0% found this document useful (0 votes)
56 views12 pages

LELACON Boiler Project Method Statement

The document outlines the civil work method statement for the Heineken Breweries S.C. Electrical Boiler Installation Project, detailing the project's purpose, scope, roles, responsibilities, and health and safety procedures. It specifies the construction processes including excavation, concrete placement, and masonry work, along with required materials, manpower, and equipment. The project is set to start on January 15, 2025, and emphasizes compliance with health, safety, and environmental standards throughout the construction phase.

Uploaded by

Yoseph Shiferaw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views12 pages

LELACON Boiler Project Method Statement

The document outlines the civil work method statement for the Heineken Breweries S.C. Electrical Boiler Installation Project, detailing the project's purpose, scope, roles, responsibilities, and health and safety procedures. It specifies the construction processes including excavation, concrete placement, and masonry work, along with required materials, manpower, and equipment. The project is set to start on January 15, 2025, and emphasizes compliance with health, safety, and environmental standards throughout the construction phase.

Uploaded by

Yoseph Shiferaw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 12

Heineken Breweries S.C.

Electrical Boiler Installation Project


Civil Work Method Statement

First Revision,
December 2024, Addis Ababa

1
1.

Table of Contents

PROJECT SUMMARY 2

1. PURPOSE 3

2. SCOPE 3

3. ROLES & RESPONSIBILITY 3


3.1. Project Manager--------------------------------------------------------------------------------3
3.2. Site Engineer:------------------------------------------------------------------------------------3
3.3. Safety Officer:-----------------------------------------------------------------------------------4
3.4. Supervisor/Foreman:--------------------------------------------------------------------------4

4. WORK PERMITS 4

5. HEALTH, SAFETY AND ENVIRONMENTAL PROCEDURES 4

6. MATERIALS 5

7. MANPOWER 5

8. EQUIPMENT & TOOLS 5

9. WORK PROCEDURE FOR CONSTRUCTION OF OTHER CIVIL JOBS 6


9.1. Initial Survey & Site Checking-------------------------------------------------------------6
9.2. Excavation Safe method statements----------------------------------------------------6
9.2.1. PRE-START CHECKS......................................................................................................................6
9.3. Back filling and Compaction.---------------------------------------------------------------7

10. REINFORCING STEEL 7

11. FORM WORK 7

12. Placing of concrete 8

2
Project Summary
SUMMARY

Project name: Electrical Boiler Project


Installation project reference:

Summary of the Civil work: Excvation and Masonary/Concrete work,


project:

Site address: HBSC, Kilinto, Start date: January 15, 2025


Addis Ababa

Finish date:

Issue date: Document


number:

CONTRACTED COMPANY’S DETAILS

Company name: Lelacon Engineering Main contact +251-912506754


and Trade number:

Lideta Sub-city, Kasahun Kindu


Address: Name of works
Addis Ababa
supervisor:

Job title: Lelacon Engineering


and Trade, Managing
Director

Contact number: +251-912506754

HEALTH & SAFETY CONTACT DETAILS

Name: Yoseph Shiferaw Contact number: +251-911979063

Name: Contact number:

3
HEALTH & SAFETY PROCEDURES

Name of on-site On-site first aid box


first aider: location:

Address of nearest HBSC- Clinic; Designated evacuation Brewery Assembly


Tirunesh Bejing Hospital
hospital: meeting point: point

REQUIRED PERSONAL PROTECTIVE EQUIPMENT (PPE)

Hard hats Safety High-visibility jackets Safety Eye protection Hearing Respiratory
boots gloves protection protection

Yes No Yes No Yes No Yes No Yes No Yes No Yes No

2. PURPOSE
 To specify the requirements of civil construction including excavation, filling, and allied
activities complying with the contract document, specification, and scope of work and
approved drawings/documents. It also includes earthworks associated with trenches
for pipelines or service ducts.

3. SCOPE
 This Method Statement applies to all the civil works - Excavation including ground
preparation, setting out, backfilling, soil compaction, concreting, waterproofing,
masonry, plastering, joinery - related to the construction of building as per project
requirements, referring with approved Civil and MEP drawing.

4. ROLES & RESPONSIBILITY

 The primary responsibility of carrying out all the activities mentioned in this procedure
rests with the project manager unless mentioned otherwise.

