332 Lecture Notes
332 Lecture Notes
LECTURE NOTES
FEBRUARY 2016
TABLE OF CONTENTS
FOREWORD ...................................................................................................................... 2
CHAPTERS
1.CONSTRUCTION PROJECT MANAGEMENT AND
COMPANY ORGANISATION ......................................................................................... 3
2.THE CONSTRUCTION INDUSTRY ........................................................................... 15
3.PROJECT DELIVERY SYSTEMS AND CONTRACTUAL ARRANGEMENTS .... 27
4.CONSTRUCTION COST ESTIMATING .................................................................... 39
5.CONSTRUCTION PROJECT PLANNING ................................................................. 55
6.MANAGING QUALITY............................................................................................... 90
7.MANAGING HEALTH AND SAFETY..................................................................... 102
8.CONSTRUCTION MACHINERY AND EQUIPMENT ............................................ 108
1
FOREWORD
These Lecture Notes have been prepared for the use of METU Civil Engineering students
taking CE 332 Construction Engineering and Management Course. It brings together the
collected chapters on contemporary construction management topics. Some parts of these
Lecture Notes have been compiled from the various books and articles about the
construction management discipline in order to provide civil engineering students with a
complete coverage of the construction management topic.
2
CHAPTER 1
DEFINITION OF A PROJECT
3
Each project is unique. Although exactly the same project is to be carried out, as
the location, external factors (climate etc.), parties involved, time and budget
constraints etc. are different, projects have their unique features which make them
unique undertakings.
1. Project initiation: A project is initiated when its “promoter” predicts that there
will be a demand for the goods or services that the project may produce.
Alternative ideas and schemes are considered to meet the demand, thus the
context (scope) of the project is determined.
2. Feasibility study/appraisal stage: The project costs and benefits are determined
and compared. Appraisal stage is about prediction of demand, estimation of
revenues and costs to question whether it is feasible to carry out the project or not.
Many projects are cancelled at this stage as they cannot be proved
profitable/feasible. If the promoter decides to go on with the project, how best it
should be realized and what needs to be done are discussed.
3. Design: The main design stage includes deciding on which materials are used,
construction methods are utilized etc. to make the project ideas succeed.
Decisions made in design determine almost entirely quality and cost, thus, the
success of a project.
The phases of a construction project may be explained in detail, as given below (Barrie
and Paulson, 1990);
1. Concept and feasibility studies: Most construction projects begin with the
recognition of a need for a new facility. Long before designers start preparing
drawings and construction commences, a broad-scale planning is necessary.
Elements of this phase cover conceptual analysis, technical and economic
feasibility studies and environmental impact analysis.
4
impacts of the plant on the community? What is the environmental impact? What is
technical and economic feasibility? In order to find out answers to the above
addressed questions, normally, this phase is carried out by the client and/or its
consultants.
Once the preliminary engineering and design is complete, there is an extensive review
process before detailed work is allowed to proceed.
Detailed engineering and design: Detailed engineering and design involves the
process of successively breaking down, analyzing, and designing the structure and its
elements so that it complies with recognized standards of safety and performance
while presenting the design in the form of a set of explicit drawings and specifications
that will tell the constructors exactly how to build the structure in the field.
5
4. Construction: It is the process whereby designer’s plans and specifications are
converted into physical structures and facilities. It involves the organization and
coordination of all the resources for the project-labor, equipment, materials,
money, technology, time etc.-to complete the project on schedule, within the
budget and according to the standards of quality and performance as specified by
the designer.
6. Operation: Operation is the last stage within the life cycle of a project. During
this phase, the constructed facility is used by direct users (in case of a house, users
are households), operated for production of goods (e.g. in case of industrial plants,
factories) or used by the public (e.g. in case of roads). Sometimes, in Build-
Operate-Transfer (BOT) projects, the construction company is given a concession
to operate the facility for a given time period.
Figure 1.1 demonstrates the stages within the life cycle of the project.
6
Owner’s need for
project
Determination of alternatives,
technical feasibility and cost
estimate for each design
alternative
Execution of construction
works by the selected
contractor
Operation
7
PARTIES INVOLVED IN A CONSTRUCTION PROJECT
Figure 1.2 demonstrates the basic parties involved in a construction project and
contractual relationships in the traditional approach.
OWNER
SUBCONTRACTORS
The contractual relationships and types of contract will be discussed in more detail during
the “project delivery systems” part of this course.
8
PROJECT MANAGEMENT
Project management: it involves coordination of one time work by a team of people who
often have never previously worked together.
When a project is first assigned to a project manager, it is important that all three of these
components must be clearly defined. Not only individually defined but each must be
linked together since one affects the other significantly.
In order to put together the scope, budget and schedule within a project, project
management team has to carry out some basic functions. 5 basic functions of project
management and tasks of a project manager (PM) may be summarized as follows;
9
Build contingencies into the plan to provide a reserve in the schedule for
unforeseen future problems
Communicate the project plan
3. Staffing: It is the selection of individuals who have the expertise to produce the
work.
All of the above explained 5 functions are necessary for carrying out the following
“generic project management tasks” (Winch, 2002);
10
1. Defining the project mission: deciding what the client wants
2. Mobilizing the resource base: Forming the project coalition, managing the
supply chain
3. Riding the project life cycle: managing the budget, managing the schedule,
managing quality, managing risk, managing information flow, managing health
and safety
4. Leading the project coalition: Designing effective project organizations,
communicating the project mission (leadership)
5. Maintaining the resource base
Also, it can be argued that, the major role of PM is to “set systems” (Kelly et al., 2002).
Systems are necessary to realize the management functions for successful completion of
the project. Those systems may include;
1. Financial systems that will ensure payments are made according to contract
agreements
2. Decision systems that will ensure decisions are communicated at the appropriate
time and with the appropriate authority
3. Design change systems that will implement and monitor change
4. Cost and time monitoring systems that will chart real progress against the plan.
A firm or business is simply a fairly efficient way of combining the skills and talents of
people into an “organization” that can produce the goods and services in sufficient
quality to satisfy the desires of the community in which it exists and at the same time,
provide sufficient return on the capital invested (Harris and McCaffer, 2001). The choices
of “organizational structure” best suited for the company depend on several factors such
as the size of the company, its geographical location, type of product/services, etc. As the
construction industry is project-based, companies operating in this sector are organized
accordingly and there are 2 different management levels:
11
management levels. Figure 1.3 demonstrates a construction company as an open system
operating within an environment.
INPUTS:
Human resources OUTPUTS:
Materials ORGANIZATION Constructed
Money The transformation facility
Equipment process Construction
Information services
Feedback
ENVIRONMENT
Figure 1.3: Construction Organization as an Open System (adapted from Pilcher, 1992)
12
EXTERNAL SYSTEMS
Competitors, clients, designers, government etc.
GENERAL MANAGERS
and requirements
Setting long-range objectives, policy making, coping with
risks and uncertainties
Estimating and tendering: This function is about pricing the work, involving a bill of
quantities to which a mark-up/profit margin is added for the final bid. It involves
estimating the cost of the work and preparing the tender documents where assistance is
required from the planning department in preparing the tender programme and from the
purchasing department for obtaining quotations for materials supplies and subcontractors’
work. This function is very critical for a construction company, as it is directly related
with the ability to get or lose the job.
Head office planning: The functions of the central planning department are usually
twofold;
13
be negotiated by the purchasers. Thus, having a central purchasing department provides
a central point of responsibility for several contracts and bulk purchasing is possible.
Engineering support: Technical assistance may be given to the site in activities such as
formwork design, temporary works design, work study etc.
Health and safety: The task of setting up health and safety assurance procedures for the
company and assessing provision in the workplace is carried out by this department.
Quality management: With the introduction of ISO 9000 quality standards into a
company, the role of quality management unit is to advise departmental managers in
preparing quality assurance procedures and work instructions and then follow up with
audits and assessments in order to sustain the expected performance levels.
Finance and accounts: The company accountant is responsible for the bookkeeping
function and the payment of all invoices together with providing information on balance
sheet, profit-loss accounts etc. Thus, it is the finance department’s concern to monitor the
overall financial position of the company.
Legal services: This administrative function is related with legal issues such as claims,
contracts, rules-regulations etc.
Once a contract is secured, on a large extent the manager on site is independent of the rest
of the company, relying on head office functions only when necessary.
As a final remark, the topics covered in this course include mainly the “process of
construction project management”. However, some head office functions such as
estimating, quality management etc. will also be discussed.
1.3 REFERENCES
14
CHAPTER 2
Construction activity takes place everywhere there is human settlement and one of the
main characteristics of civilization is the presence of a built environment. Every day new
demand for infrastructure, buildings and utilities appears. Sheltering, one of the primary
needs of human beings, is met by construction of residential buildings such as houses or
apartment houses. The importance of the sector to society as a whole is immense.
Construction, perhaps more than any other industry, is fundamental to the quality of our
lives. It provides the drinking water and shelter we need to survive as people and it
provides the infrastructure needed for the economy.
The role of construction in national economy and development has been widely studied.
Gross domestic product GDP (gayri safi yurt içi hasıla - GSYİH) is the total annual value
of all goods and services produced by a country less income from investments abroad.
Various development patterns for construction related to GDP have been suggested. The
Gross National Product (GNP) is a similar figure, but unlike GDP it includes earnings of
domestic companies abroad. The inverse ‘U’ shape pattern by Ranko Bon (1992)
suggests that the share of construction in national output increases in the early stages of
development but ultimately will decrease in absolute and relative terms in more advanced
industrial countries (Bon 1992, Figure 2.1). An important aspect is that while the
proportion for new construction decreases with later stages of development, the share of
improvement and maintenance in total construction increases (Bon, 1992).
National Construction Output
Construction share of GDP
New
dev
elop
men
t
ent
i shm
rb
efu
a n dr
na nce
inte
Ma
After rapid expansion in the early stage of economic growth, the rate of growth of
construction output tends to slow down in mature economies (Strassmann, 1970; Bon and
Crosthwaite, 2000). In many of the richer countries output, in real terms, has more or less
15
stabilized. Stable output combined with a trend towards mechanization/prefabrication has
led in some rich countries to stagnant or declining employment in the construction
industry. European countries with declining construction employment between 1970 and
1998 include Belgium, Denmark, Finland, France, Italy, Netherlands and Sweden.
However, in other high-income countries, employment is still expanding. In Austria,
Germany, Ireland, Norway, Portugal, Spain and Turkey construction employment
increased between 1970 and 1998, while in Switzerland it remained stable (UN/ECE,
various dates). In some developed countries increasing employment follows increasing
output, however this is caused by a higher proportion of repair and maintenance activity
in the product mix which is very labor-intensive and also very skill-intensive.
(International Labor Organization, 2001).
The amount that a country spends on construction is closely related to its income. In
1998, expenditure varied from US$5 per head in Ethiopia to almost US$5,000 in Japan.
This means that construction output, by value, is heavily concentrated in the rich,
developed world. The high income countries of Europe are responsible for 30% of global
output, the United States for 21% and Japan for 20%. China, despite its huge size and
rapid economic growth in recent years, lags a long way behind with only 6%. India has
1.7% (International Labor Organization, 2003).
16
Figure 2.3: Construction Employment (source ILO)
A trend between construction investment and economic growth rate has not been clearly
identified, as various studies has contradicting conclusions. Researchers have in some
occasions found a positive association between construction activity and economic
growth. Given that industrialization is the growth engine, the construction sector, through
its relation with numerous other sectors of the economy, would play a determinant role in
this development process. In other views, the construction sector does not lead but rather
accompany economic growth.
Construction constitutes 10% of the European GDP and consumes nearly 60% of the total
investments in Europe amounting to 1,000 billion Euros. It is a major European job-
provider, employing around 10 million people (8% of total employment), making it the
region’s biggest industrial employer. There are in Europe over 200,000 firms associated
with this industry most of whom are small and medium-size enterprises (SMEs), and 28%
of industrial employments in Europe are construction related. In Europe a considerable
proportion of construction activity is attributable to building maintenance. Over the past
two decades, the contribution to maintenance has increased from 40% to over 50% of
total construction output, which accounts for over 5% of the GDP of many European
counties. Narrowly defined, the industry comprises only those enterprises 'adding value'
through production or assembly operations on the construction site. A broader definition
would include firms and individuals involved in planning, design, the supply of building
materials, plant, equipment, transport and other services. Some definitions also include
the customer, particularly the professional client or 'property developer'. The recent
increase in the number of contractor-financed infrastructure projects might make it
sensible to include the financial services sectors as well.
In recent years, global construction sector presented an unsteady outlook. After the rapid
growth in 1999, the sector reduced around 3 % in size from 3,6 trillion dollars to 3,4
17
trillion dollars. This situation continued between 2001 and 2002 where the market
dropped to 3 trillion dollars. In 2003, the sector showed increased activity and a better
performance was anticipated in the years ahead. In 2007, world construction output
reached 4,7 trillion dollars with 5% percent growth. However, global economic crisis in
2008 dropped output of the sector significantly. The construction sector showed signs of
recovery in 2010 and output reached 4,6 trillion dollars in 2011 but it was below the
levels achieved in 2007. It is predicted that volume of output in the construction sector
will grow to 15 trillion dollars worldwide by 2025. (DPT 9. Kalkınma Planı, 2006; WTO,
2007; AECOM, 2012; Global Construction, 2013).
Drawing the boundaries of the construction industry is therefore not easy. Construction
can be seen not as a separate industry, but as agents and activities which can be
unpackaged and packaged in different ways. The enterprises engaged in construction
activity are extremely diverse. They range from self-employed individuals providing a
service to private house owners in the local community to multinational firms operating
on a global scale (ILO, 2003).
GLOBALIZATION
Traditionally, construction used to be a domestic industry, but this is now far from the
case. The construction market is now international. The general trend towards
globalization of markets caused by elimination of trade barriers, adoption of international
standards, opening of private and public national markets to foreign competition increase
the feasibility of exporting construction services to foreign markets. Contractors may be
motivated to operate internationally by saturation or instability of home construction
demand. Merger and acquisition activity has increased dramatically over the past decade,
leading to rapid, international consolidation within the industry. The largest players of the
construction industry are operating world-wide, and many Turkish contractors are
operating internationally. With new information technologies the distance and spatial
boundaries have been blurred to the point where any organization can theoretically
participate in a design and construction project in any location. However, the vast
majority of enterprises involved in on-site construction are small and local. Despite the
existence of an international construction industry, more than 95% of construction
activity is still undertaken by firms from within the country, the region or the
neighborhood (ILO, 2003). A global main contractor will subcontract large portions of
the works when performing international work. In specialized civil engineering and
facilities projects, the main contractor will typically subcontract low-skill civil works.
The construction industry differs in a number of ways from other industrial sectors in
terms of structure and mode of operation. The fundamental operating level of
construction is the project; it is the main operating process to deliver the end product.
Each project is unique – designed once, built once which contrasts to products of
manufacturing (designed once – built many times). Construction is not the only industry
18
with a project-based operation; it has however characteristics unique for the construction
industry (Harris and McCaffer, 2001; Riley and Clare-Brown, 2001; ILO, 2003):
Clients of the construction industry in the public sector such as central government
departments, local authorities and public corporations rely almost exclusively on
competitive tendering to justify the awarding of contracts. Clients from private industry
tend to follow the same practices and also largely employ competitive tendering
procedures. Thus, most construction contracts are awarded after several contractors have
submitted a tender and most civil engineering and building contractors derive the major
portion of their workload in this way (Harris and McCaffer, 2001).
