Question Bank
Question Bank
4 Mechanized Track Maintenance A false flange may split open points while travelling in:
5 Curves Design and 5. Maximum rate of change of cant or cant deficiency in BG is
Curves Design and
6 Maximum Cant gradient permissible in exceptional cases on BG curve is
Realignment
Curves Design and Check Rail is provided on curve if the degree of curve is
7
Realignment or more
Curves Design and
8 8. Maximum degree of lead curve that can be permitted/allowed in BG for goods train is
Realignment
Curves Design and
9 9. Extra clearance required for two adjacent curve will be
Realignment
Curves Design and
10 12. In contrary flexure turnout the negative cant can be permitted upto
Realignment
Curves Design and
11 Shift is calculated from the formula
Realignment
Curves Design and
12 The minimum radii of vertical curve on BG group A route is
Realignment
Curves Design and
13 The maximum allowable super elevation on BG suburban section is ?
Realignment
14 Ballast On BG Rajdhani route maximum aggregate abrasion value permitted :
15 Ballast The retention of 65 mm mesh sieve permitted with full accepted rates is –
16 Ballast The retention of 40 mm square mesh sieve with 10% reduction in contract rates is permitted upto –
17 Ballast The minimum cubic content of stack in plain areas is –
18 Ballast Depth of ballast on A route doubling project shall be
19 Ballast For stack having 150 cum quantity the number of samples shall be –
20 Ballast During contract supply period the abrasion value impact value test shall be done ?
21 Ballast For a meter gauge section which is planned for gauge conversion following statement is correct ?
24 Long & Short Welded Rails A fracture repair without use of rail tensor
A vertical curve is required to be provided at those points of grade where the algebraic difference
25 Track Inspections
between the grades is equal to or more than
Curves Design and A vertical curve is required to be provided at those points of grade where the algebraic difference
26
Realignment between the grades is equal to or more than –
27 TMS AEN of open line can feed the asset data like rails, sleepers, SEJ etc. using his login ID
28 Long & Short Welded Rails During working with BCM in high temp ranges on newly completed TRR, the best option is
29 Long & Short Welded Rails The Value of induced thermal force per degree change of temperature for 52 kg
30 Long & Short Welded Rails Distressing temperature for zone IV, 52 kg & 60 kg rail station is
31 Long & Short Welded Rails LWR/SWR may be continued through reverse curves not sharper than (ZONE IV)
32 Formation & Soil At least one test for quality check of blanket material shall be done per volume of:
33 Formation & Soil Mechanics What is the steepest embankment side slope adopted on Indian Railway :
34 Formation & Soil Mechanics Permissible range of cross slope on top of formation is:
35 select As per IRTMM squeezing pressure for point & PSC sleeper is
36 Formation & Soil Mechanics Most suitable roller breaking the clods in cohesive soil is:
37 Formation & Soil Mechanics Fines in a soil mass are the particles which have size smaller than:
38 Formation & Soil Mechanics Clay size particles in a soil mass have size less than:
39 Formation & Soil Mechanics What is the standard formation width for new BG Single line & Double line:
40 Formation & Soil Mechanics For a soil to be classified as "well graded", what condition should be satisfied:
41 Formation & Soil Mechanics The Liquid Limit minus Plastic Limit is termed as:
42 Formation & Soil Mechanics The symbol ‘OH’ for classification indicates
54 Formation & Soil Mechanics Slope Stability analysis of new bank shall be made considering:
55 Formation & Soil Mechanics Black cotton soil is not suitable for construction of embankment because of:
56 Formation & Soil Mechanics Vane shear test is a:
57 Formation & Soil Mechanics During Final Location Survey, the boring is normally done along the alignment at a spacing of :
58 Formation & Soil Mechanics Borrow areas/pits should not be located within what distance away from toe of the embankment:
59 Formation & Soil Mechanics What is the term used specifically in "two layer system" of embankment construction:
60 Formation & Soil Mechanics What "N" value (from SPT) of sub-soil will necessitate Ground Improvement:
61 Formation & Soil Mechanics Which out of following type of soil category will have less than 12% of fines:
62 Long & Short Welded Rails Gap at SEJ for 52 kg/60 kg Rail section at td is
63 Long & Short Welded Rails The period of consolidation for BG concrete sleeper track
64 Long & Short Welded Rails Longitudinal Ballast resistance for BG PRC SD 1660 No./Km in Kg/cm/Rail
65 Long & Short Welded Rails At td the distance of tongue rail tip from reference line at SEJ in case of 52 kg Rail section is
66 Long & Short Welded Rails Glued Joints to be used in LWR
67 Long & Short Welded Rails LWR to be distressed if no. of fracture in one km exceeds
68 Long & Short Welded Rails In level crossing approach SEJ can be laid
69 Mechanized Track Maintenance At the close of tamping work, ramp should be flatter than
70 Long & Short Welded Rails Buffer rails are provided in lieu of SEJ at the end of LWR with the permission of
71 Long & Short Welded Rails Destressing of LWR is the operation to be carried out
73 Long & Short Welded Rails Emergency repairs to a buckled track involves
74 Long & Short Welded Rails Normally, while performing manual attention to track on LWR, opening of sleepers is limited to
75 Long & Short Welded Rails The maximum length of CWR is
76 Long & Short Welded Rails As per latest correction slip formation width for single line LWR/CWR is
77 Long & Short Welded Rails The steepest gradient permitted for laying LWR/CWR is
78 Long & Short Welded Rails Minimum cushion of ballast for LWR for speed upto 130 kmph is
79 Long & Short Welded Rails In the breathing length there is movement as well as thermal force
80 Long & Short Welded Rails The maximum curvature permitted is 50 for LWR laying in zone I. (True / False).
Curves Design and
81 The radius of 5 deg. curve is 35 deg meter (True/False)
Realignment
82 Long & Short Welded Rails For LWR on 60 kg rail section in Zone I, the destressing temperature is fixed as
Curves Design and
83 The frequency of curve inspection for AEN on PSC sleeper track is
Realignment
Curves Design and
84 With direction inward (Inward/outward).
Realignment
85 Ballast what is the maximum imapact value permitted for BG ballast in normal course
86 Ballast what is the maximum abraision value permitted for BG ballast in normal course
87 Ballast what is the maximum water absorption value permitted for BG ballast in normal course
88 Formation & Soil Mechanics what is the maximum height permitted for BG ballast stack in normal course
89 Ballast what is the minimum height permitted for BG ballast stack in hilly terrain
90 Ballast which is the test to determine the hardness of the ballast
91 Ballast which is the test to determine the toughness of the ballast
92 Long & Short Welded Rails Destressing temeprature td for 52kg rails will be within temperature range
For 52 kg rail section, thermit force in LWR is. per
93 Long & Short Welded Rails
degree centigrade
94 Long & Short Welded Rails The welded rail passes through yards including points & crossings is known as:
95 Long & Short Welded Rails The sleeper density for LWR track with PRC sleeper for Zone III & IV is
96 Long & Short Welded Rails Deep screening can be done in LWr/CWR when temperature falls within;
97 Track Inspections ADEN Should carry out night foot plate inspection once Â… Â…Â…Â…Â…Â…Â…Â…..
98 Long & Short Welded Rails All types of maintenance in lWR/CWR can be done within temp.
99 Track Inspections ADEN should inspect each water supply installationÂ…Â… Â…Â…Â…Â…Â…Â…..
100 Long & Short Welded Rails Formula for calculating breathing length in LWR
Conventional Track
101 Speed potential for ‘D’ route on B.G.
Maintenance and Renewals
102 Long & Short Welded Rails Breathing Length depends on
Conventional Track
103 Gang diary and Gang chart to be preserved for -
Maintenance and Renewals
Conventional Track
104 Overhauling of track is done to –
Maintenance and Renewals
Conventional Track
105 Frequency of over hauling of track is –
Maintenance and Renewals
106 Long & Short Welded Rails Cold weather patrol will be introduced when rail temp. falls below:
Conventional Track
107 Deep Screening of track is done to
Maintenance and Renewals
108 Rail/Weld failures and USFD USFD machine Calibration is to be Done Once----------
109 Long & Short Welded Rails During hot weather patrol, patrolman will carry:
110 Rail/Weld failures and USFD USFD machine Sensitivity setting is to be done --.
111 Rail/Weld failures and USFD USFD Machine Characteristic are to be checked -------------
112 Rail/Weld failures and USFD ------------------ button/s are used for calibration of USFD machine.
113 Long & Short Welded Rails For manual consolidation of ballast for LWR it is required to pass traffic in gross tones (B.G.)
114 Rail/Weld failures and USFD -------------- button/s is to be used for sensitivity setting of the USFD machine.
115 Rail/Weld failures and USFD At rail manufacturing plant complete rail section is being tested by USFD
116 Long & Short Welded Rails How many rounds of machine packing are required after deep screening in LWr/CWR
Out put of DRT is approximately as compared to
117 Rail/Weld failures and USFD
SRT.
118 Rail/Weld failures and USFD NO of probes on SRT ------------
119 Rail/Weld failures and USFD No of probes on DRT
120 Rail/Weld failures and USFD In case of IMR defect has to impose SR.
121 Rail/Weld failures and USFD Frequency of Ultrasonic waves are
136 Long & Short Welded Rails Hot weather patrolling is to introduced in LWR territory having sleepers other than PRC
137 Mechanized Track Maintenance Max. no. of machines which can work in one block section
138 Mechanized Track Maintenance Min. clean cushion required for TTM working
139 Mechanized Track Maintenance Tamping tool depth below the bottom adge of sleeper in case of flat bottom sleepers
142 Mechanized Track Maintenance Progressive of CSM tamping m/c per effective hour
At the close of tamping work in mechanised maintenance. P.Way Manula prescribes ramp gentler
144 Mechanized Track Maintenance
than:
145 Rolling Stock An accident will be termed as serious accident when the loss of Railway property is more than:
146 Rail/Weld failures and USFD Probe angle are angle of Wave---
Prominent failure on IR are on account of ----------------------
147 Rail/Weld failures and USFD
failure of Rail
154 Rolling Stock When a cause of a derailment is disputed, track measurements shall be taken. in rear & ahead
155 Rolling Stock For taking track measurement at accident site stations shall be marked at apart
156 Rolling Stock In a semi permanent (BG) diversion the gradient should not be steeper than
157 Long & Short Welded Rails Central portion of LWR means
158 Rolling Stock Min. sleeper density in case of semi permanent diversion
159 Rolling Stock For permitting non stop 15 kmph S/R the gradient shall not be steeper than
160 Rolling Stock Derailing Force in Nadal egination is devoted by
161 Rolling Stock A wheel is clarified as Woon root when root radius of wheel radius to less then. mm
162 Rolling Stock For having non-stop 15 kmph speed restriction for semi permanent division
163 Rolling Stock Radius of the curves for B.G. Semi permanent diversion should not less than. metres
165 Schedule of Dimensions Maximum horizontal distance from centre of track to face of passenger platform coping for B.G. is
The BG track with section speed more than 110 kmph having >
166 Formation & Soil Mechanics
g location require attention
167 select Centre line method for layout calculation is used for
168 Formation & Soil Mechanics First Track Recording Car called the Amsler Car was imported by Indian Railways in the year 1963.
169 Track Machine Maintenance For maintenance tamping squeezing time as per latest instruction is
170 Project Management CRS sanction is not required for
171 Track CRS sanction is required for raising of speed from 105 to 110 KMPH
172 Track Machine Maintenance What is the maximum lift which can be applied to PSC track with single insertion
173 select During tamping on concrete sleeper track, the maximum general lift allowed is
Curves Design and Fan shaped layout of Points and Crossing is having fan shaped sleeper orientation in Crossing
175
Realignment portion.
