Design of Distribution Substations
Design of Distribution Substations
Substations
1
Objectives
♦ Discussion of the types of substation and
their functions
♦ Discussion of the substation bus
configuration
♦ Discussion of substation’s reliability
concepts
♦ Calculation of the substation rating
♦ Illustration of the discussed analytical
methods by some numerical examples
Introduction
♦ Selection of substation switchyard system schemes
represented in the substation buses and switches
configuration is based mainly on reliability and
economical aspects.
This substation
interconnects different
parts of transmission
system without changing
the voltage levels
Transmission Substation which can step-down
or step-up voltage to interconnect the network
♦ From the construction point of view, there are three main types of
distribution substations.
– Conventional outdoor (open terminal) substation in which busbars and
live parts can be seen.
♦ These three phase primary feeder distributes energy from the low voltage
bus through three phase feeder and three or single phase laterals.
20
Single Bus Scheme
Advantages
♦ Lowest cost compared to other schemes
♦ Simple
Disadvantages
♦ Failure of the circuit breaker results in shutdown of entire
substation.
♦ Difficult to do any maintenance.
♦ Bus can’t be extended without completely de-energizing
substation.
♦ Can be used only in places where loads can be interrupted
or have other supply arrangements.
21
Sectionalized (Radial) Bus Scheme
Incoming Line Incoming Line
CB Bus-Tie CB
CB
Bus 1 Bus 2
N.O. bypass
switch
Disconnecting
switch
Incoming line
♦ It consists of main
and transfer buses
connected through a Main bus
N.O. transfer CB.
N.O.
24
Main-And-Transfer Bus Scheme
Advantages
♦ Low cost.
♦ Any breaker can be taken out of service for maintenance.
Disadvantages
♦ Requires one extra breaker for the bus tie.
♦ Switching is somewhat complicated when maintaining a
breaker.
♦ Failure of bus or any circuit breaker results in shutdown of
entire substation.
25
Double Bus-Single Breaker Scheme
Bus 1
N.O.
♦ Two buses are connected
through a tie breaker. Bus
N.O. tie
breaker
♦ Each circuit can be
N.O.
connected to one bus
through CB and
disconnecting switches. Bus 2 N.O.
Outgoing line 26
Double Bus-Single Breaker Scheme
Advantages
♦ Permits some flexibility with two operating buses.
♦ Either main bus can be isolated for maintenance.
♦ Circuits can be transferred readily from one bus to the
other by use of bus-tie breaker bus selector disconnect
switches.
Disadvantages
♦ One extra breaker is required for the bus tie.
♦ Four switches are required per circuit.
♦ Bus protection scheme may cause loss of substation when
it is connected to that bus.
♦ Line breaker failure takes all circuits connected in that
bus out of service.
27
Ring Bus Scheme
♦ In this scheme several Line Line
sectionalized single bus schemes
are connected in series.
♦ In the case of occurrence of bus
or circuit fault, one position is
disconnected through its CB.
♦ Each line is equipped by a
disconnecting switch.
♦ To make preparations for this
line to go out of service: the two
CBs are opened first; then the
line disconnecting switch is Line Line
opened; following that the two
CBs are closed.
28
Ring Bus Scheme
Advantages
♦ Flexible operation for breaker maintenance
♦ Any breaker can be removed for maintenance without
interrupting load.
♦ Requires only one breaker per circuit.
♦ Each circuit is fed by two breakers.
♦ All switching is done with breakers.
Disadvantages
♦ For a fault during breaker maintenance period, the ring can
be separated into two sections.
♦ Automatic reclosing and protective relaying rather complex.
29
Breaker-And-A-Half Scheme
Line Line
33
Bus Schemes and Their Applied Voltage
Ring bus X X X X X X X
Beaker-and-a-half scheme X X X X X X
40
Distribution Substation Rating
♦ It is helpful to assume that the system changes at:
– Constant load density for short term distribution planning
– Increasing load density for long term planning.
41
Four Feeders Service Area
♦ The square service area can be assumed that it is
served by four feeders from a central feed point as
shown below.
♦ Each feeder and its laterals are of three-phase.
42
Four Feeders Service Area
♦ The percent voltage drop from the feed point A to
the end of the last lateral point C is:
%VDAC = %VDAB + %VDBC
♦ Each feeder serves a total load of:
S 4 = A4 × D = L4 × D
2
Where :S4 is the kVA load served by one of four feeders, A4 is the area
served by the feeder and D is the load density.
43
Four Feeders Service Area
44
Six Feeders Service Area
♦ The previous discussion can be extended to a
hexagonal shape service area.
♦ The substation loads are supplied by six feeders
from a feed point at the center of the substation
service area as shown in the following figure.
