SEN QB
SEN QB
Q1.
d) Name two cost estimation approaches / four software quality assurance activities .
e) Specify following cost directives of cocomo: (i) Product attributes (any two) (ii) Hardware
attributes (any two).
f) Differentiate between Software Quality Management and Software Quality Assurance / quality
assurance and quality control (any two points).
g) Define Software Quality Assurance / project Cost Estimation/ software engineering / risk and list
any two type of risk.
Q2.
c) Explain following elements of management spectrum: (i) People (ii) Process (iii) Product (iv) Project
Q3.
c) Draw : proper labeled “LEVEL I Data Flow Diagram” (DFD) for student attendance system.
d) State : importance of “Function Point (FP)” and “Lines of codes (LOC)” in concerned with project
estimation.
g) Prepare : Macro Timeline chart for 20 days of Hotel Management system (6 days a week) consider
broad phase of SDLC.
: GANTT chart and its application for project tracking with an example.
e) Prepare : time line chart for Library Managements System (five days a week) Consider phases of
SDLC.
: Gantt chart for hostel management system. (Five days a week). consider phases of SDLC.
Q5.
a) Enlist Requirement Gathering and Analysis for web based project for registering candidates for
contest (any six points).
b) Differentiate between : White box and Black box testing (any six points).
c) Describe Co-Como II model for evaluating size of software project with any three parameters in
detail.
d) Sketch a use case diagram for library management system with minimum four use cases and two
actors.
e) Explain : the concept of Black box testing and white box testing.
: software process framework with neat labelled diagram and also describe software
process framework activities.
f) Calculate using COCOMO model (i) Effort (ii) Project duration (iii) Average staff size if estimated size
of project is 200 KLOC using organic mode.
: use-case diagram for ATM system with minimum four use cases and two actors.
h) Describe following project cost estimation approaches. i) Heuristic ii) Analytical iii) Empirical
Q6.
a) Draw and explain : Transition diagram from requirement model to design model.
: conceptual data model with E-R diagram for employee management
system.
c) Identify and enlist requirement for given modules of employee management software: (i)
Employee detail (ii) Employee salary (iii) Employee performance.
e) Compare CMMI and ISO for software w.r.to i) Scope ii) Approach iii) Implementation.
h) Use COCOMO model to calculate. i) Effort ii) Development Time iii) Average staff size iv)
Productivity if estimated size of project is 400 KLOC using embedded mode.
i) State requirements for given modules of online shopping system. i) Order module ii) Accountant
module iii) Categories module