The construction market is very volatile to the national economic situation. It is also a
competitive market, i.e. a market with sellers and buyers that are small and numerous
enough to take the market price as given when they decide how much to buy and sell.
The construction market has characteristics of a competitive market, e.g. many buyers
and sellers, and this creates a supply and demand situation. In times of recession,
competition for available construction work intensifies, and contractors will tend to lower
the mark-up (profit margin) of their bids to increase chances of winning. If the contractor
is really desperate to win they could submit a bid at something less than cost (Harris and
McCaffer, 2001). When a contractor obtains such a contract based on a very low cost
estimate, they issue claims to attempt to achieve a positive mark-up. This was an often
seen situation in the UK, and other places in Europe, in the early 1990’s. Jobs would end
without the contractor being fully paid, but with large claim files for conclusion after
completion of the works.
As terms of human resources, construction has the following characteristics (Riley and
Clare-Brown, 2001; Harris and McCaffer, 2001; ILO, 2003):
19
Low investment in skills training
Other industrial sectors and commerce are commonly able to benefit from
better prospects in attracting skilled workers either by providing superior
working conditions or in being able to pay better wages arising from more
intense application of mechanization and advanced technology in general.
Public sector is a much more important client than in most other sectors
Contracts are based on relationships where the project participants constantly
oppose each other instead of co-operating and sharing joint objectives.
Tendency to competition on price alone
Cash flow dominates behavior (‘cash is king’)
Reliance on credit and retention
During the 1980s there was an enormous growth in the use of subcontractors by the main
contractors. The reason for this development was to enable the contractor take on
additional workload without the need for increasing internally the level of employment
and capacity required to execute the extra workload, thus ensuring greater flexibility. The
trend towards the use of subcontractors has continued through the 1999s (Harris and
McCaffer, 2001).
Construction sector is one of the leading sectors of the Turkish economy. Its potential to
bring foreign exchange to local markets as a result of works carried out abroad and
multiplier effect on the economy due to the existence of strong input-output relations
with other sectors highlights its importance.
The construction sector creates demand for the products and services of more than 200
sub sectors. This effect is the basic indicator for the construction sector being considered
as the locomotive of the economy. It is anticipated that due to its inter-sectoral
transactions, the overall effect of construction industry is much higher on the general
economy. The overall share of construction sector, together with the contribution of other
sectors that supply input to construction, is around 30 %. Today Turkish contractors are
working in over 108 countries, realizing around 8750 projects, generating foreign
exchange for the Turkish economy, implementing new technologies, joining international
partnerships and creating markets to export Turkish goods abroad. Turkish construction
industry is also known as one of the leading sectors of economy due its potential for
generating employment. It constitutes 5.7% of GDP and employing approximately 1.9
million people. The share of the construction sector in the Turkish economy reaches 30%
when direct and indirect impacts on other sectors are considered. Moreover, the
employment rate of the sector reaches %10 (excluding agriculture). Table 2.1
demonstrates relationships between construction sector and gross domestic product
(GDP) of Turkey (Turkish Contractors Association, 2016).
20
Table 2.1: GDP Growth Rate and Construction Sector Growth Rate (TCA, 2015)
Construction Sector
Years GDP Growth Rate (%)
Growth Rate (%)
1999 -3.4 -3.1
2000 6.8 4.9
2001 -5.7 -17.4
2002 6.2 13.9
2003 5.3 7.8
2004 9.4 14.1
2005 8.4 9.3
2006 6.9 18.5
2007 4.7 5.7
2008 0.7 -8.1
2009 -4.7 -16.1
2010 9.2 18.3
2011 8.5 11.3
2012 2.1 0.6
2013 4.2 7.4
2014 3.0 2.2
2015 4.0 1.7
The Turkish Contractors Association (TCA) was founded on 26 January 1952 in Ankara.
The main objective of the association is to assist Turkish contractors in all their activities
and inform them about developments in the field of contracting at home and abroad. The
association deals with problems faced by member and non-member contractors from the
contract-award stage to final close-out of the works.
The current membership of the association consists of 136 representatives, which have
undertaken about 70% of the domestic projects and 90% of the international projects
awarded to date. They are not only involved in construction but are also active in the field
of industry and engineering.
The projects completed by the member companies cover a range of works related to all
kinds of civil engineering and industrial activities, such as dams, hydropower and thermal
power plants, industrial buildings, large scale oil and natural gas pipelines, petrochemical
refineries and complexes, motorways, tunnels and bridges, seaports and airports, large-
scale housing projects, high-rise and prestige buildings, hotels and tourist resorts.
21
Table 2.2: Total Project Value and Average Distribution of Works Conducted by TCA
Member Firms (TCA, 2016)
TCA prepares and submits reports to the relevant public authorities reflecting its
members' opinions and observations on matters related to the construction industry. The
association also provides technical counsel in the determination of short and long term
general policies concerning the construction sector. The TCA is member to the European
Union of Developers and House Builders (UEPC) since 1992 and became full member to
the European Construction Industry Federation (FIEC) on 25 May 2000 (Turkish
Contractors Association, 2012).
Turkish contractors started working internationally during the early 1970’s, a period
when Turkey faced serious economic and political difficulties. The embargo imposed
after the Cyprus crisis in 1974 particularly hurt the economy. The depressed home market
coincided with the recession in the world caused by the surge in oil prices. The first
country where Turkish contractors offered their services was Libya. Turkish contractors
started their Libyan projects by importing the necessary technology from European
countries. Later on, the growing Turkish contracting activities extended to other
international markets, beginning with the Middle-East countries such as Iraq, Jordan,
Saudi Arabia, Kuwait, the United Arab Emirates (UAE), Yemen and Iran. Today, they
are working in approximately 108 countries with a business capacity of 326 billion USA
Dollars. Turkish contractors have established very good relations with clients, gained
first-hand knowledge of the region and its business environment and successfully
completed a wide variety of projects employing Turkish labor and using Turkish goods
and materials (Turkish Contractors Association, 2016).
22
Three decades of international work are described in the following paragraphs (Turkish
Contractors Association, 2015):
In the first decade (1972-1979) most of the works were undertaken in North
Africa, primarily in Libya (72.52%), followed by Saudi Arabia (15.45%), Iraq
(7.25%), Kuwait (4.71%), Greece (0.06%), and Iran (0.01%). The most important
activity field in this period was housing (32.1%) followed by seaports (18.1%),
industrial plant (15.6%), road/bridge/tunnel construction (11.7%), and urban
infrastructure (8.2%), amounting to a total revenue for the period of US$ 1.5
billion.
In the second decade (1980-1989) the largest share of the total work performed
was still in Libya (55.2%), although the importance of this country declined in
relative terms. Saudi Arabia (23.4%) and Iraq (11.5%), which were the second
and third countries respectively in the first decade, maintained their position while
operation in other countries commenced. A new development in this period was
the emergence of the former USSR as a market (3.8%). In this decade the share of
housing (36.7%) and urban infrastructure (17.2%) increased, followed by
road/bridge/tunnel construction (7%) and irrigation (5.4%). The total value of
projects undertaken in this period was US$ 11.5 billion.
In the third decade (1990-1999) the trend changed. The share of the Russian
Federation rose to 34.5% while the share of Libya fell drastically to 13.7%,
followed by Kazakhstan (7.8%) and Turkmenistan (6.7%). Seen as a whole, the
share of the former USSR countries amounted to 58.3%. A development in this
period was the great diversification of the countries where work was carried out,
with the emergence of markets such as Kazakhstan (7.8%), Turkmenistan (6.7%),
Pakistan (6.6%), Uzbekistan (3.9%), Azerbaijan (2.6%), Bulgaria (2.6%), USA
(2.5%), and Croatia (2.2%). A drastic fall in the share of Saudi Arabia (3.1%) and
the clearance of Iraq from the scene are very significant. Under the classification
"others" there are 33 countries accounting for 6.2 % of the work volume. The
share of housing decreased (24.9%), followed by road/bridge/tunnel construction
(12.7%), industrial facilities (9%) and commercial centers (8.1%). The total value
of the projects in this period amounts to US$ 18.2 billion. The Russian Federation
accounts for US$ 6.3 billion and US$ 10.6 billion together with the former USSR
countries.
In 2001, Turkish contracting firms continued the negotiations for projects totaling to an
amount of approximately US$ 1 billion. As a result of these business development
activities, several projects have been undertaken in Ireland, India and Morocco. Being a
new and potential market, Ireland has an important place in business development
activities of the member firms. In Ireland, projects totaling to US$ 100 million varying
from power plants to highways and housing are being carried on. Also, a US$ 55 million
highway rehabilitation project in India and a US$ 85 million highway construction
project in Morocco are few examples of the achievements of Turkish contracting firms in
23
2001. Romania, the Russian Federation and Iran are also among countries where the
member firms have progressed to contract signing stage for various projects.
During the 2000-2014 period, the annual volume of business undertaken abroad increased
from 4.1 billion dollars in 2002 to 25.1 billion dollars in 2007. In the following years,
under the effects of the global crisis, this figure decreased to 20.2 billion dollars in 2009.
However, in 2013 Turkish international contracting services reached its peak level by
30.0 billion dollars.
Project Value
Number of Project Share (%)
(USD)
Russian
24 5.331.328.572 25,1%
Federation
Kuwait 3 4.518.076.782 21,2%
Turkmenistan 20 3.235.323.089 15,2%
Algeria 18 2.094.546.442 9,8%
Saudi Arabia 7 1.039.408.890 4,9%
Azerbaijan 10 847.610.491 4,0%
Kazakhstan 13 808.449.211 3,8%
Ghana 5 576.000.000 2,7%
Congo 2 559.881.359 2,6%
Iraq 19 391.813.548 1,8%
Other 67 1.874.972.333 8,9%
Total 188 21.277.410.717 100.00%
24
COMPETITIVENESS OF TURKISH CONTRACTORS
Every year a list of top 250 contractors is published by the Engineering News Record
(ENR). Evaluation parameters cover the annual income and the value of contracts
awarded within the year. In years 2009, 2010, 2011, 2012, 2013, and 2014, numbers of
Turkish contractors included in the list were 33, 31, 33, 38, 42, and 43 respectively. In
2014, there were 43 Turkish contractors among the top 250 international contractors of
ENR list. Turkey ranked the second in the World after China in terms of numbers of
contractors entered the list.
Turkish design engineering and consultancy is also operating internationally but has a
relatively weak competitive position compared to the contractors. The lag may be
explained by the fact that related Turkish government agencies assumed the engineering
role themselves for a long period of time. An example is the State Hydraulic Works
(Devlet Su İşleri – DSİ) which did their own engineering rather than acquiring
engineering services from private firms.
The lag of Turkish engineering has also been attributed to the fact that Turkish firms first
started internationalize as subcontractors to foreign firms during the 1970’s, which
delayed the development of design engineering and consultancy firms. It has been argued
that the relative lagging competitive position of Turkish design engineering and
consultancy firms is not favorable for long-term competitiveness of Turkish construction
as a whole. Weaknesses in engineering services could result in uncompetitive bids in
design and build contracts, and furthermore during the design phase of a project it may
lessen the opportunity to promote the use of materials and/or contractors from Turkey
(Öz, 2001).
25
2.4 REFERENCES
26
CHAPTER 3
Project Delivery System (PDS): A PDS is a way (a method) of organizing all phases of
a construction project by establishing relations (contractual or non-contractual) between
parties involved in the project. PDS is chosen by the client (or known as the owner) and it
determines the responsibilities of different parties involved in the construction process.
Client (project owner) may carry out the construction process himself/herself; hire a
single contractor or a number of specialty contractors to carry out the construction work.
He may assign design to a separate design company or to the contractor. He may organize
the construction process himself or hire a professional construction management firm to
organize everything. Thus, a number of methods, which are known as PDSs, are used in
the construction industry depending on the needs of the client, project characteristics etc.
A PDS is also called as a procurement method or contracting method.
Contract Type: Construction contracts may be classified into two major categories on
the basis of payment terms: fixed-price contracts and cost-plus contracts. A contractor
may be paid in fixed prices (which is also divided into two categories such as lump-sum
and unit-price contracts) determined before the construction starts or actual costs realized
during the construction plus a fee. Thus, contract type determines how a contractor is
paid. There are no strict rules about which contract types may be used in different PDS.
For example, in design-build, contract type is usually lump-sum. However, this cannot be
generalized as it depends on project characteristics. For example, if necessary, a
combination of lump-sum and unit-price payments may be preferred in design-build
depending on type of job, predictability of quantities etc.
27
certain “common practices” which are widely observed in the construction industry. For
example, in negotiated bidding, cost-plus types of contracts are mostly used.
To sum up, there are three decisions that should be made by the client before
commencement of the project:
Which PDS shall be used?
Which contract type shall be used?
What kind of bidding shall be used?
In the forthcoming chapters, factors that affect the answers of these questions are
discussed in detail.
Legal obligations
Owner Informal, inf. exchange
Designer
Workers Subcontractors
Workers
Figure 3.1: Traditional Contracting Method (DBB)
28
The responsibilities of parties shown in Figure 3.1 are as follows:
In DBB, owner has a dominant role due to separate contractual relationships with both
the design entity and the contractor. In this arrangement, the owner warrants to the
contractor that the plans and specifications are buildable. If problems arise during the
course of construction - or even after substantial completion - the owner becomes the
intermediary between the contractor and design firm. The traditional system has several
disadvantages. The primary disadvantage is the potential for conflict. The traditional
system often hinders communication among the parties which can result in misinterpreted
plans and specifications causing delay, cost overruns and legal problems. DBB creates
greater potential for time and cost overrun since the design and construction processes are
performed independently.
In this type of system, owner lets contracts to a number of specialty contractors. In other
words, owner acts as a general contractor which hires a number of subcontractors to carry
out the work (Figure 3.2). The owner should have the necessary organizational skills,
knowledge and experience in construction works so that this PDS can be successful.
Owner
Engineer
Designer
Contractor1 Contractor2 Contractor3
Workers Subcontractors
29
3.2.3 Self-Performance Method (Force Account Method)
In self-performance method, also known as force account method, owner deals with the
organization and management of construction works, thus takes the risk of construction
works (Figure 3.3). His expected benefit from this is cost minimization by not paying the
profit to the general contractor and subcontractors. However, this method requires a
permanent construction team in the owner’s organization, extensive knowledge and
experience in construction works. It is a preferred method if the owner has a continuous
construction activity that justifies employing an in-house construction team financially.
Owner
Engineer
Designer Workers
In design-build (DB), the owner contracts with a single entity which provides both the
design and construction services. Unlike the DBB scenario where the owner assigns the
design to the contractor, the DB agency has the responsibility for the design. In this
situation, the owner will call upon the DB agency to respond to and correct any design
problem that may arise during the course of construction, or following completion of the
project. A typical organization chart for DB system is shown in Figure 3.4.
Designer-Contractor
Owner or
Designer
Engineer
Workers Subcontractors
30
DB is very popular in recent years, especially for industrial type projects. It gives design
firms and contractors the opportunity to work as a team, and to deliver a quality project
on time and within budget. Design and construction are overlapped resulting in time
savings from the project completion time. For example, once foundation design is
completed, the construction may start. Fewer changes will arise during construction since
the design evolves with construction. When compared with DBB, DB has significantly
less design changes and construction cost overrun. Quality associated with DB is usually
claimed to be better than quality performance in DBB. Also, an advantage for the owner
is that the owner is in communication with one company for the responsibility of the
whole project. In this type of system, the owner is less involved with the project.