4.1. Project Manager


 Overall execution and administration of the project as per HSE standards, contract
requirements, specifications and the for preparation and updating of procedures,

4.2. Site Engineer:


 Assess manpower, equipment or other resources required to ensure timely completion
of the project. Monitor availability of all materials as per schedule. Inform the Project
Manager for any non-availability of materials to take proper action. Carry out receiving
inspectionand ensure that the drawings and documents are up to date and the latest
drawing is available and is being utilized in the project site works.

4
4.3. Safety Officer:
 Responsible for monitoring and implementation of safety related matters such as work
permits, First Aid, PPE, approval of diversions, follow the safety and traffic regulations
by all the workmen during the construction, according to the approved project HSE
plan. Coordinates new employees induction trainings, daily toolbox meetings, conduct
risk assessments.

4.4. Supervisor/Foreman:
 Plan and obtain required manpower and resources in coordination with the Site
Engineer. Carry out all activities as per the planned schedule to achieve target dates.
Coordinate with respective disciplines of work and liaise with the site engineer for day
to day activities. Inform Discipline Engineer regarding site inspections when it is ready.
Ensure pre task briefing is to be conducted prior to start of work at each session.

5. WORK PERMITS
 All necessary work permits shall be obtained prior to the commencement of any
activity at site and shall remain valid throughout the entire duration of the operation.
 Safety Barriers and Site sign boards will be installed prior to the work commencement.

6. HEALTH, SAFETY AND ENVIRONMENTAL PROCEDURES

 Requirements of Health, Safety and Environmental for the project shall be in


accordance with approved Project HSE Plan.
 Before commencing of any work, the required and applicable work permits shall be
checked and ensure all requirements of WP are compiled and they are valid until
completion of the activity and as per approved HSE plan.
 All personnel accessing their site will wear the mandatory PPE. All workmen and staff
shall wear the mandatory and job specific Personnel Protective Equipment's.
 Pre-task briefing shall be conducted on every day before starting the work.
Experienced and HSE inducted workmen shall be deployed for the work.
 All personnel shall be cautioned while working near any live lines such as power cable,
water lines, drainage lines, telecom etc.
 Prior to commencement of work all workers shall be given pre-task briefing. Hazards
identified for the activity shall be disseminated during pre-task briefing, especially for
underground services, slip & trip, improper access, excavation tools handling, no
access or aggress, vehicle collision, heat exhaustion, which shall be identified and
documented separately by permit to work system as per approved HSE plan.
 First aid stations complete with all first aid equipment and trained first aiders shall be
maintained for the initial care.
 Safety and security procedures shall be implemented as a minimal, warning signs and
lights, barricades, railing and other safeguards shall be provided as required by the
nature and location of the work.

5
 The environmental risk assessment and environmental management plans have been
reviewed for the work activities proposed in the method statement and found to be
suitable and adequate.
 Waste will be segregated at source and transported to dedicated segregated waste
storage area and not be allowed to accumulate on site in undesignated areas.
Concrete waste will be removed from work areas daily at regular intervals to
designated areas.
 Construction waste will be disposed as per local laws & client guidelines by licensed
carrier to a licensed facility.

7. MATERIALS
 Approval shall be obtained for all the materials with reference to Client’s preferred
vendor list, prior to commencement of activities as per contract.
 Material Inspection Request (MIR) will be submitted to client upon material arrival to
storage.
 All materials must be stored properly as per the manufacturer’s recommendations and
the Material shelf life will be monitored as per Manufacturer’s data sheets

8. MANPOWER
 Project Manager
 Site Engineer/ Supervisor
 Forman,
 HSE officer
 Surveyer,
 Carpenters
 Steel Fixers
 Masons
 Helpers
 Painters
 Operators
 Drivers & Technicians

9. EQUIPMENT & TOOLS


The following equipments and tools shall be used for the various acti, ities.
 Excavators, Manual jack hammer,
 Shovels,

6
 Tipper Trucks, dumpers
 Concrete Mixers (Stationery and Truck mixres as required)
 Vibrators
 Grinders Cutters
 Drilling Machines
 Hand tools
 Surveying equipments with accessaries.

10. WORK PROCEDURE FOR CONSTRUCTION OF OTHER CIVIL JOBS

10.1. Initial Survey & Site Checking


 Upon receipt of Job Instruction / Drawing form Consultant Engineer, an initial site visit
to be made along with the consultant representative to confirm the site and
demarcations.
 Proper Safety Fencing and site sign boards will be installed prior to the construction.