176 Track Machine Maintenance Total No of Tamping Tool in Tamping Express is
177 Track Machine Maintenance The reference Rail for lining on curve is normally
178 Track Machine Vm correction when entering from straight to transition will be directed
179 Track Machine Maintenance Error reduction ratio in 3-Point Lining is around
180 Track Machine Maintenance Which of the machine has crane for handling material
181 Track Machine Maintenance Best Method for lining when fixed reference point for position of original curve is available is
182 Track Machine Maintenance Best Method for lining when track geometry and fixed references are not known
183 Track Machine Maintenance Which does not give Fd value (Front trolley slew) for design lining
184 Track Machine Maintenance Datum Rail on curves is normally
185 Track Machine Maintenance Rear pendulum in some machines are provided for
186 Track Machine Maintenance Two insertions during Tamping should be done if general Lift is
187 Track Machine Maintenance Adjustment during tamping on vertical curve is called
Following is not required to be fed during Geometry/Elementary mode of 3 point lining and
188 Track Machine Maintenance
levelling
189 Track Machine Maintenance 3rd Rail Lifting facility is provided in
190 Track Machine Maintenance During Maintenance tamping, DTS should be used in
191 Track Machine Maintenance DTS should not be used
192 Track Machine Maintenance In DGS 62 N supplied by M/s Plasser, the vibration of track with constant vertical pre load is in
198 Track Machine Maintenance Central plough is provided in which of the BRM machine
199 Track Machine Maintenance Frequency of deep screening is
200 Track Machine Maintenance SBCM is for cleaning of
201 Track Machine Maintenance The cutting chain in BCM rotates
202 Track Machine Maintenance The progress of Duomatic Tamping Machine in an hour of block is
203 Track Machine Maintenance In which of the following tamping machine satellite unit is not provided
204 Track Machine Maintenance Which is the special feature of Points & Xing tamping machine (UNIMAT)
205 Track Machine Maintenance The auxiliary track rail should not be above the running rail by more than
206 Track Machine Maintenance The machine used for Points & Xings renewal is
Conventional Track
207 Flat tyre causes maximum damage at a speed of
Maintenance and Renewals
208 Track Machine Maintenance Minimum clean ballast cushion required for deployment of tamping machine is
209 Track Machine Maintenance The Vm correction in four point lining is fed in front cabin in
210 Track Machine Maintenance In 3 point lining method
221 Mechanized Track Maintenance For maintenance tamping squeezing time as per IRTMM is
245 select In case of detection of IMR defect 30 Kmph or stricter speed restriction should be imposed by
The limit of SD for planned maintenance and urgent maintenance for unevenness on 9.6 m chord is
5.5 mm and 6.2 mm respectively. The measured SD value for a km is 6.1 mm for unevenness on 9.6
246 Mechanized Track Maintenance
m chord for a given block. The marking in the TGI report for that given block due to this parameter
will be -
249 Mechanized Track Maintenance Foot Plate/Rear window inspection is a subjective assessment of track condition.
Higher the numerical value of the Ride Index, better will be the quality of track from comfort point
250 Mechanized Track Maintenance
of view.
251 Mechanized Track Maintenance The track tolerances prescribed in para 607(2) of IRPWM are safety tolerances
252 Mechanized Track Maintenance The SD based tolerances are available for a minimum speed of 100 Km/h
254 Mechanized Track Maintenance Three point lining can not be used on curves.
255 Mechanized Track Maintenance For transition curves Vm correction is to be applied while working in three point lining mode.
Track Monitoring, Track In case of track where maximum permissible speed is 120 kmph, for through tamping of a PWI
256
Tolerances section
257 Turnouts and Curves The switch length of a turnout is measured from:
258 Turnouts and Curves The check rail clearance for turnout with 1673 mm gauge is:
In case of right hand turnout when the point is set for turnout side the gap between left hand Stock
260 Turnouts and Curves
Rail and left hand Tongue Rail at JOH should be:
Curves Design and In non-transitioned curves on BG routes the Cant is run up and run out in m long virtual
261
Realignment transition:
262 Point & Crossings In PSC sleeper layout the approach sleepers (1AS, 2AS, 3A, 4A) are provided for:
A 1 in 12 turnout is taking off from outside of a 1° curve. The resultant curvature of the turnout
263 Turnouts and Curves
will be approximately .
264 select Inadequate pre-heating will cause ----------------------------
265 Track Increase in temp in LWR from td level will generate
266 Mechanized Track Maintenance Lifting cum lining unit is situated close to
267 new title Lurch is parasitic movement -
268 select lurching of vehicles on track may happen due to alignment and/or gauge defects in track.
Curves Design and
269 On I.R., the Chord Length for measurement of Versine on curves is taken as
Realignment
Curves Design and Dynamic gauge for BG on Indian Railways is taken as
270
Realignment mm
Curves Design and The length of transition curve is generally governed by
271
Realignment criteria.
Curves Design and
272 10. The Criteria, governing the Limiting value of the cant deficiency is .
Realignment
Curves Design and The maximum value of cant excess for a B.G. curve on I.R. is
273
Realignment mm :
Curves Design and
274 Maximum value of actual cant on BG group ‘A’ route is restricted to:
Realignment
Curves Design and
275 Shift for a circular curve of 600 m radius provided with 120 m long transition curve is:
Realignment
276 Long & Short Welded Rails Minimum authorized official to certify track after attending buckling of track is
Curves Design and
278 If transition length of a curve is increased, the circular curve will shift inward.
Realignment
Curves Design and Overturning can occur due to Cant deficiency, though it is not a governing criteria to decide the
279
Realignment limiting value of Cd .
Curves Design and
280 The maximum Cant that can be provided on group ‘A’ route is 185 mm.
Realignment
285 Mechanized Track Maintenance What is the maximum lift which can be applied to PSC track with single insertion ?
286 Mechanized Track Maintenance The maximum wear of tamping tool permitted is:
Name the Unimat Machine which is having facility for lifting and tamping the third rail on points
287 Mechanized Track Maintenance
and crossing:
289 Mechanized Track Maintenance The tamping cycle of track on PSC sleepers is:
290 Mechanized Track Maintenance The Operators of track machines should be fit in:
291 Mechanized Track Maintenance During working of TRT, there should not be any infringements within
292 Mechanized Track Maintenance The lifting capacity of PQRS 201 portal crane is:
The minimum separation between two machines when moving as convoy in a block section should
293 Mechanized Track Maintenance
be:
294 Track Machine Maintenance If exsting curve has SE, X mm more the desired SE, the general lift should be
295 Points & Xings and Curves Maximum thickness of flange of wheel as per SOD is
296 Points & Xings and Curves Limiting Radius of curves on BG as per SOD is 220m
Curves Design and On heel of switch spherical washer is provided on left or right hand side depending upon whether it
297
Realignment is LH or RH turnout.
The versine value(in cm) at mid-chord position approximately represents the degree of curvature, if
298 Points & Xings and Curves
the chord length is
On Cuves for doubling work on a goup 'A' route with speed increse potential to 200 km/h the, SE to
299 Points & Xings and Curves
be provided will be
300 Points & Xings and Curves For future layouts the recommended cant gradient for transition curves is
301 Points & Xings and Curves The virtual transition length for BG is 14.785m
Track Monitoring, Track The track has to be maintained to C&M-1 tolerances as provided in paragraph 607(2) – of
302
Tolerances IRPWM (CS No.45 of IRPWM) for the sections
303 Track Monitoring, Which is track monitoring system that does not give the Ride Index values –
Track Monitoring, Track Which is not a different systems/mechanical means available with Indian Railways to assess the
305
Tolerances track parameters and behaviour?
Track Monitoring, Track If the value of TGI of the PWIÂ’s section is greater than 80, we should not look at the other
313
Tolerances resultsin the TGI reports as all the parametres are taken care of and considered good.
314 Track RDSO report CT-35 is for
Track Monitoring, Track
315 OMS-2000 result will not give
Tolerances
The limit of SD for priority II (planned maintenance) and priority I (urgent maintenance) for
Track Monitoring, Track unevenness on 9.6 m chord is 5.5 mm and 6.2 mm respectively. The measured SD value for a km is
316
Tolerances 6.1 mm for unevenness on 9.6 m chord for a given block .The marking the column MI in the Km
wise report for that block due to this parameter will be –
Track Monitoring, Track For a coaching stock running at 90 km/h, whose natural frequency is 1 cycle per second, the chord
317
Tolerances length for measurement and reporting of defects would be approximately.
Track Monitoring, Track If we do OMS recording of the same section using the same coach at speed of 80 kmph and the at a
318
Tolerances 120 kmph, then the following statement will generally be true-
Track Monitoring, Track TGI value of a block is calculated as 55 using the ALI (alignment index) value of 60 by mistake.
319
Tolerances The correct value of ALI was 80. What would be the correct value of TGI?
Track Monitoring, Track In a PWIÂ’s section more than 40 % of section has a TGI value of more than 90.But the index for
327
Tolerances twist parameter for 20 kms has TGI value ranging from 30-45.Should he ask for machine ?
Track Monitoring, Track If the value of TGI of the PWIÂ’s section 100, means that all the parameters are within acceptable
329
Tolerances limit.
Track Monitoring, Track A typical kilometre of track with more than 10 peaks exceeding the limits of a particular category is
330
Tolerances classified in next lower category for a given track parameter
Track Monitoring, Track
331 Non-recording speed for OMS on “A” Routes is Less than 75 Kmph
Tolerances
Track Monitoring, Track Measuring system has to be calibrated so that it gives the same measurement for the same
332
Tolerances entity/defect every time.
Track Monitoring, Track
333 is due to alignment defect either due to bad alignment or varying gauge.
Tolerances
Track Monitoring, Track
334 In TRCs KM of track is further devided into units of M each, which are called blocks.
Tolerances
Track Monitoring, Track
335 Alignment defect is measured by measuring the chord versine on specified chord.
Tolerances
Track Monitoring, Track
336 A block could be less than 200 m in length.
Tolerances
Track Monitoring, Track For new track the indices value of each of the four parametres- Alignment,Twist,Gauge &
337
Tolerances Uneveness would be
Track Monitoring, Track What is the track category (as per details of peak exceedences for Twist given below) For Band A
338
Tolerances no. of peaks 17, for B - 10, for c - 6 & for D - 0.
Track Monitoring, Track What is the track category of a defect which is as under (for uneveness defect)? FOR BAND A -27
339
Tolerances PEAKS, FOR B - 15, FOR C - 11 & FOR D - 5.
Track Monitoring, Track Write down the Track Category for the track having Alignment defects for Band A -32 Peaks, For B
340
Tolerances - 17, For C - 12 & For D - 0.
Track Monitoring, Track What is the track category of defect Alignment for the peaks exceeding the band A -27, B-18, C-13
341
Tolerances & D-11.?
Track Monitoring, Track Select the correct track category of a Twist defect from aoptions given under for a band A - 15
342
Tolerances Peaks, for B - 12, for C - 9 & for D - 0.
343 Fastenings Greasing of ERC inserts should be done by using grease meeting following requirements
344 Fastenings Toe load testing of ERC during maintenance is done at a frequency of
346 Level Crossing Special class Level Crossing has TVU greater than
347 Level Crossing All special, ‘A’ and ‘B’ class of Level Crossing shall be
348 Level Crossing Engineering gates are gates that are situated
349 Level Crossing Number of detonators to be provided at Level Crossing gate are
350 Level Crossing Height gauge should be provided normally away from gate post at a distance of
351 Level Crossing Census for Level Crossing should be taken at a frequency of
352 MMU MMU-I as in IRPWM Para-228 is to be provided as
353 MMU Reconditioning of Points & Crossings is to be executed by
354 MMU Rail borne maintenance vehicle has following facilities
355 Schedule of Inspection Trolley inspection of entire subdivision should be done by AEN at a frequency of
356 Schedule of Inspection Fast train inspection should be done by AEN covering his Sub- division at a frequency
357 Schedule of Inspection Night foot plate inspection should be done by AEN between
358 Small Track Machine Drilling time for rail drilling machine is specified as
359 Small Track Machine Rail tensor in Small Track Machine manual has a pulling capacity of
360 Small Track Machine Specified weight of self propelled light weight trolley is
361 Small Track Machine AEN should inspect Small Track machineÂ’s once in
Track Monitoring, Track SD based track index helps in identifying localized defects while Peak based index helps in
362
Tolerances identifying continuous bad stretch.