Supporters of this method claim that the owner enjoys lowest cost in shortest time. Thus,
DB can minimize many of the problems which often lead to claims in the DBB process.
One of the many advantages of DB is that the general contractor is involved early in
coordinating cost issues and structural issues with the architect. The architect and
contractor are more motivated to communicate well and work together since they are part
of the same team or venture. This decreases the risk of delay and poor constructability.
However, for DB system to be successful, owner should clearly define the scope of the
project prior to construction during design brief. The most important task for an owner is
to prepare clear performance, technical and quality criteria for the project. These criteria
will include objectives for durability, design life, operational criteria, standards of finish
and aesthetics, community and environmental standards. The next input from the owner
is conditions of contract that appropriately allocate risks and create contractual
arrangements that can accommodate a likely range of events and circumstances. In this
way, uncertainty and the potential for dispute can be minimized.
Lack of clarity in respect of the specifications in the design brief may lead to
disputes as it may be unclear whether the contractor has in fact constructed the
product described in the contract or not. The finished product may not turn out to
be what was expected.
It can be difficult for the owner to comparatively assess tender proposals
submitted by prospective contractors as proposals may differ significantly.
The total cost of project is usually not known until the construction phase.
There is a potential for contractors to affect savings and increase profit within the
lump sum contract by under-designing some aspects of the project. This may
happen as a result of the design brief which defines performance or quality
requirements inadequately.
From a practical viewpoint, the owner has significantly less control than it would
by other delivery methods.
31
3.2.5 Construction Management (CM)
Owner CM
Engineer
Designer
General
Contractor
The construction management approach has the advantage of a single party being
responsible for the entire project. Thus, an owner should make all efforts to find the most
knowledgeable, experienced manager available. To achieve the best project results under
a construction manager, there should be a strong working relationship between the owner
and the manager. Although better construction management skills (planning, estimating
etc.) and better organization may lead to significant savings, the fee for construction
manager may be too high and increase overall cost of the project. Moreover, as
construction manager does not guarantee the total cost and quality of work, client may
face with the risk of underperformance if the right selection is not made about the
construction manager.
The BOT structure was developed specifically as a way of involving the private sector in
the provision of new infrastructure. Due to lack of governmental funds to finance basic
infrastructure projects such as hydropower plants, tolled motorways, tolled crossings
(Bridges, tunnels, channels) etc., a private company is given the right to first develop and
then to operate these facilities. Thus, it is usually implemented in developing countries
where the government does not have sufficient financing to carry out infrastructure
projects. In BOT, usually, a consortium of firms (contractors, designers, financial
32
institutions, operator firms etc.) is established to finance, construct and operate the
facility for a concession period awarded by the government. Ownership of the facility is
transferred to the government at the end of the concession period, which will be of such
length as to allow the builders and financiers to recover their outlays with a return. In
some cases, government guarantees a certain amount of demand to generate agreed
minimum revenue for the organization to recover the investment costs. Although it is an
innovative PDS specifically developed to finance infrastructure projects needed in
developing countries, its success is not guaranteed. It may be sometimes difficult for the
government to find a company that may be financially strong enough to cover the project
budget. The project must be feasible so that it may attract potential investors. Thus,
government should give some guarantees to increase feasibility of projects such as
demand guarantee etc. The legal background of the BOT system has to be very strong so
that responsibilities of parties and risk allocation schemes can be clearly defined. Another
complication about this system is that the government has limited control over a facility
during the operation period by the company, which can be a very strategic project for the
country. Finally, due to the high number of parties involved, significant uncertainties
about future revenues and cost, and legal complications, BOT projects are risky
undertakings. BOOT (Build Own Operate Transfer) and BOO (Build Own Operate) are
variations of the BOT system which are developed to increase applicability of BOT
formula.
There are two general classifications of contracts used in the construction industry based
on the way in which a contractor is paid for: fixed price contracts and cost-plus contracts.
In fixed price contracts, contractors agree to construct the facility on a fixed price basis
where either the overall price (lump sum contract) or unit prices (unit price contract) are
fixed.
The unit pricing method (birim fiyat) establishes payments based on the amount of
production or quantity of works completed at a fixed price. In Turkey, in unit price
contracts, costs can be calculated by multiplying quantities with unit prices which are
published every year by the Ministry of Environment and Urban Planning. Sometimes,
33
rather than the unit prices published by Ministry of Environment and Urban Planning,
unit prices offered by the contractor are used. In case of offered unit-prices, the contractor
should accurately estimate the unit price of production and complete the job successfully
to ensure profitability.
In cost-plus-fee (maliyet artı kar) pricing (often called simply “cost-plus”), payments
for services are based on the contractor’s actual expenses plus a predetermined fee, which
is usually a percentage of the expenses. Here the contractor has the advantage that if he
carefully records all his costs, he is almost certain of a profit. On the other hand, the
enormous amount of paperwork involved can be very time-consuming, and if any
expenses are not recorded, the costs of those expenses as well as the profits may be lost.
The success of a cost-plus contract relies heavily on the good faith of the contractor.
Client should control that the contractor claims the “real costs” and does not exaggerate
the costs with the aim of earning more money. Cost-plus-fee contracts are mostly used in
negotiated bidding. Most widely used forms of cost-plus contracts are “cost-plus fixed-
fee” and the “cost-plus-percentage fee” contracts. A cost-plus contract provides a formula
for determining the fair price of the work as it is done and often sets a guaranteed
maximum price (GMP) for the project. As a result, both the contractor and the project
owner are protected. In this type of contract, only major changes in the scope of work or
the original intent of the contract results in adjustment of the GMP. Finally, although
quality of the work is claimed to be higher in cost-plus contracts, it is also known that
cost-plus may not be the most economical solution for the client.
A contract is necessary because each party has its own expectations, which sometimes
conflict with the expectations of the other party. A contractor expects a reasonable profit,
satisfactory working conditions, fair treatment and timely payment. The project owner
34
expects quality work at a reasonable cost, timely completion and fair treatment. Both sets
of expectations are based on the desire for profit. Seen from this perspective, the contract
becomes the ground on which each party tries to establish conditions in which it can
maximize its profit. For his part, the contractor wants a contract that allows him
maximum opportunities for doing a quality job at the lowest reasonable cost and for the
highest reasonable fee. The project owner, on the other hand, wants the contract to ensure
that he gets quality work but for the lowest reasonable fixed price or fee, and here is
where the potential for conflict arises. The contract recognizes that the conflict exists but
also expresses each side’s willingness to compromise for mutual benefit and to trust the
other’s fairness. It defines the business relationship and provides guidelines for dealing
with the unforeseen events that plague every project and threaten one or both parties’
profits.
Gaining an advantage begins with thoroughly understanding what the contract says and
then organizing and implementing the construction efforts accordingly (ASCE, 1988).
Despite its legal terminology, a construction contract essentially states six simple things:
Unfortunately, it is the nature of the construction process for these simple things to
become enormously complicated. Thus, contract documents must be precisely worded
and thoroughly detailed.
The term “contract documents” includes the contract for construction between the owner
and constructor, together with other documents referenced by and made a part of the
owner/constructor agreement. These documents, taken together, define the
responsibilities of each party during the construction phase. Contract documents
generally include:
35
Terms and methods of payment.
Insurance and bonds.
Contract change-order procedure.
Settlement of disputes.
Contract termination conditions.
Indemnifications.
Warranties/guarantees.
The basic definitions of various terms discussed in a contract are listed below:
Construction plans are drawings that show the location, dimensions, and details of
the work to be performed. Taken together with the specifications, they should provide a
complete description of the facility to be constructed. Types of contract drawings include
site drawings and detailed working drawings. Contract drawings are usually organized
and numbered according to specialty, such as structural, electrical, and mechanical.
Construction technical specifications provide the detailed requirements for the materials,
equipment, and workmanship to be incorporated into the project. Contract
drawings and specifications complement each other and must be used together.
Shop drawings are drawings, charts, and other data prepared by a contractor or supplier
which describe the detailed characteristics of equipment or show how specific
structural elements or items of equipment are to be fabricated and installed. Thus
they complement but do not replace the contract drawings.
A claim is a request by the contractor for a time extension or for additional payment
based on the occurrence of an event beyond the contractor's control that has not
been covered by the contract. Most claims fit into one of the following categories; injury
or damage claims, delay or disruption claims, change in conditions claims, change in
scope claims, time extension claims, termination claims and payment delay claims.
Disputes are disagreements between the contractor and owner over some aspect
of contract performance.
In general, one will have a good basic understanding of the project contract if the
following questions (MCAA, 1984) can be readily answered:
36
5. Are designers, subcontractors, suppliers, etc. involved in the project and what are
their duties about the project?
6. What permits and inspections are required by the Government? (Codes, standards,
etc.)
7. Are there any subcontractors and what are their duties?
8. What are the specific details of construction? (Special tool or equipment
requirements, potential coordination problems, feasibility of design)
9. What is the project schedule? Are there any penalty fees if the project is delayed?
10. What are the important administrative details? (Procedures for billing, approving
change orders and its estimates, accepting work, back charges, getting
compensation for delays, filing claims, etc.)
11. Who determines the project schedule and how can the schedule be modified if
there changes out of the original scope?
12. What is the procedure for changes? (Who has the authority to approve change
orders? How are changes to be billed? When are changes to be billed? When will
payments be made?)
13. What happens if something goes wrong? (Who is liable for losses due to
accidents, delays, changes? How will the amounts of claims be calculated?)
Substantial efforts by professional and industry associations have advanced the cause of
standardization of contract content, form, and language with a large body of information.
For example, as a standard form of contract, FIDIC Conditions of Contract prepared by
International Federation of Consulting Engineers, is widely used in international
construction projects.
General Specification for Construction Works describes the fundamentals that will be
applied in execution of all kinds of public construction works. This specification becomes
automatically part of the contract when the client makes an agreement with the contractor
according to Public Bidding Law (2002).
37
3.6 REFERENCES AND BIBLIOGRAPHY
1. ASCE (1988). Manuals and Reports on Engineering Practice No. 73. ‘Quality in
the Construction Project’. First Edition.
2. Bayındırlık İşleri Genel Şartnamesi, 29. 8 .1984 Tarih, 84 /8520 Sayılı Bakanlar
Kurulu Kararı, Başbakanlık Basımevi -1984, Ankara.
3. Bosch J.C.V., P.E. (1997). Comparing Project Delivery Systems, A Report
Submitted To Construction Industry Institute.
4. COBRA (2001) Conference Papers, retrieved from www.Rics-Foundation.Org
5. Genesis (2003). Selecting the Right Project Delivery System, retrieved from
www.Genesisplanners.Com
6. Gould, F. (1997). Managing the Construction Process. Prentice Hall. Upper
Saddle River, NJ.
7. Hanna, A.S. (2001). CEE 498 Class Notes, Integrated Project Estimating and
Scheduling. University of Wisconsin, Madison.
8. Harris, F. and McCaffer, R. (2001). Modern Construction Management, 5th
Edition, Blackwell Science, UK.
9. HK Highways Department Project Delivery System (2003), Volume 1, Selection
of Project Delivery Options.
10. Humphreys, K. and Wellman, P. (1987). Basic Cost Engineering. Second Edition.
Marcel Dekker Inc. New York, NY.
11. Ibbs C.W., Young H. K., Tzeyu N., and Odabasi, A. M. (2003). Project Delivery
Systems And Project Change: Quantitative Analysis, ASCE Journal Of
Construction Engineering And Management, Vol. 129, No. 4, July/August 2003,
pp. 382-387.
12. MCAA Project Managers Manual (1984). Mechanical Contractors Association of
America, Inc. Bethesda, MD.
13. Mcwhorter, V.S., and Hanson, M. E. (2000). Twenty-First Century Project
Delivery Systems. Proceedings of North American Tunneling 2000 Conference.
14. Mincks, W., and Johnston, H. (1998). Construction Jobsite Management. Delmar
Publishers.
15. Newcombe, R. (1999). Procurement as a Learning Process. Journal of
Construction Procurement, 5(2), 211-220.
16. Nunnally S.W. (1993). Construction Methods and Management. Third Edition.
Regents /Prentice Hall, Englewood Cliffs, NJ 07632.
17. Parsons Brinkerhoff Network, March (2000). Alternative Project Delivery
Systems.
18. Robertson P.A., and Associates, P.A. (1997). Newsletter. Project Delivery
System: Methods and Risks.
19. Russell, J.R. (2001). CEE 498 Notes. Construction Project Management.
University of Wisconsin, Madison.
20. Tennant, T.R. (1998). ‘Advanced Project Delivery Systems: Design-Build And
Design Delegation Insurance Issues, Presented At The American Bar Association
Forum On The Construction Industry And Section Of Public Contract Law By
Terry R. Tennant On October 16-17, 1998 At The Fairmont Hotel, Chicago, IL.
38
CHAPTER 4
4.1 INTRODUCTION
Cost estimating is an attempt to forecast the actual cost of a project. Cost estimates play
an important role for determination of the bid amount as well as development of the
project budget. Inaccurate cost estimates may lead to lost opportunities, lower than
expected returns, and unsuccessful projects. Estimating in general requires detailed study
of the bidding documents including construction drawings and specifications, a quantity
takeoff, and determination of costs. There are numerous estimating methods that could
be used depending on the project type, delivery method, and details of the drawings
available. This chapter presents only general aspects of construction estimating rather
than a very detailed discussion of estimating methods.
TYPES OF ESTIMATES
There are several classifications about the cost estimates depending on their accuracy
level, or methods being used to determine the estimated cost. In general cost estimates
could be classified into two groups; preliminary cost estimates and detailed cost
estimates. Preliminary cost estimates also sometimes named as conceptual cost estimates
are usually prepared before drawings and specifications are available and detailed cost
estimates are prepared after construction drawings and specifications are available.
According to cost estimate definitions of Construction Cost Institute (CII SD-6)
preliminary cost estimates are expected to have an accuracy range of ±10% to ±50%
depending on the level of information and estimating method being used. Detailed cost
estimates on the other hand, are expected to have an accuracy of ±1 to ±10% depending
on the type of project.
Preliminary cost estimates are usually performed at the early stages of the projects with
very limited information since drawing and specifications are not available. One of the
main reasons for having preliminary estimates is to decide about feasibility of a project.
If a project is determined as feasible based on the preliminary estimate than detailed
design, bidding, and construction stages could be initiated, therefore early estimates play
a crucial role on committing resources for further development of a project. Preliminary
estimates could also be used for evaluation of different project alternatives and also for
development of an initial project budget.
Preliminary cost estimates are not expected to be very accurate since detailed drawings
are not available and there are several uncertainties present about project cost at the early
39
stages of a project. However, a quick and reasonably accurate estimate is needed based
on the information available, especially when a feasibility decision is to be made.
Numerous techniques could be used for preliminary cost estimating. In general data of
past projects are used to develop preliminary cost estimates. A very simple method to
determine a preliminary cost estimate is to use average unit cost of similar projects such
as 250 $/ m2 for building construction, or 100 million $/km. for metro construction. Cost
estimates determined by average unit cost method are not expected to be accurate since
these estimates are very general, and are based on very limited project information.
