LELACON Boiler Project Method Statement
LELACON Boiler Project Method Statement
First Revision,
December 2024, Addis Ababa
1
1.
Table of Contents
PROJECT SUMMARY 2
1. PURPOSE 3
2. SCOPE 3
4. WORK PERMITS 4
6. MATERIALS 5
7. MANPOWER 5
2
Project Summary
SUMMARY
Finish date:
3
HEALTH & SAFETY PROCEDURES
Hard hats Safety High-visibility jackets Safety Eye protection Hearing Respiratory
boots gloves protection protection
2. PURPOSE
To specify the requirements of civil construction including excavation, filling, and allied
activities complying with the contract document, specification, and scope of work and
approved drawings/documents. It also includes earthworks associated with trenches
for pipelines or service ducts.
3. SCOPE
This Method Statement applies to all the civil works - Excavation including ground
preparation, setting out, backfilling, soil compaction, concreting, waterproofing,
masonry, plastering, joinery - related to the construction of building as per project
requirements, referring with approved Civil and MEP drawing.
The primary responsibility of carrying out all the activities mentioned in this procedure
rests with the project manager unless mentioned otherwise.
4
4.3. Safety Officer:
Responsible for monitoring and implementation of safety related matters such as work
permits, First Aid, PPE, approval of diversions, follow the safety and traffic regulations
by all the workmen during the construction, according to the approved project HSE
plan. Coordinates new employees induction trainings, daily toolbox meetings, conduct
risk assessments.
4.4. Supervisor/Foreman:
Plan and obtain required manpower and resources in coordination with the Site
Engineer. Carry out all activities as per the planned schedule to achieve target dates.
Coordinate with respective disciplines of work and liaise with the site engineer for day
to day activities. Inform Discipline Engineer regarding site inspections when it is ready.
Ensure pre task briefing is to be conducted prior to start of work at each session.
5. WORK PERMITS
All necessary work permits shall be obtained prior to the commencement of any
activity at site and shall remain valid throughout the entire duration of the operation.
Safety Barriers and Site sign boards will be installed prior to the work commencement.
5
The environmental risk assessment and environmental management plans have been
reviewed for the work activities proposed in the method statement and found to be
suitable and adequate.
Waste will be segregated at source and transported to dedicated segregated waste
storage area and not be allowed to accumulate on site in undesignated areas.
Concrete waste will be removed from work areas daily at regular intervals to
designated areas.
Construction waste will be disposed as per local laws & client guidelines by licensed
carrier to a licensed facility.
7. MATERIALS
Approval shall be obtained for all the materials with reference to Client’s preferred
vendor list, prior to commencement of activities as per contract.
Material Inspection Request (MIR) will be submitted to client upon material arrival to
storage.
All materials must be stored properly as per the manufacturer’s recommendations and
the Material shelf life will be monitored as per Manufacturer’s data sheets
8. MANPOWER
Project Manager
Site Engineer/ Supervisor
Forman,
HSE officer
Surveyer,
Carpenters
Steel Fixers
Masons
Helpers
Painters
Operators
Drivers & Technicians
6
Tipper Trucks, dumpers
Concrete Mixers (Stationery and Truck mixres as required)
Vibrators
Grinders Cutters
Drilling Machines
Hand tools
Surveying equipments with accessaries.
7
Formation level to be inspected and passed. The excavation is to be filled with
concrete to the required level as set out using a laser.
Ready mixed concrete will be used. Where the concrete cannot be poured directly into
the excavation via the chutes on the concrete lorry, the concrete will be placed in the
clean excavator bucket which will then place the concrete in the strip foundations.
Back filling shall be done in layers Testing of compaction will be performed as directed
by the engineer.
Earth work under substructure shall be provided with anti-termite treatment for the
approval of the Engineer.
The bottom of excavation shall be compacted and offered for inspection and testing by
the consultant Engineer.
8
Before fixing of form work, detailed drawing will be submitted to the engineer for
approval. Well qualified foremans will be appointed for fixing on formworks &
reinforcement work.
15. Curing
Continuous curing will be carried out in a moist atmosphere for a minimum period of
10 days and for a further period required by engineer.
Concrete area will be kept covered with hessian clothes or Polyethylene sheets which
will be kept moist throughout the curing period.
16. Masonry
Block works shall be done as per approved drawings and shall comply with QCS.
Samples of each type of masonry unit and accessory shall be submitted to consultant
for approval.
Marking up of exact location of block walls and openings as per approved shop
drawings shall be done before commencing the work.
Block marked areas shall be cleaned and wet before to start with the activity. Mortar
mix shall comply with project specifications and QCS.
One course of block only will be executed for testing and approval by the consultant.
9
Walls shall be kept level at all times and carried up in a uniform manner. No part being
raised more than 1500mm above any adjacent unbuilt course.
Angles & Reveals shall be kept true, square and plumb all the time.
Horizontal joints shall be leveled all the time and vertical joints in alternate courses
shall be plumb and line.
Opening frames shall be set and maintained square, plumb, true and furnished with
anchors.
Install reinforced concrete block lintels or GI steel lintels over openings as per
approved shop drawing or cast in places as per specification.
Top of block partitions and sides will be supported by using galvanized steel
anchors/ties as per approved shop drawings and material submittals.
Concrete block walls and partitions shall be reinforced horizontally each second
course, last top course, second and third course above lintels and below sills of
opening with the required over lap.
After completing of each section of the walls, cleaning shall be done to the down
surfaces and curing will start immediately.
Final inspection shall be carried out for the entire work for approval of the engineer.
17. Plastering
Prepare surfaces for the smooth or non-absorbent solid surfaces that do not have the
suction capability to receive a solid plaster bases by chipping, wire brushing or sand
blasting, as appropriate.
Install beads at their locations plumbed and squared. And it will be best achieved by
using galvanized nails or small quantities of mortar and as per manufacturer’s
recommendations.
Install the corner, control joints and movement beads at locations indicated in the
drawings and manufacturer’s instructions.
Prepare plaster in a mechanical mixer, using sufficient water to produce a workable
consistency and uniform color shall be used to mix a batch containing one bag of
Portland cement, 5 parts aggregate, aerating plasticizer as per manufacturer’s
recommendation for use over Concrete Unit Masonry.
Spray water on the wall surface and throw the spatter dash mix (scratch coat) by using
a spatter dash manual machine in a way to form a rough layer 3-5mm thick without
any attempt to level or smooth it. The rough surface shall be kept damp with fine water
spray or by covering with polyethylene sheet until it sets down.
Apply plaster/render coat after the scratch coat had hardened. Initially, a thin coat is
troweled on the scratch coat to ensure a thorough bonding at the surface.
The remainder of the render coat is then built up using wooden float to receive
textured finish until the required thickness met.
10
Apply final thin coat plastering using steel trowel on the interior surface to match with
the Architect’s sample as specified.
The newly applied external coatings shall be cured and protected against frost, heat,
and rain for the first 48 hours using canvass, cloth or sheet, hung clear at the plaster
surface.
Moist curing by applying a fine fog spray of water, generally twice daily in the morning
and evening.
PPE shall be issued to all workers such as safety shoes, hard hat, working gloves, ear
plugs, safety goggles and safety belt and or safety harness for workers who will be
assigned in elevated places.
Wearing of the basic PPE shall be enforced fully.
18.3. EMERGENCY CONTACTS
11
1 Wendemsesha Ayale Project Manager +251-912163319
2 Site Supervisor
12