Ch-4 - Net Work
Ch-4 - Net Work
PROJECT MANAGEMENT
2
What is project
A project is a temporary effort to create a unique Dr. Shime
product or service. Projects usually include
constraints and risks regarding cost, schedule or
performance outcome.
Project management is the application of
knowledge, skills, tools, and techniques to project
activities in order to meet or exceed stakeholder
needs and expectations from a project.
Meeting or exceeding stakeholder needs and
expectations invariably involves balancing competing
demands among:
Scope, time, cost, and quality
3
Stakeholders with differing needs and
expectations
8
Indicate EVENT, a point in time where one or more
activities start and/or finish.
EXAMPLE 2
A Seminar Development Project: An Illustration
Suppose the state council on mental health and mental
retardation has developed an information system that it expects
will provide the council with state-wide program information and
the many county agencies with local program and client
information.
9
The coordinator has identified the activities that must be Dr. Shime
completed prior to the seminars themselves. She has also
identified which activities must be completed prior to any one
he
listImmedi
With ate of diateEstimated
theseActivity eces of basicDescription imme predeces
two pi information, t predecesso sors time
rs (weeks
and the time for each anning for the
estimated activity, the pl project seminars
describedA blePlan seminar content - 2
as in Ta 1 A 1
B - 2
Obtain speakers
C B,C 3
Select seminar sites
D D 3
Prepare and mail
E flyer/invitations D 1
F Accept reservations
Notify press 1
0
activity and has estimated the number of weeks needed to
perform each activity.
is
CONT……
PROJECT NETWORK
11
Dr. Shime
B Critical
A E
2
1
3
path
Star
t D Finish
3
F
C 1
2
CONT….
THE CRITICAL PATH
A series of connected activities are called path.
1
2
The length of time associated with the path is the
sum of the time estimates associated with each of the
activities on the path.
Dr. Shime
Thepath with the greatest time estimate is called
the critical path.
13
EARLY TIME, LATE TIME, AND SLACK
1
4
Finding ES and EF times involves “a forward
pass” through the network. The method
associated with finding ES and EF is called
forward pass method.
Ground rule
1. The early start time of an activity with no
predecessors is zero.
2. The early finish time (EF) of each activity is
the sum of its early start time plus the Dr. Shime
time required to complete it.( EF= ES + t)
15
3. The early start time of any other activity is
the latest of its immediate predecessors'
early finish times.
SUMMARIZED EARLY START AND EARLY FINISH TABLE
Activity Duration ES EF
A 2 0 2
B 1 2 3
C 2 0 2
D 3 3 6
E 3 6 9
F 1 6 7
1
6
0 2 2 3
B1 6 9
A
2
E3
3 6
st Finis
D3 6 7 h
art 0 2
F1
C2
17
The late start time for any activity is the latest
that activity can commence without delaying
the whole project.
The late finish time of any activity is the latest Dr. Shime
CONT……
Activity Duration LF LS
F 1 9 8
E 3 9 6
D 3 6 3
C 2 3 1
B 1 3 2
A 2 2 0
19
A2 B1
E3
start 2 3
0 2 D3 6 9
Finish
C2 36 F1
1 3 8 9
PROJECT SCHEDULING WITH UNCERTAIN ACTIVITY TIMES
CONT….
21
Dr. Shime
23
EXAMPLE 2
SUPPOSE A CIVIL ENGINEERING FIRM HAS TO BID FOR THE CONSTRUCTION OF A DAM. THE ACTIVITIES AND
TIME ESTIMATES ARE GIVEN BELOW. DO THE NEXT REQUIREMENTS.
Activity a m b
1-2 (a) 1 3 4
1-3 (b) 2 4 6
1-4 (c) 2 3 5
2-5 (d) 3 4 5
3-6 (e) 3 5 7
4- 7 (f) 5 7 9
5-8 (g) 2 3 6
6-8 (h) 4 6 8
7-8 (I) 3 4 6
19
CONT…..
The policy of the firm respect to submitting
bids is to bid the minimum amount that will 2
5Dr. Shime
provide a 95% of probability of at best
breaking even. The fixed costs for the project
600,000 and the variable costs are 8,0000
every month spent working on the project.
CONT……….
REQUIRED:
a) Draw the project network and identify all the paths.
b) Compute the expected time for each activity and Dr. Shime
the expected duration for each path.
c) Determine the expected project length.
2
6
d) Identify the critical path and critical activities.
e) Compute the variance for each activity and the
variance for path .
2
7
A)
Dr. Shime
SOLUTION 2
8
CONT…..
Solution
B)
Times
Path Activity a m b te =a+4m+b Path total
6 Dr. Shime
1-2-5-8 a 1 3 4 2.83
b 2 4 6 4.00 10.00
c 2 3 5 3.17
1-3-6-8 d 3 4 5 4.00
e 3 5 7 5.00 16.00
f 5 7 9 7.00
1-4-7-8 g 2 3 6 3.33
h 4 6 8 6.00 13.5
i 3 4 6 4.17
23
CONT…..
31
C) The critical path is path 1-3-6-8, since it has the
longest expected
CONT….
Knowledge of the expected path time and their
standard deviation enables a manager to make
probabilistic estimate of the project
complementation time.
Dr. Shime
33
TIME-COST TRADE-OFFS _CRASHING:
3
4
Among the most obvious options are using
additional personnel or more efficient
equipment and relaxing work specifications.
CONTD…
aproject manager may be able to shorten a
project, there by realizing a savings on
Dr. Shime
indirect project cost by increasing direct
expenses to speed up the project.
3
5
The goal in evaluating time-cost trade-offs is
to identify a plan that will minimize the sum
of the indirect and direct project costs.
In order to make a rational decision about
Dr. Shime
3
7
Cost Shorten
Total cost
Shorten
Cumulative
cost of crashing
Crash
Expected
indirect cost
Shorten
Project
length
Optimum
4
0
6
10
a
Start b 2
En
5 f d
9
4 e
c
A. Determine which
d activities are on the critical
path, its
4
1
Dr. Shime
4
2
2 d 700 3 f
800 1
4
3
becomes 18 days, which is the same as
the length of path a-b-f.
4
4
Dr. Shime
c no further reduction
possible d $ 700
e 600 f
800
f. at this point no additional improvement is feasible.
The cost to crash b is $ 500 and the cost to crash
e is $600 for a total of $1,100.
Dr. Shime
4
5