Modeling techniques such as regression analysis method could be used to improve
accuracy of preliminary cost estimates.
Detailed estimating requires determination of the quantities and all of the costs to
complete the project. The costs to complete the project can be grouped into four
categories; material, labor, equipment and machinery, and overhead costs. A profit is
added to the total cost estimate for determination of the bidding price. Material costs
include cost of all the bulk materials such as concrete, steel, lumber, cables, as well as
cost of the mechanical and electrical items such as elevators, boilers and transformers.
Labor costs are the cost of the workers that will participate in the project such as;
carpenters, electricians, welders and helpers. Equipment and machinery costs include
expenses for the construction equipment and machinery such as cranes, trucks and
excavators. Overhead costs are the expenses that cannot be related to a specific
construction activity but rather general project expenses such as; office expenses,
mobilization and camp expenses, bond and insurance expenses.
QUANTITY TAKEOFF
The first step of detailed estimation is investigation of the bidding documents for
preparation of quantity takeoff. A quantity takeoff is a detailed calculation of quantities
for each work item that is going to be performed to complete the project. Quantity
takeoff is an important step of estimating and bidding and a complete set of bid
documents including drawings, specifications and conditions of contract are needed for
preparation of quantity takeoff accurately. Although the bid documents for a unit-price
project usually provide contractors with estimated quantities of each bid item, these are
approximate quantities and contractors should perform their own quantity takeoff not
only to check bid quantities but also to provide more detailed quantities for accurate
pricing of the project.
40
each item included. For example; for excavation and backfill m3, for formwork m2, for
concrete m3, for structural steel tons are used as a unit of measure.
At the end of this chapter quantity take-off for basic building activities are illustrated with
two examples. It is important for the quantity surveyor to visualize the drawings properly
and adjust calculated quantities for waste. As an example, when ordering concrete some
concrete may be spilled when transported from the mixer by a bucket and this waste
amount should be considered during takeoff.
MATERIAL COSTS
Once the approximate quantities of material that will be used for the project are
determined the contractor would request quotations (prices) from material suppliers and
manufacturers for all materials required. Although sometimes prices of manufacturers
may be available as a list, it is more desirable to obtain written quotations that include
specifications of the material, transportation details, time required for delivery, materials
included in the price, taxes, guarantees and terms of payment. When material costs
quoted by different manufacturers are being compared they must be brought to common
basis; for example, delivered to site including all expenses.
LABOR COSTS
Labor costs are generally classified into two groups; direct labor costs, and indirect labor
costs. Direct labor contributes physical completion of a construction task for completion
of a permanent facility. Examples for direct labor are; carpenter, electrician, concrete
finisher, welder. Indirect labor supports the completion of the project but cannot be
identified as directly working for a specific task. Examples for indirect labor are; project
manager, planning engineer, and timekeeper.
In order to estimate direct labor costs accurately the estimator must make a detailed
quantity takeoff, analyze job conditions and project schedule carefully, and also maintain
a comprehensive library of actual worker hours and labor costs from past projects. One
of the methods that is being used commonly for estimating direct labor costs is to use
average worker hours per unit quantity. For example using historical records it could be
estimated that to produce 1m2 of formwork 0.75 carpenter and 0.75 laborer hours is
needed. Once the average work hours per unit is determined for a task this could be
multiplied by the total quantities calculated to determine total worker hours, and the total
worker hours are multiplied by the hourly wages of the workers including taxes and
social security expenses to calculate labor cost. If major deviations from average job
conditions are expected average worker hours should be adjusted to reflect these
deviations.
Indirect labor costs could be estimated after staffing requirements for the project is
determined. Once the decision about the size of the indirect project staff is made using
project schedule the periods that the staff will be needed for the project could be
41
determined. These durations are multiplied by the gross salaries to determine the indirect
labor costs.
Determination of the equipment and machinery that will be used for the project and
durations that the equipment and machinery will be used are needed for estimation of
equipment and machinery costs. In order to estimate equipment and machinery expenses
accurately, early management decision must be made concerning the machinery sizes and
types and also whether existing machinery will be used or additional machinery will be
rented or purchased. Estimation of equipment and machinery expenses will be discussed
in Chapter 8.
OVERHEAD COSTS
Overhead costs are expenses that cannot be related to any specific item of work. If the
costs can be related to an item of work they should be included under the material, labor,
or equipment costs. The overhead costs are usually estimated as a percentage of total
project cost. In calculation of unit prices of Ministry of Environment and Urban Planning
the overhead expenses and profit is taken as % 25 of the cost.
The overhead costs are generally divided into two groups; general overhead costs and
project overhead costs. General overhead expenses cannot be related to a specific project
but often referred as general or administrative costs. Examples for general overhead
expenses are head office expenses, salaries of personnel at the head office, and company
legal expenses. Project overhead costs are expenses that are related to a specific project
but that cannot be related to a specific item of work. Some examples for project
overhead cost are salaries of indirect site personnel, mobilization costs, site office
expenses, project travel expenses, cost of bonds, project insurance expenses. Since most
of the project overhead costs depend on the project duration a project schedule is
necessary for calculation of project overhead expenses.
One of the critical decisions for bidding is determining the amount of profit that will be
added to the detailed cost estimate. If profit amount is too high, than the company may
not be awarded the contract but on the other hand, if profit amount is too low there may
be a risk of a loss at the end of the project instead of a profit. The profit amount depends
on several parameters including market conditions, the workload of the contractor, the
number of companies bidding for the project and contractor’s business strategy. A risk
premium called contingency may also be included in the bid amount. The contingency is
generally used to cover the uncertainties and risks involved for the bid project.
42
4.5 EXAMPLES
Example-1: Section views, normal floor column and ceiling plans of a building project
are given in Figures 4.1 to 4.5. Determine the quantities of following items:
1) Formwork for slab D302, beam K302 (between S2 and S3), and column S2
(between +3.70 to +6.50).
2) Support for ceiling formwork for Bedroom 1 and Bedroom 2 (including K301,
K313, K312, K308, K314, K305 and, K315 but, excluding roof extensions)
3) Reinforcement for column S2 between +3.70 to +6.50, excluding reinforcement
extensions from previous floor (For Ф8 rebars unit weight is 0.395 kg/m and for
Ф16 rebars unit weight is 1.578 kg/m)
4) Concrete (C20) for slab D302, beam K302, and column S2 (between +3.70 to
+6.50).
5) Exterior walls between +3.70 to +6.50 (masonry block-Gazbeton)
6) Interior walls for the normal floor. (Lintel length is 1.3 m.)
7) Interior plastering for the bedrooms and bathrooms (1.2 cm thickness).
8) Scaffolding for interior plastering of ceiling for the gallery opening.
9) Exterior plastering of wall in A1-D1 direction (between +3.70 to +6.38, excluding
roof extensions)
10) Interior painting for the bedrooms
43
1 2 3 4 5
A A
B B
B B
C C
44
BEDROOM 3
BEDROOM 2
Bathroom2
Bathroom 1
D D
1 2 A 3 4 5
49
Cum.
NO TYPE OF JOB Location Width(m) Length(m) Height(m) Void Qty. Qty. Unit
5 Exterior Walls Window 0.25 2.50 1.8 1.125 -1.125 m3
Continued Column S4 0.25 0.35 1.8 0.1575 -0.1575 0.4725 m3
C5-D5 0.25 (4.15–0.25*) 2.2 2.145 m3
*The portion of 0.25m is already included in D3-D5 Section.
C5 Extension 0.25 0.45 2.2 0.2475 m3
Window 0.25 0.45 1.6 0.18 -0.18 m3
Window 0.25 0.85 1.6 0.34 -0.34 m3
Window 0.25 0.85 1.6 0.34 -0.34 m3
Window 0.25 0.85 1.6 0.34 -0.34 1.1925 m3
Total 13.68 m3
6 Internal Wall A2-C2 3.90 2.20 8.58 m2
(Normal Floor) Column S5 0.70 2.20 1.54 -1.54 m2
Door 0.90 2.10 1.89 -1.89 m2
Lintel 1.30 0.10 0.13 -0.13 5.02 m2
C2-D2 3.80 2.20 8.36 m2
Door 0.90 2.10 1.89 -1.89 m2
Lintel 1.30 0.10 0.13 -0.13 6.34 m2
C3-D3 3.80 2.20 8.36 m2
Door 0.90 2.10 1.89 -1.89 m2
Lintel 1.30 0.10 0.13 -0.13 6.34 m2
C1-C2 3.60 2.20 7.92 7.92 m2
C3-C5 (5.10–0.35) 2.20 10.45 10.45
2--3 (BR 1) 2.40 2.68 6.432 m2
Door 0.90 2.10 1.89 -1.89 m2
Lintel 1.30 0.25 0.325 -0.325 4.217 m2
3--4 (BR 2 a) 1.50 2.68 4.02 m2
Door 0.90 2.10 1.89 -1.89 m2
Lintel 1.30 0.25 0.325 -0.325 1.805 m2
C--D (BR 2 b) (3.80–1.25) 2.68 6.834 6.834 m2
Total 48.926 m2
Interior Plastering of
7a Bedroom 1 A1-A2 3.50 2.68 9.38 m2
C1-C2 3.50 2.68 9.38 m2
A1-C1 3.90 2.68 10.452 m2
Window 1.60 2.20 3.52 -3.52 m2
A2-C2 3.90 2.68 10.452 m2
S5 Extension (2*0.15) 2.20 0.66 m2
Door 0.90 2.10 1.89 -1.89 m2
Interior Plastering of
Ceiling A1-A2-C1-C2 3.90 3.50 13.65 m2
Column S5 0.15 0.70 0.105 -0.105 m2
Total 48.459 m2
Interior Plastering of
7b Bedroom 2 C1-C2 3.50 2.68 9.38 m2
D1-D2 3.50 2.68 9.38 m2
Window (2*0.85) 1.30 2.21 -2.21
C1-D1 3.80 2.68 10.184 m2
Window 1.60 2.20 3.52 -3.52
C2-D2 3.80 2.68 10.184 m2
Door 0.90 2.10 1.89 -1.89
Interior Plastering of
Ceiling C1-C2-D1-D2 3.80 3.50 13.30 m2
Total 44.808 m2
50
Cum.
NO TYPE OF JOB Location Width(m) Length(m) Height(m) Void Qty. Qty. Unit
Interior Plastering
7c of Bathroom 1 C2-C3 2.40 2.68 6.432 m2
Door 0.90 2.10 1.89 -1.89 m2
D2-D3 2.40 2.68 6.432 m2
Window 0.50 0.60 0.30 -0.30 m2
C2-D2 2.45 2.68 6.566 m2
C3-D3 2.45 2.68 6.566 m2
Interior Plastering of
Ceiling C2-C3-D2-D3 2.45 2.40 5.88 m2
Total 29.686 m2
Interior Plastering of
7d Bedroom 3 C3-C5 5.70 2.68 15.276 m2
S8 Extension (2*0.15) 2.20 0.66
Window 0.45 1.60 0.72 -0.72 m2
D3-D5 4.10 2.68 10.988 m2
1.60 2.68 4.288 m2
Window 0.45 1.60 0.72 -0.72 m2
Door 0.90 2.10 1.89 -1.89 m2
C3-D3 1.25 2.68 3.35 m2
(3.80 – 1.25) 2.68 6.834 m2
Door 0.90 2.10 1.89 -1.89 m2
C5-D5 3.80 2.68 10.184 m2
Window (3*0.85) 1.60 4.08 -4.08 m2
Interior Plastering of
Ceiling C3-C5-D3-D5 4.10 3.80 15.58 m2
1.60 1.25 2.00
Column S8 0.15 0.60 0.09 -0.09
Total 59.77 m2
Interior Plastering of
7e Bathroom 2 C3-C4 1.50 2.68 4.02 m2
Door 0.90 2.10 1.89 -1.89 m2
D3-D4 1.50 2.68 4.02 m2
Window 0.50 0.60 0.30 -0.30 m2
C3-D3 2.45 2.68 6.566 m2
C4-D4 2.45 2.68 6.566 m2
Interior Plastering of
Ceiling 1.50 2.45 3.675 m2
Total 22.657 m2
Scaffolding for
8 Gallery Opening A3-A5-C3-C5 3.90 5.00 (5.48-1.50*) 77.61 m3
*1.50m is reserved for worker on scaffolding.
Column S6 0.15 0.70 (5.48-1.50*) 0.418 -0.418 m3
K316 & K317 0.15 (3.90-0.70) 0.48 0.2304 -0.230 m3
Total 76.962 m3
9 Exterior Plastering A1-D1 8.30 2.68 22.244 m2
of the Wall A1-D1 Window 1.60 2.20 3.52 -3.52 m2
for Normal Floor Window 1.60 2.20 3.52 -3.52 m2
Total 15.204 m2
Painting of Same as
10a Bedroom 1 Plastering 48.603 m2
Painting of Same as
10b Bedroom 2 Plastering 44.808 m2
Painting of Same as
10c Bedroom 3 Plastering 55.558 m2
51
Example-2: For the quantities calculated in Example-1 determine the cost of the
following items using 2006 unit prices of Ministry of Environment and Urban Planning
(including overhead expenses and profit).
Example-3: Typical plan and sections views of a building footing and foundation wall
are given in Figure 4.6.
a) Determine the volume of excavation for the site which has been graded to
elevation +17.9 m.
b) Determine the amount of formwork required to pour footings, walls and slab.
c) Determine the total labor and material cost of formwork. To complete 1m2 of
formwork 0.75 carpenter and 0.75 laborer hours is needed. Hourly wage for the
carpenter is 4 TL/hour and hourly wage for the laborer is 3 TL/hour. Material
cost of 1 m2 of formwork is 8 TL.
52
Figure 4.6: Plan and section views for the footing and walls
a) Excavation calculations:
The excavation is in a form of shape called prismoid. The volume of prismoid is
calculated by the formula:
Note that the calculations are made assuming that first walls are poured than slab is
poured. If slab is poured first total amount of formwork needed will be also 249.1 m2.
53
c) Formwork cost calculations:
4.6 REFERENCES
54
CHAPTER 5
One way of describing management from managers’ duties point of view can be as
“efforts made to achieve organizational goals by using technical knowledge to perform
planning and control duties, and by using human relations abilities to perform duties of
organizing and directing people”. There is not an agreed single definition of management
among management scientists, but above definition has received acceptance among the so
called classical viewers. According to this definition, planning is considered as a duty of
managers.
PLANNING
Everyone, whether good or bad, short-term or long-term, important or unimportant,
consciously or unconsciously, makes plans. Construction managers do make plans also
like everyone else.
“Trying to anticipate what will happen and devising ways of achieving the set of
objectives and targets” (Fryer, 1992).
Both definitions emphasize that in planning there are goals (objectives) that are desired
(or instructed or specified) to be realized in future, and that planning is a process during
which efforts and decisions are made to achieve the goals at the desired time in the
desired way.
55
to complete it in compliance with technical and administrative specifications.
Before going into the discussion of construction project planning, a few points will be
highlighted about planning in general.
3. Who should perform each activity and with what means? (resources)
Generally speaking, the purpose of planning is to assist the manager to fulfill his primary
function, namely, direction and control. Direction can be subdivided into execution (or
action planning) and coordination. Execution concerns the directing of the parties under
the supervision of the construction company in the implementation of the projects
56
components (work items). Execution should be understood to mean that early decisions –
the plans – become either direct assignment, or at least guide-lines for site management to
make operational decisions later on. The essential elements of how, when and who are
thus prepared for the execution of the construction project.