363 Point & Crossings If F is the crossing angle then crossing number N is equal to:
364 Mechanized Track Maintenance Seive size of BCM as per IRTMM is
On account of cant in wing rail of CMS crossing wing rail, wear measured on 60kg CMS crossing is
365 Point & Crossings
reduced by
A 1 in 12 turnout is taking off from inside of a 1° curve. The resultant curvature of the lead curve
366 Point & Crossings
of the turnout will be approximately
Insertion or removal of P & C in a running line affecting layout may be carried out without sanction
367 Point & Crossings
of CRS
368 Point & Crossings The gap between top of stretcher bar and bottom of stock rail should be at least 3.0 mm
369 Point & Crossings Fan shaped layout of Points and Crossing is due to sleeper orientation in Crossing portion
370 Point & Crossings There could be difference in the rail top level of stock and tongue rail in case of overriding switch
371 Schedule of Dimensions As per Schedule I, chapter I, minimum distance centre to centre of tracks for existing work shall be
372 select SEJ for LWR cannot be located at
Where 25KV AC traction is likely to be used, minimum height above rail level, at centre of track,
373 Schedule of Dimensions
for light overhead structures such as Foot Over Bridges shall be
As per chapter II, Schedule I for new works & alteration to existing work, recommended Gradient in
374 Schedule of Dimensions
station yard shall be
375 Schedule of Dimensions There must be no change of grades within Â…Â…Â…Â… Â…m of any points & crossings
376 Schedule of Dimensions Minimum horizontal distance from centre of track to face of passenger platform coping shall be
377 Schedule of Dimensions Maximum horizontal distance from centre of track to face of any platform wall shall be
378 Schedule of Dimensions Minimum clearance between toe of open switch and stock rail for existing work
If any material stack is by the side of the track. Does its clearance from centre line of track have
379 Schedule of Dimensions
SOD implications?
382 Mechanized Track Maintenance Squeezing pressure to be set for PSC sleepers on normal track
383 TMS For the asset data e.g. curve fed by JE not confirmed by SSE - Mark the correct one
384 TMS For which feature the data can be fed for only one km of track at a time?
385 TMS Inspection of any asset has to be done by JE/SSE and then confirmed by SSE/AEN
386 TMS In case inspection of an ASSET becomes overdue
In a division where TMS is fully implemented, once the data for assets is confirmed by SE, no
387 TMS
change can done except for be doing it through the asset change. (True/False)
The compliance for replacement of IMR weld can be done through the sub-module -Location
394 TMS
needing attention- (True/False)
From message center, message can be sent to anyone on Indian Railways right from JE to ME
395 TMS
without even knowing there email address (True/False)
The schedule/ programme of inspections of the junior official can be modified by senior official i.e.
396 TMS
SSE can modify the inspection planning of JE (True/False)
If we change a defective weld and replace it with a 6 m rail piece, this rail piece can be seen in the
397 TMS
track diagram, once this is fed through the asset change (True/False).
For complying the items appearing in Location needing attention, the following details are to be
398 TMS
filled
399 TMS The following conditions should be complied before the inspection of LWR can be done and saved
401 select If condition warrant to stop train at the site, the driver should be advised through written memo.
Works of short duration are the works which can be completed by sunset and no S/R thereafter is
402 select
required.
403 Track Inspections 52 Kg. rail on 60 Kg. sleeper will have GFN liner combination of
404 Mechanized Track Maintenance Squeezing pressure to be set for PSC sleepers on turnout in UNIMAT is
405 select Extra clearance required for two adjacent curve will be
406 select Standard play in case of new wheels is. mm
407 select For stack having 150 cum quantity the number of samples shall be ânn
408 select As per revised instruction height of height gauge should be kept where height of OHE is 5.5 meter
409 select As per Schedule I, chapter I, minimum distance center to center of tracks for new work shall be
410 Mechanized Track Maintenance Tamping machine does not make correction to
411 Turnouts and Curves The 1 in 8.5/1 in 12 switches used on PSC sleeper layout are
412 Long & Short Welded Rails The anchor length of LWR on BG is
413 Track The behavior of LWR shall depend upon
Curves Design and The cant gradient in exceptional circumstances for BG on transition curve should not be steeper
414
Realignment than:
415 Point & Crossings The check rail clearance for turnout with 1673 mm gauge is
416 select Premature tapping ânn can cause--------------------
The BG track with sectional speed more than 110 kmph having
417 select
> g location require attention, if acceleration peaks exceeds
418 select Three point lining cannot be used on curves.
419 select The condition will be called as thin flange, when the flange thickness becomes less than:
420 select Which of works are pre requisites for tamping machine
425 Rail/Weld failures and USFD A introduction of longer rail when removed during fracture repaired
426 Track Machine Maintenance The function that cannot be performed by MPT is
427 Track The minimum competency for supervision of tamping operation is
The maximum possible rail temp variation for 60 kg rail section under Zone—IV shall be (When td
428 Track
= tm + 10)
429 Track How much gap is kept in double gap SEJ at the time of de- stressing?
446 Track The level crossing inspection done by the SSE. (P. Way) in the entire section
450 select Lateral alignment of rail for AT welding when checked with 1.0 m straight edge is.
451 select Unsquared cut of rail end for AT welding shall cause.
452 select For AT welding with compressed air petrol mix pre-heating time and pressure of compressed air is
469 select DTS machine has two mode of working which is.
For lining , track machine correct the alignment of only one pre selected rail and other rail gets
470 select
aligned automatically being fixed with other rail.
471 select During Lining, tamping machine correct
472 select Gauge of Auxilary Track at PQRS site is
473 select Quality of track parameter after tamping by machine depends upon.
474 select Increase in temp in LWR from td level will generate.
475 Rail/Weld failures and USFD Introduction of longer rail when removed during fracture repair.
476 select Destressing of LWR is the operation to be carried out .
477 select Normally, while performing manual attention to track On LWR, opening of sleepers is limited to.
478 select The steepest gradient permitted for laying LWR/CWR in LWR manual is
479 select A length greater than m will normally function as LWR on BG
480 select For carrying out repair of rail fracture, the length of rail taken out must be
486 Mechanized Track Maintenance The lifting capacity of PQRS 201 portal crane is
491 select In case of closed to road level crossing responsibility of exchange of number for opening of LC
492 select Check rail clearance at level crossing is
493 select Level crossing having TVU > 50000 is classified as
494 select Speed breaker at level crossing is provided at
495 select Medical category of gateman is
496 select Stores which are obtained for specific works are classified as
497 select Switch length is the distance between
498 select Block overlap distance is measured from
499 select Ballast resistance in DC track circuited area is
500 select Now-a-days Overriding switches are used in Indian railway
501 select For new work minimum throw of switch for 1 in 12 normal turnout (not thick web switch) is
502 select Switch entry angle for 1 in 12 curved PSC turnout is
TNC (Theoretical Nose of Crossing) is used as a reference point for all layout calculations specially
503 select
for the turnout laid on curve
504 select Hook bolt is used for connection between
USFD machine Calibration is to be Done Once in a
505 select
.
USFD Machine Sensitivity Setting is to be done Once in a
506 select
.
USFD Machine Characterstics checking is to be done Once in a
507 select
.
508 select USFD Machine Sensitivity Setting for Temperature Variation is to be done Once in a .
509 select Visual Examination of USFD Machine and Equipment is to be done .
510 select Button is used for calibation for Machine.
Button is used for Sensitivity Setting of
511 select
Machine.
517 Rail/Weld failures and USFD Soft grease to RDSO Specification No. is to be used for Weld Testing.
Any thick oil of high viscosity grade of cst or more can be used as a couplant while
518 select
undertaking hand probing.
Calibration Range for '0' deg Probe is mm of longitudinal wave in case of Multiplexure
519 select
machine for Rail Testing.
520 select Calibration Range for '70' deg Central Probe is mm of shear wave for Rail Testing.
521 select Standard hole is used for sensitivity setting of '70' deg NGF probe in Rail Testing.
522 select Standard hole is used for sensitivity setting of '70' deg probe in AT Weld Testing.
In Standard Test Piece of AT Weld the dimension of Half Moon Saw cut is mm Height,
523 select
mm Width and mm Thick.
524 select Frequency of Rail Testing for the Route having 48 GMT other than reduced frequency period.
525 Rail/Weld failures and USFD Frequency of AT Weld Testing for the Route having 50 GMT.
526 select Frequency of AT Weld Testing for the Route having 61 GMT.
527 select Frequency of FB Weld Testing for the Route having 61 GMT.
The Testing Interval of USFD Testing of Defective AT Welds should be reduced by % of
528 select
Normal Testing Interval of AT Weld.
Through Weld Renewal should be planned after the welds have carried % of the stipulated GMT
529 select of rails.(As per Para No
8.16 of USFD Manual)
FB welded joint when tested with specified gain setting showing flaw signal of 46% by 45 deg
530 select
Probe shall be considered as .
AT welded joint when tested with specified gain setting showing flaw signal of 46% by 45 deg
531 select
Probe shall be considered as .
The probe shall be positioned mm away from the weld centre while testing the web of FB
532 Rail/Weld failures and USFD
Weld.
The probe shall be positioned mm away from the weld centre while testing the Flange of FB
533 select
Weld.
534 select may order testing of FB Weld with hand probing in case failure rates are high in his opinion.
Calibration block of 60x50x50mm block of steel to grade 45C8 of IS : code is used for
535 Rail/Weld failures and USFD
calibration of Normal Probe.
536 select The Codal Life of USFD Machine is Years.
537 select For Testing the Head of FB Weld deg. Probe is Used.
The Crystal of 70 deg Side Looking Probe is twisted at
538 select
deg Angle to propogate the beam at the centre of weld foot.
70 deg Side Looking Probe is placed mm away from weld centre for thesting the Half Moon
539 select
Defect.
Any Defect found of Height 20 % or more shall be classified as
540 select
by 70 deg Side Looking Probe.
Sectional AEN should spent minimum in each month during his routine trolley inspection
541 select
with USFD team.
The signal amplitude of individual probe shall be checked on
542 select
basis while doing the Sensitivity Setting on account of variation in rail temperature.
543 select Sensitivity Setting of 70 deg probe is done on mm Dia through hole for AT Weld Testing.
544 select While testing on single line section, additional gain of is to be employed.
While testing the Scabbed Rail Location with Test RIG in 52 kg Rail Section, the Probe shall be
545 select
fixed at mm apart.
546 select Minimum size can be detected by '0', 4 Mhz Probe is mm.
Maintain proper gap of mm between probing face and probe shoe for Rail Testing and check
547 select
with using Feeler Gauge.
Normally the DFWR defect is to be removed from track within
548 select
from the date of detection.
DFWO defect shall be protected by within 3 days of detection to relax the Normal
549 select
speed.
550 select Velocity of Longitudinal wave in steel is m/s.
551 select Velocity of Shear wave in steel is m/s.
552 select Thickness of perspex in IIW Block is mm.
553 Rail/Weld failures and USFD Tandem Rig is used to detect the defects present in the Weld.
554 select Calibration is done to ensure the proper of the Defect.
555 select Sensitivity Setting is done to ensure the of the Defect.
While Turnout out testing, the Visual Examination is done in
556 Rail/Weld failures and USFD
By P.way Officials.
557 select 0' deg Probe is Used to detect the Horizontal defects in Rail Testing.
For Charecterstics checking of of Machine we use 0 degree
558 Rail/Weld failures and USFD
Probe.
559 select Dead Zone of Double Crystal Probe is mm.
560 Rail/Weld failures and USFD Piping Defect can be detected by which Probe ?
561 select Piezoelectric crystals are cut to a thickness that is the desired wavelength.
If the First Medium is Steel and the Second medium is Air what will be the amount of reflected
562 select
sound waves ?
563 select What is the value of first Critical Angle ?
