MS Project Lab 1 - CONS0009
MS Project Lab 1 - CONS0009
MS Project Lab 1
In this lab session, students will do the following tasks:
After you complete all the lab tasks, ask your tutor to check your work and award you the mark
out of 5. Make sure you always keep a copy of your work.
Outlining a project
Tasks A, B, C, D, E, & F are Major Tasks - MS Project calls these SUMMARY TASKS
The other Tasks are Minor Tasks - MS Project calls these SUBTASKS
“Outlining a project” is merely the process of dividing the project into Major Tasks and Minor
Tasks.
Preliminary - Prepare Gantt Chart columns for entering Task Information, etc.
1. Load MS PROJECT 2016: Start/ All Programs/Project 2016
1
Name your project:
in File /Info/Project Information/Advanced Properties
Title = HOUSE PROJECT IN SYDNEY + Your zID
Manager = Your name.
Click “OK”.
2
3. By default, there should be seven columns called:
Indicators (i)
Task Name
Duration
Start
Finish
Predecessors
Resource Names
3
[SHORTCUT – Select column / right click mouse / Insert Column]
/Top Tier/None
/Middle Tier/Units = weeks
/Bottom Tier/Units = days.
Left align the week commencing dates (all weeks commence on Mondays).
4
Using the Gantt Chart View, enter the Tasks for Building a House
Note: MS PROJECT will calculate all the task Start Dates and End Dates,
using the Durations that you enter.
5. Enter the Tasks, Durations, and Predecessors by double clicking the rows.
Type all the tasks into the columns of the Gantt Chart. (excluding the comment)
5
Note:
To promote a task to a summary task
1. Select the tasks directly below the task that you want to make a summary task.
2. On the Task tab, in the Schedule group, click the Indent Task button.
Click the “indent” arrow from the tool bar to make a task become “sub-task”.
You achieve this by connecting the Summary Tasks (only) together [using Predecessors/ use
the Summary task ID].
Then you connect the Subtasks together (independently of, and ignoring the Summary Tasks)
[using Predecessors use the Subtasks ID as in the table above].
6
To switch several tasks from manual to automatic task scheduling
1. Select the manually scheduled tasks you want to change.
2. On the Task tab, in the Tasks group, click the Auto Schedule button.
To change the default scheduling mode that Project applies to all new plans
1. On the File tab, click Options, and then in the Project Options dialog box, click
the Schedule tab.
2. In the “Scheduling Options For This Project” box, click All New Projects, and then
in the New Tasks Created box, click Auto Scheduled.
3. Click OK.
7
6. Critical Path
7. Set the Project Start Date = The date that is one week earlier.
Project / Project Information / Start Date = the date that is one week earlier
(You can write down the date here__________)
Check that all Tasks have moved back one week, note the finish date.
Any tasks with fixed dates will not change when the project date is changed. Task with fixed
dates will appear on the “Indicator” column.
You could specify fixed dates for a task:
Change in Task, Gantt Chart view / Format/double click Task/Task Information / Advanced:
“Constraint Type = Start no earlier than”, or other options.
After you had a try, change it back to“Constraint Type = As soon as possible” to remove fixed
date.
8
8. Insert progress information
In Task, Gantt Chart view/ click on the task name you want to record progress
1. In the Task Name column, select the task for which you want to record a percent
complete value.
2. On the Task tab, in the Schedule group, click the 25%, 50%, 75%, or 100%
Complete button.
OR
1. In the Task Name column, select the task for which you want to record a percent
complete value.
2. On the Task tab, in the Properties group, click Information.
The Task Information dialog box opens.
3. On the General tab of the dialog box, enter the Percent Complete value you want.
Enter the following tasks progress (percentage complete and note the difference)
9
9. Set the Current Date, for the “Time Now” vertical line
The “Time Now” vertical line is shown on Bar Charts.
[After the Project has started, and when actual progress has been input for some of the Bars.]
11. Use the Drawing palette, to place Text comments on the Bar Chart
In Task, Gantt Chart view/Format/ Drawing / Text Box :
Place a Text Box with “Time Now = (Date of today)” and an arrow pointed to the red line.
10
12. Printing Layout
Display your name, PC System Date and Time in the Gantt Chart Legend.
Set the Legend to display:
Project Title: &[Project Title]
Date/Time: &[Date] &[Time]
Student: &[Manager]
select Project Title, Date, Time and Manager Name from the “General” pull
down list and click Add. (Note: & is a “pointer”, so “&[Date]” will displace
the current date, while “Date” will display the text Date.) Click “Ok” to
complete.
11
Suppress printing of Blank Pages, by
File / Print / Page Setup / View
Print Blank Pages = de-select.
14. Ask your tutor to check your work and award marks.
You are also required to save a copy by yourself (email yourself or save on a USB drive)
as the copy on the lab computer may be removed by the system admin staff.
----------------------------------------------------------------------
12