0% found this document useful (0 votes)
29 views4 pages

Project Scheduling

The document outlines a project schedule for construction tasks, detailing specific tasks, their durations, and start dates from January to May 2024. Key tasks include external walling, suspended slab erection, and various stages of column casting and steel fixing. The schedule provides a timeline for each task, indicating when they are set to begin and their expected duration.

Uploaded by

noah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views4 pages

Project Scheduling

The document outlines a project schedule for construction tasks, detailing specific tasks, their durations, and start dates from January to May 2024. Key tasks include external walling, suspended slab erection, and various stages of column casting and steel fixing. The schedule provides a timeline for each task, indicating when they are set to begin and their expected duration.

Uploaded by

noah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Mode Task Name Duration Start Jan 28, '24 Feb 4, '24 Feb 11, '24 Feb

rt Jan 28, '24 Feb 4, '24 Feb 11, '24 Feb 18, '24 Feb 25, '24 Mar 3, '24 Mar 10, '24
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1
2 External walling 15 days
3 200mm Thick walling at 3m 5 days Fri 2/2/24
4 Reinforcement fixing and shuttering for 3 days Thu 2/8/24
5 columnscolumns
casting 1 day Wed 3/13/24
6 Steel fixing for beams at walls 3 days Wed 2/14/24
7 shutterings for beams at walls 2 days Wed 2/14/24
8 casting conc for beams 1 day Sat 2/17/24
9
10 Suspended slab - Gallery&Staircase 16 days
11 Erection of formwork to slabs 7 days Mon 2/19/24
12 steel fixing to beams 5 days Wed 2/28/24
13 steel fixing to slabs 3 days Tue 3/5/24
14 casting concrete to slabs 1 day Fri 3/8/24
15
16 External walling 84 days
17 200mm Thick walling at +6m 5 days Mon 2/19/24
18 Reinforcement fixing and shuttering for 3 days Sat 2/24/24
19 columns
casting columns 1 day Wed 2/28/24
20 Steel fixing for beams at walls 3 days Thu 2/29/24
21 shutterings for beams at walls 2 days Sat 3/2/24
22 casting conc for beams 1 day Tue 3/5/24
23 200 mm thick walling at + 9m 5 days Thu 3/7/24
24 Reinforcement fixing and shuttering for 3 days Thu 3/14/24
25 columnscolumns
casting 1 day Fri 3/15/24
26 Steel fixing for beams at walls 3 days Sat 3/16/24
27 shutterings for beams at walls 2 days Mon 3/18/24
28 casting conc for beams 1 day Wed 3/20/24
29 200mm thick walling at +9m 5 days Fri 3/22/24
30 Reinforcement fixing and shuttering for 3 days Fri 3/29/24
31 columnscolumns
casting 1 day Wed 4/3/24
32 Steel fixing for beams at walls 3 days Thu 4/4/24
33 shutterings for beams at walls 2 days Mon 4/8/24
34 casting conc for beams 1 day Wed 4/10/24
35 200mm thick walling at + 12m 5 days Thu 4/11/24
36 Reinforcement fixing and shuttering for 3 days Tue 4/16/24
37 columns
casting columns 1 day Fri 4/19/24
38 Steel fixing for beams at walls 3 days Sat 4/20/24
39 shutterings for beams at walls 2 days Mon 4/22/24
40 casting conc for beams 1 day Wed 4/24/24
41 200mm thick walling at +14.19m 5 days Fri 4/26/24
42 Reinforcement fixing and shuttering for 3 days Fri 5/3/24
columns
Task Project Summary Manual Task Start-only Deadline

Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress

Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Mode Task Name Duration Start Jan 28, '24 Feb 4, '24 Feb 11, '24 Feb 18, '24 Feb 25, '24 Mar 3, '24 Mar 10, '24
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
43 casting columns 1 day Wed 5/8/24
44 Steel fixing for beams at walls 3 days Thu 5/9/24
45 shutterings for beams at walls 2 days Sat 5/11/24
46 casting conc for Rng beams 1 day Tue 5/14/24
47
48 Site Handover 1 day Fri 5/17/24

Task Project Summary Manual Task Start-only Deadline

Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress

Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
4 Mar 17, '24 Mar 24, '24 Mar 31, '24 Apr 7, '24 Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Project Summary Manual Task Start-only Deadline

Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress

Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
4 Mar 17, '24 Mar 24, '24 Mar 31, '24 Apr 7, '24 Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Project Summary Manual Task Start-only Deadline

Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress

Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4

You might also like