Exercise 1 2024 Solutions
Exercise 1 2024 Solutions
EXERCISE 1
Solutions
PROBLEM 1.
Initial values
𝑆𝑡 𝐽𝐴
𝑁𝑃𝑉 = ∑𝑛𝑡=1 − (𝐼 − (1+𝑖)𝑛 𝑛 ) ≥ 0 (1)
(1+𝑖)𝑡
where
St net cash inflow-outflows (net savings or net income) in year t, €
i discount rate of interest, %
t year
I investment cost, € (in the end of year 0 or in the beginning of year 1)
JAn salvage value of the investment at the end of lifetime, €
n Investment lifetime.
Annual cash flows can be described as follows over the 25 years’ time as shown in the figure:
Investment I
n = 25 years
present moment
(t = 0)
Salvage value (JAn) is usually assumed zero for power plant investments. Here we have
constant annual net income (electricity production is assumed to be same every year). So,
Net present value NPV can be written as
𝑁𝑃𝑉 = 𝑎𝑛,𝑖 ∙ 𝑠 − 𝐼 (2)
where
(1+𝑖)𝑛 −1
an,i = = present value factor of periodic payments
𝑖∙(1+𝑖)𝑛
s = annual net income, €/year (same amount each year)
I = investment, €.
In Net present value method, the investment is profitable, if the net present value of the
investment is positive (or zero).
For example, the investment cost is varied -20% (I = 10,4 m€) and +20% (I = 15,6 m€). Other
values are kept as they are. Net present value of the project is calculated for both cases, which
can be seen in the table 1 below.
Investment cost changes -20 %: I = 0,8 · 13 · 106 € = 10,4 · 106 €
NPV= 𝑎𝑛/𝑖 ∙ 𝑠 − 𝐼 =14,09394 · 991 765 €/a – 10,4 · 106 € = 3 577 877 €
Investment cost changes +20 %: I = 1,2 · 13 · 106 € = 15,6 · 106 €
NPV= 𝑎𝑛/𝑖 ∙ 𝑠 − 𝐼 =14,09394 · 9j91 765 €/a – 15,6 · 106 € = -1 622 123 €
The same is done with electricity price, see the table 2 and fuel price (table 3).
Table 3. Sensitivity analysis of the investment project by changing the fuel price.
Fuel price
-20 % 0 +20 %
hfu €/MWh 17,6 22 26,4
KFu €/year 1,367 1,708 2,050
s m€/year 1,333 0,992 0,650
NPV m€ +5,793 +0,978 --3,837
Sensitivity analysis shows that fuel price has significant effect on the profitability of the
project. Therefore, accuracy of the fuel price estimation should be the first priority in
profitability calculation.
PROBLEM 2.
Secondary heat for paper machine hood
Secondary heat is planned to be used for heating the replacement air of the paper machine
hood instead of back-pressure steam.
Find a) Cumulative discounted net cash-flow calculation
Is the investment project profitable?
What is the net present value of the project if economical lifetime is 8 years?
What is the repayment time with interest?
Initial values
availability time t 7 months/year
air mass flow (to be heated) qm,i 58 kg/s
air temperature difference ΔT (60-38) K
air specific heat capacity cp 1,01 kJ/kgK
steam price hH 3,6 €/GJ
investment cost I 500 000 €
annual additional costs hadd 5 000 €/year
discount rate of interest i 5 %
economical lifetime n 10 years
Thermal power:
𝑘𝑔 𝑘𝐽
Φ = 𝑞𝑚,𝑖 ∙ 𝑐𝑝 ∙ Δ𝑇 = 58 ∙ 1,01 ∙ (60 − 38)𝐾 = 1289 𝑘𝑊
𝑠 𝑘𝑔𝐾
Thermal energy:
7 ℎ
𝑄 = Φ ∙ 𝑡 = 1289 𝑘𝑊 ∙ ∙ 8760 = 6586 𝑀𝑊ℎ/𝑦𝑒𝑎𝑟
12 𝑦𝑒𝑎𝑟
€ 𝐺𝐽 € €
ℎ𝐻 = 3,6 ∙ 3600 = 12 960 = 12,96
𝐺𝐽 𝐺𝑊ℎ 𝐺𝑊ℎ 𝑀𝑊ℎ
Annual savings:
€ €
𝑆 = 𝑄 ∙ ℎ𝐻 = 6586 𝑀𝑊ℎ/𝑦𝑒𝑎𝑟 ∙ 12,96 𝑀𝑊ℎ = 85 349 𝑦𝑒𝑎𝑟
Annual net savings
To get cumulative discounted net cash flow, annual net savings are discounted one by one at
the discount rate. Present value factor for the individual payments (discount factor) vt,i
𝟏
=(𝟏+𝒊)𝒕 is used, where i is the discount rate of interest and t is the year. It can be found in table
too.
Present value factor vt,i is calculated for each year. The savings in each year are multiplied by
the corresponding present value factor.
Cumulative discounted net cash flow is solved by adding the present value of savings of year
t+1 to the net cash flow of year n:
Present
Net value Cumulative
Inv. Savings Discount of savings discounted
Year I Snet factor Snet· vt,i net cash flow
t € € vt,i € €
0 500 000 -500 000
1 80 349 0,9524 76 523 -423 477
2 80 349 0,9070 72 879 -350 598
3 80 349 0,8638 69 408 -281 190
4 80 349 0,8227 66 103 -215 086
5 80 349 0,7835 62 956 -152 131
6 80 349 0,7462 59 958 -92 173
7 80 349 0,7107 57 103 -35 071
8 80 349 0,6768 54 383 19 313
9 80 349 0,6446 51 794 71 106
10 80 349 0,6139 49 327 120 434
The net present value of the project for t = n = 8 is +19 313 € (See the table)
(1+𝑖)𝑛 −1 (1+0,05)8 −1
ani = = 0,05∙(1+0,05)8 = 6,4632
𝑖∙(1+𝑖)𝑛
35071
➔ 𝑥 = 7 + 54383 ≈ 7,6 𝑦𝑒𝑎𝑟𝑠
b) Repayment diagram:
Repayment diagram
200 000
Cumulative discounted net cash flow, €
100 000
0
0 1 2 3 4 5 6 7 8 9 10
-100 000
-200 000
-300 000
-400 000
-500 000
-600 000
year