Method Statement of Concrete Pouring
Method Statement of Concrete Pouring
Suntrust Amadea
(Substructure)
Concrete Works
1. TITLE
Concrete Works
2. SCOPE OF WORK
2.1 General Description
2.3 Materials
2.3.1 List of materials:
Concrete – 8,000 psi, 4,000 psi
b. Verify manpower, status and condition of materials tools & equipment necessary
during execution.
c. Check with representative from Main Contractor, all materials for use are in
compliance with the approved specifications and the activities are guided by approved
method statement.
d. Check all workers daily before reporting to site and inspect wearing complete
Personal Protective Equipment.
f. Prepare daily work permit, Daily Safety Task Instruction (DSTI) sheet and conduct
daily Tool Box Meeting with the workers in order to prevent an unwanted incident.
h. Coordinate with the associated parties if there are any concerns related to the
work location.
i. Check daily all the tools and equipment to be use on working to prevent any
unwanted accidents during implementation.
j. Every work place must ensure proper housekeeping before leaving the activity
area, all tools are on proper place and secure the materials from deterioration or damaged.
l. Due to the work shall be held at the Construction Area, scheduling as well as the
time of start and finish shall be dictated by the Contractor.
m. All workers shall have preapproval and permits to enter to the Construction Area.
The passes should be worn at all times and/or readily available to present whenever demanded by
proper authorities.
n. All incoming materials at the site location shall be screened and should follow the
procedures provided before mobilizing.
o. Supervision must be present at all times in the place of work while commencing
any activity.
b. Before commencement of any work activity, coordinate with the contractor for daily
work permit approval.
c. Check and verify all activities if there shall be implications to associated parties.
Inform immediately the person in charge through a formal letter informing the activities required to be
undertaken.
d. Request for Information must be submitted to the Contractor for coordinating with
other Contract Package Contractors and also to clarify and discrepancies from pan to actual site
condition, solve issues and proper information support.
e. Inform immediately the Contractor for work coordination to the other
Subcontractors for proper execution of the activities.
f. Ensure that all activities are in compliance with the Contractor’s HSE Policy.
a. After the initial set of the concrete and when the concrete is hard enough to not
be damaged by such an action, the exposed concrete surface shall be covered
with drenched hessian sacks. These sacks shall be left in position and
maintained in a soaked condition for seven days.
b. For formed surfaces the curing shall be applied as described above after the
formwork has been removed, or a curing compound shall be applied.
c. Laitance may be removed once the concrete is hard by light chipping wire
brushing.
d. Preparation of Construction joints shall be done by mechanical chipping taking
care not to dislodge the coarse aggregates. This is to be done at least 24 hours
after the completion of placing or a concrete surface retarder may be used.
2.5.6 Inspection
a. Project Director
i. Responsible in overall run and progress of the entire project.
ii. Responsible and controls accounting, general affairs and report the
progress of work to the Contractor.
iii. The one responsible on project planning and scheduling. Also, he
will be responsible on all administrative matters including establishing
project organization.
iv. Checks and controls all the documents such as shop drawings,
construction schedules, progress billing statements, submittals, etc.
v. Assigns the Design Manager to overlook overseas logistics, design
and conceptualization and solving issues with regards to materials and shop
drawings.
vi. Assigns the General Manager to establish policies with regards to
personnel recruitment, promote Safety and Health, to check the quality of
works and all administrative matters.
vii. Checks the works of all his staff to provide the necessary work and
accomplishment needed.
viii. The Project Director is ultimately responsible for HS&E Policy
Performance and must champion zero accidents at all staff meetings and in
the field.
b. General Manager
i. Responsible on assisting the Project Director for controlling the work
of the project.
ii. Responsible on project planning and project scheduling. Also he will
be responsible on all administrative matters including establishing project
organization.
iii. Responsible on safety matters and related issues. Also,
responsible in orienting and reminding all his staff safety before reporting
to site and also aware on actual site condition.
c. Project Manager
i. Responsible on checking all shop drawings before submission to the
Contractor. Also responsible in coordinating to the Contractor for the
associated work schedule and activities.
ii. Checks all QA/QC matters and informing the Project Director for
awareness.
iii. Responsible on studying all cost variance and Scope of Works.
iv. Coordinating all Shop Drawings to Contractor for approval before
turnover to Project Engineer.
v. Responsible on all design related activities.
vi. Responsible on checking the material availability to the procurement
department.
vii. Ensuring the field personnel are working to the latest available
information.
d. Site Engineer
i. Assists the Project Director and Design Manager in executing the
activities. Responsible on overlooking the activities on the project and
preparing work progress.
ii. Ensures all activities for implementation is as per approved
drawings. Checks the Method Statement procedures are properly executed.
iii. Responsible on all work safety during execution.
iv. Conducts daily toolbox meeting at site to all workers prior the start
of activities.
v. Coordinate the activities to other trade contractor before
implementing at the site.
e. Design Engineer
i. Responsible on all drawings submittals, as-built plans and updating
all changes occurs during implementation.
ii. Coordinate from time to time to the Contractor’s Design Department
for any changes on the plans.