The second planning function is to coordinate and communicate with the many parties
involved into the realization of a construction project, i.e. owner, designer, licensing
authorities, subcontractors and suppliers, and numerous specialists and functionaries on
site and in home office. The construction technology being inherently interdependent
provides few or no “buffers”, and requires many diverse parties to work in close liaison
with each other in terms of time and / or space. Maintaining coordinated production
becomes thus a key function of construction management.
The third function of the planning is to facilitate project control which encompasses
control and forecasting. If planning establishes targets and the course to reach them,
control is the process that ensures the course of action is maintained and desired targets
are reached. Control involves measuring and evaluating performance and the taking of
corrective action when performance diverges from plans. To be effective, a control
system must be modeled closely after planning system.
information gathering
preparation of plans
information diffusion
57
Planning the →→ Gathering Preparation Diffusion of →→ Evaluation of
planning information of the information the planning
process plans process
Project Cycle
Action
updating frequency,
58
The planner further decides on
Information gathering
The next phase, information gathering, may require considerable resources. The source
material required for planning a typical construction project includes:
Contract documents
Construction technology
self-resources
Goals and constrains dictated by top management, the client, and various external
authorities regarding quality control, finance and law.
After construction has started, information regarding progress on site is also collected for
control and forecasting purposes, with emphasis on resources consumed and goals
achieved.
Preparation of plans
In the third stage, working out the plans, decisions are made based on the evaluation of
the collected information using techniques adapted to resource planning and scheduling
(e.g. site layout, temporary facilities, flow diagrams and process charts, Gantt, Line of
Balance (LOB), Critical Path Method (CPM) and Program Evaluation and Review
59
Technique (PERT)) and their respective cost implications (e.g. cash flow, break-even and
risk analysis).
Information diffusion
60
Scope of information (e.g. by entire projects or by area, comprehensive or
selective)
Content (e.g. guidelines and goals, results and status, variances and reasons,
analysis and calculations, assumptions and explanations, and remedy suggestions)
Medium (e.g. visual – paper screen, auditory – take, telephone, direct meeting)
61
5.2 PROJECT SCHEDULING
A bar chart is generally organized so that all activities are listed in a column at the left
side of the diagram. A horizontal time scale extends to the right of the list, with a line
corresponding to each activity in the list. A bar representing the progress of each activity
is drawn between its corresponding scheduled start and finish times along its horizontal
line. A simple bar chart is shown in Figure 5.2.
Bar charts are the easiest to understand and the most widely used form of planning tools.
Even when the network analysis is used, the initial work schedule is presented usually in
bar chart form.
62
CRITICAL PATH METHOD (CPM)
The CPM was developed in 1956 by the DuPont Company, with Remington Rand as
consultants, as a deterministic approach to scheduling. The CPM method is commonly
used in the engineering and construction industry. In order for a project to be scheduled
by CPM the followings have to be known:
Work breakdown structure of the project, so that each activity of the project is
determined,
Predictions about the activity durations,
Logical relations between the activities
For project management the CPM is the most commonly used network analysis
technique. The concept is simple, the computations only require basic arithmetic, and a
large number of computer programs are available to automate the work required of CPM
scheduling. There are two basic methods of constructing CPM diagrams: the arrow
diagram (activity on arrow) and the precedence diagram (activity on node). Although
both methods achieve the same results, most project managers prefer the precedence
diagram because it does not require the use of dummy activities.
63
64
activity name
i j Activity Activity
duration A Flow B
event line
Arrow Diagram Precedence Diagram
D B D F
F
B
A H
A H
C G
E C E G
Duration (D) : The estimated time required to perform an activity. The time
should indicate all resources that are assigned to the activity.
Early Start : The earliest time an activity can be started.
(ES)
Early Finish : The earliest time an activity can be finished and is equal to the
(EF) early start plus the duration
EF = ES + D
Late Finish : The latest time an activity can be finished.
(LF)
Late Start : The latest time an activity can be started without delaying the
(LS) completion date of the project.
65
Total Float : The amount of time an activity may be delayed without
(TF) delaying the completion date of the project.
TF=LETj-EETi-D
where the subscript i represents the preceding event and the
subscript j represents the following event.
Free Float : The amount of time an activity may be delayed without
(FF) delaying the early start time of the immediately following
activity.
FF=EETj-EETi-D
66
dummy are completed. The dummy does not require any time
and resource.
dummy
i j
identity
Installation of dummy
window frames
Painting of walls
RIGHT!!
Installation of
door frames
Installation of
window frames Glazing of windows
RIGHT!!
Installation of Painting of walls
door frames
67
NETWORK CONSTRUCTION
Network diagramming techniques:
Activity on Arrow (AoA)
Activity on Node (AoN)
Summary of Denotations:
A-o-A A-o-N
denotation denotation
Activity
Event none
Dummy none
Flow line none
B depends on A A B
A B
C depends on A
A&B; A
C
C
A&B starts at the
same time B B
C depends on A; A C
A C
D depends on
A&B
B D B D
C depends on A C A C
A&B;
D depends on
B D B D
A&B
D depends on A; A D A D
E depends on
A,B&C;
B E B E
F depends on C
C F C F
B depends on A;
C depends on A; C C
B and C starts at A B D
A D
the same time;
D depends on B
B&C
68
CPM CALCULATIONS
The major aims of calculation of activity times are to find the critical path, total
project time and floats of activities. As a result of forward pass and backward passes,
the activities are classified as critical and non-critical; free and total floats of the
activities are determined.
Forward Pass: In forward pass calculations, early start and early finish of each
activity are calculated. The largest early finish of all preceding activities defines the
early start of all following activities. The calculations start from the first event to the
last.
Backward Pass: In backward pass calculations, late start and late finish of each
activity are calculated. The smallest late start of all following activities defines the
late finish of all preceding activities. These calculations cannot be performed without
ending the forward pass calculations. This pass starts from the last event to the first.
Example 5.1:
In the following table you are given a set of activities, their durations and
relationships between them.
Activity Duration Dependence
(days)
A 4 -
B 7 A
C 5 A
D 4 B
E 8 -
F 8 B,C,E
G 16 -
69
Solution:
a) A-o-A diagram
B D
3
7 4
A C F
1 2 4 5
4 5 8
E
8
G
16
b) A-o-N diagram
A B D
Start
C F Finish
A C F
1 2 4 5 19
4 5 8
0 4 11 15,16,19
E 8,9,11
8
G
16
70
Backward pass calculations:
BP:15
11
11 11
B D
3
7 4
A C F
1 2 4 5 19 19
4 5 8
0 0 4 4 FP:15
11 11
16
BP:6
BP:3 FP:8 19
3 E 4 9
0 8 11
G
16
11 11
B D
3
7 4
A C F
1 2 4 5 19 19
4 5 8
0 0 4 4 11 11
E
8
G
16
Act. name
LS dur LF
71
Forward Pass:
4 11 11 15
B D
7 4
0 4 4 9 11 19 19 19
A C F Finish
0 0
4 5 8 0
Start
0
0 8
E
8
0 16
G
16
Backward Pass:
4 11 11 15
B D
4 7 11 15 4 19
0 4 4 9 11 19 19 19
A C F Finish
0 0
0 4 4 6 5 11 11 8 19 19 0 19
Start
0 0 0
0 8
E
3 8 11
0 16
G
3 16 19
72
4 0 11 11 4 15
B D
4 7 11 15 4 19
0 0 4 4 2 9 11 0 19 19 0 19
A C F Finish
0 0 0
0 4 4 6 5 11 11 8 19 19 0 19
Start
0 0 0
0 3 8
E
3 8 11
0 3 16
G
3 16 19
Example 5.2:
Carry out CPM calculations for the given A-o-A network below to find project
duration (days) and the critical path(s).
A D I
2 5
3 5 6
E
3
B J
1 4 F 6 8
4 5 4
G
6
C K
3 H 7
4 5 3
73
Solution:
3 3 8 8
A D I
2 5
3 5 6
E
0 0 4 5 10 10 14 14
3
B J
1 4 F 6 8
4 5 4
G
6 9 11
C K
3 H 7
4 5 3
4 4
74
Example 5.3:
A contractor is responsible to complete the excavation and basic construction works
(except the finish works) of a 2 story building. There is one excavator and 1 team for
each activity (R/C works, formwork, plastering, wall construction, floor covering etc.)
Following are the activities and estimated durations of these activities:
Abbreviation Activity Description Duration
(days)
EXC Excavation 5
FORMF Formwork for foundation 6
MECH Installation of mechanical & electrical conduits and 8
pipes
R/CF R/C works (reinforcement and concrete casting) for 5
the foundation
INSU Water insulation of foundation 2
FORM1 Formwork for 1st floor 8
R/C1 R/C works for 1st floor 6
FORM2 Formwork for 2nd floor 8
R/C2 R/C works for 2nd floor 6
WALL1 Wall construction in 1st floor 10
WALL2 Wall construction in 2nd floor 10
PLAS1 Plastering in 1st floor 8
PLAS2 Plastering in 2nd floor 8
FRAM1 Installation of window/door frames in the 1st floor 2
FRAM2 Installation of window/door frames in the 2nd floor 2
FLOOR1 Floor covering in the 1st floor 10
FLOOR2 Floor covering in the 2nd floor 10
CLEAN Cleaning, mobilizing 1
Required:
1. Draw the A-o-A and A-o-N diagrams
2. Perform the CPM calculations on both of the network diagrams; find the total
project time and critical path.
75
Activity Duration EST LST EFT LFT TF Critical
(days)
EXC 5 0 0 5 5 0* Yes
FORMF 6 5 7 11 13 2 No
MECH 8 5 5 13 13 0* Yes
R/CF 5 13 13 18 18 0* Yes
INSU 2 18 24 20 26 6 No
FORM1 8 18 18 26 26 0* Yes
R/C1 6 26 26 32 32 0* Yes
FORM2 8 32 32 40 40 0* Yes
R/C2 6 40 40 46 46 0* Yes
WALL1 10 32 36 42 46 4 No
WALL2 10 46 46 56 56 0* Yes
PLAS1 8 42 46 50 54 4 No
PLAS2 8 56 56 64 64 0* Yes
FRAM1 2 50 70 52 72 20 No
FRAM2 2 64 72 66 74 8 No
FLOOR1 10 50 54 60 64 4 No
FLOOR2 10 64 64 74 74 0* Yes
CLEAN 1 74 74 75 75 0* Yes
76
PART1: A-o-A diagram
3
MEC
7
EXC FORMF R/CF INSU
1 2 4 5 6
5 6 5 2 4
81
FLOOR1 15 FLOOR2
10 10
CPM Calculations: Forward Pass
13
3
MEC
8 18 20
EXC FORMF R/CF INSU
FP:52
1 2 4 5 6
5 6 5 2 64
4 FP:42
0 5 13 46
FP:11 32 40 46 56 64 64
13 FORM1 R/C1 FORM2 FRAM2
82
FLOOR1 15 FLOOR2
10 10
64
FP:50
64
CPM Calculations: Backward Pass
13 13
3
BP:24
18
MEC
8 18 18 20 26
EXC FORMF R/CF INSU
1 2 4 5 6
5 6 5 2 4 BP:36 BP:72
0 0 5 5 13 13 32 64
BP:7 32 32 40 40 46 46 56 56 64 64 64 72
83
84
PART 2: A-o-N diagram
MECH INSU
EXC
R/C1 FORM2 R/C2 WALL2 PLAS2 FRAM2
R/CF
CLEAN
FORMF FORM1
WALL1 PLAS1 FRAM1
85
FLOOR2
FLOOR1
CPM Calculations: Forward Pass
Legend
ES TF EF
Act. name
LS dur LF FP: 42 FP: 50 FP: 52
46 56 64
3 4 4 4 4 5 5 6 6 6
1 2 2 0 0 6 6 6 6 4 4 6
5 1 FP: 66
8 0
3 FORM2 R/C2 WALL2 PLAS2 FRAM2
INSU FP: 20 74
MECH
FP: 11 26 8 6 1 8 2 7 7
8 2 0 4 5
13 2 3
1 1 6 2 CLEAN
3 8 FP: 60
0 5 R/C1 1
R/CF 64
6
86
6 7
EXC 5 4 4
1 2
5 8 6 FLOOR2
1 3 4 4 5 5 5
5 FORM1 2 2 2 0 0 2 1
1
0
8 WALL1 PLAS1 FRAM1
FORMF
1 8 2
6 0
5 6
0 0
FLOOR1
1
0
CPM Calculations: Backward Pass
3 4 4 4 4 5 5 6 6 6
1 2 2 0 0 6 6 6 6 4 4 6
5 1
8 0 WALL2
3 FORM2 R/C2 PLAS2 FRAM2
MECH INSU
3 8 4 4 6 4 4 1 5 5 8 6 7 2 7 7 7
5 8 1 2 2 2 2 0 0 6 6 0 6 6 4 2 4 4 5
3 4 6 2 3 BP: 72
1 1 6 2 CLEAN
3 8
64
0 5 R/C1 7 1 7
R/CF
87
4 5
2 6 3 6 7
EXC 1 5 1 6 2 4 4
3 8 1 2 BP: 36
0 5 5 BP: 24 8 6 FLOOR2
32 3 4
BP: 7 5 1 18 4 5 5 5
FORM1 2 2 2 0 0 2 6 1 7
5 1
4 0 4
1 8 2 WALL1 PLAS1 FRAM1
FORMF
8 6
3 1 4 4 8 5 7 2 7
7 6 1 6 0 6 6 4 0 2
3 BP: 46 BP: 70
1
3
46 56
54 5 6
0 0
FLOOR1
5 1 6
4 0 4
Calculation of total floats:
3 0 4 4 0 4 4 0 5 5 0 6 6 8 6
1 6 2 2 0 0 6 6 6 6 4 4 6
5 0
8 0 WALL2
FORM2 R/C2 PLAS2 FRAM2
MECH INSU
3 8 4 4 6 4 4 1 5 5 8 6 7 2 7 7 0 7
5 8 1 2 2 2 2 0 0 6 6 0 6 6 4 2 4 4 5
3 4 6 2 0 3
1 0 1 6 2 CLEAN
88
3 8
0 0 5 R/C1 7 1 7
R/CF 4 5
2 6 3 6 0 7
EXC 1 5 1 6 2 4 4
3 8 1 0 2
0 5 5 8 6 FLOOR2
1 3 4 4 4 4 5 5 2 5
5 2 FORM1 2 2 2 0 0 0 2 6 1 7
1
WALL1 4 0 4
FORMF 1 8 2 PLAS1 FRAM1
8 6
3 1 4 4 8 5 7 2 7
7 6 1 6 0 6
3 6 4 0 2
1
3
5 4 6
0 0
FLOOR1
5 1 6
CP: EXC-MECH-R/CF-FORM1-R/C1-FORM2-R/C2-WALL2-PLAS2-FLOOR2-CLEAN 4 0 4
5.3 REFERENCES
1. Harris, F., and McCaffer, R. (2001). Modern Construction Management, 5th Edition,
Blackwell Science, UK.
2. Fryer, B.G. (1997). The Practice of Construction Management, 2nd Edition, Blackwell
Science, UK.
3. Oberlender, G.D. (1993). Project Management for Engineering and Construction,
McGraw-Hill, USA.
