help management evaluate alternatives by answering such questions as
how time delays will influence project completion, where slack exists between
elements, and what elements are crucial to meet the completion date.
◦ ● They provide a basis for obtaining facts for decision-making
Advantages of Network Scheduling
◦ ● They utilize a so-called time network analysis as the basic method to
determine manpower, material, and capital requirements, as well as to provide
a means for checking progress.
◦ ● They provide the basic structure for reporting information.
◦ ● They reveal interdependencies of activities.
◦ ● They facilitate “what if” exercises.
◦ ● They identify the longest path or critical paths.
◦ ● They aid in scheduling risk analysis.
Program Evaluation and Review
Technique (PERT) Pros and Cons
◦ PERT allows extensive planning.
◦ PERT allows one to determine the probability of meeting deadlines by development of alternative plan.
◦ PERT creates the ability to evaluate the effects of the changes in program.
◦ PERT allows large amount of sophisticated date to be presented in a well organized diagram from which
contractors and customers can make joint decisions.
Since there exists only one path through the network that is
the longest, the other paths must be either equal in length to
or shorter than that path. Therefore, there must exist events
and activities that can be completed before the time when
they are actually needed. The time differential between the
scheduled completion date and the required date to meet
critical path is referred to as the slack time.
The critical path is vital for resource scheduling and allocation because the
project manager, with coordination from the functional manager, can
reschedule those events not on the critical path for accomplishment during
other time periods when maximum utilization of resources can be
achieved, provided that the critical path time is not extended. This type of
rescheduling through the use of slack times provides for a better balance of
resources throughout the company, and may possibly reduce project costs
by eliminating idle or waiting time.
◦TE = the earliest time (date) on which an event can be
expected to take place
◦TL = the latest date on which an event can take place
without extending the completion date of the project
◦Slack time = TL - TE
PERT Network with Slack Time
The calculation for slack time is performed for each event in the network, as shown in the figure, by
identifying the earliest expected date and the latest starting date. For event 1, TL & TE =0. Event 1
serves as the reference point for the network and could just as easily have been defined as a calendar
date. As before, the critical path is represented as a bold line. The events on the critical path have no
slack (i.e., TL- TE) and provide the boundaries for the noncritical path events. Since event 2 is critical,
TL= TE =3 +7 =10 for event 5. Event 6 terminates the critical path with a completion time of fifteen
weeks. The earliest time for event 3, which is not on the critical path, would be two weeks (TE =0+2
=2), assuming that it started as early as possible. The latest allowable date is obtained by subtracting the
time required to complete the activity from events 3 to 5 from the latest starting date of event 5.
Therefore, TL (for event 3) =10- 5= 5 weeks. Event 3 can now occur anywhere between weeks 2 and 5
without interfering with the scheduled completion date of the project. This same procedure can be
applied to event 4, in which case TE =6 and TL =9.
Capabilities of PERT/CPM
◦● The earliest time when an activity can start (ES)
◦● The earliest time when an activity can finish (EF)
◦● The latest time when an activity can start (LS)
◦● The latest time when an activity can finish (LF)