CBRA Application Guide
CBRA Application Guide
TRUST
Department
of Energy &
Climate Change
MAINSTREAM
RENEWABLE
POWER
VATTENFALL
Statkraft
Application Guide for the specification of the Depth of Lowering using CBRA
2
Table of Contents
List of Figures 4
List of Tables 5
Definitions 8
2. Input data 13
2.1. Surveys 13
2.2. Essential data and information 13
3. CBRA methodology 16
3.1. Process flow 16
3.2. Risks and hazards affecting cable burial 16
3.3. Benthic Fishing 17
3.4. Shipping 19
3.5. FoS and specification of the DoL 33
3.6. Conclusions and recommendations 35
4. References 36
List of Figures
Figure 2 CBRA process flow ........................................... ........ ........ ........ ........ ........ ...... 16
Figure 4 Illustration of the buffer zone for anchor risk analysis (Dship Drag) ... . ....... • ..... 27
Figure 6 Main levers affecting the final specification of the DoL ................................ 34
Figure 7 Cable route and seabed conditions for the example ..................................... 45
Figure 8 Vessel traffic per section of the considered cable route .............................. 46
Figure 9 DoL specification without FoS and varying acceptable return period .......... 50
4
Application Guide for the specification of the Depth of Lowering using CBRA
List of Tables
Table 7 Example of Failure rates and return periods from the literature .................. 29
Table 13 Estimation of the Dship drag and Pwd for the vessels/anchor sizes of interest
47
Table 15 DoL specification mitigating the risk from anchor without FoS ................... 48
5
Application Guide for the specification of the Depth of Lowering using CBRA
EN Equipment Number
KP Kilometre Point
7
Definitions
A B C
Depth of Cover (D in Figure 1) - The thickness of material on top of the cable after
trenching and accounting for potential backfill / seabed mobility. It may not be
required for cable protection however could be required for consenting conditions
e.g. BSH imposes the 2 K rule in the German Exclusive Economic Zone of the North
Sea and the Baltic Sea; the thermal properties of the soil could influence the cable
design [e.g. cable overheating].
Factor of Safety - Factor used to provide a design margin over the theoretical
design capacity to allow for uncertainties in the process. This is generally specified
by the developer.
Mean seabed level - The average undisturbed/natural level of the seabed before
construction works.
Return period - Average period of time between occurrences of a given event. The
inverse of return period expressed in years is the probability of such an event
occurring in any given year.
Residual Risk - Risk remaining after protective measures have been taken.
Target Depth of Lowering (8 in Figure 1) - This is the depth that cable installation
contractors should target. Generally this is specified by the developer. Target Depth
of Lowering should be equal to or greater than the recommended minimum Depth of
Lowering to allow for any uncertainty and/or anticipated localised depth variations
during trenching operations. Where the target Depth of Lowering is not achieved no
remedial action would be required as long as the recommended Minimum Depth of
Lowering is achieved.
Target Trench Depth (C in Figure 1) - This is the trench depth specified to achieve
the target Depth of Lowering. The cable installation contractors should determine
the target trench depth according to the target DoL, cable properties, preferred
trenching tool and taking into account the seabed conditions such as minor
bedforms.
9
Application Guide for the specification of the Depth of Lowering using CBRA
This Application Guide aims to illustrate how to specify the DoL with the CBRA
methodology. The structure of the document is as follows. In chapter 1 the
background and scope of the CBRA methodology is explained. In chapter 2 all the
required inputs that should be available to apply a robust CBRA are briefly
presented. In chapter 3 the CBRA methodology is presented in detail illustrating the
process that should be followed to specify the DoL focusing on the description of
what have been historically perceived as the main anthropogenic hazards to subsea
cables [shipping and fishing]. In appendix A is given more background information on
the motivation to develop CBRA. In appendix B the common risks that affect cable
burial are described. Finally a worked step by step example is given in appendix C.
1.2. Background
The OWA is a world leading industry-led collaborative programme designed and
managed by the Carbon Trust, between DECC, the Scottish Government, Carbon
Trust and nine major offshore wind farm developers representing 72% of the
licensed capacity in UK waters [DONG Energy, E.ON, Mainstream Renewable Power,
RWE lnnogy, Scottish Power Renewables/lberdrola, SSE Renewables, Statkraft,
Statoil and Vattenfall]. The multi-million pound programme has been running since
2008 with the objective of bringing down the costs of low carbon electricity produced
by offshore wind farms. Five Technical Working Groups have been formed on specific
areas of offshore wind farm development [Access Systems, Cable Installation,
Electrical Systems, Foundations, and Wake Effects].
In late 2013 the OWA Cable Installation Technical Working Group [TWG] contracted
UTEC Geomarine, Cathie Associates and Xodus Group to complete a study on site
investigations, trenching assessments and burial risk assessments that are
completed in the design stage of wind farm projects. The study included consultation
with trenching contractors, consultancies and the wind farm developers of the OWA.
The development of the Cable Burial Risk Assessment methodology [CBRA] was part
of that project.