4. Pilcher, R. (1992). Principles of Construction Management, 3rd Edition, Mc-Graw
Hill International Series, UK.
5. Ackoff, R.L. (1970). A Concept to Corporate Planning, Wiley-Interscience, USA.
89
CHAPTER 6
MANAGING QUALITY
In everyday usage, the word “quality” is usually related with excellence or durability. In
quality management however, quality means those features of a product, i.e. goods or
services, which meet customer needs and thereby provide customer satisfaction. This
definition implies freedom from deficiencies – i.e. from errors that require doing work
over again (rework) or otherwise result in customer dissatisfaction. Quality implies
“fitness for purpose” - that the product works for the purpose for which it was intended.
A long-standing quality definition was “conformance to specification” however this
definition can be in error, as customer needs may include many things not found in
product specifications. On some occasions it may be extremely difficult for the customer
to express his actual requirements.
QUALITY OF PROCESSES
Quality assurance (QA) has the objective to provide the client with the quality of work
required without the need for clients checking during the process. A customer for a car
does not insist on checking the assembly of the car, for example. This objective is
achieved by documenting what processes are performed and how they are accomplished,
by self-checking that each process is completed correctly and finally by creating records
of the processes. The policy of recording the processes undertaken, together with the
checking and recording of procedures, provides the customer with the assurance that the
company is aiming to achieve an acceptable standard of quality. Although 'satisfying the
client' is the most important objective, the essence of QA is primarily to address 'getting it
right first time' in order to avoid unnecessary costs to the contractor.
90
Management of quality normally involves three steps (Harris and McCaffer, 2001):
Every contractor may have his own quality system practiced at work but by the help of
the standards, quality is understood easily and applied more efficiently by creating
uniformity. Companies are being persuaded to adopt quality management systems in
order to meet the demands of customers in a globalized market (Chini and Valdez, 2003).
The most established and used international quality management standard is the ISO
9000 Standard, which is widely adopted by a large number of countries around the world.
The frame of reference for quality assurance is the ISO 9000 set of standards. The
emergence of the ISO 9000 Quality Systems standard greatly increased the interest in
formalized quality and certification. The role of ISO has also been important in
coordinating the various national systems (Euronorm EN, TS, etc.) (Nee, 1996). ISO
9000 registration, or certification, is increasingly essential for anyone wishing to supply
large corporations or to tender for public contracts. One idea about registration is that
money can be saved on inspectors by simply demanding ISO 9000 from suppliers (Harris
and McCaffer, 2001).
There are special features in the construction industry that limit the implementation of the
ISO 9000 standard. The following are some of these features:
91
The organizational structure of a construction company varies depending on the
nature of the project, while the same structure in a manufacturing company is
almost unchanging. This affects the smoothness of communication and interface
between the responsible individuals.
Turnover of manpower in construction is higher than in manufacturing, which
affecting the precision of long-term plans.
Construction projects are very complicated and their execution may take years.
(Phenol, 1994)
There are also advantages of implementing the ISO 9000 to a construction company,
which are:
A possible disadvantage of ISO 9000 is that registration may become the goal in itself.
To be certified as operating to the ISO 9000 standard is now virtually seen as essential in
today’s construction industry, many companies has set up QA systems merely to register.
Many clients will not do business with companies not certified to ISO 9000. ISO 9000
currently includes three main quality standards, as seen in Figure 6.1:
92
ISO 9000:2000
Figure 6.1: Structure of the ISO 9000 Standard (adapted from Nee, 1996)
ISO 9001 presents requirements, while ISO 9000 and ISO 9004 present guidelines. ISO
9004 is recommended as a guide for organizations whose top management wishes to
move beyond the requirements of ISO 9001, in pursuit of continual improvement of
performance. However, it is not intended for certification or for contractual purposes.
All of these are process standards, not product standards.
Planning
Receive tender documents; perform tender review; and prepare QA
submission
On award of contract undertake a contract review and set up site team
Prepare project quality plan and submit for approval
Conduct suppliers and sub-contractors assessment
Place sub-contracts including QA conditions where appropriate to work
package. Include requirement for documentation submissions, approvals and
records
Receive detailed quality plans from sub-contractors for approval prior to start
of works
Site work
93
Prepare detailed quality plans for own work
Prepare inspection and test plans with 'hold points', etc. to monitor work
packages and for approval prior to works
Perform goods inwards inspection
Undertake plant inspection
Control work on site against quality plans, inspection checklist, etc.
Audits on- and off-site according to audit schedule
Ongoing supplier and sub-contractor evaluations
Generate records as construction proceeds, e.g. filled-out inspection sheets
Monitor off-site work (against detailed quality plans)
Hand-over / completion
Mark up drawing to as-built state
Prepare handover packages and submit
Figure 6.2: Contractors Quality Actions (adapted from Harris and McCaffer, 2001)
Some often used documents in construction site quality management are mentioned in the
following text.
METHOD STATEMENTS
Method statements are frequently seen documents in construction QA. Method statements
are the equivalent of a standard operating procedure (SOP), however SOP’s are often
used for works having a repetitive character. SOPs may apply to many functions in a
construction firm, for example workflow in the site or head office. However, few site jobs
in construction are completely identical and contractors are therefore required, as part of
their QA submittals, to prepare site-specific method statement for major tasks, such as
excavation, concreting, cladding, painting etc. The method statement serves to explain
that proper procedures and best practice will be followed. In many cases a method
statement is required for a very specific sub-task, such as concreting in extreme weather
conditions, early striking of formwork or also where extraordinary construction methods
are used.
94
The execution steps are normally explained in plain language. As an example for an
excavation job:
The method statement must emphasize those details that are critical for quality. For
example, a method statement for concreting works must stress the issues of joints - e.g.
exposure of aggregate in joint prior to adjacent casting - temperature control, curing
conditions, formwork level and plane, and so on.
Inspection and test plans (ITPs) are lists with check-points of a specific work tasks. It
may or may not also function as record of work performed, in some cases the ITP will
just refer to the relevant quality document or record. In-process activities that cannot be
verified after the fact by inspection must have stringent in-process controls by qualified
personnel to assure conformance to specifications. Construction has numerous such
examples and many features of a construction project are hidden by subsequent
construction, and these are often the most vital. Examples are the concrete reinforcement
or sealing of concrete walls prior to backfill. In such cases check items may be hold
points; i.e. points where production cannot continue before the item is checked off on the
inspection sheet, a typical example is reinforcement before concrete is poured. A variety
of the hold point is the witness point, meaning that the work item cannot continue unless
the controlling engineer is witnessing the work.
Table 6.1: Example Excerpt of Inspection and Test Plan for a Deep Excavation
Inspection
methods and Criteria of Documentation
Item Inspection When Who
reference acceptance (QD)
papers
Earthwork
Construction In
Excavation supervisor, All Site
sequence accordance RIW
plan Site excavations engineers
drawings to drawing
personal
Plant Earthwork All Site
Plant dept. Site diary
requirements supervisor excavations engineers
Site All Site
Dewatering FOR/MS/1303 60 m3/h Site diary
engineer excavations engineers
95
NON-CONFORMANCE REPORTS
ISO 9000 requires documented procedures for handling of non-conforming product, and
the NCR is the typical instrument in construction. The objectives for such control are to
prevent the customer receiving nonconforming product and to optimize costs of further
processing. NCR forms often require several signatures, and the NCR work flow can be
very bureaucratic, having a negative bearing on progress. It is therefore important to have
a simple NCR system. The accept-as-is solution to an NCR can be chosen when the non-
conformance is a deviance from the specification, but extremely costly to rectify and not
a major breach of design intent. The disposition must therefore be made by someone with
authority, and the owner’s representative must have the final signature.
Quality assurance was not adapted as easily in construction as in manufacturing and other
sectors. Within traditionally procured construction problems experienced in
implementing quality assurance often occur at interface points in the building process,
notably at the interface between the client and designer and the interface between the
designer and the contractor. Some reasons for the project failing to meet with the client's
needs may include the following (Nee, 1996; Griffith, 1990):
Client and designer may misunderstand the details of the brief with regard to the
building's purpose, performance or appearance.
The designer may perceive quality in a different way to the client. The designer
may, through misunderstanding or ignorance, misinterpret the objectives
regarding quality specified by the client.
The construction may be insufficiently financed to build to the quality levels
desired by the client. Failure to balance cost with quality at the brief and design
96
stages can lead to a reduction in the level of quality achieved during construction
through re-specification of some items to an inferior standard.
The time schedule may be strained, putting at risk the desired quality level
through hasty work.
The designer may design the building that cannot be built to the required levels of
quality due to buildability issues not being addressed.
The contractor may fail to understand what the desired standards of quality are. If
the design stage is completed before appointing the contractor, as in the case of
'traditional' procurement, there is no opportunity for the designer to effectively
communicate desired quality levels to the contractor first hand. The designer has
to rely on the clarity of drawings and specifications and upon the contractor's
correct interpretation of these when construction proceeds. The builder does not
always know the 'real' standards before commencing work on site.
The contractor may not be able to build to the desired quality standards due to a
mismatch between the design and construction systems. The contractor may not
be sufficiently competent to undertake the task or may misunderstand the
requirements through inadequate communication of the design concept.
Construction quality assurance has in certain instances been confined to
‘permanent works’, i.e. excluding the contractor’s temporary works. In many
types of construction, this is a very are artificial division. QA must include all
aspects vital to the permanent works, and temporary works must not escape QA.
Design requirements may not be communicated simply and effectively to the
operative at the workplace.
Life cycle, operation and maintenance cost of the project are not properly
addressed. This can result from an inadequate brief making the building too
expensive to operate and maintain.
In Quality Management, the most often used definition of Quality Costs are the costs
associated with preventing, finding, and correcting defective work. It is the cost of “not
getting it right the first time” (Juran, 1999).
97
Cost of conformance:
(a) Prevention
Quality planning
Process control
Design and development of quality information equipment
Quality training and work force development
Product design verification
Systems development
Other prevention costs
(b) Appraisal
Test and inspection of purchased materials
Laboratory acceptance testing
Laboratory and other measurement services
Inspection, testing, checking labor, setup for test and inspection
Test and inspection and material and minor quality equipment
Quality audits
Outside endorsements
Maintenance and calibration of quality information test and inspection equipment
Product engineering review and shipping release
Field testing
Cost of Non-conformance
These are not the only ways of organizing costs. In construction some of these do not
apply, and certain costs are often seen in construction or project work in general:
98
It should be kept in mind that the more effort spent on prevention means that the less
failure costs will arise. In quality environment this principle is summarized by the general
rule of thumb: “Ounce of prevention is worth a pound of cure” On the other hand
spending too much money on the prevention and appraisal costs decreases the failure but
increases the total cost of quality. Figure 6.3 indicates conceptually the trade-off between
failure cost and prevention/appraisal costs. The figure indicates the optimal level of
quality efforts, at which the total quality costs are minimized.
Total cost of
quality
COST
Minimum
100% 0%
Defects
QUALITY LEVEL Defects
Figure 6.3: Cost versus Quality Level – classic view adapted from Brown and Kane,
1984
An important non-conformance cost is revenue loss (lost sales) due to poor quality – this
is a ‘hidden’ cost because it is not easily measured. Costs associated with poor quality are
identified and measured for three reasons:
To quantify the size of the quality problem to help justify an improvement effort
To guide the development of that effort
To track progress of improvements
Quality cost data should not be used for ‘reporting’ purposes; publication of costs alone
has shown to solve no problems. Quality-related costs should be used to support a quality
improvement program and to ‘sell’ the quality efforts to higher management by using the
language of money.
99
improved. The management representative shall oversee the quality system and report on
its performance to management for review and improvement. There must not be any
conflict of interest if the representative has other duties than quality, and typically the
Quality Manager will report directly to the General Manager.
This management representative can be entitled the Quality Manager, Quality Assurance
Manager, QA/QC Manager or similar. In a construction firm, however, there is usually a
project official with quality-related duties assigned to the quality of each project. This
official will usually be entitled QA Manager or similar.
6.6 REFERENCES
1. Harris, F., and McCaffer, R. (2001). Modern Construction Management, 5th Edition,
Blackwell Science, UK.
2. EN ISO 9001:2000, Quality management systems–Requirements, International
Standards Organization.
3. Nee, P. (1996). ISO 9000 in Construction, John Wiley & Sons, Inc.
4. Griffith, A. (1990). Quality Assurance in Building, Macmillan.
5. Bennett, F.L. (1996). The Management of Engineering, Wiley & Sons, Inc.
6. Juran, J.M. (1999). Juran’s Quality Handbook Fifth Edition, McGraw-Hill.
7. Brown, F.B., and Kane, R.W. (1984). Quality cost and profit performance, in:
Campanella, J. Editor, Quality costs: Ideas and application, Milwaukee, WI: ASQC
Press.
8. Bubshait, A.A. and Al-Atiq T.H. (1999). “ISO 9000 Quality Standards in
Construction”, Journal of Management in Engineering, Vol. 15, No. 6,
November/December 1999, pp. 41-46.
9. Chini, A.R. and Valdez, H.E. (2003). “ISO 9000 Implementation in Turkish Industry”,
Journal of Management in Engineering, Vol. 19, No. 2, April 2003, pp. 69-77.
10.Phenol, L.U. (1994). “ISO 9000: Implementation Problems in the Construction
Industry”, Quality World, American Society of Quality Control, May, pp. 2-4.
100
11.Chew, Y.S., and Chai, L.N. (1996). ISO 9002 in Malaysian Construction Industry.
McGraw Hill Book Co.
12. http://www.iso.org/iso/en/ISO 9000-14000/ISO 9000/ISO 9000index.html
13. http://www.baldrige.nist.gov/
14. http://www.efqm.org/model_awards/eqa/intro.htm
15. http://www.juse.or.jp/e/deming/index.html
16. http://www.kalder.org.tr
17. http://www.bath.ac.uk/management/agile/summary/summary.html
101
CHAPTER 7
Safety is engineer’s liability. It is a liability that can be shared but never completely
delegated, a responsibility for the lives and well-being of the workers themselves.
Safety affects the bottom line (AGC, 1989). Accidents are expensive. They incapacitate
skilled workers, disrupt construction activities, raise the company's insurance and
workman's compensation rates, and can place the company in legal threat. On the other
hand, a good safety record and safe working conditions boost employee morale and
therefore contribute to increased productivity. Safety is also the law (MCAA, 1984).
All construction firms need a carefully planned and directed safety program to minimize
accidents and ensure compliance with the safety regulations. However, no safety program
will be successful without the active support of top management. Job-site supervisors
have traditionally neglected safety in their haste to get the job done on time and within
budget. Only when supervisors are convinced by higher management that safety is
equally as important as production, will the benefits of an effective safety program be
achieved. An effective safety program must inspire a sense of safety consciousness in
every employee (Nunnally, 1993).
Although there are many ingredients in a comprehensive safety program, some of the
major elements are listed below.
102
7.3 COMPANY POLICIES
MCAA (1984) states that an effective project safety program begins with a written
company safety program that provides:
A company should base its safety program not on one source of safety information
but on a variety of sources, such as:
Current laws
Company records and experience
Industry safety materials such as Jobsite Safety Manuals.
Where possible, one individual in the company should be appointed Safety Engineer
and charged with responsibility for staying informed on new safety developments and
laws, reviewing company policies and recommending changes, and enforcing company
safety policies on the jobsite.