Snell's Law describes the relationship between the angles of wave and the of the waves
564 select
?
565 select If the Acoustic Impedance of a material is less the amount of sound wave reflection is ?
566 select If Attenuation is more, the loss of energy is ?
In Longitudinal wave, the vibration of the particles of the material are in the direction as
567 select
that of propagation of the wave ?
In case of right hand turnout when the point is set for turnout side, the gap between left hand stock
574 Turnouts and Curves
rail and left hand tongue rail at JOH should be
575 Turnouts and Curves On account of cant in CMS crossing wing rail, wear measured on 60kg CMS crossing is reduced by
576 Turnouts and Curves The permitted check rail clearance for turnout with 1673 mm gauge is?
577 Turnouts and Curves While laying 1:8.5 turnout, taking off from straight turn-in- curve radius on BG should preferably be
579 Turnouts and Curves The gap between top of stretcher bar to bottom of stock rail should be
On a curve in the central circular portion, if station no. 50 is slewed by 70 mm towards outside,
580 Turnouts and Curves
itânns effect on versine measured at station number 49 will be
581 Turnouts and Curves Value of heel divergence for 1:12, 52Kg, curved switch on PSC sleeper is
582 Turnouts and Curves Most critical case for functioning of check rail is
583 Turnouts and Curves Check rails are mandatory for track on curves (on BG track) sharper than
584 Turnouts and Curves The 1 in 8.5 / 1 in 12 switches used on PSC sleeper layout are
1 in 8.5
585 Turnouts and Curves
turnout .
586 Turnouts and Curves Maximum vertical wear permitted on 60 Kg CMS crossing on Rajdhani Route is
Overall length of a crossover
587 Turnouts and Curves
is .
In case of CMS crossing, wear of nose is
588 Turnouts and Curves
measured .
In case of curved switches made out of normal rail, the level of tongue rail is higher by 6 mm from
589 Turnouts and Curves
stock rail-
590 Turnouts and Curves H3C class electrode for reconditioning of points & Xing have a minimum service life of
591 Turnouts and Curves For reconditioning of CMS crossing temperature of crossing should not exceed-
While carrying out layout calculations for over all length of a cross over between two parallel track
592 Turnouts and Curves at 6.0 m track centres the results will remain same whether you provide CMS crossing or BUILT-up
Crossing.
Curves Design and
593 Realignment of curve should be planned:
Realignment
594 Turnouts and Curves There should be no change of super elevation on (On BG)
595 Turnouts and Curves The second summation of versine difference represents .
596 Turnouts and Curves For checking correct curvature of tongue rail, ordinates should be measured
604 Turnouts and Curves In layout Calculations, Turnout Parameters A, M & K are
On a fan-shaped lay-out same sleepers can be used for a right hand T/O and left hand T/O For this
605 Turnout
purpose
608 new title During contract supply period the abrasion value impact value test shall be done .
609 new title What is the steepest embankment side slope adopted on Indian Railway?
610 new title Vane shear test is a .
611 new title Buffer rails are provided in lieu of SEJ at the end of LWR with the permission of .
612 new title What is the maximum height permitted for BG ballast stack in normal course ?
Track Monitoring, Track The major advantage of mechanised track monitoring over manual monitoring of track which
613
Tolerances simulates the real conditions is
Velocity of Longitudinal Waves (Normal Probe) are
614 Rail/Weld failures and USFD
than Transverse/Shear Waves (angular Probe).
615 Turnouts and Curves Curve connecting the turnout curve after heel of crossing and the adjoining part is called
Curves Design and
616 While providing transition curve, the original circular curve is .
Realignment
Curves Design and
617 Grade Compensation for BG curve per degree of curvature is .
Realignment
618 Point & Crossings Maximum Cant gradient permissible in exceptional cases on BG curve is .
Curves Design and Check Rail is provided on curve if the degree of curve is
619
Realignment or more.
Curves Design and
620 Extra clearance required for two adjacent curve will be .
Realignment
621 Ballast For stack having 150 cum quantity the number of samples of Ballast shall be .
622 Long & Short Welded Rails A fracture repair without use of rail tensor .
During working with BCM in high temp ranges on newly completed TRR, the best option
623 Mechanized Track Maintenance
is .
The permitted range of rail temperature for regular track maintenance of LWR track
624 Long & Short Welded Rails
is .
625 Long & Short Welded Rails Gap at SEJ for 52 kg/60 kg Rail section at td is .
626 Long & Short Welded Rails Glued Joints to be used in LWR .
627 Long & Short Welded Rails Emergency repairs to a buckled track involves .
628 Long & Short Welded Rails The steepest gradient permitted for laying LWR/CWR is .
629 Long & Short Welded Rails SEJ for LWR cannot be located at .
Cold weather patroling will be introduced when rail temp falls
630 Long & Short Welded Rails
below .
631 Mechanized Track Maintenance How many rounds of machine packing are required after deep screening in LWR/CWR ?
632 Rail/Weld failures and USFD No of probes in DRT machine is .
Curves Design and
633 Maximum radius of vertical curve on A Route is .
Realignment
634 Long & Short Welded Rails In case of destressing by Rail tensor destressing temp will be .
635 Long & Short Welded Rails Minimum shoulder ballast on outside of curve in LWR track is .
636 Mechanized Track Maintenance Squeezing pressure in case of PRC sleeper is .
637 Rail/Weld failures and USFD Support on mould during tapping can cause .
638 Rail/Weld failures and USFD Inadequate pre-heating will cause .
639 Rail/Weld failures and USFD Premature tapping can cause .
When a cause of a derailment is disputed, track measurements shall be taken in rear
640 Derailments
& ahead.
643 Mechanized Track Maintenance Tamping machine does not make correction to .
645 Mechanized Track Maintenance Squeezing pressure to be set for PSC sleepers on turnout in UNIMAT is .
647 Mechanized Track Maintenance Number of PQRS portal generally required at site during track renewal is .
648 Mechanized Track Maintenance The Vm correction in four point lining is fed in front cabin in .
649 Mechanized Track Maintenance In 3 point lining method .
Curves Design and The maximum cant deficiency which can be considered for BG with permission of Chief Engineer
651
Realignment is
A 1 in 12 turnout is taking off from outside of a 1 deg curve. The resultant curvature lead of the
652 Point & Crossings
turnout will be approximately .
Track Monitoring, Track
653 Riding comfort as given by Ride Index depends on .
Tolerances
661 Derailments When coefficient of friction between Rail and wheel is High ?
As per IRPWM when in curved parallel Track cross over is not laid in inclined plane amount of SE
662 Point & Crossings to be limited
to .
In case of similar Flexure turnout followed by reverse curve, cant can be changed behind Heel of
663 Point & Crossings
crossing.
Curves Design and
664 Degree of 350 m Radius curve is .
Realignment
665 Point & Crossings Design versine value for 1 in 12 Turnout lead curve is .
At the location of SSD in TWS the gap between Gauge face of Stock Rail & Non Gauge face of
666 Point & Crossings
Tounge Rail to be maintained .
In case of measurement of versine for curved switches, Turnout station number 0 is considered
667 Point & Crossings
at .
668 Point & Crossings Straightness of stock rail is measured as mid ordinate at the chord of meter.
Track Monitoring, Track
669 Frequency of TRC, OMS & Oscillograph car runs is based on .
Tolerances
Track Monitoring, Track There are 4 speed band when acceleration peak more than 0.20 g found in which speed band caution
670
Tolerances order to be imposed as per IRPWM.
Track Monitoring, Track In PWI section of 30 KM, what is the Track Quality as per OMS recording if there are 40 peak more
671
Tolerances than 0.20 g and section having speed of 110 KMPH ?
672 Track Monitoring, TQI for short chord is prescribed for overall assessment of track quality for .
675 Long & Short Welded Rails Increase in temp in LWR from td level will generate:
676 Long & Short Welded Rails In Breathing length (BL) portion,
677 Long & Short Welded Rails Destressing temperature for zone IV, 52 kg & 60 kg rail section is
678 Track Machine Maintenance The maximum wear of tamping tool permitted is
679 Long & Short Welded Rails ADEN Shall inspect LWR track once
680 Long & Short Welded Rails Cold weather patrolling will be introduced when rail temp. falls below
681 Formation & Soil Mechanics The steepest permitted side slope for soil embankment is :
682 Track Machine Maintenance In 3-point lining method .
683 Track Machine Maintenance The slew in front cabin is fed in .
684 Track Machine Maintenance Name the BCM Machine that can deep screen only plain track and not turn out .
685 Track Machine Maintenance UNIMAT 3S cannot perform which of the below given function:
686 Track Machine Maintenance Gauge of Auxillary track for TLE Portal is
687 Track Machine Maintenance Maximum slewing by BCM possible is .
688 Track Machine Maintenance Total width of screening done by BCM is .
689 Track Machine Maintenance Total motorised trolleys used for laying points and crossing by T-28 machine is
690 Track Machine Maintenance K correction in lift value to datum rail is .
Track Monitoring, Track In case the measured SD values by TRC are equal to the specified SD values for new track, the TQI
698
Tolerances value of Alignment and unevenness would be-
704 Rail/Weld failures and USFD To detect the half moon defect we use :-
705 Rail/Weld failures and USFD Dead Zone of Single Crystal Probe is mm.
706 Rail/Weld failures and USFD For scab or wheel burn rail testing, we use two probe of :-
707 Rail/Weld failures and USFD In weld testing by tandem rig, it will be declared DFWR if flaw echo height is :-
708 Rail/Weld failures and USFD 0 degree 4 Mhz double crystal probe is used for :-
709 Rail/Weld failures and USFD In weld testing, 70 degree side looking probe is used for :-
710 Rail/Weld failures and USFD For calibration setting of angle probe, We use :-
711 Rail/Weld failures and USFD Horizontal defects can be detected by : -
In weld testing, sensitivity setting of 0 degree probe is done by
712 Rail/Weld failures and USFD
:-
713 Rail/Weld failures and USFD Transverse defect can be detected by :-
714 Rail/Weld failures and USFD Vertical longitudinal defect, can be detected during Rail testing by:-
715 Rail/Weld failures and USFD IMR defects have to be replaced :-
716 Rail/Weld failures and USFD In characteristics check, limitation of probe angle is :-
717 Rail/Weld failures and USFD In characteristics check, limitation of probe Index is :-
718 Rail/Weld failures and USFD In rail testing, sensitivity setting of 70 degree central probe is done on :-
719 Rail/Weld failures and USFD In case of OBS/OBS(W), speed restriction will be imposed of :-
Track Monitoring, Track
720 Long chord base for twist measurement is m.
Tolerances
Track Monitoring, Track For assessing the quality of running by OMS, the vertical acceleration acceding g be taken
721
Tolerances for the routes having Speed up to 110 Kmph
722 Track Inspections Gauge for Straight track including curves of radius up to 350 m and more is between .
Wheel dia difference on same axle, same bogie & same coach for coaching stock respectively is
738 Rolling Stock
(In mm).
739 Rolling Stock Vertical load transfer through following in ICF BOGIE -
740 Rolling Stock A false flange may split open points while travelling in .
Derailment proneness will increase
741 Rolling Stock
with .
742 Rolling Stock Term safety depth is associate with .
743 Rail/Weld failures and USFD In DRT, bolt hole defects are detected using probe of degree
The minimum flaw size detectable by USFD testing is
744 Rail/Weld failures and USFD
mm.
745 Rail/Weld failures and USFD What is the speed of Ultrasonic waves for angular Probe in Steel Material ?
What is the reflective index at steel air interface or crack in rail
746 Rail/Weld failures and
?
If λ is the wave length of the ultrasonic wave, the minimum flaw size which can be reliably
747 Rail/Weld failures and USFD
detectable is .
758 new title Minimum rail lengths that shall be provided between SRJ of points and Crossing and SEJ of LWR.
Normally, while performing manual attention to track On LWR, opening of sleepers is limited
767 Long & Short Welded Rails
to .