The main driver to develop CBRA is that the optimisation of the DoL specification will
result in a reduction of the required DoL in many ground conditions and external risk
10
Application Guide for the specification of the Depth of Lowering using CBRA
scenarios thus leading to significant reduction of risks and costs associated with
cable installation. The motivation to develop CBRA is further described in Appendix
2.
11
Application Guide for the specification of the Depth of Lowering using CBRA
Finally, the CBRA methodology whilst intended to be used in array and export cables
in offshore wind farms may equally apply to interconnectors or any other subsea
cable.
12
Application Guide for the specification of the Depth of Lowering using CBRA
2. Input data
2.1. Surveys
The objective of the site survey for offshore cable projects is to obtain sufficiently
detailed and reliable site specific seabed information to enable the safe and
economic design and installation of assets on or below the seabed level. Detailed
data needs to be obtained for the total length of the planned cable route, covering a
corridor of sufficient width to provide adequate information for the design of the
cable route as well as installation and operation related activities, taking into
account possible route adjustments due to subsequent findings. Offshore surveys
are required at varying stages of the project as follows:
Project Planning/feasibility survey;
- Side Scan Sonar to locate and determine the nature and geometry of
seabed features;
AIS Shipping Data including information on the vessels in transit (age, type,
possible failure rate etc.) that will help the designer assess the likelihood of
emergency situations requiring the deployment of anchors as well as the
behaviour of captains in emergencies;
Fishing Studies: Although useful, extensive studies are not considered crucial.
As explained in section 3.3 a pragmatic approach is possible limiting the
required amount of analysis;
Cable Dimensions;
The AIS shipping data should be processed to yield the following track information:
14
Application Guide for the specification of the Depth of Lowering using CBRA
Type Description
Desk study/ Desk Studies and/or Regional geological data [maps and
background data memoirs]
Geotechnical survey
Fishing studies
15
Application Guide for the specification of the Depth of Lowering using CBRA
3. CBRA methodology
3 .1. Process flow
Figure 2 illustrates the CBRA process flow, thus the steps taken to specify the DoL.
Once the inputs have been collated as discussed in section 2, the risk assessment is
performed. The DoL is successively specified based on the outcome of the iterative
probabilistic process and the acceptable risk. The CBRA assessment could be
revisited several times during the lifecycle of a project as discussed in Section 1.4.
Cable Routeing
Data Collation
CBRA considers the risks that are mitigated by means of cable burial and the risks
that affect the burial of cables e.g. sediment mobility. Table 2 summarises the
considered risks. There are two types of hazards namely natural and anthropogenic.
In appendix B a short description is given for each hazard, whereas the following
subsections focus on the risks related to the main anthropogenic hazards for the
mitigation of which the DoL has been historically specified [fishing and shipping]. The
discussion on each risk is not intended to be exhaustive and focuses on describing
the impact of each risk to the specification of the DoL. It should be highlighted that
although the approach is the same in inter-array cables and export cables, the
outcome of the risk assessment is different in the two cases due to the different
magnitude of the risks and/or consequences. For example in the infield area the risk
16
Application Guide for the specification of the Depth of Lowering using CBRA
from shipping is in principle limited compared to export cables since the infield area
in principle excludes major shipping lanes.
There are a number of hazards to cables that are not covered by CBRA since they are
not normally mitigated by means of cable burial. However, these risks need to be
addressed on a project by project basis. A brief description of these hazards is given
in appendix B3.
Seismic activity
Submarine landslide
Anthropogenic Fishing
Vessel anchoring
17
Application Guide for the specification of the Depth of Lowering using CBRA
Work by Linnane et al. (2000) indicates that fishing gear penetration is limited to a
maximum of 0.3 m penetration even in soft sediment. Table 3 reports the fishing
gear penetration summary produced by Linnane et al. (2000).
18
Application Guide for the specification of the Depth of Lowering using CBRA
In assessing the threat from fishing gear the following should be taken into account:
2. It is common knowledge in the industry and evidence suggests that the fishing
gear currently used for benthic fishing [Pelagic Trawl, Gill Nets, Beam Trawl,
Pots & Traps, Demersal Trawl and Seine Nets) does not normally penetrate
the seabed beyond 0.3 m [30 cm].
3.4. Shipping
3.4.1. Factors affecting the risk profile
Grounding of ships in shallow water may present a hazard to subsea cables, however
errant or emergency anchoring of vessels is perceived as the most significant threat
to subsea cables from shipping. That said, the magnitude of this risk is often
exaggerated. CBRA provides a methodology with high potential for standardisation to
robustly assess the risk and specify an appropriate mitigating measure. In assessing
the risk from shipping the following should be taken into account:
The vessel traffic should be divided into categories of similar threat levels e.g.
the vessels should be categorised according to their type, their deadweight
and corresponding anchor they carry;
19
Application Guide for the specification of the Depth of Lowering using CBRA
All the vessels do not fail with the same rate. It is important to understand
that modern vessels with enhanced redundancy in navigation and safety
systems will most likely fail less than old tankers (see the following section
for a discussion on failure rates];
The vessel traffic is expected to significantly differ within the offshore wind
farm infield area and along the export cable corridor. Between export cables
and interconnector cables the vessel traffic is expected to be of similar
pattern and magnitude [local variations do exist but the main aspects are
similar].
