User Manual For WBS Rescheduling

This document outlines the procedure for rescheduling an existing project using transaction codes CJ20N and CJ21, primarily due to delays in procurement or client requests. It details the steps for adjusting project definitions and WBS elements, emphasizing the importance of maintaining the original start date while updating the end date. The final step involves manually resetting network and activity dates in Project Builder as necessary.

Uploaded by

OMKAR PARULEKAR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views7 pages

User Manual For WBS Rescheduling

This document outlines the procedure for rescheduling an existing project using transaction codes CJ20N and CJ21, primarily due to delays in procurement or client requests. It details the steps for adjusting project definitions and WBS elements, emphasizing the importance of maintaining the original start date while updating the end date. The final step involves manually resetting network and activity dates in Project Builder as necessary.

Uploaded by

OMKAR PARULEKAR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

P u r p o s e

Use this procedure for rescheduling an existing Project with reference to WBS elements of the network
(Activity scheduling if required has to be done manually)

Transaction Codes

CJ 20N

CJ21

Created By Yuvraj 01.07.2016 Version 0


Purpose: An existing Project has to be rescheduled due to reasons like delay in Procurement, delay in advance payment
receipt or request from client of Rochem

Let us reschedule this Project released partially

Step 1: Tcode CJ21

Shifting Project definition and Project WBS to the new dates

ENTER

Created By Yuvraj 01.07.2016 Version 0


Existing Project schedule is as under:

Click on WBS Basic data

Created By Yuvraj 01.07.2016 Version 0


Click on Go to -> Project definition

Here we have 2 options namely

1. Change the start date and end date (not advisable)


2. Change only the end date – this is a better option to keep track of initial start date

Going with option 2 above change the Finished date alone to 05.07.2016

Created By Yuvraj 01.07.2016 Version 0


Click on go back to reschedule the WBS elements

Step 2: Scheduling WBS elements in line with Project Definition (if revised dates of WBS elements are not within Project
Definition end date system will not permit to reschedule the WBS elements)

Scenario – Design phase got delayed and hence WBS elements have to be rescheduled (Design Phase start date should
not be changed)

Created By Yuvraj 01.07.2016 Version 0


Save

Created By Yuvraj 01.07.2016 Version 0


Now go to Project Builder CJ20N and note the change of dates of WBS elements (that is rescheduling at WBS elements
level).

Network dates and activity dates if required (when requirement dates of activities to decide the date of PRs in MRP Run)
have to be reset manually in Project Builder itself