Conventional Track
768 As per rail specification deflection of over 1.5m span renders a rail unacceptable.
Maintenance and Renewals
Conventional Track
769 While stacking rails, number of layers in stack should not to be more than
Maintenance and Renewals
Conventional Track
770 EUR means
Maintenance and Renewals
िकी आठवीं अनुसूची म अब तक ि
कतनी भाषाओं को शािमल
771 Ballast
ि गया है ?
772 Ballast ि ि े ों ि िलए
े ों देश को ि
कतने े
ों
म बांटा गया है ?
Conventional Track If 20% or more of sample size records toe load below 400 kg, then sample size to be conformed for
773
Maintenance and Renewals proposal for TFR is
774 Turnouts and Curves In fan shaped Turn-outs hitting of nose of crossing can be avoided by
777 Long & Short Welded Rails Hot weather patrolling for LWR/CWR track shall be introduced when:-
778 Point & Crossings On I.R., the Chord Length for measurement of Versine on Turn in curves is taken at every :
When more than one track machine is running in a block section, there should be a minimum
779 Mechanized Track
distance of
Conventional Track
780 Periodicity of renewal of Block joint (insulated rail joints)
Maintenance and Renewals
781 Point & Crossings Codal life of point machine for A and B route is
Track Monitoring, Track
782 The virtual transition length for BG is m.
Tolerances
783 Track Machine Maintenance The muck in BCM is disposed outside the track by
791 Derailments An accident will be termed as serious accident when the loss of Railway property is more than
800 Mechanized Track Maintenance The tamping cycle of track on PSC sleepers as per IRTMM- 2000 is
Cold weather patrol on freshly deep screened track will be introduced when rail temperature falls
803 Long & Short Welded Rails
below
At td, immediately after destressing, the distance of tongue rail tip from reference line at SEJ in case
804 Long & Short Welded Rails
of 52 kg Rail section is
805 Long & Short Welded Rails SEJ in LWR territory with an LC in between should be laid
807 Long & Short Welded Rails The Rail Thermometer shall be inspected for reliability
808 Long & Short Welded Rails In case gap in SEJ is noticed to be abnormal
Conventional Track In case of renewal of Rubber pad in LWR, fastening up to 5 sleepers on either side may be removed
811
Maintenance and Renewals for replacement of rubber pad under the rail.
813 Point & Crossings In PSC sleeper layout the approach sleepers (1AS, 2AS, 3A, 4A) are provided for
814 Point & Crossings There is a 6 mm difference in the rail top level of stock and Tongue rail in case of Thick web switch
The speed potential of Thick Web switches (TWS) when compared with over riding switch (ORS)
815 Point & Crossings on PSC layouts is
for 1 in 12 turnouts.
816 Turnouts and Curves The speed potential of a Turnout primarily depends on
In B-scan System on Y axis of Screen,
817 Rolling Stock
of Sound wave is produced to represent the data.
While using only B-scan System, we are not able to get the
818 Rail/Weld failures and USFD
of the Defect.
819 Rail/Weld failures and USFD Most Advantageous feature of B-scan System is .
820 Rail/Weld failures and USFD In Flash Butt welding process, joining of surfaces take place by
823 select Dimensional tolerences for the finished weld in FB welding are
824 select In FB Welding, QAP approval is done by
826 select Sample tests on welds are to be conducted in Flash Butt welding for
827 select Frequency of testing on Sample welds for Mobile Flash butt welding is
830 Turnouts and Curves Turnout parameters - A, M & K in centre line method of layout calculation depend upon
831 Turnouts and Curves For determing the Overall length of layout on curved parallel tracks, the method used is
832 Rail/Weld failures and USFD Full Skip distance for 70 deg Probe is =
833 Rail/Weld failures and USFD Half skip distance for 45 deg Probe is =
During Initial Weld Testing if flaw echo found of amplitude 51% using Tanedm RIG with 45 deg
834 Rail/Weld failures and USFD
Probe, it shall be declared as
835 Rail/Weld failures and USFD Which Probe/Probes can detect Star cracks during rail testing in DRT/SRT machine.
836 Rail/Weld failures and USFD Increase in Rail temp in LWR from td level will generate
837 Track Inspections Datum Rail for Mechanised Maintenance on curves is normally
838 Track Inspections Hot weather patrolling is to introduced in LWR territory having PSC sleepers with density 1660
839 new title What is the minimum number of layers allowed in a drawing?
840 Track Inspections Minimum number of persons required to operate push trolley are -
841 Track Inspections Push trolley persons should be operated by persons holding
842 Track Inspections Medical category for operating push trolley is
843 Track Inspections Trollyes in all case shall be:-
844 Track Inspections When a train is sighted , the flagman should -
845 Track Inspections During night and during day when visibility is poor trolley-
846 Fastenings Following is not the function of Grooved Rubber Sole Plate
Conventional Track
852 Central binding of sleepers may cause
Maintenance and Renewals
Conventional Track
853 Depot Engineer shall be responsible for all track maintenance activities at
Maintenance and Renewals
It shall be responsibility of the Depot Engineer to ensure that all his tasks, duties and responsibilities
854 select
are undertaken in accordance and absolute compliance with the DFCCILânns
856 Derailments On receipt of intimation of the occurrence of an accident Sr Executive/ Executive should
When accompanying higher officials on periodical or special inspections Sr Executive/ Executive
857 select
should carry
870 Mechanized Track Maintenance Corrections required in Design Lift values are
874 Mechanized Track Maintenance Shoulder Ballast Cleaning Machine is used for
875 Mechanized Track In a zonal Railway, track machines are under the overall charge of
876 Mechanized Track Maintenance Track machines are to be inspected regularly by
878 Turnouts and Curves There could be difference in the rail top level of stock and tongue rail in case of overriding switch.
879 Geotechnical Soil The diameter of soil less than 75 microns is called :
880 Geotechnical Soil In SQ1 type soil, the percentage of Fines is :
881 Geotechnical Soil In case of Embankment design, the Pressure on Subsoil should not generally exceed
882 select Through Destressing of CWR on DFCCIL shall be done Once in
883 Geotechnical Soil Minimum soaked CBR Value for a Blanket material should be equal or more than :
884 Geotechnical Soil Plasticity Index is the difference between
902 Mechanized Track Maintenance Versine Modification values in 4-point lining are required
962 select As per IS 456, Maximum area of tension reinforcement in RC beam shall not exceed
963 select Minimum tension reinforcement in RC Beam is provided
964 select Maximum Stress in concrete in bending is equal to
965 select Impact of axial compression to shear strength of concrete is
966 new title If the shear stress in concrete is more than the maximum permissible limit.
967 select T beam can be designed like rectangular beam if the depth of neutral axis xu is
968 new title As per IRC 112, the angle of compression strut for shear design shall be
969 select For cantilever retaining wall, heel and toe slab is designed as
Soil pressure below open foundation should be less than Safe bearing pressure. For calculating soil
970 select
pressure the loads to be considered are
fck is the strength of concrete below which not more than x% of test results are expected to fall.
971 select
Here x is equal to
975 select Normally which type of piles are used as bridge foundation
976 select Natural rubbers are not preferred to synthetic rubbers for bridge bearings because-
977 Long & Short Welded Rails Inspection of LWR / CWR by on DFCCIL by Executive/Sr. Executive shall be done once in
Hot / Cold Weather Patrolling Inspection in DFCCIL by Executive/Sr. Executive shall be done once
978 Long & Short Welded Rails
in
979 Mechanized Track Which machine is used for tamping of turnouts?
980 Long & Short Welded Rails Through Renewal of Fitting (Track)on DFCCIL shall be done Once in
981 Long & Short Welded Rails After emergency repair following a Rail fracrure on DFCCIL, traffic may be restored at a speed of
982 Long & Short Welded Rails Minimum Length of Closure rail on DFCCIL shall be
983 Long & Short Welded Rails destressing temperature range in DFCCIL shall be
984 Long & Short Welded Rails ideal destressing temperature should be, preferably -
985 Long & Short Welded Rails while replacing rail after frature, the principle should be
Equalization of Forces shall be done for a length of on both sides of the final weld after rail
986 Long & Short Welded Rails
fracture repairs
while making cut in rail for rail replacement, the Heat affected Zone shall be taken as mm
987 Long & Short Welded Rails
from the AT weld.
while making cut in rail for rail replacement, the Heat affected Zone shall be taken as mm
988 Long & Short Welded Rails
from the FB weld.
989 Long & Short Welded Rails Minimum Anchor length in DFCCIL when fitting are new and in good condition shall be
990 Long & Short Welded Rails Anchor length in DFCCIL when fitting and ballast consitions are not good shall be
while destrsssing with tensor or Super puller, some movement is expected at Inner Reference mark
991 Long & Short Welded Rails
(IRM)
while destrsssing with tensor or Super puller, some movement is expected at Outer Reference mark
992 Long & Short Welded Rails
(ORM)
Maximum length that can be tackled while destressing using Tensor / super puller on straight track
993 Long & Short Welded Rails
shall be on either side of the tensor / puller
994 Long & Short Welded Rails use of rail tensor / Super puller is to be done when prevailing temperature is than SFT / Td
995 Long & Short Welded Rails The frequency of Checking accuracy of Rail thermometer is : once in
996 Long & Short Welded Rails while doing destressing, maximum distance apart of thermometers shall be
997 Long & Short Welded Rails Extension required while doing destressing with tensor / super puller shall be calculated for
998 Long & Short Welded Rails The maximum pull to be applied in tensor shall not exceed the lesser of
while welding the final weld using rail tensor, minimum time after pouring of metal before passing
999 Long & Short Welded Rails
first train is
The SFTs of the two rails of the track should not differ by more than when checked with
1000 Long & Short Welded Rails
VERSE
In P&C areas, after replacement of Rail / Stock Rail / Tongue rail, destressing can be done using
1001 Long & Short Welded Rails
Rail tensor
1002 Long & Short Welded Rails In P&C areas, replacement of Stock Rail / Tongue rail should always be done together
If one side tongue rail is fractured, the traffic on other side tongue rail route, which is intact, can be
1003 Long & Short Welded Rails
permitted at
If one side tongue rail is fractured, the traffic on other side tongue rail route, which is intact, can be
1004 Long & Short Welded Rails
permitted at
1005 Long & Short Welded Rails In case CMS crossing is fractured,
1006 Long & Short Welded Rails while replacing the CMS crossing, the refernce mark shall be
1007 Long & Short Welded Rails The mean position of ACD or ideal gap in ACD shall be
1008 Long & Short Welded Rails In trap switches / derailing switches, the number of ACD devices is
1009 Long & Short Welded Rails Regular tightening of bolts of ACD with torque wrench shall be done at a maximum Torque of
1010 Long & Short Welded Rails sluing inward on horizontal curves will lead to
1011 Long & Short Welded Rails sluing outward on horizontal curves will lead to
Work which may reduce the stability of track shall not be done when the prevailing rail temperature
1012 Long & Short Welded Rails
exceeds
1013 Long & Short Welded Rails In LWR portion Rail creep in excess of shall not be permitted
1014 Long & Short Welded Rails Left and Right Rails absolute creep difference shall not be more than
1015 Long & Short Welded Rails Creep measurement shall be done by Executive once in
1016 Long & Short Welded Rails Time taken for VERSE measurement is about
1017 Long & Short Welded Rails Patrolling of track shall be started as soon as rail temperature rises beyond
1018 Long & Short Welded Rails during Destressing, if fastenings on alternate sleepers are loosened, Speed restriction shall be
1019 Turnouts and Curves 1 in 12 Turnout can be taken off from inside of a curve of
1020 Turnouts and Curves For determining the overall length of layout on curved parallel tracks, the method used is
1021 Turnouts and Curves When Turnout is provided in transition of a curve
1022 Mechanized Track Maintenance Correction required in Design Lift values are
1023 select What is the recommended radius of curve (in meter) on DFCCIL routes.
How much degree of curve when versine of horizontal circular curve measured on 20 meter chord
1024 select
measured as 57mm
1025 select What extra dimension are to be consider when inside of curve track any structure is planned.