CBRA only considers the deployment of anchors under emergency situations in the
probabilistic risk assessment. There could be different situations e.g. accidental
deployment of anchors due to equipment failure or a mistake by the crew. These are
not considered by CBRA as it is complex to assess the probability of a human error
with a standardised approach. However, it should be highlighted that by mitigating
against the probability of occurrence of an anchor deployment in emergency
situations, the cases that are not considered only affect the level of
residual/acceptable risk [thus related to the largest and less frequent anchors] and
therefore the impact from the additional risk occurring is marginal. Moreover, in the
case of errant or accidental deployment of anchors it is unlikely that the anchors will
exert their ultimate holding capacity thus reaching their maximum penetration
depth. As a consequence although CBRA does not consider errant deployment of
anchors, accounting for the maximum penetration depth and the exertion of the
ultimate holding capacity from a given anchor is a conservative approach, thus the
additional effective risk from errant anchoring due to equipment failure or crew
error is marginal.
In order to determine a cost effective and practically achievable DoL which provides
an appropriate level of protection, it is important to assess the risk of anchoring with
a systematic, accurate and quantitative approach. The CBRA method has been
conceived in such a way that removes as far as possible the qualitative inputs and
clearly identifies all the influential parameters to allow an informed discussion.
CBRA evaluates the exposure of the cable to external threats by considering the
amount of time a vessel spends within a critical distance of the cable and the
probability that this vessel might have an incident that requires the deployment of an
anchor. The fundamental assumption on this point is that the deployment of an
anchor is a risk to the cable and therefore no consideration is made on whether
the anchor actually hits the cable or not. In practice there is always a likelihood
that when an anchor is deployed it could bounce along the seabed (anchor tripping)
or not penetrate deep enough to hit the cable or even get dragged for a distance
inferior to what is expected and therefore not effectively representing a threat. CBRA
does not consider the dynamics of the interaction between the anchor, the seabed
20
Application Guide for the specification of the Depth of Lowering using CBRA
and the cable to avoid complexity and uncertainty due to the lack of reliable data
which would introduce room for interpretations to the analysis. Moreover, by
assuming that the anchor is a threat when deployed and not only when it hits the
cable, a conservative and safe approach is adopted that avoids the underestimation
of the risk.
Where:
PTrafficRisk probability modifier based on the tolerable level of risk
PWD probability modifier for nature and depth of seabed
Vship (metre/hr) ship speed when the anchor is deployed
DShipDrag (metres) distance travelled by the anchor in order to be a threat to the cable
probability of incident requiring the deployment of an anchor for that
vessel size and type
8760 hrs factor to annualise the results
21
Application Guide for the specification of the Depth of Lowering using CBRA
requires mitigation
18.00% 90.00%
The required OoL is Agree the value of
derived and if considered
16.00% 80.00% Pstrike that wou ld be
impractical the acceptable accept able to the
level of r isk shou ld be re- st akeholders
considered 14.00% 70.00%
PTraffic
Risk
12.00% 60.00% C
The risk from these
; 10.00%
vessels is tolerable 50.00%
>
8.00% 40.00%
E
6.00% 30.00%
4.00% 20.00%
The anchor/vessel size
required for this % of Calculat e t he value
vessels is t aken from the 2.00% 10.00% of Ptraffic Risk {Scale 0
vessel distribution curve to 1) wh ich achieves
0.00% 0.00% this tolerable level
Vessel SizeDistribution
22
Application Guide for the specification of the Depth of Lowering using CBRA
1. Calculate the value of Pstrike for all vessels ( PTraffic Risk = 1I;
2. Calculate the value of the return period corresponding to this value of the
Pstrike [the inverse of the probability);
4. Calculate the value of the Pstrike that satisfies the acceptable return period;
5. Calculate the value of PTraffic Risk (Scale 0 to 1) which achieves the tolerable
level of the Pstrike;
6. The value of ( 1- PTraffic Risk) x 100% is the percentage of vessels for which cable
burial is required for protection;
7. The anchor/vessel size required for this percentage of vessels is taken from
the appropriate distribution curve;
9. If the DoL is considered impractical the acceptable level of risk should be re-
considered.
If the cable burial depth exceeds the expected penetration depth of the largest
anchor identified for a vessel in transit in the vicinity of the cable then the probability
of a strike is zero (PTrafficRisk= 0). Similarly, if no shipping is anticipated in the area the
probability of a strike is zero (PTraffic Risk= 0). If the cable is not buried the results of the
assessment represent the worst case scenario for the cable being subject to risk
from any anchoring vessel, i.e. PTraffic Risk = 1. If very limited infield shipping traffic is
anticipated [i.e. PTraffic Risk ==0) further analysis to assess the risk from anchors may be
redundant.
