Pre-commissioning check list Customer Remarks
1 End Customer Name : Mitsubishi Power India Private Limited
Address & Contact No, E-mail ID :
2X660MW NTPC, Mouda.
2
Chandrasekaran Nataraj - 9611049318
[email protected]3 PO no and Date : VE/Danfoss/20-21/22 Dated 20.01.2021.
4 Application Details : Bulk Receiving Unit.
Drive model and Rating and Quantity of Drives :
5
6-Pulse ,415VAC,VFD PANEL FOR BRU-1 & 2 MOTORS (2X5.5KW)
6 Reference Material
a Installation, Operation and Maintenance Manual availability O&M Manual available at site
b Customer Drawings as provided/ Danfoss drawings availability Drawing's available at site
7 Pre-Installation Checks
a Compare the drive model number to what was ordered ok
b All Connectors accessory available Yes
c Condition of drive- physically ok Found ok
8 Installation Checks
a Environmental concerns.
i Non-corrosive environment or unit conformal coated. No corrosion was observed on the panel.
Panel has been installed in the air-conditioned
ii Clean & neat environment or dust free room for IP 20 enclosures
room
b Mounting.
Panel has been installed as per Industrial
i See the Instruction Manual for mounting clearances.
standard.
ii No excessive vibration. NA
iii Customer's enclosure properly ventilated. Yes
c Connections.
i Internal drive components and connections secure.(pl. check for tightness) Internal/External cable tightness completed.
ii External wiring connections secure (Power & controls). Yes
iii Drive properly grounded, all earth made common Drive earthing completed.
iv Drives analoge reference 0-10 VDC and mA signal wires are shielded. Yes
v Ensured that Mains power, motor power and control wiring are running seperately. Yes
vi Total motor cable length within drive specifications.( mention cable length) 50 Meter
vii Motor thermistor wires separate from load wires if any NA
viii Connection for Auto and Manual mode has to be secure Yes
ix Feedback source must be connected with Drive Yes
x System should be ready for Working in Auto and Manual mode during Engineer visit Yes
xi Drive options properly installed and wired correctly. Yes
Extra care to be taken where star Delta by pass system given to isolate drive out put before
xii NA
switching on power to star Delta.
d Line and Load
i Mains supply available to give power to the panel Yes
ii Multiple motors have individual motor overload Individual OLR protection is available.
iii Motor connections to panel (or drive) are secured Yes
e Motor side
i Motor Insulation test by disconnecting UVW connections from drive. Motor winding IR test completed.
ii Cables inulation testing disconnecting both ends Power Cable IR test completed.
iii If motor kept for long time without using greasing & condition of motor to be checked Motor testing and greasing done.
iv Motor earthing is done Motor earthing completed.
9 Mains Data
a Verifying mains supply.
i Measured mains voltage is within drive specifications.( pl. mention voltage) Input Voltage Range: 415V - 435V
ii Value of earth-neutral voltage.( pl mention the value in volts) Neutral to Earth voltage : 0V
63A HRC fuse has been installed in the switchgear
iii RCD / ELCB or ground fault device installed. ( If applicable)
panel.
Pre-commissioning check list Customer Remarks
10 VFD reformation
If VFD drive is not poweredup for more than 8 months, drive capaciptor should be reformed.
i
Reformation should be done by commissioning Engineer only
MPW-IND will arrange the 3-phase auto
3 phase Auto tranformer (0 to 415 VAC) is required to reform the drive capacitor before powering
ii transformer for the capacitor reformation of the
up the drive panel
VFD drive.
iii Without reformiation of VFD , Panel should not powerup.
iv Reformation kit should be avaliable before engineer arrives at site.
11 Site Images
Panel installation, input & output power cable connectivity, Panel earthing and field control
i
wiring to the panel.
No pending activity,the drive is ready for no-
12 Mention any pending work at site before Engineer visit.
load/load testing.