1026 select What is not consider when spacing between two parallel curved track is planned.
1027 select Calculate radius of six degree curve (in meter).
1028 select How much maximum cant deficiency is taken on DFCCIL routes.
1029 select Permitted speed on 1 in 12 thick web turnout
1030 select which stock rail of turnout is curved when LH turnout is laid.
1031 select what is the chord for versine measurment of a turnout curve
1032 select Full form of SSD
1033 select Full form of SRJ
1034 select When a contrary turnout laid super elevation provided to main line is ân¦ân¦. SE for turnout.
1035 select laying of turnout should be avoided inân¦ân¦ân¦ân¦ân¦ portion of track.
1036 select Calculate equilibrium SE in mm when vehicle moves with 100 kmph speed on two degree curve.
1037 select what is degine value of versine for 1 in 12 turnout.
1038 select Minimum check rail cLearance at opposite nose of crossing on DFCCIL TURNOUT.
1039 select Extra width of ballast on outer side of curve in mm is ân¦.
1040 select Realignment of curve is done by ân¦ân¦ân¦ân¦.. Method
1041 Track Machine Maintenance Tamping depth depends upon
1042 Track Machine Maintenance NTC machine is used for
While Reconditioning of CMS Crossings, temperature during the welding process should not exceed
1073 Turnouts and Curves
beyond .
If gauge of track adjoining the points and crossings is maintained wider/tighter than the gauge on
points and crossings the gauge on adjoining track must be brought to the same gauge as in the points
1074 new title
and crossings and run out at the rate
of to the require site extent
1075 select In Points & Crossings, switch angle is the angle subtended between gauge face of the rails
Speed in excess of kmph can not be permitted on 1in 12 turnouts with thick
1076 select
web switches on PSC sleepers.
While measuring wear on 60kg CMS
1077 select
crossing mm to be deduced from the measured wear?
1078 select For 60Kg / 60 EI Min. height of the old Rail to be welded by
1079 new title The joint shall be kept higher by few higher UTS Rail when measured at the end of 1m straight edge
1080 select The mould waiting time for the 25mm Weld:
1081 new title The rail temperature after the pre heating of the rail
During exothermic reaction the slag (Al2 O3) separate from the reaction minimum temperature
1082 new title
required
1083 select Maximum Cant Allowed on curves in DFCCIL is
1084 new title Ideal Transition curve for speeds permissible in DFCCIL is
1085 Point & Crossings The speed potential of a 1 in 12 TWS Turnout In DFCCIL routes in KMPH
1086 Point & Crossings The speed potential of a 1 in 8.5 TWS Turnout In DFCCIL routes in KMPH
1087 Point & Crossings Gauge to be maintain in opposite nose of crossing asper nominal gauge of turnout.
1088 Point & Crossings Wear at nose of 1 in 12 WCMS crossing is measured at 252 mm away from ANC
1089 Point & Crossings At DFCCL Turnout initial Gap at ACD to be maintained as
1090 Point & Crossings Thickness of Tounge Rail in 1 in 12 Thick Web Switch
1091 Point & Crossings Radius of 1 in 12 Thick Web Switch in meter for DFCCIL Routes
1092 Point & Crossings Check Rail Clearances for T/O in DFCCIL in mm.
1093 Point & Crossings Nos of sleepers in 1 in 8.5 Thick Web Switch
1094 Point & Crossings As per Codal provision in DFCCIL- Renewal of Point and crossing from main line to be done in
1095 Point & Crossings Permissible limit of Lateral wear of rail on curve in DFCCIL in mm
1096 Point & Crossings Frequency of inspection of Point and Crossing in main line by Sr.Executive /Executive
Choice 1 Choice 1 Choice 2 Choice 3 Answer
leading direction Trailing direction both the above condition none of above 2
(a) 50 mm/s (b) 25 mm/s (c) 55mm/s d) 40 mm/s 3
(a) 1:1200 (b) 1:600 (c) 1:360 (d) 1:720 3
(a) Ca + Ct for turnout (b) Ca – Ct for turnout (c) Cd + Ct for turnout (d) Cd-Ct for turnout. 4
c) retention of 20 mm sieve is
a) retention of 40 mm b) retention of 40 mm sieve is less d) retention of 20 mm sieve
more than 98% d) retention of 2
sieve is more than 40% than 40% is more than 95%
20 mm sieve is more than 95%
Total Stress Parameters Normal Stress Parameters Effective Stress Parameters Residual Stress Parameters 3
a) Machine cut a rail piece b) Gas cut of rail piece of 6.5 m c) Wait for temperature to go
from track and slew back length approx... and slewing back down before slewing back track NONE OF THESE 2
the track track to original alignment to original position
0
15% 20% 25% 30% 2
20% 25% 30% 35% 3
1% 2% 3% 4% 1
1m 1.5m 2.0m 2.5m 3
50cm 75cm 100cm 125cm 1
imapct value test abrasion value test water absorption test flakiness index 2
imapct value test abrasion value test water absorption test flakiness index 1
tm to tm +5 C0 tm+5 to tm + 10 0 C tm +5 to tm+20 C None of them 2
1.452 tonnes 1.638 tonnes* 1.750 tonnes 1.962 tonnes 2
SWR LWR CWR* none of them 3
1310 1540* 1660 None of them 2
td+0C to td - 150C td+50C to td-200C td+ 100 to td 250C td + 10 0 to td 200 C 4
A Year in six month in a Quarter Non of above. 4
td + 0 C to td - 50 C td + 50C to td - 100 C td + 10 to td - 20 C td + 10 to td - 300C 4
During every trolley
A Year in six month in a Quarter 3
inspection
EA EA Lαt/r EA αt/r 4
110 kmph 120 kmph Up to 100 kmph less then 100 kmph 1
Track structure Ballast resistance Rail temperature All of these 4
1 year 2 years 3 years 5 years 4
Improve running quality Improve drainage Improve track geometry All the above 2
when the rail temperature when the rail temperature goes when the rail temperature goes
none of above 2
goes beyond tm+10 beyond td+20 beyond td+10
30GMT or 01 year which 40 GMT or 18 months which ever 50 GMT or 02 years which ever 50 GMT or 3
3
ever is earlier is earlier is earlier years which ever is earlier
Riding will be rough, Riding will be rough, Riding will be smooth, Riding will be smooth,
maintenance requirement maintenance requirement will be maintenance requirement will be maintenance requirement will 3
will be more less less be more
Sand Inclusion Lack of fusion slag inclusion nothing will happen 3
0
38mm 25.4mm 16mm 12mm 3
to assess the volume of to ensure that full train has arrived to expedite the movement of
none of above 2
traffic passing on the track at next station train
3 rail length on either side 100 m & 45 m 100 m on both sides none of above 2
1m 2m 3m 5m 3
1 in 75 1 in 125 1 in 100 1 in 150 3
a) No thermal movement
b) Thermal movement in it but no c) Thermal force & movement
but thermal force available none of these 1
thermal force both not available in it
in it
(M+2) (M+3) (M+4) (M+7) 2
1 in 150 1 in 200 1 in 100 1 in 80 1
u Y Q L 2
22mm 19mm 16mm 13mm 4
1 in 150 1 in 100 1 in 80 1 in 60 3
750 600 450 300 3
Method of Financial
method of recording of Method of Exchequer
Appraisal of Railway method of cash control 1
measurement book Control
Project
True False -- -- 2
16 32 48 56 3
Inner Rail Outer rail, Any of the Two rail None of the above. 2
Towards inside of curve Towards Outside of Curve Can be in any Direction, None of the above. 2
Fd/7 Fd/6 Fd/4 Fd/3 4
UNIMAT TAMPING EXPRESS UTV DTS 3
3-Point geometry/Elimentary
4-Point smoothening mode 4-Point Design mode 3-Point Design mode 4
Mode
3-Point geometry/Elimentary Using Measuring Run By
4-Point smoothening mode 4-Point Design mode 4
Mode ALC
Slew for Realignment of curve
Field survey of Alignment Laser system for straight track CMS system 4
using software
Inner Rail Outer Rail Better of the two Rail Any of the two Rail 1
Lining correction Gauge correction Twist Correction Unevenness correction 3
Upto 20 mm Between 20 to 30 mm Between 30-50 mm Above 50 mm 3
K adjustment X adjustment H adjustmen V adjustment 2
Versine
Superelevation-SE Front offset - Fd General lift 2
correction(H,Hx,Hy,Hz,Hw)
UNIMAT 08-275 UNIMAT 08-275 3S MPT BCM 2
Maximum Settlement
Constant Settlement Mode Zero settlement mode Any of the above 2
mode
On Bridges In Tunnels On Points and Crossing In Station Limit 2
Both Horizontal and vertical
Horizontal direction only Vertical Direction Only None of the above 1
Direction
Time for Lowering and
Squeezing and Holding time Travelling time to next sleeper All the above 4
lifting of Tamping Unit
2 Kmph 5 Kmph 10 Kmph 15 Kmph 3
1000mm 700mm 500mm 200mm 3
100mm 200mm 300mm 250mm 3
BRM model 66 (M/s PBR 400 R ( M/s BRM Model SPZ-210 K USP 2000 SWS
4
Kershaw) Plasser India) (Gemac China) (M/s Plasser)
BRM model 66 (M/s PBR 400 R ( M/s BRM Model SPZ-210 K USP 2000 SWS
4
Kershaw) Plasser India) (Gemac China) (M/s Plasser)
550 GMT 10 Years 15 Years 450 GMT 2
complete track ballast shoulder ballast crib ballast All of the above 2
anticlockwise clockwise up to down down to up 1
1000 sleepers 1600 sleepers 2000 sleepers 2600 sleepers 2
UNIMAT TAMPING EXPRESS CSM All of the above 1
Tamping unit rotation
Tilting tamping tool Tamping unit lateral movement All of the above 4
facility
80mm 60mm 50mm 40mm 3
PQRS TRT RBMV T-28 4
90 to 100 kmph 25 to 30 kmph 10 to 15 kmph none of above 2
100mm 150mm 200mm 250mm 2
Height potentiometer. Slew potentiometer Versine potentiometer. None of above. 3
Both the transducers are Transducer at C is only switched Transducer at B is only switched
None of the above 4
switched off off off
On 4 point method slews On 3 point method slew values, On 3 point method slew
On 4 point method, slews values
values, versine value and versine value and transition values and versine values are 4
and versine values are fed
transition correction is fed correction is fed fed.
100 mm and 100 mm 200 mm and 200 mm 300 mm and 300 mm 400 mm and 400 mm 3
X correction K Correction Vm correction H correction 2
ATS to Heel of Switch ATS to the end of T/R TTS to Heel of switch TTS to the end of Stock Rail 1
510 mm 450 mm 250 mm 200 mm 4
Equal to built up crossings. Shorter than built up crossings. Longer than built up crossings. None of the above. 2
13 mm 10 mm 8 mm 6 mm 3
True False -- -- 1
0.4 to 0.6 seconds 0.4 to 0.8 seconds 0.6 to 1.0 seconds 0.2 to 1.0 seconds 4
55 mm/sec with 35
35mm/sec with 55 mm/sec in
mm/sec in exceptional 75 mm/sec None of the above is correct 2
exceptional cases
cases
Track Relaying Train Track Rennovation Train Track Repair Train Track Laying Train 1
1676 mm 1750 mm 1673 mm 1600 mm 2
20 m 3m 6m 10 m 1
True False -- -- 1
True False -- -- 1
TRUE FALSE . . 2
True False -- -- 1
True False -- -- 2
Inward Outward No Change in Position None of the above 1
OMU MMU-I MMU-II Sectional Gang 3
A9 B0 C 12 D 15 4
True False -- -- 1
True False -- -- 2
True False -- -- 2
True False -- -- 2
True False -- -- 2
True False -- -- 2
True False -- -- 2
ATS to Heel of Switch ATS to the end of T/R TTS to Heel of switch TTS to the end of Stock Rail 4
41 mm to 45 mm 51 mm to 57 mm 44 mm to 48 mm 57 mm to 61 mm 4
Riding will be rough, Riding will be rough, Riding will be smooth, Riding will be smooth,
maintenance requirement maintenance requirement will be maintenance requirement will be maintenance requirement will 4
will be more less less be more
14.6 m 20 m 14.785 m 10 m 4
Reverse-canting of approach
Strengthening of approach. Signalling installations. none of these. 3
rail.