With the availability of accurate shipping information it is possible to estimate the
consequences of selecting a recommended minimum DoL which will not provide
protection from some percentage of the largest vessels. It is important at this point
that project developers/owners consider if it is realistic to require protection from all
vessels that might cross the route. In order to answer this question an iterative
probabilistic approach is adopted: by changing the value of PTraffic Risk the minimum
DoL is determined which results in a probability of cable strike (equivalently an
acceptable return period] which is acceptable to the project developers/owners, or
determines the risk at an economically achievable DoL. The selection will be driven
by the risk profile which is acceptable to be used to inform the potential for incidents
during the life span of the cable and hence estimate the full life costs.
23
Application Guide for the specification of the Depth of Lowering using CBRA
Table 4 Example of categorisation of the frequency of an event based on the wind farm lifetime
The acceptable risk is not a straightforward topic as it depends on the risk appetite
of the involved stakeholders and is therefore open to interpretations on what is or is
not acceptable. Often the risk categories from the DNV-RP-F107 are adopted to
indicate a level of probability with the risk profile. However, as discussed in Appendix
A 1.2 this failure frequency is derived based on operations and risks/consequences
that are not present in offshore wind farms [environmental risks etc.). In addition,
the categorisation of the DNV-RP-F107 is deemed not to be entirely appropriate for
offshore wind farms. Table 4 indicates an alternative approach which categorises a
certain event based on the wind farm lifetime. It should be highlighted that this
table does not give any indication on what is a high, a low or an acceptable risk
(the identified categorisation in this document is given as purely a numerical
exercise). As a consequence due to the lack of fit for purpose industry standards on
the acceptable return period the engagement with all the project stakeholders is
strongly recommended for the definition of the acceptable level of risk for subsea
cables in offshore wind farms.
Finally, the probabilistic risk assessment may be repeated after cable installation
and burial, or later in the life time of the cable when vessel traffic and/or seabed
24
Application Guide for the specification of the Depth of Lowering using CBRA
levels may have changed. The DoL should be used to inform the percentage of
vessels which carry anchors large enough to be a threat to the cable. This defines
the value of PTraffic Risk which represents the actual residual risk to the cable. This will
define the requirement for eventual remedial operations on the cable.
3.4.4. Pwd
Table 5 Example of Probability Modifiers for Water Depth
Water Depth between e.g. 30m and 50m 0.0 0.1 0.3
Water Depth between e.g. 1Om and 30m 0.3 0.5 0.9
The effect of the water depth [and of the bathymetric profile] is considered important
and is included as a qualitative factor. Although qualitative, if the model is developed
logically the results will be repeatable. The water depth and the bathymetric profile
influence the navigation of vessels and their behaviour in emergency situations, thus
the likelihood of anchor deployment. In addition water depth also affects the
selection of the trenching tool [e.g. ROV jet trenchers are affected by the water
depth].
The risk of the vessel going into very shallow water, thus the risk of
grounding.
These two aspects will guide the decision of the Captain whether to deploy the
anchors. For example assuming a vessel with 10 m draft drifting in 50 m water depth
and heading towards a windfarm is clearly a situation where the vessel will deploy
the anchor as quickly as possible. If however, no obstacle is around and the vessel is
drifting towards areas with no significant change in water depth, it is more likely that
the Captain will not deploy the anchor and will focus on recovering control of the
25
Application Guide for the specification of the Depth of Lowering using CBRA
For example, at some locations along the cable route, the water depth may be great
enough to prevent the use of an anchor, reducing the probability of damage to a
cable to 0; however, at the other extreme, close to an anchorage a modifier of 1
might be used. In any case local conditions should be thoroughly assessed to
develop the modifiers.
Table 5 gives an illustration of the assignment of Pwo in various situations for three
vessel sizes; however, this is only intended to be an example and therefore these
values are not expected to be appropriate in the vast majority of practical
scenarios. The assessment can be made conservative by setting the value to 1.0 for
all water depths. However this will introduce the paradox that the calculation is the
same in 10 m water depth and in 1000 m water depth, thereby implying that the
vessel behaviour is the same during emergencies regardless of the water depth.
and Dship Drag determine the exposure of the cable in terms of the number of hours
Vship
per year that a vessel is close enough to the cable to become a threat if it deploys its
anchor. Vship and Dship Drag vary for each vessel type/size. The sum of the exposure time
of each vessel along the route [or section] gives the total exposure time of the cable
per year.
Vshipis the velocity with which the vessel drifts while it is deploying an anchor. The
deployment of anchors at high vessel drift speed is undesirable due to personnel and
equipment safety requirements. Vship is typically less than 1 knot while for smaller
vessels its maximum could even be 2 knots. For the largest vessels Vship is
considerably less than 1 knot as they should almost stationary to safely deploy an
anchor. However, it should be highlighted that there could be situations where the
deployment of the anchor will occur at a higher vessel velocity e.g. in close proximity
of an obstacle.
