02 O&M of Trans
02 O&M of Trans
Age
MAITENANCE SCHEDULES
A. TRANSFOEMERS AND REACTORS.
Note: Insulation resistance measurement, tan δ of bushings, winding resistance at all taps to
be carried out once before expiry of warranty and then to be continued as per schedule.
Vibration measurement for reactor to be carried out initially after 3 months and 6 months
after commissioning and then to be continued as per schedule.
FRA at factory and during pre-commissioning is preferable to serve as base signature.
(ii) Shutdown activities
1 BDV, ppm of OLTC Diverter Switch compartment oil ( Less frequently if operations Y
are not more)
2 External cleaning of radiators Y
3 Cleaning of oil bushings Y
4 Checking of auto starting of cooler pumps and fans Y
5 Marshaling boxes of transformer/reactor
(i) Cleaning of Marshaling boxes of transformer/reactor and OLTC Y
(ii) Tightening of terminations Y
(iii) Checking of contacts , space heaters, illumination etc., Y
6 Maintenance of OLTC driving mechanism Y
7 Checking of all remote indications and top up oil in pockets, if required Y
8 Electrical checking/testing of pressure relief device, Buchholz relay, Y
OLTC surge relay/ checking of alarm/ trip and checking / replacement of the gaskets
of the terminal box
9 checking/testing of Buchholz relay by oil draining Y
10 Frequency response analysis SOS
11 Tan δ measurement of bushings Y
12 Recovery voltage measurement SOS
Causes of failure of power transformer(CIGRE survey)
Cause % of failures
Design 36
Manufacturing Problem 28
Material Defects 13
Poor maintenance 5
Lightning surges 4
Short circuits 2
Winding 29
Terminal 29
Tank and di-electric fluid 13
Magnetic circuit 11
Other accessories 5
Causes of failure of power transformer(Indian utilities)
Cause % of failures
Design defects 35.7
Manufacturing Problem 28.6
Loose winding and Results in inter turn or inter disc Proper sizing for keeping winding
improper sizing short circuit under clamping condition
Burrs on lamination Results in local short circuit and Burr free condition to be ensured by
heating good manufacturing practices
Burrs on spacers and Results in damaging conductor Burr free condition to be ensured by
blocks insulation good manufacturing practices
Bad brazed joints Damage the conductor Adopt good brazing procedures
insulation and winding may fail
Metallic parts leftover May cause partial discharge Better house keeping to be ensured
during manufacture
Insulation surface Results in insulation failure Cleanliness to be ensured
contamination
All metal components not Partial discharge may start and All metal components are to be
earthed oil quality may get affected properly earthed and this is to be
added in check list
Bad and porous welding Results in oil leakage Surface cleanliness to be ensured and
of transformer tank adopt good welding procedures
Improper drying process Winding and insulation are not Extensive drying and oil impregnation
fully stabilized due to moisture process should be strictly followed as
leading to failure per voltage class
Failure due to Defective materials
Poor quality Insulation failure, copper Maintain oil parameters as per relevant
sulphide formation standards (IS-1866)
Bare copper for Formation of oxidation and Provide enamel coating or paper
connection sludges covering on bare copper
Failure of magnetic circuits
There have been failure of transformers due to overheating of core and
core burning, failure of core insulation and core assembly getting loose,
slipping of stampings and coming in contact with tank bottom. To
overcome the above problems separate provision for core earthing and
core fixing, earthing through bushings is being to. This facilitates
monitoring of core leakage current, if any, and in ascertaining that core is
not getting multiple earth and also healthiness of core board insulation.
On-load tap changers are the second largest reason for trouble in power
transformer after short circuit. The defects in OLTC are of the following
type:
Burning of transition resistance
Burning and damage of rollers and fixed contacts.
Misalignment of the tap changer assembly.
Error in time sequence operation
Defect in tap changing driving gear, i.e. mal-operation of limit switches
and step-by-step contactors, etc..
Some of the failures due to defective design
Failure of yoke bolt in insulation Causes local short circuit in the Insulated yoke bands preferred
lamination resulting in intense or yoke bolt insulation should
local eddy currents be class ‘B‘ insulation or higher
High flux density in core Causes large amount of force at Flux density should not exceed
the time of switching and 1.9 tesla at maximum operating
repeated switching damage voltage
winding insulation
Narrow oil duct in winding Results in improper cooling and Adequate duct from point of
damages insulation effective cooling
Improper transportation Results in more loss and more Adjust the transportations so
heating that all conductors have equal
reactance
Inadequate clearance between May result in short circuit Provide adequate clearance as
phases per voltage class
Clamping ring nor properly May fail during short circuit Thickness of clamping ring
designed condition should be designed such as to
withstand short circuit forces
Insufficient bracing of leads May fail during short circuit Proper calculation of radiators
condition is necessary
(n) Oxidation stability of inhibited oil Minimum 0.08 % by Not essential IS 1866-2000
mass and maximum
: Anti-Oxidant additive content 0.4% by mass
Dissolved gas analysis (DGA)
Typical rates of gas increase for Power Values in Milliliters per
Transformers day
Hydrogen (H2 ) <5
Methane (CH4 ) <2
Ethane (C2 H6 ) <2 IEC 60599-1999
Ethylene (C2 H4 ) <2 See Note below
Acetylene (C2 H2 ) < 0.1
Carbon Monoxide (CO) < 50
Carbon di-oxide (CO2 ) < 200
Equations to calculate the rate of gas increase as per IEC 60599-1999
ANNUAL MAINTENANCE PLAN
Scheduled Shutdown Maintenance Activities
YES NO
ANNUAL MAINTENANCE PLAN
Scheduled Shutdown Maintenance Activities
(To be maintained at substation/TL-office)
YES NO
Types of Faults
CONDITION MONITORING
Decrease in DP - reduction in
mechanical strength
Drying of old insulation - brittleness
increases
Pressing of aged insulation - insulation
damage
CONDITION ASSESSMENT OF
POWER TRANSFORMER
BUSHINGS
i. Typical defects and failure mode
ii. Test tap
iii. Danger due to tap connection not properly earthed
iv. Corrosion of threads on tap connection cap causes
high resistance arcing
v. Moisture absorption by test tap
1. Economic
Adaptive Maintenance
Reduction of Maintenance personnel
Minimum period of outage
Minimum cost of outage
2. Safety
Reduction of risk by early warning
Timely technical input
Less stress on service personnel
3. Technical
Optimum use of operation
Optimum use of systems
Registration of system problems for future action
Better correlation of testing & symptoms
Up gradation of standards for tests
Life extension & planned replacement
• Tests on Oil
Physical
Chemical
Electrical
D.G.A
• Tests on Transformer
• Insulation resistance / Polarization index
• Winding resistance
• Magnetic balance test
•Tan delta and capacitance measurements on
transformer winding and bushings
• Recovery voltage measurement
• Frequency response analysis
• Partial Discharge Test-Electrical &
• Acoustic Methods
• Radio inter frerenceTest
RVM MEASUREMENT
• Humidity content
Test method:
Chemical decomposition
Partial Discharges
of oil and paper
The gases generated inside the transformers are
hydrogen and hydrocarbon gases.