True False -- -- 4
True False -- -- 4
1.50 meters from track 2.50 meters from the end of 1 meter from the end of
1 meter from track centre 4
centre sleeper sleeper.
7t 8t 6t 9t 4
Track Geometry
Vehicle Design Parameters Speed of Operation All of the above 4
Parameters
True False -- -- 4
TRUE False . . 2
For handling of rails for ballast specification for AT welding for Flash Butt Welding 1
Lateral and vertical
Parameter wise bad location Ride Index Speed of the vehicle run. 2
acceleration
50 M 12.5 M 25 M 100 M 1
60 67 80 77 2
TRUE FALSE . . 1
c) Accelerations measured by
a) Track Structure b) Type of the sleepers d) Ballast Cushion 3
the accelerometer
TRUE FALSE . . 2
TRUE FALSE . . 1
TRUE FALSE . . 1
TRUE FALSE . . 1
TRUE FALSE . . 1
A9 B0 C 12 D 15 3
IS: 409-1981 IS: 406-1981 IS: 408-1981 IS: 407-1981 3
4 years or 200 GMT 5 years or 100 GMT 6 years or 200 GMT 3 years or 200 GMT 1
20% or more test results
30% or more test results record 20% or more test results record 30% or more test results
record toe load below 400 1
toe load below 400 Kg toe load below 600 Kg record toe load below 600 Kg
Kg
20,000 30,000 40,000 50,000 4
Normally open to road May not be protected by
Normally closed to road traffic Not be interlocked 1
traffic signals
Within outer most stop
Beyond outer most stop signal Not protected by signal Protected by signal 2
signal
20 nos 15 nos 10 nos 12 nos 3
6m 7m 8m 9m 3
Two years Three years One year Four years 2
One for each Section DEN/Sr. One for each SSE/JE (P. Way)
One for each Subdivision One for each Division 3
DEN Section
MMU-I MMU-II Both None of the above 2
Space for storing of Small Track
Crane for lifting of rails Space for carriage manpower All of the above. 4
Machines
Once in Six months Once in Two months Once in Four months Once in a year 2
Once in Fortnight Once in month Once in Two month Once in Three month 2
23:00 Hrs. to 03:00 22:00 Hrs. to 02:00 01:00 Hrs. to
00:00 Hrs. to 04:00 Hrs. 3
Hrs. Hrs. 05:00 Hrs.
4-5 min. 3-4 min. 5-6 min. 2-3 min. 2
50 ton 60 ton 70 ton 80 ton 3
100-110 Kg. 90-95 Kg. 80-85 Kg. 70-75 Kg. 2
4 months 6 months 2 months 12 months 2
TRUE FALSE . . 2
Sin F Cos F Tan F Cot F 4
80x50x36mm 80x40x32mm 80x40x30mm 80x50x25mm 4
1 mm 2 mm 2.5 mm 3.5 mm 3
TRUE FALSE -- -- 2
TRUE FALSE -- -- 1
TRUE FALSE -- -- 2
TRUE FALSE -- -- 1
10 m 50 m 20 m 30 m 2
1670mm 1700mm 1760mm 1690mm 1
2000mm 1670mm 1905mm 1680mm 3
115mm 95mm 100mm 160mm 2
TRUE FALSE -- -- 1
Asset Data can be seen by Asset Data cannot be changed by Asset is not available for
Non of the above 3
AEN and higher officials SSE inspection
TRUE FALSE -- -- 1
Can be created by JE and Can be Created and saved by SSE Created by SSE and confirmed Created at Divisional level
2
confirmed by SSE no confirmation is required. by AEN only
TRUE FALSE -- -- 2
TRUE FALSE -- -- 1
Location of defect Date of compliance Manpower used in compliance All the above 2
Downloading of inspection,
Downloading of inspection, assets, track diagram etc. to
Deleting of unnecessary Dumping of old inspection
assets, track diagram etc. for a display before higher official 4
information for a JE/SSE records not required for a JE/SSE
JE/SSE without having net
connection
Alignment Longitudinal level and cross level Gauge Packing under sleeper 4
split switches overriding switches curved switches all of these 4
1.5 m (to - tp) 4.5 m ( to - tp ) 2.5 m (to - tp) 100 metres 3
Behavior of elastic Availability of compacted ballast
Laying on stable bank All of Above 4
fastening section
a) Filling of adequate
b) Squaring of sleeper c) Gauging d) All above 4
ballast in shoulder & crib.
a) 0.4 to 0.6 sec. b) 0.6 to 0.8 sec c) 0.8 to 1.2 sec. d) 1.2 to 1.4 sec. 3
a) True b) False -- -- 1
c) suspending traffic & protect
a) Emergency repair b) Temporary repair NONE OF THESE 3
line
Free to move so no Thermal force gradually
Uniform force equal to half the
thermal force throughout increasing from SEJ to central All of Above 3
force in central portion
B.L portion
Will not affect td level Will affect td by increasing it Will affect td by lowering it None of Above 3
Tamping 3rd rail of Points
Lining of track Slewing of track Carrying of men and material 4
and crossing
ADEN JE / SE / SSE Gang Mate None of Above 2
50 deg C 60 deg C 76 deg C 48 deg C 4
190 mm 120 mm 65 mm 40 mm 4
After 10 years or passage If the clean ballast cushion is <
of 500 GMT whichever is 150 mm in machine maintained All of Above None of Above 3
earlier section.
150 mm 10 mm 75 mm 50 mm 3
190 mm 120 mm 80 mm 65 mm 4
05 cuts 06 cuts 07 cuts 08 cuts 3
1 mm 0.5 mm 1.5 mm 0.75 mm 1
1 Inch 2 Inch 3 Inch 4 Inch 3
True False _ _ 1
1 Month 2 Months 3 Month 6 Month 3
3.25 m 4.00 m 5.00 m 4.50 2
8 6 15 10 4
1% 2% 3% 5% 2
once in 10 days once in 7 days once in 15 days once in 30 days 2
once in 3 days once in 7 days once in 15 days once in 30 days 1
6 months 1 Year 2 Year 3 Year 2
5 mm 6 mm 9 mm 13 mm 2
If JE done the Trolly
G.M.T. less than 5
Once in a month Once in fortnightly inspection once in the 2 1
G.M.T once in 2 month
month.
Once in a month rotation Once in 2 month rotation with
Once in fortnightly rotation with Once in a month without any
with systematic manner systematic manner with JE 1
JE (P.Way) rotation with JE (P.Way)
with JE. (P.Way) (P.Way)
28.5 mm 57 mm 1750 mm 114 mm 4
Number of track only. Speed of section. None A & B Both 4
LL, AL and XL is attended LL, AL and XL is attended on Main line is tamped first and
both a & c is correct 4
on main line only both line then the loop line
True False - -- 1
Cant Versine Gauge Twist 2
2.3 m 4.3 m 3.4 m 5.3 m 3
Gauge of track Condition of track fittings Condition of tamping tools All of above 4
will depend upon hysteresis
compressive force tensile force None of the above 1
curve
Will not affect td level Will affect td by increasing it Will affect td by lowering it None of the above 3
After initial laying of when the SEJ gap observed if temporary repairs exceed 3
All of above 4
LWR beyond the specifined limits per km in LWR
upto 100 sleepers to be
no restriction, but the temperature
opened at a time by Gang only 30 sleepers to be opened None of the above 3
restriction to be observed
mate,
1 in 200 1 in 50 1 in 100 1 in 500 3
200 m 250 m 300 m 500 m 2
less than length of rail put
more than length of rail put in equal to length of rail put in None of the above 3
in
Equal to built up crossings. Shorter than built up crossings. Longer than built up crossings. None of the above. 2
156 mm 165 mm 185 mm 140 mm 2
100 mm 95 mm 115 mm 160 mm 2
Tongue rail is 6 mm high from
There is inbuilt Twist in Thick Swing nose crossings cannot
SSD is provided at ATS Stock rail at JOH in OR 3
web switches be used on High speed routes
switches
Only SSE (in-charge) can transact Both JE & SSE can transact
JE can transact stores ADEN can transact stores 2
stores stores
Between 20 and
More than 20,000 Hz Less than 20 Hz None of Above 1
20,000 Hz
4 2 2.5 0 2
Angle of Crystal Reflection Incidence Refraction 4
Half Same Double Three times 3
IS:12666-1988 IS:12686-1966 IS:12600-1988 IS:12673-1991 1
WD-17
WD-17 Misc.-1992 or WD-21 Misc.-1996 or WD-22 WD-12 Misc.-1992 or WD- 12
Misc.-1999 or WD-24 1
WD-24 Misc.-2004 Misc.-2002 Misc.-2004
Misc.-2004
30 50 55 40 2
70 180 100 85 4
5 mm 3 mm 12 mm None of Above 2
6 dB 10 dB 12 dB None of Above 2
100 mm 70 mm 165 mm 134 mm 4
0.8 mm 1 mm 0.75 mm 1.6 mm 3
0.8 mm 0.2 mm 0.75 mm 1 mm 2
Joggle Fish Plate with Two Joggle fishplate with one Far end Joggle Fish Plate with Two
None of above 1
Far End Bolt Bolt clamps
3230 3220 5920 5930 3
3230 3220 5920 5930 1
50 mm 25 mm 21 mm 23 mm 4
Horizontal Vertical Vertical Longitudinal Transverse 2
Severity Location Size Area 2
Severity Location Size Area 1
2 Mhz S/C Probe 4 Mhz S/C Probe 2 Mhz D/C Probe 4 Mhz D/C Probe 1
3 to 4 mm 5 to 7 mm 10 to 12 mm 8 to 10 mm 1
37 deg 70 deg 45 deg 0 deg side Probing 4
Double Half Same None of Above 2
70 % 50 % 100 % 0% 3
27.5 deg 57.7 deg 25.7 deg 75.7 deg 1
Velocities of the wave Frequency of Wave Wave Length Grain Size 1
44 mm Zero 48 mm 57 - 60 mm 4
1 mm 2 mm 2.5 mm 3.5 mm 3
41 mm to 45 mm 51 mm to 57 mm 44 mm to 48 mm 57 mm to 61 mm 1
maximum 350 mts maximum 441 mts minimum 350 mts minimum 441 mts 3
6 mm 8 mm 10 mm 12 mm 2
from SRJ to Heel of from SRJ to last long sleeper after from SRJ to tangent point on
from SRJ to SRJ 4
crossing crossing other track
150 mm behind ANC 100 mm behind ANC 50 mm behind ANC 75 mm behind ANC 2
from ATS to heel of from JOH to 1st sleeper after (1) and (2) depending on
from JOH to TNC 3
switch heel of switch design
35 GMT 50 GMT 75 GMT 100 GMT 2
400 deg. cel. 300 deg. cel. 250 deg. cel. 150 deg. cel. 4
half the slew at a station Double the slew at a station 1.5 times the slew at a station equal to the slew at a station 1
41 mm 57 mm 61 mm 65 mm 2
Summation of existing
Summation of existing versine is There is no relation between Correcting couple is applied
versine is half of
same that of summation of existing versine and proposed for correction in transition 2
summation of proposed
proposed versines. versines. length.
versines.