26
Application Guide for the specification of the Depth of Lowering using CBRA
AIS Tracks
Fishing Vessels
Dredging
Cargo
Other
Passenger
Port Authority, Pilots and Crew Boats
Tanker
Tug
Unspecified
Sailing or Pleasure
Cable Route
200m Buffer
500m Buffer
Figure 4 Illustration of the buffer zone for anchor risk analysis (DShip Drag)
Scenario Vship
I
Small vessel anchoring <2knots
Local current speed Depends on local conditions but could potentially be e.g.
-4knots
In the event of losing the propulsion system, the vessel will be influenced by the met
ocean conditions e.g. currents. There are locations where currents could have a
higher velocity e.g. 4 knots and this means that the anchor could be deployed at
higher velocity, thus potentially increasing the exposure time of the cable. Table 6
summarises indicative speeds for controlled anchoring. It is strongly recommended
to carefully consider the local conditions and specify V ship in accordance with the
specific behaviour during emergencies of each vessel type in transit.
D ship Drag is the distance travelled by the anchor when deployed in order to exert its
holding capacity and (theoretically) immobilise the vessel. A vessel transiting beyond
a distance equal to D ship Drag from the cable is not a hazard. D ship Drag can be estimated
using the kinetic energy theorem based on the vessel's weight, speed and anchor
holding capacity in the anticipated conditions (equation 2).
27
Application Guide for the specification of the Depth of Lowering using CBRA
m*
Dship Drag = 4 * UHC
Where:
D ship drag (m) distance traveled by the anchor in order to be a threat to the cable
m Vessel mass (deadweight + ship light weight), usually taken as displacement (tons)
(m/s)
Vship ship speed when the anchor is deployed
UHC Ultimate Holding Capacity of the anchor
However, this equation ignores the hydrodynamics of the anchor movement on the
seabed and has uncertainty with regards to the estimation of the UHC as it depends
on the anchor type, size, weight and the soil characteristics. The UHC can be
estimated upon consultation with anchor manuals [e.g. an anchor manual from an
anchor supplier [Vryhof] can be found here) where normally is defined as anchor
weight multiplied by an efficiency factor. The efficiency factor can vary significantly
with the soil conditions and therefore this estimation is highly approximate.
A more pragmatic approach suggests the use (where possible) of empirical data
from anchor trials where the drag distance of various anchor types may be
measured in various soil conditions. The anchor penetration trials of BSH and
TenneT performed in the German Bight have given experimental results on the drag
distance of anchors in various types of sand. By expanding the trials in other soil
types and anchor sizes/types, Dship Drag could be obtained from experimental data and
not from theoretical formulas.
28
Application Guide for the specification of the Depth of Lowering using CBRA
3 .4. 2. P incident
Table 7 Example of Failure rates and return periods from the literature
Probability Return
Reference per vessel period
per year (years)
DNV-RP-F107:
DNV-RP-F107: 5.7
1.75x10- 1
Machinery breakdown for single engine tankers in the
north sea
OGP
3x10- 3 333
Total loss per ship per year
is therefore critical to properly assess the probability that a vessel may have an
incident which requires the use of an anchor. It is recognised that developing an
accurate value for the probability of an incident is complex and that the availability of
information varies significantly from location to location. In some locations the
availability of incident data from National Authorities allows assessment of the
number of incidents for a certain vessel type or class [e.g. Marine Accident
Investigation Board [UK]). Alternatively, Lloyds Register annually publish both World
Casualty Statistics and World Fleet Statistics which can be used to determine a
frequency rate for a given region.
Where statistical data on the number of incidents is not available figures from the
literature can be used. However, careful consideration is recommended to ensure
that unrealistically low or high values are avoided. At it can be seen in table 7 the
variability of failure rates found in the literature is striking with a range of return
periods from 5 to 5000 years. This enhances the need for local investigation and
should at least include the larger vessels since these will drive the decision on the
29
acceptable risk and the mitigating measure. In addition, the behaviour of these
vessels in emergenciesshould be assessed (see discussion on PWD).