Each project should have a written safety policy that addresses the job's particular
safety situations. The policy should be prepared by the project team based on the
company's normal safety program. It should also include pertinent parts of the safety
program established by the project owner and/or the general contractor.
To develop an inclusive safety policy, the project team must obtain copies of the
owner's and/or general contractor's safety policies and review it carefully to identify:
103
Specific safety requirements and procedures related to the job
Necessary safety procedures that are lacking or unclear in the existing policies
Some companies have a designated Safety Engineer. Others rely on their project
managers to assign responsibilities for safety on each individual project. Regardless of
which situation holds true in your company, the duties of the responsible person are
essentially the same, namely to (MCAA, 1984):
Provide and maintain safety-related equipment such as: first aid kits, hard
hats, gloves, goggles, helmets, respirators, and other personal protection
equipment
Regularly inspect tools and construction equipment, including extension
cords, and tag worn or damaged items for return to the company shop for
repair or replacement
Regularly inspect personnel and material handling equipment and facilities,
particularly hoists and rigging, scaffolding and man lifts, storage areas and
traffic paths
Enforce and verify lock-out/tag-out procedures
Regularly check the condition of special items such as fire extinguishers and
acetylene and oxygen cylinders, valves, hoses and other accessories
Ensure that mechanics know how to use the tools needed for the job,
instructing new mechanics in the proper use of bask tools and all mechanics in
the proper use of specialized tools
Monitor the use of all tools, construction equipment, and jobsite facilities
Enforce safety procedures for special conditions such as working inside tanks,
enclosures and other confined spaces
Monitor compliance of company personnel and subcontractors with all
company and project-specific safety policies
Correct or have corrected all safety violations and hazardous conditions that
are the responsibility of the contractor
Report to the project manager or other project authority all unsafe practices
by other trades and hazardous conditions that are the responsibility of the
general contractor or the owner to correct
Educate field personnel in safety matters, making sure that every employee
receives a copy of and clearly understands all company, owner/general
contractor, and the safety regulations
104
Post safety information, as required, including the safety regulations,
emergency telephone numbers, hand signals for directing cranes, special
project safety notices, and the address and telephone number of the company
office where the government-required illness and accident reports are stored,
and
Conduct weekly safety meetings to cite safety procedures not being followed
in the field, introduce new safety policies, and review procedures for handling
emergency situations.
It has been found that most serious construction accidents involve construction equipment
operations, trench and embankment failure, fall from elevated positions, collapse of
temporary structures and formwork, or the failure of structures under construction. The
safety regulations are quite specific in many of these areas, and special management
attention should be devoted to the safety of these activities.
Lumber, used formwork and other material lying around a work area increase the
likelihood of falls and puncture wounds. Different types of safety procedures to be
directed by the safety engineer and/or project manager are discussed below:
Utilize guides or signalmen when the operator's visibility is limited or when there
is danger to nearby workers. Backup alarms or guides must be used when
equipment operates in reverse.
Exercise extreme caution and comply with safety regulations when operating near
high-voltage lines. In case of contact with a high-voltage line, the operator should
attempt to move the equipment enough to break contact.
Use care when operating equipment on side slopes to prevent overturning.
When operating cranes, be extremely careful not to exceed safe load limits for the
operating radius and boom position. Electronic load indicators are available.
Do not allow workers to ride on equipment unless proper seating is provided.
Park equipment with the brake set, blade or bowl grounded, and ignition key
removed at the end of work.
When hauling heavy or oversized loads on highways, make sure that loads are
properly secured and covered if necessary. Slow-moving and over-sized vehicles
must use required markings and signals to warn other traffic.
Take positive action to ensure that equipment under repair cannot be accidentally
operated.
Utilize blocking or other positive support when employees must work under
heavy loads supported by cables, jacks, or hydraulic systems.
105
Ensure that any guards or safety devices removed during equipment repair are
promptly replaced.
Shut down engines and do not allow smoking during refueling.
7.6.3 Excavations
The sides of excavations must be properly shored or sloped to the angle of repose
to prevent cave-ins in accordance with safety regulations.
Avoid the operation of equipment near the top edge of an excavation because this
increases the chance of slope failure. The storage of materials near the top edge of
an excavation, vibration, and the presence of water also increase the chance of
slope failure. When these conditions cannot be avoided, additional measures must
be taken to increase slope stability. If workers are required to enter the excavation,
no spoil or other material may be stored within the close edge of the excavation.
Ensure that workers are not allowed under loads being handled by excavators or
cranes.
Watch out for buried lines and containers when excavating. Possible hazards
include toxic and flammable gases, electricity, and collapse of side slopes due to
sudden release of liquids. If a gas line is ruptured and catches fire, get personnel
and flammable material away from the fire and have the gas turned off as quickly
as possible. Do not attempt to extinguish the fire because an accumulation of
unburned gas poses a great threat for environment.
106
Special caution should be exercised in high-rise concrete construction. Forms
must be of adequate strength and properly braced. The rate of pour must be
maintained at or below design limits. Shoring and re-shoring must be adequately
braced and not removed until the concrete has developed the required strength.
Marine or over-water construction operations present all of the usual construction hazards
plus additional hazards posed by the marine environment. These additional hazards
include drowning, slippery surfaces, height hazards, as well as weather and wave action.
Some of the major safety precautions that should be taken are listed below.
Unless workers can safely step onto vessels, a ramp or safe walkway must be
provided. Access ways must be adequately illuminated, free of obstructions, and
located clear of suspended loads.
Working areas should have nonslip surfaces, be maintained clear of obstructions,
and be equipped with adequate handrails.
Workers on unguarded decks or surfaces over water must wear approved
lifejackets or buoyant vests. Life rings and a rescue boat must also be available.
Workers high above a water surface must be protected by safety belts, safety nets,
or similar protective equipment.
7.7 REFERENCES
1. AGC Guidelines for a Basic Safety Program (1989). The Associated General
Contractors of America, Inc., Washington, D.C.
2. Akçalı, Ünal (1998). Yapı Yasaları ve Şartnameleri Dökümü. Yapı İşlerinde İşçi
Sağlığı ve İş Güvenliği Tüzüğü. 6. Baskı, Ankara.
3. Feld, J. (1968). Construction Failure. New York: Wiley.
4. Manual of Accident Prevention in Construction (1992). The Associated General
Contractors of America, Inc., Washington, D.C.
5. MCAA Project Managers Manual (1984). Mechanical Contractors Association of
America, Inc. Bethesda, MD.
6. Nunnally, S.W. (1993). Construction Methods and Management. Third Edition.
Regents /Prentice Hall, Englewood Cliffs, NJ 07632.
107
CHAPTER 8
8.1 INTRODUCTION
Construction can also be defined as making a facility, on land, for the use of people using
the materials of nature, raw or processed, by the help of manpower and equipment. In the
definition, the word equipment has been used in general to mean also machines and
plants. A few examples of construction machines, equipment and plants are given below.
It should be noted that plant is also meant to be the collection of several machines,
equipment and plants. In this chapter, the words machines, equipment and plants will be
used to mean the same thing.
Why should machines be used? What are the points to consider to be economical when
machines are used in construction?
Should standard or special machines be used? What about maintenance of machines?
108
6. Maintaining the high standards required particularly in the context of structural
engineering works (concrete plant).
Economical considerations
To be economical, machines and equipment must be fully utilized and not left standing
idle since they will have to be paid for if hired or they will cost if owned even if when
they are non-productive. Full utilization of plant is usually considered to be in the region
of 85% of on-site time, thus making an allowance for routine, daily and planned
maintenance. Maintenance of machines needs to be carried out to avoid, as far as
practicable, machine breakdowns which could disrupt the construction program. Many
pieces of plant work in conjunction with other items of plant such as excavators and
haulage trucks, therefore a correct balance of such plant items must be obtained to
achieve an economical result. In Table 8.1, purchase costs (initial brand new purchase
price) of some of construction equipment are given.
LOADERS
Type HP Bucket (m3) A ($)
WA320-1 150 2.5 140,000
WA420-1 204 3.7 165,000
WA500-1 291 4.0 210,000
WA600-1 415 5.4 258,000
EXCAVATORS
Type HP Bucket (m3) A ($)
PC200-5 123 0.80 152,000
PC300-5 207 1.32 187,000
PC400-5 276 1.3-2.2 360,000
PC650-3 404 3.8-4.5 800,000
MOTOR GRADERS
Type HP Blade Size A ($)
GD611A-1 155 3710x645x19mm 259,000
GD621A-1 155 3710x645x19mm 283,000
GD661A-1 180 3710x645x19mm 307,000
109
Maintenance considerations
On large contracts where quite a number of plant items are to be used, it may be
advantageous to employ a skilled mechanic to be on site to carry out all the necessary
daily, preventive and planned maintenance tasks together with any running repairs which
could be carried out on site. If there are many different types of machines and equipment,
it might be necessary to set up a workshop.
110
8.2 ESTIMATING HOURLY COST OF EQUIPMENT
Whether the equipment is owned or hired, the hourly cost of the equipment should be
known for the purpose of:
pricing,
consciousness (it means that unnecessary idleness of the equipment is not
allowed), and
cost control.
In general, the hourly cost of a machine is broken into two main components as fixed cost
and operating costs. Fixed cost consists of those costs that occur whether the machine is
used or not, on the other hand operating costs occur when the machine is used.
Breakdown of the main components may change from company to company or from
country to country. In this Chapter, the practice of Turkish Ministry of Environment and
Urban Planning will be explained. In Table 8.2, the cost components given by Peurifoy
and Schexnayder (2002) are also indicated to compare with the Ministry’s cost
breakdown.
111
Table 8.2: Hourly Cost Components by Turkish Ministry of Environment and Urban
Planning and by Peurifoy
6. Insurance
- Fuel - Fuel
- Motor oil, lube oils, grease, etc. - Motor oil, lube oils, grease
- Manpower - Repairs
- Tires
C. Manpower Costs
112
PROCEDURE PRACTICED BY TURKISH MINISTRY OF ENVIRONMENT
AND URBAN PLANNING
1) Depreciation Cost:
This is the cost contribution of initial price (cost) of machine due to the loss in value of
the machine due to time.
Turkish practice is to use Straight Line Depreciation with no salvage value, therefore:
Hourly Depreciation Cost = A/(Nn)
where,
A = Initial purchase price of the equipment,
N = Depreciation life of the equipment
n = Working hours per year
For some equipment, N and n values used by the Ministry given in Table 8.3.
2) Spare Parts
Spare parts cost is assumed to be 53% of depreciation cost:
Hourly Spare Parts Cost = 0.53 A/(Nn)
4) Investment Cost
Investment cost is considered because money spent to purchase the equipment could be
made use of in other ways to earn money, for example could be deposited in a bank.
113
Either capital recovery or average value per year consideration can be employed.
Ministry’s practice is to use average value of equipment for interest amount calculations.
Average value per year can be calculated directly from the following expression:
Average Value per year= A (N+1) / (2N)
or can be numerically evaluated as shown in Table 8.4 for an equipment purchased for
75,000 TL with a depreciation life of 5 years and no salvage value, (Depreciation per year
=75,000/5 = 15,000 TL)
114
Hourly Fixed Cost
Hourly fixed cost is given by the summation of the expressions expressed above for fixed
cost components.
Hourly Fixed Cost= A/(Nn) + 0.13A/(Nn) + 0.53A/(Nn) + 0.08 A(N+1)/(2Nn) + 0.02A/n
Hourly Fixed Cost= [A/(Nn)] [1+ 0.13 + 0.53 + 0.04 (N+1) + 0.02 N]
Hourly Fixed Cost = (1.7 + 0.06N) [A/(Nn)]
Caution: Use this expression when all data is same as Ministry’s data, for example if
i=12% expression will not hold.
1) Fuel Cost
Fuel consumption is directly related to engine power of the machine.
for a diesel engine = (0.0855 kg/HP) per hour
for a gasoline engine = (0.114 kg/HP) per hour
where HP is engine power in Horse Power.
3) Workmanship Cost
i) Hourly paid labor is paid for the hours they actually worked
Cost = Number of Hours Actually Worked x Hourly Rate
ii) Monthly paid personnel (operators, foremen, etc.) are paid for 240 hours but
actual hours worked in a month is usually 167 hours (2000 hours per year/12
months), the remaining hours are weekends, holidays and paid vacations.
115
Hourly rate calculation of monthly paid personnel is:
Hourly rate = Total Cost of Salary / 240 hours
This rate is valid if the person works actually 240 hours per month. Therefore,
actual hours worked must be adjusted to the 240 hours by which the hourly rate is
established.
Actual hours worked in a year = n given in Table 8.3
Hours in a year paid by monthly salary = 240 hours * 12
Therefore, Adjustment factor for actual hours worked = 240 * 12 / n
or directly obtain hourly rate of operator as = (12 x salary) / n
Example 8.1
In this example, rate calculation of a 1 cu.yd. excavator is given according to the
procedure of the Ministry Environment And Urban Planning. Calculations are shown in
Table 8.5 in the same way as it is shown in the Price Analysis Book of the Ministry
(Bayındırlık ve İskan Bakanlığı, 2006). Prices are for the year 2006. For comparison, cost
rates are also given in US dollars.
116
Table 8.5: Hourly Rate Calculation of The Excavator: Pos. No. 05.501
EXAMPLE 8.1
Pos.no.03.501/1 EXCAVATOR (3/4-1&5/8) cu.yd. diesel engine 125HP
year = 2006
A= 169,713.00
i= 0.08
N= 8.00 (Table 8.3)
n= 2,000.00 (Table 8.3)
HP = 125.00
1$ = 2.20
Annual Annual Hourly
Depreciation A/N 21,214.125 10.607
Spare Parts 0.53 * A/N 11,243.486 5.622
Maintenance 0.13 * A/N 2,757.836 1.380
Investment Cost i*(N+1)*A/2N 7,637.085 3.819
Freight, Unloading 0.02 * A 3,394.26 1.697
∑ Fixed Cost 46,246.792 23.125
by fixed cost factor (1.7+0.06N)/(Nn) *A 1.3625*10-4 *A 23.123
*Operator works “n” hours as Machine Adjustment factor for operator = (240x12)/2,000=1.44
**Helper works independently however serves for three Machines Adjustment factor for helper = 1/3 = 0.3333
117
Example 8.2
In this example, hourly rate calculation of a wheel loader is shown for year 2002 in Table
8.6 where the tires cost is included in the initial purchase price A.
Table 8.6: Hourly Rate Calculation of The Wheel Loader: Pos. No. 03.521
EXAMPLE 8.2
Pos.no.03.521 LOADER WITH TIRES 1.5 cu.yd. diesel engine 80HP
yr= 2002
A= 26,190.00
i= 0.08
N= 5.00 (Table 8.3)
n= 2,000.00 (Table 8.3)
HP = 80.00
1$ = 2.20
Annual Annual Hourly
Depreciation A/N 5,238.00 2.619
Spare Parts 0.53 * A/N 2,776.14 1.388
Maintenance 0.13 * A/N 680.94 0.341
Investment Cost i*(N+1)*A/2N 1,257.12 0.629
Freight, Unloading 0.02 * A 523.80 0.262
∑ Fixed Cost 10,476.00 5.238
by fixed cost factor (1.7+0.06N)/(Nn) *A 0.0002 *A 5.238
*Operator works “n” hours as Machine Adjustment factor for operator = (240x12)/2,000=1.44
**Helper works independently however serves for three Machines Adjustment factor for helper = 1/3 = 0.3333
118
Example 8.3
Tires are considered separately
Same loader as in example 8.2, but tires are taken separately to see how much it effects
the hourly cost.