10.2. Excavation Safe method statements


10.2.1.Pre-start checks
 The pre-start checks must cover the following areas: - availability of plant and
equipment to be used; ground conditions; proximity hazards and welfare facilities.
Ensure the excavation area has been checked for overhead and underground services
prior to the commencement of work.
 No workers are to enter excavation. The concrete will be poured directly into the
excavation and moved using rakes without the workers having to enter the excavation.
 The area to be excavated will be clearly marked on the surface using lime;
 Physical barriers will be erected around the excavation where appropriate.
 The groundworks contractor will liaise with the client/contractor to ensure that any live
services on the site have been identified and clearly marked. Where necessary
handdigging measures will be used to expose existing services.
 The material from the excavation will be loaded into a dumper and tipped away from
the working area so it does not apply a surcharge to the side of the excavation.
 The dumper will be fitted with roll-over protection and the driver must wear the seat
belt. No edge tipping is to take place.
 A flagman will be used to assist in the safe operation of the plant and to observe the
area being excavated to ensure there are no undiscovered services.
 Loose soil from both the base and the sides of the trench is to be removed prior to
placing concrete using the excavator.

7
 Formation level to be inspected and passed. The excavation is to be filled with
concrete to the required level as set out using a laser.
 Ready mixed concrete will be used. Where the concrete cannot be poured directly into
the excavation via the chutes on the concrete lorry, the concrete will be placed in the
clean excavator bucket which will then place the concrete in the strip foundations.

10.3.Back filling and Compaction.

 Back filling shall be done in layers Testing of compaction will be performed as directed
by the engineer.
 Earth work under substructure shall be provided with anti-termite treatment for the
approval of the Engineer.
 The bottom of excavation shall be compacted and offered for inspection and testing by
the consultant Engineer.

11. Reinforcing steel

 Engineer’s approval will be obtained for reinforcement before using in permanent


works.
 All reinforcement will be stored on racks inside the stores. Different types & sizes will
be kept separately. All reinforcement will be kept to protect from damage, free from
dirt, loose mill scale, rust scale paint, oil, or other foreign substances.
 As per the specifications & drawing, the bar bending schedules & bar lists, cutting
schedules for each individual structure will be prepared by the contractor and will
obtain the approval from the engineer.
 Manual cutter or mechanical cutter will be used for cutting of bars & manual bending
will be used for bending of bars.
 All reinforcement will be cleaned by a wire brush or any other means before placing.
 All reinforcement placed should comply with the drawings. Lap length will be taken in
to account according to the project specification when binding reinforcement bars.

12. Form work


 All formworks will be made by using plywood sheets, timber or by metal.
 Supports and scaffolding will be G I pipes, Arco props, sawn timber or round timber.
All surfaces of formwork will be finished smooth and mortar tight.
 The dimensions & position of formwork will be carefully checked after erection.
 Before placing concrete all dirt, wood chips, hardened concrete or mortar and all other
foreign matter will be removed from the forms.

8
 Before fixing of form work, detailed drawing will be submitted to the engineer for
approval. Well qualified foremans will be appointed for fixing on formworks &
reinforcement work.

13. Placing of concrete


 The method for placing of concrete will be worked out to prevent segregation of the
material & Engineer’s approval will be taken before concreting begins.
 Before placing concrete all formwork therein will be cleaned of all extraneous material
and dust and made free of any standing water.
 In continuing concrete, fresh concrete will be placed before the already placed
concrete is less than 20 minutes.
 Concrete of specified grade will be placed & compacted in horizontal layers normally
not exceeding 300mm in depth.
 Concrete will not be dropped from a height greater than 1.5m to prevent segregation.
Concrete will be free of all rock pockets, honey combs & voids.
 Complete Records showing the details of placing concrete in each part of the work will
be maintained and will be available for inspection at the site.

14. Compacting / vibrating of concrete


 Mechanical vibrators will be used for compaction. For this stand by units will available
in the site during the period of compacting. All operators handling vibrators will be
trained in their operation properly.

15. Curing
 Continuous curing will be carried out in a moist atmosphere for a minimum period of
10 days and for a further period required by engineer.
 Concrete area will be kept covered with hessian clothes or Polyethylene sheets which
will be kept moist throughout the curing period.