3cing de:.ign::·d t~ ::enetr;;tc· the 5C.lb::·d tn .ic:hievr. i1 holding c:.lp.lc: ty, .l"c:hcr5 m;;y
dilm.lge c:ilhle5. All 5hip!; .1rr. f tt::·d with .inc: "ar5 thilt mily b::· r.cpb~-ed eith::·-- il:i .l
tempo--.ll)' m~oring, .l5 p.l '1 of i1 pl.lnned prnc:er. ure, or for !.ilkt~, if the !;hir- i!. .it risk
.:or some re~!:;D .. Ifor ex;: mple l::>!.!:; of pcwer). Anchor size requirements are based en
various regulations i ndudi .. g th::>!i•: ::u ::lished by Ll::>~'d::;, Americ~n 3L. r:·~u of
Shipp ng and IA::S. Lsin~ :·e IACS r J les it is possible to d,:termine the approximat,:
s ze of ,mc .. cr!:; u!:ed by th,: \'C!:;!:el!. cro!:sirg : .. c c~blc rcutes. Th,: ,clc in£ c~ =~ci:y
of ~n ~ .. chor i!i determinec =~' th:· soil ,:::>rditi::>n!. ~nd by the ge::>metry ~ .. d ,,vei£ ht c.:
lhe anc··ar, wh eh ~ proportional to the fluke lenglh. The UH C ar lhe anchor ma~• be
roughly e~lirnaled by as~uming an erriciency rac:lor mulliplied by lhe cin:hor ,,•eigt· L
-loweve .. , lhe erriciency r=cLor .cirgely va .. ies arnon£ lhe c:;r•1"1anly c1vc1ilal::le an:hor!::i
(e.g. kcrn 3 lo 100) rraking Lhis esli"1,;tlion L.ncerla n. The s Le or lhe anc··ar Legal
requiremenll en ;;t vesse. is de .errni ··ed by ils Ee uipme·· LNumber rEN: (equalion 3).
! .4
EN = Dl111'• + 2. h. 8 + l O
Ar~:, I' Jlf:"I" lr: ·.·i~Y.' :"I" th~ hull. ~-.1!"•~'~,t'll!"t .Jr~ ;1 "I(: h:"IU,r:,. -,,~:"10.'~ -h~ 51.r·,m••r I n:.rt
Wu.-;.•rlin..:
30
Application Guide for the specification of the Depth of Lowering using CBRA
18000
16000
14000
12000
~
10000
u
8000
6000
4000
2000
0
0 10000 20000 30000 40000 50000 60000 70000 80000 90000 100000
DWT
The EN is related to the displacement and sail area both above and below the
waterline. The calculation includes parameters for breadth and effective height and
therefore, the analysis should be considered an approximation; however the DWT
represents approximately 2/3 of the classification value. Figure 5 illustrates the
relationship between vessel DWT and anchor size. This relationship correlates well
with anchor sizing proposed by Luger and that IACS rules result in broadly similar
anchor sizes to Lloyds and DNV. Using this relationship and the distribution of
vessels crossing the cable route, the distribution of anchor weights can be
estimated.
Alternatively once the EN is calculated the weight of the anchor can be estimated
from the IACS tables [table 8). From the commonly available anchor catalogues it is
possible to identify the distribution of the fluke length of anchors on vessels crossing
the cable route. It should be noted that the fluke length can vary significantly
depending on the manufacturer and type of anchor used, particularly where high
holding power anchors (IHHPl are in use . H HP anchors have bee n designed to be
much smaller in weight for the same performance; however, the penetration depths
do not vary with the EN. Having identified the fluke length of anchors anticipated in
an area the potential penetration depth can be determined.
The nature of the seabed affects the potential penetration depth of an anchor;
therefore an assessment of the seabed conditions along the route is important as
part of the threat assessment. Work by the US Naval Civil Engineering Laboratory
[NCEL] indica tes that in sands and stiff clays the fluke tip penetration is limited to 1
fluke length [i.e. 1 time the fluke tip depth). In soft silt s and clays anchor penetration
is between 3 and 5 fluke lengths [i.e. 3- 5 times the fluke tip depth). Tab le 9
illustrates an exa mple of theo retical penetration depths for a rang e of anchor sizes.
31
Application Gui de for the specification of the Depth of Lowering using CBRA
Table 8 Anchor weight and equipment number relationship [IACS Requirements concerning
Mooring, Anchoring and Towing)
Min. dia.
Mass
E.N. No. per Total Mild Special Extra
• anchor length steel quality special
quality
Gr. I Gr. 2 Gr. 3
(kg) (m) (mm) (mm) (mm)
I 2 3 4 5 6 7
32
Application Guide for the specification of the Depth of Lowering using CBRA
The FoS may vary between projects and con si derat ion should be given to the va Ii dity
of a constant FoS particularly along long export or interconnector cables. An
example of the factors that should be considered when selecting a FoS are:
In areas of high shipping density the un ncerta i nty in an
nc hor sizing
increases, therefore an increased FoS may be app ro priat e;
The FoS should be varied based on the quality, appropriateness and
distribution of the route survey data;
FoS m ay vary based on sensitivity and variability checks of seabed
strength;
FoS may vary along the cable route or the infield array area according to
factors that may influence the risk profile.
35
Application Guide for the specification of the Depth of Lowering using CBRA
4. References
The work presented in this document is based on the following references:
36
Application Guide for the specification of the Depth of Lowering using CBRA
- DNV [201 Ob]: Interference Between Trawl Gear and Pipelines. Recommended
Practice DNV-RP-F111, Det Norske Veritas [DNV]. October 2010
37
Application Guide for the specification of the Depth of Lowering using CBRA
- The Crown Estate [2012]: Export transmission cables for offshore renewable
installations - Guideline for leasing of export cable routes/corridors
- United Nations [1958b]: The Geneva Convention on the High Seas of 29 April
1958
- United Nations [1982]: The United Nations Convention on the Law of the Sea of
10 December 1982
38
Application Guide for the specification of the Depth of Lowering using CBRA
The BPI has been in use since the late 90's and was originally developed to assess
the required protection level of fibre optic telecommunication cables. Although it has
been widely applied to the 1st and 2nd generation offshore wind farms the BPI is now
associated with conservativism and an inherently oversimplified approach that
ignores the site specific factors and the real risk to which the cables are exposed.