1 2 3 4 3
7 14 5 8 2
2000 m 3000 m 4000 m 5000 m 3
td and to is same td is less than to td is more than to None of the above 1
300 mm 350 mm 500 mm 600 mm 3
50-60 kg/cm2 60-70 kg/cm2 90-100 kg/cm2 110-120 kg/cm2 4
Sand Inclusion Lack of fusion Slag inclusion nothing will happen 1
Sand Inclusion Lack of fusion Slag inclusion nothing will happen 2
Sand Inclusion Lack of fusion Slag inclusion nothing will happen 3
3 rail length on either side 100 m & 45 m 100 m both sides None of the above 2
more prone to derailment less prone to derailment as lateral has lower capacity of
None of the above 3
as lateral forces are higher forces are higher negotiating twist in track
Alignment Longitudinal level and cross level Gauge Packing under sleeper 3
90 to 100 kg/cm2 100 to 110 kg/cm2 110 to 120 kg/cm2 125 to 135 kg/cm2 4
Track Relaying Train Track Rennovation Train Track Repair Train Track Laying Train 1
1 2 3 4 2
In 4 point method slews In 3 point method slew values, In 3 point method, slew
In 4 point method, slews values
values, versine value and versine value and transition values and versine values are 4
and versine values are fed
transition correction is fed correction is fed fed.
75 mm 100 mm 65 mm 90 mm 2
20 m 3m 6m 10 m 1
2 3 4 5 4
10 mm 12 mm 14 mm 19 mm 1
57 mm 60 +/- 2 mm 115 mm 160 +/- 3 mm 2
Speed below 100 KMPH Speed above 100 KMPH Speed of 100 KMPH For all Speed 4
Measured SD values are Measured SD values are near to Measured SD values are near to Measured SD values are near
3
near to UML PML NBML to NTL
Spot attention To put caution order Through tamping attention None of the above 3
tm to tm+5 Degree Celsius tm+5 to tm+10 Degree Celsius tm to tm+10 Degree Celsius tm to tm+20 Degree Celsius 2
10% 15% 20% 25% 3
During every trolley
in a Year in six months in a Quarter 2
inspection
td-10 Degree Celsius td - 15 Degree Celsius td - 25 Degree Celsius td - 30 Degree Celsius 4
2H : 1V 1.5H : 1V 1.25H : 1V 1H : 1V 1
Both the transducers are Transducer at C is only switched Transducer at B is clamped to
None of the above 3
switched off. off. Zero.
SE potentiometer Slew potentiometer Versine potentiometer None of the above 2
BCM RM 76 BCM RM 80 BCM 80-92U None of the above 2
1 2 3 4 3
1 2 4 None of the above 2
Block Section wise Block Wise Location wise Block and Location wise 1
-6 to +4 -5 to +3 -5 to +5 -3 to +3 2
1 2 3 4 2
4 mm/m 3 mm/m 2 mm/m 1 mm/m 1
1 Km 2 Km 3 Km 4 Km 1
5 nos. 15 nos. 10 nos. 8 nos. 3
A B C None of the above 4
Versine Slew Lift Vm Correction. 1
10 30 20 50 3
0.4 to 0.6 0.5 to 0.8 0.8 to 1.2 1.0 to 1.5 3
100 200 300 150 1
200 500 600 300 2
λ λ/2 λ/4 2λ 2
Between 200 Hz
More than 20000 Hz Less than 20000 Hz Between 50Hz to 200 Hz 1
to 20000 Hz
SSE/P.way ADEN DEN Sr. DEN 2
Only in without Both under and without Always without 1
30 600 1200 45 2
60 50 45 40 3
Motor trolley Push trolley Dip lorry None of the above 1
Week Month Two month Quarter 2
PCE Sr. DEN CTE ADEN 1
5 2 1.5 3 3
10 20 25 30 4
1 2 3 4 2
12 11 10 14 3
End Unloading Rake End Unloading Rail Easy Unloading Rake Emergency Unloading Rake 1
18 19 26 22 4
1 े 2 े 3 े 5 े 3
2% 10 % 5% 12 % 3
Once in three month Once in Six month Once in a year None of the above 2
7 years 15 years 1 years 12 years 4
1.4785 m 14.785 m 1.7485 m 17.485 m 2
distribution conveyor belt main conveyor belt waste conveyor belt lateral conveyor belt 3
38 mm 25.4 mm 16 mm 12 mm 3
SE potentiometer. Slew potentiometer. Versine potentiometer. None of above. 2
True False -- -- 2
Once in 3 years or 200 Once in 1.5 years or 100 GMT Once in 2 years or 100 GMT
None of the above 3
GMT whichever is earlier whichever is earlier whichever is earlier
True False -- -- 2
More than ORS Less than ORS Same as that of ORS None of these 1
Inner rail Outer rail better Levelled rail of the two Any of the rails can be taken 1
when the rail temperature when the rail temperature goes when the rail temperature goes when the rail temperature
4
goes beyond tm+10 beyond td+20 beyond td+10 goes beyond td+25
0 5 1 2 3
3 5 4 10 3
Driving Licence Valid competency certificate CRS Certificate Adhaar Card 2
B1 or below B2 A3 B2 or below 3
Pulled Pushed Pushed then pulled Pulled and then pushed 2
Place Three detonators 10 m
Place Banner flag Shout vogourously Run towards trolley 4
apart on the line
Can be placed on track and
Should be run under block Can be placed on track
Can run without block protection informed to the station 1
protection only cautiousely
master
Absorbs shocks and damp Increase frictional resistance to
Distribute load uniformly
out vibrations and reduce longitudinal and lateral movement Helps Tamping operation 3
over sleeper
sleeper strain of rail
Three layers of different Two layers of different types of One layers of different types of Three layers of different
types of rubber which has rubber which has top layer higher rubber which has top layer types of rubber which has top 2
top layer higher modulus modulus higher modulus of layer higher
Manufacturers initial, Year Railway, method of
Method of manufacturing,
& Month of manufacturing Hardness, Type of rail and sleeper manufacturing and tensile 1
Tensile strength and elongation
and Drawing number strength
Safety management
Works manual Works management system None of above 1
system.
Improving the cross Increasing the Ballast cushion Removal of Ballast from
Regulating the ballast 1
drainage of track below the sleepers track
Chief Track Engineer Chief Engineer/Track Machine Chief Mechanical Engineer Chief Electrical Engineer 2
Both Open Line and Track
Only Open line Officials Only Track Machine Officials RDSO 3
machine officials
Location with worst defects of
Unevenness, Alignment, twist and Defects due to cupped weld
Riding quality of track unevenness, alignment, twist 4
gauge defects and rail corrugations.
and gauge
True False -- -- 2
Fine grained Coarse grained Sand Fines 4
< 50 % > 50 % 12 ânn 50 % < 12 % 2
0.1 kg/cm2 0.3 kg/cm2 1 kg/cm2 3 kg/cm2 3
Every 10 Years Every 2 Years Every 15 Years Every 5 Years 4
7 10 20 25 4
Liquid Limit and
Liquid Limit and Plastic Limit Both (a) and (b) None of these 2
Shrinkage Limit
Track Maintenance System Track Modernization System Track Mechanization System Track Management System 4
>6 <6 >4 <4 3
<6 >6 >4 <4 2
PI>4 PI<4 PI>7 PI<7 2
PI>4 PI<4 PI>7 PI<7 3
PI>4 PI<7 PI>4 &<7 None of the above 3
Ip=0.43(WL-20) WL=0.43(Ip-20) WL=0.73(Ip-20) Ip=0.73(WL-20) 4
IS:1948 IS:1498 IS:1894 None of the above 2
SQ3 SQ2 SQ1 None of the above 3
SQ1 SQ2 SQ3 None of the above 3
300 400 550 700 3
300 400 550 700 4
140 MPa 120 MPa 100 MPa 80 MPa 3
140 MPa 120 MPa 100 MPa 80 MPa 2
40% 30% 25% 20% 3
>12 KPa <12 KPa <25KPa >25 KPa 3
Will cause relatively less gap
Allow girder to freely
Cause extra forces on substructure during fracture near girder All of Above 1
expand & contract
bridges
Irrespective of whether
when working in when working in design mode Neither in design mode nor in
working in smoothening 4
smoothening mode only only smoothening mode
mode or design mode
Sectional theory Interaction theory Variable angle truss theory Modified compression theory 3
Beam in flexure Beam in shear Column in pure compression All of the above 1
Full passive pressure shall No passive pressure shall be 1/3rd passive pressure shall
1/2 passive pressure shall be taken 4
be taken taken be taken
Strain Stress BM SF 1
As grade of concrete
As grade of concrete decreases Will remain constant None of the above 2
increases
Initial tangent modules Tangent modulus Secant modulus All of above 3
5700 X square root of fck 6000 X square root of fck 4000 X square root of fck 5000 X square root of fck 4
5 10 50 95 1
75 85 95 105 2
20m or two sleepers per
40m or four sleepers per degC
degC temperature
temperature difference from the
difference from the 30m 15m 1
proposed SFT, whichever is
proposed SFT, whichever
greater
is greater
135 m Minimum 135m maximum 125m minimum 125m maximum 1
TRUE FALSE -- -- 1
TRUE FALSE -- -- 2
TRUE FALSE -- -- 2
TRUE FALSE -- -- 1
25 KMPH for Main line 50 KMPH for Main line 75 KMPH for Main line Full speed for Main line 2
45 KMPH for Loop Line 30 KMPH for Loop Line 20 KMPH for Loop Line 10 KMPH for Loop Line 3
Train can be permitted at NO Trains can be permitted till Train can be permitted at 10 Train can be permitted at 45
2
20 KMPH replacement KMPH KMPH
Heel of Crossing Toe of crossing ANC TNC 4
7mm on either side 8mm on either side 5mm on either side 6mm on either side 1
One Two Absent one on each side 2
800Nm 900Nm 100Nm 1200NM 2
Lowering of SFT Increase in SFT No change in SFT has no effect 1
Lowering of SFT Increase in SFT No change in SFT has no effect 2
td+10 degree Celsius td+15 degree Celsius td+20 degree Celsius td+25 degree Celsius 1
Plus or minus 20 mm Plus or minus 15 mm Plus or minus 25 mm Plus or minus 30 mm 1
20 mm 25mm 30mm 35mm 3
Every Month during the
Every fortnight during the two
two coldest / hottest
coldest / hottest months of the
months of the year and
year and once in two months Every fortnight during the year Every Month during the year 2
once in two months during
during the other months of the
the other months of the
year
year
1 hour minimum 45 Minutes 2 Hours 20 to 30 minutes 4
td+10 degree centigrade td+15 degree centigrade td+20 degree centigrade td+25 degree centigrade 3
20 KMPH 30 KMPH 45 KMPH 60 KMPH 2
Normally Max 1 degree but up
Maximum 1 degree curve Maximum 2 degree curve without
to 2 degree with the personal Not permitted 3
only approval of PCE
approval of PCE.
Both center line and outer rail
Centre line method Outer Rail Method None of the above 2
method
Versine changes but Cant remains
Versines and Cant both Both Versine and Cant can be
the same upto 20 mtr on both None of the above 2
remains constant. changed
sides.
K-correction for
Horizantal curves and X-
Only K-correction Only X-correction Nil for Design Lift 1
correction for Vertical
curve.
292 392 492 700 4
2 3 4 1 1
Tongue & Check Points & Wings Stock & Tongue Points & Splice 3
30 15 50 75 3
0 2 3 2.5 4
163 mm 160 mm 162 mm 161 mm 1
2 to 2.4 mm 3 to 4 mm upto +1 mm upto ±0.5 mm 1
5 to 7 minutes 7 to 9 minutes 12 minutes None of these 1
650 to 850°C 600°C 2400°C 2800°C 1
More than 2400°C Less than 2400°C No relation with temperature 650°C to 900°C 1
100 mm 140 mm 165 mm 185 mm 2
Cubic Parabola Spiral Hyperbola Ninth Parabola 2
25 30 50 65 3
25 30 50 65 1
0-4 mm 6 to -6 up to 10 up to 20 1
TRUE FALSE -- -- 1
2 mm 5 mm 7 mm 10 mm 3
20 25 30 44 4
430 450 460 470 3
41-44 41-45 44-48 45-50 3
52 54 58 64 2
5 year 8 year 10 year 15 year 1
5 6 8 10 4
2 months 3 months 4 months 6 months 2