45
Six Feeders Service Area
L6
S6 = A6 ⋅ D = ⋅ L6 ⋅ D = 0.578 ⋅ D ⋅ L26
3
2
% VD6,main = ⋅ L6 ⋅ K ⋅ S6 = 0.385 ⋅ K ⋅ D ⋅ L36
3
46
A General Geometrical Shape Service Area
A General Geometrical Shape Service Area
2 360
% VDn ,main = ⋅ K ⋅ D ⋅ Ln ⋅ tan
3
∀n≥ 3
3 2n
♦ Where: n represents the number of feeders
♦ Where: ⋅ 2 θ 360
n= ∀n≥ 3
Comparison Between Four And Six Feeder’s
Service Area Characteristics
n=4 n=6
The feeder service area (A) 2 1
L ⋅ L26
4 3
6
The substation service area (TA)
4 L24 3
⋅ L26
D⋅L
The feeder service area loading (S) 2 1
⋅ D ⋅ L26
4 3
The substation service area loading (TS)
4 D ⋅ L24 6
3
⋅ D ⋅ L26
𝟐𝟐 2
% VDmain � 𝑲𝑲 � 𝑫𝑫 � 𝑳𝑳𝟑𝟑𝟒𝟒 ⋅ K ⋅ D ⋅ L36
𝟑𝟑 3 3
The load current in main feeder (I) S4 D ⋅ L24 S6 D ⋅ L26
=I4 = =I6 =
3 ⋅VL − L 3 ⋅VL − L 3 ⋅VL − L 3 ⋅VL − L
49
Comparison Between Four And Six Feeder’s
Service Area Characteristics
♦ Based on the comparison shown in previous Table,
the relation between four and six feeder service areas
can be discussed under two different assumptions:
a) Assuming equal feeder’s thermal capacity and
neglecting the voltage drop for a given conductor size:
6
× L26 2
TA6 3 3 L6 3
Hence: = = =
TA4 4 × L4
2
2 L4 2
Therefore, the six-feeder can hold up to 3/2 of the total load
of the four-feeder for the same conductor thermal capacity.
50
Comparison Between Four And Six Feeder’s
Service Area Characteristics
b) Assume equal feeder’s percentage voltage drop and
ignore thermal capacity for a given conductor size::
6
× L 2
2
Hence: TA6 3
6
3 L6 5
= = =
TA4 4 × L4
2
2 L4 4
Hence, the six-feeder can hold up to 5/4 of the total load of
the four-feeder for the same conductor percentage voltage
drop.
51
Example 1
A substation is serving a square service area as shown
below. Assume that the substation is served by a three
phase 4.16 kV primary feeders. The feeder mains are
made of either #2 AWG copper or #1/0 ACSR (max
current capacity is 230A). The distance between phases
are 37 inches. Assume a lagging power factor of 0.9 and
1000 kVA/mi2 uniformly distributed load density.
Calculate the following:
a) Consider thermally loaded feeder mains, find
I. Maximum load per feeder
II. Substation size
III. Substation spacing, both ways
IV. Total voltage drop till the end of the main
52
Example 1, solution
S n = An × D = L24 × D
1/ 2 1/ 2
Sn 1657.2
L4 = = = 1.287 mile
D 1000
53
Example 1, solution
Total percent voltage drop:
2
%𝑉𝑉𝑉𝑉𝑛𝑛 = � 𝐾𝐾 � 𝐷𝐷 � 𝐿𝐿34
3
From the figure, K = 0.007
2
%𝑉𝑉𝑉𝑉𝑛𝑛 = × 0.007 × 1000 × 1.2873
3
= 9.95%
54
Example 1, continue
55
Example 1, solution
Substation spacing, both ways, can be found from:
2
%𝑉𝑉𝑉𝑉𝑛𝑛 = � 𝐾𝐾 � 𝐷𝐷 � 𝐿𝐿34
3
1� 1�
3 × %𝑉𝑉𝑉𝑉𝑛𝑛 3 3×3 3
𝐿𝐿4 = = =0.86 𝑚𝑚𝑚𝑚
2 × 𝐾𝐾 × 𝐷𝐷 2 × 0.007 × 1000
1 D. Area
Area = ( w1 + w2 ) ⋅ l IT = ∠ − cos −1 ( PF )
2 3kVLL
The current that is delivered to the trapezoid abef is
D. Area x
Ix = ∠ − cos −1 ( PF )
3kVLL
where Areax is the area of the trapezoid abef given by
1
Area x = ( w1 + wx ) ⋅ x
2 57
The Trapezoid Area
w1 + 2 w 2
Vdrop = Re Z .I T .
3( w1 + w 2 )
2 8 w 2 + 9 w1w 2 + 3 w 1
2 2
Ploss = 3. R. IT .
15(w1 + w2 )
2
7-Mar-22 58
Geometric Patterns and Service Areas
Rectangular
1 2
Ploss = 3. .R. I T 0.5L 0.5L
3 I
7-Mar-22 59
Geometric Patterns and Service Areas
- Triangular Model for Voltage drop
a) If source at A:
2
Vdrop = Re .Z .I T
3 A B
W
8 2
Ploss = 3. .R. IT
15
B) If source at B: (2/3)L (1/3) L
1 I
Vdrop = Re .Z .IT
3
1 2
Ploss = 3. .R. IT
5
7-Mar-22 60
Substation Application Curves
♦ This an other technique used to calculate the
number of feeders and substation service area.
♦ For each conductor size, phase spacing, voltage
drop there is a different substation application
curve.
♦ In general these substation application curves
link: load density (D), substation service area (A)
substation loading (TS), primary feeder’s voltage
(V), number of feeders (n), and allowable feeder
loading (Sn).
61
Substation Application Curves
6% Voltage drop
62
Substation Application Curves
3% Voltage drop
63
Example 2
Calculate the substation design parameters for the
following substation input data
♦Given:
1- A load density (D) of 500 kVA/mi2
2- Substation voltage 13.2/22.9 kV
3- Substation rating (TS) of 40MVA
4- 3 % voltage drop
♦Determine:
1- Substation service area (TA)
2- Substation outgoing feeders number (n)
64
Example 2, Solution
66
Example 3
67
Example 3
Table 1
68
69
Example 3, solution
70
Example 3, solution