This often leads to over burial of cables. In summary the main limitations in the BPI
include but are not limited to:
It is a semi-qualitative approach;
It is no longer widely used - individual risk based approaches have been
developed by developers and consultancies;
It only covers anchors of limited sizes with unclear definitions;
It is conservative with regards to protection from fishing gear in soft clay sea
beds;
It ignores site specific factors like:
- Water depth;
- Probability of incidents involving anchors;
- Frequency and size of vessels in transit;
- Coastal erosion and changes in the seabed profile; and,
It does not provide a means of quantifying the residual risk.
When the BPI was adopted these limitations were addressed through the
engineering judgement of the design team; however, this limits the standardisation
of specifications and introduces uncertainty as it relies on the individual experience
of the involved personnel and may either lead to conservatism or underestimation of
the hazards. Finally, the BPI was developed to address the lack of detailed data for
the installation of telecom cables [i.e. telecom cables are often thousands
kilometres long with limited survey data, however often it is the situation that the
water depth is such that no burial is required]. This is a fundamental difference
compared to offshore wind farms where high quality site specific data is potentially
available and could/should be used to assess the "real and effective" risk to which
39
Application Guide for the specification of the Depth of Lowering using CBRA
cables are exposed. CBRA aims to establish this mind-set and this document aims to
show how CBRA may be applied.
40
Application Guide for the specification of the Depth of Lowering using CBRA
with the risk from benthic fishing activity are the main anthropogenic hazards
for which cable burial is adopted as a primary mitigating measure;
The risk profile categories have been derived with different risks and
consequences compared to offshore wind farms.
"Local regulations may require minimum burial depths and shallower burial
may not be allowed. A risk based assessment may aid the discussion with the
authorities and identify sections of the cable which should be buried
shallower or deeper than the blanket requirement" (note from the authors:
The German authorities reduced the DoL requirements based on a
probabilistic risk based approach and large scale anchor trials [BSH 2015];
The CBRA methodology has been developed aiming to optimise the DoL based on the
recommendations of both DNV recommended practices and on the accumulated
experience in the industry. Where applicable CBRA introduced new approaches to
bridge the gaps [e.g. for the probabilistic assessment of anchor strikes] and
ultimately aims to establish itself as a robust, standardised and fit for purpose
methodology used for the specification of the DoL of subsea cables for offshore wind
farms.
41
Application Guide for the specification of the Depth of Lowering using CBRA
Seabed features are usually classified in terms of the characteristic length, height
and degree of mobility. Often it will be the situation that a dune or ripple moves
laterally as well as vertically when it progresses. This means that the natural
development of a cable on a relatively flat seabed will be to bury itself deeper rather
than becoming exposed, although this behaviour heavily depends on local conditions.
The sediment mobility along a cable route is assessed with numerical modelling and
multiple accurate bathymetric surveys. The surveys should ideally be completed a
number of times, at the same and different times of year possibly recording
significant weather events between surveys. The main aspects to consider include
but are not limited to:
Different Interface between the mobile layer and the underneath layer
[friction factor between layers];
CBRA does not discuss in detail or give any guidance on how to assess the sediment
mobility. However, the importance of this factor is recognised and it is strongly
recommended to accurately assess it with specific studies repeated in time. The
42
Application Guide for the specification of the Depth of Lowering using CBRA
layer of the mobile sediment and the pattern of its movement will influence the cable
route and/or the specification of the DoL. Depending on various factors the DoL
might increase or decrease or in some cases the cable route might be modified.
Dredging and aggregate extraction may pose a threat to submarine cables; however,
cable burial is not normally adopted to mitigate this risk, as it is considered
preferable to route away from these areas. Within UK waters, all active and
historical dredging areas are known and are covered by detailed surveys to allow a
certain amount of sediment to remain once a certain point is reached. All disposal
sites are also known and these should be avoided (if possible).
43
Application Guide for the specification of the Depth of Lowering using CBRA
and the owners of the extraction license. This is more likely to be achieved for future
extraction sites.
Where a cable crosses a shipping lane or harbour approach that will be dredged to
maintain access, it is recommended that cable installation is conducted immediately
after the channel is dredged to its maximum depth or the specification of the DoL
should allow for the maximum dredge depth as communicated by the relevant
authorities. Port authorities should also be consulted over plans for future expansion
and allow for burial below any future dredging depths.
