User Manual For WBS Rescheduling
User Manual For WBS Rescheduling
Use this procedure for rescheduling an existing Project with reference to WBS elements of the network
(Activity scheduling if required has to be done manually)
Transaction Codes
CJ 20N
CJ21
ENTER
Going with option 2 above change the Finished date alone to 05.07.2016
Step 2: Scheduling WBS elements in line with Project Definition (if revised dates of WBS elements are not within Project
Definition end date system will not permit to reschedule the WBS elements)
Scenario – Design phase got delayed and hence WBS elements have to be rescheduled (Design Phase start date should
not be changed)
Network dates and activity dates if required (when requirement dates of activities to decide the date of PRs in MRP Run)
have to be reset manually in Project Builder itself