A = 26,190 TL
At= cost of tires = ~2,600 TL
Nt = life of tires = 2 years
nt = 2,000 hours per year
Maintenance and repair of tires = 0.15 (At / Nt),
where (At / Nt) is depreciation of tires
Transportation of tires = 0.05 (At / Nt)
119
8.3 EXCAVATING EQUIPMENT
8.3.1 INTRODUCTION
Excavation is an important work item in construction works. For example, there is
excavation in road, airport, dam, building constructions, etc. Some of the excavated
material is sometimes left near-by the excavation area for back-fill such as in foundation
or trench excavation. But most of the time, all of the excavated material is to be
transported (hauled) to another place such as fill area or dump area.
120
3. Method of excavating,
4. Job conditions,
Excavating and loading conditions
Large, open quarry situation, well-drained floor, trucks can be spotted on
either side of the machine,
Muddy floor will delay the movement of trucks
The terrain of the natural ground, uniformly leveled; the height of cut always
close to optimum,
The cut is narrow; no room for truck to come on the side of the machine,
the angle of swing is too large
Haul road conditions, not affected by climatic conditions
5. Management conditions
Maintenance of equipment
Availability of spare parts
Haul-road condition
Loading area layout
Haul-unit sizing and number
Competency of field management
Project housekeeping (keeping good records of equipment operations)
121
The downward swing of a hoe dictates usage for excavating below the running gear. The
boom of a shovel swings upward to load; therefore, the machine requires a material face
above the running gear to work against.
Bulk pit excavation: large area, large volume, excavating equipment stands inside the
area, excavates the faces (e.g. foundation excavation of a large building) – front
shovel, loaders and hauling equipment
Limited area, vertical excavation (e.g. trench excavation, small channel) – excavators
or backhoes
122
Backhoe
Selecting an Excavator
Two main factors, which should be taken into account when selecting an excavator, are
the cost per cubic meter of excavated material and the job conditions under which the
excavator will operate. The main factor, of course, is the cost but sometimes a more
powerful excavator is needed for the hard job conditions even if it becomes costly.
123
Power shovels are more specialized compared to backhoes. Shovels are mostly utilized in
large excavation.
In this lecture notes, the output of backhoes will be discussed since these equipment are
more known in Turkey.
BACKHOE PRODUCTION
The components of a hydraulic excavator are illustrated in Figure 8.2. In this machine,
the boom and dipper arms are raised and lowered by hydraulic cylinders. In addition, the
dipper is pivoted at the end of the dipper arm so that a wrist-like action is provided.
When dipper is filled, the dipper is curled up to reduce spillage, and the bottom is raised
and swung to the unloading position. The load is then dumped by swinging the dipper up
and away from the machine.
The backhoe is widely utilized for trenching work. In addition to excavating the trench, it
can perform many other trenching functions, such as laying pipe bedding, placing pipe,
pulling trench shields, and backfilling the trench. In trench excavation the best measure of
production is the length of trench excavated per unit of time. Therefore, a dipper width
should be chosen which matches the required trench width as closely as possible. For this
reason, dippers are available in a wide range sizes and widths. Side cutters are also
124
available to increase the cutting width of dippers. Other suitable backhoe applications
include excavating basements, cleaning roadside ditches, and grading embankments.
The size of an excavator is indicated by the size of the bucket, expressed either in cu.yd
or in m3. Depending on the manufacturer, the bucket size is either given for struck
capacity or heaped capacity or both, though usually it is the heaped capacity used in
output estimation calculations.
Standard Bucket Size: range from 3 8 cu.yd (0.285 m3) to 2 1
2 cu.yd (1.9 m3) but may
be as large as up to 5 to 6 m3.
Struck Capacity: The volume actually enclosed by the bucket with no allowance for the
bucket teeth is the struck capacity.
Heaped Capacity (qh): The maximum volume of the material which can be held in the
bucket without spillage (allowance for the bucket teeth is also considered). Depending
upon rating standard, the heaped volume is given either for a repose angle of 1:1 or 2:1.
Fill Factors (kd): Rated heaped capacities represent a net section bucket volume;
therefore they must be corrected to an average value by the characteristics of the material
being handled. These corrections suggested by the manufacturers are known as “fill
factors” or “dipper factors” which will be designated by kd as the dipper factor of the
shovel (See Table 8.7).
It should be mentioned that the material in the bucket after being excavated is in loose
form. That is to say the volume of the material before excavation is not same as the
volume after it is excavated due to swelling of the material. One must be careful in
excavation calculations with the form of the material. The volume of material before
excavation is referred as in-place or bank-measure (bm), on the other hand the volume
after excavation is referred as loose. For example, a typical clay of 100 m 3 (bm) in-place
volume will measure 135 m3 loose volume after excavation due to swelling (See Table
8.8).
125
Vl = ks * Vbm = 1.35 * 100 Vloose = 135 m3
Vbm= 100 m3
126
number of trucks, a good supervisor, bonuses or incentives for personnel do considerably
affect the production and, forms the basis to apply an efficiency factor.
Type of Material & Machine Size Cs & Maximum Digging Depth (Table 8.9)
Calculate Depth Ratio (%) = Actual Average Depth of Cut / Maximum Depth of Cut
* 100
Depth Ratio (%) & Angle of Swing Swing-Depth Factor (kd) (Table 8.10)
Hence, knowing angle of swing and depth ratio, from Table 8.10 correction factor kd can
be picked up.
ke = correction due to job and management conditions efficiency; it will be found from
estimated working time in an hour for the specific job and management conditions.
3600 3600 c
Ql = qh kd kd ke = qh k d ke where ct = s
cs ct kd
127
The volume of an excavation job is usually calculated by bank-volume.
Vb = volume of material in bank-form
ks = swelling factor of the material ( conversion from loose to bm )
Loose Volume (Vl) = Bank Volume * Swelling Factor
Vl = Vb * ks volume after swelling and ks >1
If the hourly output of equipment is required to be calculated in bank-form, either the
bucket capacity of the shovel or output in loose measure should be converted into bank-
measure using swelling factor. For example for the bucket,
qb = capacity of bucket in bank-measure
qh = qb ks and
qb = (1 / ks) qh
Example 8.4
A ¾ cu. yd backhoe will be used to excavate 3,980 m3 of earth (average) in bm. Average
depth of cut is about 3.5 meter and angle of swing is about 120°. For job and management
conditions, 45 minutes working time is estimated per hour. Determine how many hours it
will take to finish this job if backhoe works 8 hours per day.
Solution:
Bucket capacity: qh = ¾ * 0.76 = 0.57 m3
Dipper factor: kd = (0.85+1.10)/2 = 0.975 from Table 8.7
Standard cycle time: cS = 18 seconds from Table 8.9 for earth and ¾ cu. yd.
Maximum depth of cut: dmax = (4+6)/2 = 5 m average from Table 8.9 for earth and
¾ cu. yd
Depth ratio: dr = (d/dmax) * 100 = (3.5/5) * 100 = 70%
Swing-depth correction kd = 0.94 from Table 8.10 for dr=70% and 120°
Job and management efficiency correction ke = 45/60 = 0.75
Finally substituting the values in output expression:
3600
Ql = qh kd kd ke
cs
128
* 0.94 * 0.75 78.4 m 3 hr loose
3600
Ql 0.57 * 0.975
18
Qb = 78.4 / 1.25 where 1.25 is the swelling factor, ks, for earth (Table 8.8)
Qb = 62.72 m3/hr (bm)
Daily output = 62.72 * 8 = 501.76 m3 (bm)
Hence,
No of work-days needed to finish the job= 3,980/501.76= 7.93 work-days 8 work days
Dumping Area
t dumping
Excavation Area
t hauling = d / vh
t return = d / vr
t loading = nct * ct
t spotting
129
Then, output of a truck in one hour is:
Output of Truck (Qt) = Capacity of truck * No of cycles/hour * Efficiency
60
Qt = Vt k t k et (loose)
t ct
On the other hand, the output of a backhoe is:
3600
Ql = q h k d k e (loose)
ct
Number of Trucks (Ntr) = Output of Backhoe / Output of Truck
If same size of trucks are used, then number of trucks needed ( Ntr ) is:
Ql q h k d 3600 t ct k e
Ntr = =
Qt Vt k t ct 60 k et
1 3600 t ct k e
hence, Ntr equation simplifies to N tr
nct ct 60 k et
Truck Loading Time (tl) = Number of cycles needed to load the Truck * Cycle Time
of Backhoe
nct ct
tl nct ct (in seconds) or t l (in minutes)
60
In estimating the truck loading time, it is reasonably assumed that while the shovel is
loading the truck, which is about 3 to 6 minutes, the shovel works with 100% efficiency.
In other words, it is not expected that for example, the operator will stop for a break to
have a cup of coffee or the rain will start all of a sudden in the middle of loading or the
machine will break suddenly. Therefore, only angle of swing and depth of cut are to be
considered in estimating the cycle time.
t l 60 1 ct
Then, nct and then Ntr is:
ct nct t l 60
130
ct 3600 t ct k e
N tr
t l 60 ct 60 k et
t ct k e
N tr , if truck cycle time is expressed in components then,
t l k et
tl t h t d t r t s k e
N tr
tl k et
The number of trucks expression simplifies to
th td tr t s
N tr 1 if ke = ket
tl
That is to say, if job and management efficiency of the backhoe is same as those of the
trucks which usually is.
Example 8.5
An excavation of 16,500 m3 (bm) is to be made for the foundation excavation of a
building in 3 weeks assuming 6 workdays per week and 10 hours working time per day. It
is expected that during excavation 1.5 workdays will be lost due to bad weather
conditions.
The excavation will be done in dry clay (hard) with an average depth of cut of 3 meter.
Angle of swing is about 75°. Estimated working time in an hour is about 51 minutes.
a) Determine the size of the backhoe if only one backhoe will be used?
b) If distance to dump area is 7.5 km, determine the number of trucks for: Truck
capacity=12 m3 (loose), vh=30 km/hr, vr=60 km/hr, ts=2 min., td=3.5 min. Truck
efficiency and dipper factor are same as those of the shovels.
c) Calculate the equipment cost and unit cost of excavation if hourly costs are 40 TL for
the selected shovel and 15 TL for the trucks.
Solution:
a) Determine the size of the excavator:
16,500
Required Hourly Output (bm) 100 m3 hr (bm)
(3 6 1.5) 10
131
ks = 1.35 (Table 8.8)
Required Hourly Output (loose) = 1.35*100 = 135 m3/hr (loose)
i) Try 1 cu. yd. backhoe
qh = 1*0.76 = 0.76 m3
0.75 0.95
kd 0.85
2 (Table 8.7)
cs = 23 seconds (Table 8.9)
dmax = (4+6)/2 = 5 m (Table 8.9)
Ratio of depth, dr = 3/5 * 100 60%
kd = (1.16+1.05) / 2= 1.105 for depth ratio=60% and =75° (Table 8.10, by linear
interpolation)
ke = 51/60 = 0.85 (job and management conditions are expressed with working time in an
hour)
then,
3600
Ql (0.76 0.85) 1.105 0.85 95 m 3 hr (loose )
23
Q1 Required output=135 m3/hr
3
ii)Try 1 cu. yd. shovel
4
qh = 1.75*0.76 = 1.33 m3
0.75 0.95
kd 0.85 (Table 8.7)
2
cs = 28 seconds (Table 8.9)
dmax= (5.5+7.5)/2 = 6.5 m (Table 8.9)
ratio of depth, dr = 3/6.5 * 100 = 46%
kd = 1.21 – [(1.21-1.16)/20*(46-30)] = 1.17 for depth ratio=46 and =75° (Table 8.10,
linear interpolation)
ke = 51/60 = 0.85
then,
3600
Ql (1.33 0.85) 1.17 0.85 145 m 3 hr (loose )
28
Ql Required output=135 m3/hr
132
3
Select 1 cu. yd. shovel
4
Days needed to finish the job:
Qb = 145/1.35 = 107.407 m3/hr (bm)
Daily output = 107.407 * 10 = 1074. 07 m3
No. of workdays needed = 16500/1074.07 =15.36 take 16 work-days
3
b) No of trucks needed for 1 cu. yd. shovel:
4
th td tr ts
N tr 1 can be used in this case since ke=ket.
tl
th = 7.5 / 30 * 60 = 15 minutes
td = 3.5 minutes (given)
tr = 7.5 / 60 *60 = 7.5 minutes
ts = 2 minutes (given)
tl = nct * ct (truck loading time=no. of cycles needed to load * cycle time of shovel)
Vt k t 12 0.85
nct 9.023 cycles are needed
q h k d 1.33 0.85
and
ct = cs / kαd = 28 / 1.17 = 23.93 seconds
tl = (9.023 * 23.93)/60 = 3.60 minutes
15 3.5 7.5 2
N tr 1 8.78 Take 9 trucks
3.60
Alternative solution for number of trucks:
3600
Ql = q h k d k e (loose)
ct
3600
Ql (1.33 0.85) 1.17 0.85 145 m 3 hr (loose )
28
60
Qt = Vt k t k et (loose)
t ct
tct = tl + th + td + tr + ts = 3.60 + 15 + 3.5 + 7.5 + 2 = 31.6 min
133
60
Qt = 12 0.85 0.85 16.46 m3/hr (loose)
31.6
Ntr = Ql / Qt = 145 / 16.46 = 8.81 Take 9 trucks
c) Cost calculations:
The equipment must work 16 work-days and must stay idle 1.5 work-days. Therefore, the
idle staying cost of equipment is needed. Since manpower is paid during this idle time,
fuel and oil costs should not be considered. For this kind of equipment, it can be seen
from the equipment data that fuel and oil cost is about 35% to 45% of the total cost. So
the cost of equipment when idle can be taken as about 60% of the total cost.
Hence, total cost of equipment:
When worked for 16 work-days = 16*10 (1*40 + 9*15) = 28,000 TL
When idle for 1.5 work-days = 1.5*10*0.60 (1*40 + 9*15) = 1,575 TL
Total cost of equipment = 29,575 TL
Unit cost of excavation is usually calculated for (bm) measure. Then,
Since 16,500 m3 (bm) of excavation work is done,
Unit cost of excavation = (29,575/16,500) = 1.79 TL/m3 (bm).
8.4 REFERENCES
1. Bayındırlık ve İskan Bakanlığı (2006). İnşaat Birim Fiyat Analizleri.
2. Nunnally, S.W. (2003). Construction Methods and Management, 6th edition,
Pearson Prentice Hall, USA.
3. Peurifoy, R.L., and Schexnayder, C.J. (2002). Construction Planning, Equipment
and Method, 6th edition, McGraw-Hill, USA.
134
Table 8.3: Hourly and Yearly Depreciation Periods of
Various Construction Machines
135
Table 8.7: Bucket (Dipper) Fill Factors for Backhoes
136
Table 8.9: Standard Cycle Time (CS) of Backhoes (In Seconds)
Average 18 23 30
Hard 23 28 36
Maximum Digging
4-6 5.5-7.5 7.5-9
Depth (In Meter)
Note: Cycle time picked up from Table 8.9 is modified by dividing it with the swing-
depth factor obtained in Table 8.10
137