44
Application Guide for the specification of the Depth of Lowering using CBRA
The example aims to show how to use the CBRA methodology illustrating the
process and highlighting important aspects. Since the objective is to illustrate the
probabilistic assessment, the determination of the various parameters is performed
in a rather simplistic manner. It is therefore expected that in real cases many
parameters will be significantly different and more analysis will be required for their
determination.
A cable route is considered with two sections of sand, one section of soft clay and
total length of 40 km.
Figure 7 Cable route and seabed conditions for the example
Water
Depth Mean sea level
5
10
I I
15
Parameter Value
Vship 2 Knots
Survey data is available informing on the sediment mobility of the site. Data for the
vessel traffic has been gathered [Figure 8] and the anchor sizes have been estimated
alongside the maximum penetration depth and the Dship Drag [Table 13]. It should be
highlighted that in this example it was chosen to assume a different Dship Drag for the
45
Application Guide for the specification of the Depth of Lowering using CBRA
0 0.0%
<500 1000 2000 3000 4000 5000 6000 8000 10000 15000
Vessel size (Displacement), te
46
Application Guide for the specification of the Depth of Lowering using CBRA
Soil conditions
Sand wave or
Sediment mobility study
megaripple mobility
Mobile has shown that there is no
could cause deburial or 0 0
Sediment evidence of mobile
increased burial of the
sediment at the site
cable
Anthropogenic
On bottom fishing Cable burial below depth
activity limited to water of fishing. Maximum
depths of <50 m. penetration of the fishing
Fishing 4 0
Snagging of cables with gear 0.3 m, thus
fishing gear and damage minimum DoL0.6 m with
during retrieval of gear. 0.3 m FoS.
Cable burial below anchor
penetration depth. CBRA
to assess the risk and
Shipping Major shipping lanes
7 amount of mitigation 2
/Anchors passing through the site.
measure. Application of
FoS on the outcome of the
DoL.
Table 13 Estimation of the Dship Drag and Pwo for the vessels/anchor sizes of interest
Estimated PwD
anchor weight
[kg]
Dship Drag Sand Dship Drag Clay KP 0-15 KP 15-32 KP32-40
DWT [Tons] [ml [ml [15-18m] [18-23m] [12-20m]
500 335 6.6 13.2 0.1 0.1 0.1
1000 524 8.4 16.9 0.1 0.1 0.1
2000 825 10.7 21.4 0.2 0.1 0.3
3000 1,077 12.3 24.6 0.2 0.1 0.3
4000 1,302 13.6 27.2 0.2 0.1 0.3
5000 1,509 14.7 29.3 0.4 0.3 0.5
6000 1,702 15.6 31.2 0.4 0.3 0.5
8000 2,060 17.2 34.3 0.5 0.4 0.6
10000 2,388 18.5 37.0 0.6 0.5 0.7
15000 3,125 21.2 42.4 0.7 0.6 0.8
47
Application Guide for the specification of the Depth of Lowering using CBRA
Probability scenario Overall probability and return period in the route section
Total probability* 3.36E-04 3.32E-04 5.50E-04
Table 15 DoL specification mitigating the risk from anchors without FoS
48
Application Guide for the specification of the Depth of Lowering using CBRA
49
Application Guide for the specification of the Depth of Lowering using CBRA
Figure 9 DoL specification with FoS and varying acceptable return period
Route KP
0 5 10 15 20 25 30 35 40
0 .0
1.0
2.0
3 .0
•••••• Acceptable return period
2,500 years
4.0 - - - Acceptable return period
25,00 0 years
5.0
50
Application Guide for the specification of the Depth of Lowering using CBRA
Acknowledgements
The OWA wishes to thank all the authors who contributed in the development of this
application guide. Further special acknowledgement is given to the all the members
of the Cable Installation Technical Working Group of the OWA and to all the
employees of the OWA partners that have reviewed the document. In addition, the
OWA would like to thank all the parties from the industry [Jan de Nul, Van Oard,
VBMS, Subsea Cables UK, Xodus] that have provided invaluable feedback on this
document. Finally the OWA would like to thank all the delegates in the many cable
related conferences in which CBRA was presented for engaging into high quality
technical discussions on the methodology and effectively steering the development
of this application guide.
www .carbontrust.com
CTC857
Whilst reasonable steps have been taken to ensure that the information contained within
this publication is correct, the authors, the Carbon Trust, its agents, contractors and
sub-contractors give no warranty and make no representation as to its accuracy and
accept no liability for any errors or omissions. Any trademarks, service marks or logos
used in this publication, and copyright in it, are the property of the Carbon Trust. Nothing
in this publication shall be construed as granting any licence or right to use or reproduce
any of the trademarks, service marks, logos, copyright or any proprietary information in
any way without the Carbon Trust's prior written permission. The Carbon Trust enforces
infringements of its intellectual property rights to the full extent permitted by law.
The Carbon Trust is a company limited by guarantee and registered in England and
Wales under Company number 4190230 with its Registered Office at:
4th Floor, Dorset House, 27-45 Stamford Street, London SE1 9NT