16. Masonry

 Block works shall be done as per approved drawings and shall comply with QCS.
 Samples of each type of masonry unit and accessory shall be submitted to consultant
for approval.
 Marking up of exact location of block walls and openings as per approved shop
drawings shall be done before commencing the work.
 Block marked areas shall be cleaned and wet before to start with the activity. Mortar
mix shall comply with project specifications and QCS.
 One course of block only will be executed for testing and approval by the consultant.

9
 Walls shall be kept level at all times and carried up in a uniform manner. No part being
raised more than 1500mm above any adjacent unbuilt course.
 Angles & Reveals shall be kept true, square and plumb all the time.
 Horizontal joints shall be leveled all the time and vertical joints in alternate courses
shall be plumb and line.
 Opening frames shall be set and maintained square, plumb, true and furnished with
anchors.
 Install reinforced concrete block lintels or GI steel lintels over openings as per
approved shop drawing or cast in places as per specification.
 Top of block partitions and sides will be supported by using galvanized steel
anchors/ties as per approved shop drawings and material submittals.
 Concrete block walls and partitions shall be reinforced horizontally each second
course, last top course, second and third course above lintels and below sills of
opening with the required over lap.
 After completing of each section of the walls, cleaning shall be done to the down
surfaces and curing will start immediately.
 Final inspection shall be carried out for the entire work for approval of the engineer.

17. Plastering
 Prepare surfaces for the smooth or non-absorbent solid surfaces that do not have the
suction capability to receive a solid plaster bases by chipping, wire brushing or sand
blasting, as appropriate.
 Install beads at their locations plumbed and squared. And it will be best achieved by
using galvanized nails or small quantities of mortar and as per manufacturer’s
recommendations.
 Install the corner, control joints and movement beads at locations indicated in the
drawings and manufacturer’s instructions.
 Prepare plaster in a mechanical mixer, using sufficient water to produce a workable
consistency and uniform color shall be used to mix a batch containing one bag of
Portland cement, 5 parts aggregate, aerating plasticizer as per manufacturer’s
recommendation for use over Concrete Unit Masonry.
 Spray water on the wall surface and throw the spatter dash mix (scratch coat) by using
a spatter dash manual machine in a way to form a rough layer 3-5mm thick without
any attempt to level or smooth it. The rough surface shall be kept damp with fine water
spray or by covering with polyethylene sheet until it sets down.
 Apply plaster/render coat after the scratch coat had hardened. Initially, a thin coat is
troweled on the scratch coat to ensure a thorough bonding at the surface.
 The remainder of the render coat is then built up using wooden float to receive
textured finish until the required thickness met.

10
 Apply final thin coat plastering using steel trowel on the interior surface to match with
the Architect’s sample as specified.
 The newly applied external coatings shall be cured and protected against frost, heat,
and rain for the first 48 hours using canvass, cloth or sheet, hung clear at the plaster
surface.
 Moist curing by applying a fine fog spray of water, generally twice daily in the morning
and evening.

18. HEALTH & SAFETY


 Refer to the site safety policy for general safety controls. One of the main aspects of
this procedure is Safety and Health Control. This is to control occurrence of injuries as
well as damage to equipment and properties during the entire construction period.
 Tool Box meetings shall be conducted on every day before the start of the work.
Experienced workmen only shall be deployed for the work.
 All personnel shall be cautioned while working near the pipes/ cables.
 Hazard identification shall be done during toolbox meetings,
 In order to ensure a safe working environment during the entire construction period,
the following safety measures will be implemented.
18.1. Machineryand Equipment:
 Prior to use any machinery/equipment at site, it shall be inspected and certified by
qualified person.
 Periodic Preventive Maintenance shall be made on all equipment and machineries.
 All operators and driver are to be equipped with valid driver’s/operator’s license or
permit from concerned government agency.
 Only authorized drivers or operators will be allowed to operate machineries or
equipment. Only authorized signalman shall be assigned together with the operator or
driver.
 All lifting equipment as well as its accessories such as sling wire, nylon sling, shackles,
chain blocks, crane hook and latch shall be inspected periodically.

18.2. Personal Protective Equipment:

 PPE shall be issued to all workers such as safety shoes, hard hat, working gloves, ear
plugs, safety goggles and safety belt and or safety harness for workers who will be
assigned in elevated places.
 Wearing of the basic PPE shall be enforced fully.
18.3. EMERGENCY CONTACTS

SN Name Position Contact #

11
1 Wendemsesha Ayale Project Manager +251-912163319

2 Site Supervisor

3 Yoseph Shiferaw Lelacon HSE Manager +251-911979063

12

You might also like