Project Scheduling
Project Scheduling
rt Jan 28, '24 Feb 4, '24 Feb 11, '24 Feb 18, '24 Feb 25, '24 Mar 3, '24 Mar 10, '24
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
1
2 External walling 15 days
3 200mm Thick walling at 3m 5 days Fri 2/2/24
4 Reinforcement fixing and shuttering for 3 days Thu 2/8/24
5 columnscolumns
casting 1 day Wed 3/13/24
6 Steel fixing for beams at walls 3 days Wed 2/14/24
7 shutterings for beams at walls 2 days Wed 2/14/24
8 casting conc for beams 1 day Sat 2/17/24
9
10 Suspended slab - Gallery&Staircase 16 days
11 Erection of formwork to slabs 7 days Mon 2/19/24
12 steel fixing to beams 5 days Wed 2/28/24
13 steel fixing to slabs 3 days Tue 3/5/24
14 casting concrete to slabs 1 day Fri 3/8/24
15
16 External walling 84 days
17 200mm Thick walling at +6m 5 days Mon 2/19/24
18 Reinforcement fixing and shuttering for 3 days Sat 2/24/24
19 columns
casting columns 1 day Wed 2/28/24
20 Steel fixing for beams at walls 3 days Thu 2/29/24
21 shutterings for beams at walls 2 days Sat 3/2/24
22 casting conc for beams 1 day Tue 3/5/24
23 200 mm thick walling at + 9m 5 days Thu 3/7/24
24 Reinforcement fixing and shuttering for 3 days Thu 3/14/24
25 columnscolumns
casting 1 day Fri 3/15/24
26 Steel fixing for beams at walls 3 days Sat 3/16/24
27 shutterings for beams at walls 2 days Mon 3/18/24
28 casting conc for beams 1 day Wed 3/20/24
29 200mm thick walling at +9m 5 days Fri 3/22/24
30 Reinforcement fixing and shuttering for 3 days Fri 3/29/24
31 columnscolumns
casting 1 day Wed 4/3/24
32 Steel fixing for beams at walls 3 days Thu 4/4/24
33 shutterings for beams at walls 2 days Mon 4/8/24
34 casting conc for beams 1 day Wed 4/10/24
35 200mm thick walling at + 12m 5 days Thu 4/11/24
36 Reinforcement fixing and shuttering for 3 days Tue 4/16/24
37 columns
casting columns 1 day Fri 4/19/24
38 Steel fixing for beams at walls 3 days Sat 4/20/24
39 shutterings for beams at walls 2 days Mon 4/22/24
40 casting conc for beams 1 day Wed 4/24/24
41 200mm thick walling at +14.19m 5 days Fri 4/26/24
42 Reinforcement fixing and shuttering for 3 days Fri 5/3/24
columns
Task Project Summary Manual Task Start-only Deadline
Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress
Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1
ID Task Mode Task Name Duration Start Jan 28, '24 Feb 4, '24 Feb 11, '24 Feb 18, '24 Feb 25, '24 Mar 3, '24 Mar 10, '24
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
43 casting columns 1 day Wed 5/8/24
44 Steel fixing for beams at walls 3 days Thu 5/9/24
45 shutterings for beams at walls 2 days Sat 5/11/24
46 casting conc for Rng beams 1 day Tue 5/14/24
47
48 Site Handover 1 day Fri 5/17/24
Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress
Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 2
4 Mar 17, '24 Mar 24, '24 Mar 31, '24 Apr 7, '24 Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress
Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 3
4 Mar 17, '24 Mar 24, '24 Mar 31, '24 Apr 7, '24 Apr 14, '24 Apr 21, '24 Apr 28, '24 May 5, '24 May 12, '24 May 19, '24 May 26, '24
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Project: Project schedule _Nagu Split Inactive Task Duration-only Finish-only Progress
Date: Wed 1/31/24 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress